CN102606174A - Four-direction connection box for lagging jacks - Google Patents

Four-direction connection box for lