CN102619234A - 一种坝基深槽处理结构及其施工方法 - Google Patents

一种坝基深槽处理结构及其施工方法 Download PDF

Info

Publication number
CN102619234A
CN102619234A CN2012101193939A CN201210119393A CN102619234A CN 102619234 A CN102619234 A CN 102619234A CN 2012101193939 A CN2012101193939 A CN 2012101193939A CN 201210119393 A CN201210119393 A CN 201210119393A CN 102619234 A CN102619234 A CN 102619234A
Authority
CN
China
Prior art keywords
loaded plate
dam foundation
dam
deep trouth
deep groove
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012101193939A
Other languages
English (en)
Inventor
叶建群
熊立刚
吴关叶
陈国良
黄成家
吕国轩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hydrochina East China Engineering Corp
Original Assignee
Hydrochina East China Engineering Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hydrochina East China Engineering Corp filed Critical Hydrochina East China Engineering Corp
Priority to CN2012101193939A priority Critical patent/CN102619234A/zh
Publication of CN102619234A publication Critical patent/CN102619234A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Foundations (AREA)

Abstract

本发明涉及一种坝基深槽处理结构及其施工方法。本发明的目的是提供一种坝基深槽处理结构及其施工方法,在处理坝基深槽的同时,不影响其上的坝体施工,深槽处理和坝体施工同步进行,既能从根本上解决深槽内砂卵砾石引起的坝基稳定、应力、变形和防渗问题,又可以缩短深槽处理工期,提前发挥工程效益。本发明的技术方案是:一种坝基深槽处理结构,其特征在于:跨坝基深槽设置承载板,承载板上部为坝体并且在承载板顶部预留施工廊道,该承载板内部预埋连通施工廊道和承载板底部的灌浆管;承载板底部坝基深槽内回填深槽置换混凝土。本发明适用于坝基存在深槽的工程。

Description

一种坝基深槽处理结构及其施工方法
技术领域
本发明涉及一种坝基深槽处理结构及其施工方法。适用于坝基存在深槽的工程,有效地解决深槽引起的大坝建基面抗滑稳定、坝基应力、沉降变形和坝基防渗的问题,并且可以极大的缩短深槽处理所占用的直线工期,加快施工工期。
背景技术
在一些复杂地形地质条件的工程中,河床部位坝基往往存在深槽,并充填砂卵砾石,对大坝抗滑稳定、坝基应力、沉降变形和坝基防渗均不利。目前对这种深槽的处理主要有明挖全置换方法和固结灌浆方法,前者采用明挖的方法将深槽内砂卵砾石全部挖除并置换混凝土,可以有效解决坝基稳定、应力和防渗问题,但上部坝体施工必须等深槽全部处理完成后才能进行,处理周期长,影响施工工期和工程效益的发挥;后者不挖除深槽内砂卵砾石,仅对其进行固结灌浆加固,采用此方法处理,固结灌浆的加固效果难以保证,抗滑稳定、坝基应力以及坝基防渗都存在不确定因素,安全度小,不适用于高坝和工程等别较高的工程。   
发明内容
本发明要解决的技术问题是:针对上述存在的问题,提供一种坝基深槽处理结构及其施工方法,在处理坝基深槽的同时,不影响其上的坝体施工,深槽处理和坝体施工同步进行,既能从根本上解决深槽内砂卵砾石引起的坝基稳定、应力、变形和防渗问题,又可以缩短深槽处理工期,提前发挥工程效益。
本发明所采用的技术方案是:一种坝基深槽处理结构,其特征在于:跨坝基深槽设置承载板,承载板上部为坝体并且在承载板顶部预留施工廊道,该承载板内部预埋连通施工廊道和承载板底部的灌浆管;承载板底部坝基深槽内回填深槽置换混凝土。
在承载板上游设防渗支挡结构。
所述承载板底面布置成拱形结构,沿上下游方向设置键槽。
所述承载板为钢筋混凝土结构,且在承载板内部受钢筋上安装有监测仪器。
所述承载板经支护锚杆固定于基岩上。
坝基深槽处理结构的施工方法,其特征在于采用以下步骤:
a、根据地质勘探结果,并综合考虑枢纽整体布置,进行承载板布置和结构分析,确定结构尺寸及配筋,承载板沿上下游方向设置键槽;
b、进行承载板建基面的开挖和支护;
c、安装承载板的钢筋、监测仪器,并浇筑承载板的混凝土,承载板顶部预留施工廊道,并在承载板内部预埋灌浆管;
d、进行承载板上部坝体的施工; 
e、施工承载板上游防渗支挡结构;
f、坝体施工的同时进行承载板底部坝基深槽内砂卵砾石的洞挖和支护;
g、洞内置换回填混凝土;
h、进行回填及固结灌浆,以使承载板与置换的混凝土之间结合紧密。 
本发明的有益效果是:
1、将坝基深槽内砂卵砾石全部挖除,并用混凝土置换,从而在根本上解决了坝基稳定、应力、沉降和防渗问题,无工程安全隐患;
2、跨坝基深槽设置了承载板,承载板能独立承受其上坝体施工期荷载,承载板施工完成后可开始上部坝体施工,而不必等待坝基深槽内砂卵砾石洞挖置换混凝土完成后,再施工上部坝体,施工上部坝体的同时,进行承载板底部槽内砂卵砾石的开挖和支护,缩短深槽处理工期,提前发挥工程效益;
3、承载板底面布置成拱形结构,沿上下游方向设有键槽,有利于结构受力和后期灌浆; 
4、承载板上游设置防渗支挡结构,以便形成干地施工条件;
5、承载板内部埋设了钢筋应力计、温度计以及多点位移计等监测仪器,施工过程中可根据承载板的监测数据了解其工作状态,保证施工安全。 
附图说明
图1为本发明的平面布置图。
图2为本发明的典型剖面图。
图3为本发明中承载板钢筋及监测仪器布置图。
具体实施方式
如图1、图2所示,本实施例为一种坝基深槽处理的设计和其施工方法。本例中包括跨越坝基深槽1设置的承载板3,该承载板经支护锚杆9与基岩2固定连接。承载板3上部为坝体5,并且在承载板3的顶部预留有施工廊道7,承载板内部预埋有连通施工廊道7与承载板3底部的灌浆管8。在承载板3上游设置防渗支挡结构4,以便为下游施工地区提供干地施工条件。在承载板3底部的坝基深槽1内回填深槽置换混凝土6。
其中承载板3为钢筋混凝土结构,可以独立支撑上部坝体5施工期荷载,承载板底面宜布置成拱形结构,沿上下游方向设有键槽12,有利于结构受力和后期灌浆。如图3所示,本例中在承载板3内部的钢筋10的关键部位设埋设监测仪器11(钢筋应力计、温度计以及多点位移计等监测设施,施工过程中可根据承载板的监测数据了解其工作状态)。
本实施例的具体施工方法如下:
1)根据地质勘探成果(深槽1的范围、走向),并综合考虑枢纽整体布置,进行钢筋混凝土承载板3布置和结构分析,确定结构尺寸及配筋,结构尺寸需满足承担其上坝体5施工荷载的要求,配筋数量尚需满足限裂要求,承载板3沿上下游方向应设置键槽12;
2)进行承载板3建基面的开挖和支护;
3)安装承载板的钢筋10、监测仪器11等,并浇筑承载板3混凝土。承载板3底面宜布置成拱形结构,有利于结构受力和后期灌浆,承载板3顶部预留施工廊道7,并在承载板3内部预埋灌浆管8;
4)进行上部坝体5的施工;
5)施工承载板3上游防渗支挡结构4;
6)进行承载板3底部坝基深槽1内砂卵砾石的洞挖和支护,可与上部坝体5的施工同时进行;
7)洞内置换回填混凝土;
8)通过灌浆管8对承载板3底部进行回填及固结(接触)灌浆,以使承载板3与步骤7中置换的混凝土之间结合紧密。 

Claims (6)

1.一种坝基深槽处理结构,其特征在于:跨坝基深槽(1)设置承载板(3),承载板(3)上部为坝体(5)并且在承载板(3)顶部预留施工廊道(7),该承载板内部预埋连通施工廊道(7)和承载板(3)底部的灌浆管(8);承载板(3)底部坝基深槽(1)内回填深槽置换混凝土(6)。
2.根据权利要求1所述的坝基深槽处理结构,其特征在于:在承载板(3)上游设防渗支挡结构(4)。
3.根据权利要求1或2所述的坝基深槽处理结构,其特征在于:所述承载板(3)底面布置成拱形结构,沿上下游方向设置键槽(12)。
4.根据权利要求3所述的坝基深槽处理结构,其特征在于:所述承载板(3)为钢筋混凝土结构,且在承载板(3)内部钢筋(10)上安装有监测仪器(11)。
5.根据权利要求1所述的坝基深槽处理结构,其特征在于:所述承载板(3)经支护锚杆(9)固定于基岩(2)上。
6.一种如权利要求1所述的坝基深槽处理结构的施工方法,其特征在于采用以下步骤:
a、根据地质勘探结果,并综合考虑枢纽整体布置,进行承载板(3)布置和结构分析,确定结构尺寸及配筋,承载板(3)沿上下游方向设置键槽(12);
b、进行承载板(3)建基面的开挖和支护;
c、安装承载板(3)的钢筋(10)、监测仪器(11),并浇筑承载板(3)的混凝土,承载板(3)顶部预留施工廊道(7),并在承载板(3)内部预埋灌浆管(8);
d、进行承载板(3)上部坝体(5)的施工; 
e、施工承载板(3)上游防渗支挡结构(4);
f、坝体(5)施工的同时进行承载板(3)底部坝基深槽(1)内砂卵砾石的洞挖和支护;
g、洞内置换回填混凝土;
h、进行回填及固结灌浆,以使承载板(3)与置换的混凝土之间结合紧密。
CN2012101193939A 2012-04-23 2012-04-23 一种坝基深槽处理结构及其施工方法 Pending CN102619234A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012101193939A CN102619234A (zh) 2012-04-23 2012-04-23 一种坝基深槽处理结构及其施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012101193939A CN102619234A (zh) 2012-04-23 2012-04-23 一种坝基深槽处理结构及其施工方法

Publications (1)

Publication Number Publication Date
CN102619234A true CN102619234A (zh) 2012-08-01

Family

ID=46559418

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012101193939A Pending CN102619234A (zh) 2012-04-23 2012-04-23 一种坝基深槽处理结构及其施工方法

Country Status (1)

Country Link
CN (1) CN102619234A (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114250746A (zh) * 2021-12-31 2022-03-29 中国水利水电建设工程咨询贵阳有限公司 一种碾压混凝土坝跨孔快速施工方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20070212173A1 (en) * 2006-03-07 2007-09-13 Schellhorn Verne L Method and apparatus for building reinforced sea walls and levees
WO2010100176A1 (de) * 2009-03-03 2010-09-10 Huesker Synthetic Gmbh Verfahren zur stabilisierung eines weichen grundes für einen damm oder eine halde, und einheit bestehend aus einem nach diesem verfahren stabilisierten grund und einem damm oder einer halde
CN201627180U (zh) * 2010-03-05 2010-11-10 中国水电顾问集团华东勘测设计研究院 重力坝坝基大断层加固结构
CN202610823U (zh) * 2012-04-23 2012-12-19 中国水电顾问集团华东勘测设计研究院 一种坝基深槽处理结构

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20070212173A1 (en) * 2006-03-07 2007-09-13 Schellhorn Verne L Method and apparatus for building reinforced sea walls and levees
WO2010100176A1 (de) * 2009-03-03 2010-09-10 Huesker Synthetic Gmbh Verfahren zur stabilisierung eines weichen grundes für einen damm oder eine halde, und einheit bestehend aus einem nach diesem verfahren stabilisierten grund und einem damm oder einer halde
CN201627180U (zh) * 2010-03-05 2010-11-10 中国水电顾问集团华东勘测设计研究院 重力坝坝基大断层加固结构
CN202610823U (zh) * 2012-04-23 2012-12-19 中国水电顾问集团华东勘测设计研究院 一种坝基深槽处理结构

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
杨青松等: "龙开口水电站坝基深槽处理设计与施工", 《中国水利学会地基与基础工程专业委员会第十一次全国学术技术研讨会论文集》 *
熊成林等: "坝基深风化槽安全监测技术应用及成果分析", 《中国水利水电科学研究院学报》 *
陈进心: "株洲航电枢纽工程7号风化槽基础处理", 《水利水电施工》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114250746A (zh) * 2021-12-31 2022-03-29 中国水利水电建设工程咨询贵阳有限公司 一种碾压混凝土坝跨孔快速施工方法
CN114250746B (zh) * 2021-12-31 2023-09-22 中国水利水电建设工程咨询贵阳有限公司 一种碾压混凝土坝跨孔快速施工方法

Similar Documents

Publication Publication Date Title
Chen et al. Long rectangular box jacking project: a case study
CN105840207B (zh) 一种穿越浅埋偏压松散堆积体大跨度隧道综合进洞结构施工方法
CN102134998B (zh) 一种风积沙隧道的施工方法
CN101122131B (zh) 一种用管件桩嵌岩的基坑支护桩
CN101775988B (zh) 软弱围岩斜井转正洞的施工方法
CN102966108B (zh) 紧临既有建筑物以地下结构为内支撑的深基坑施工方法
CN108442382B (zh) 横穿深基坑的压力管线原位保护及围护挡土结构及施工方法
CN103510959B (zh) 一种浅埋大跨小净距黄土隧道开挖技术
CN110617072B (zh) 一种极小净距斜下穿既有运营隧道的隧道开挖施工方法
CN102536273A (zh) 26m大跨度空间一次成型建造工法
CN106436720A (zh) 顶管施工用小尺寸深基坑支护结构
CN102733413A (zh) 一种运营地铁隧道沉降控制方法
CN102767180A (zh) 一种静压锚杆桩补强基础施工方法
CN103758123A (zh) 人工挖孔灌注桩护壁衬的施工方法
CN108532586A (zh) 一种停车库用地下连续墙的施工方法
CN107190752A (zh) 一种柔性复合防渗装配式可回收矩形截面排桩支护结构的设计施工方法
CN103993885A (zh) 一种暗挖隧道侧向开洞支撑体系构建方法
CN109578014A (zh) 一种抗突涌封底结构及施工方法
CN104099946B (zh) 一种新型顶管段间检修井
CN204311456U (zh) 基坑加固结构
CN205776239U (zh) 一种双排桩支护结构
CN209195412U (zh) 一种适用于软弱易滑地层的隧道进洞结构
CN202610823U (zh) 一种坝基深槽处理结构
CN103541739A (zh) 一种浅埋大跨小净距黄土隧道支护体系
CN202560234U (zh) 一种无柱大跨度地下空间结构

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20120801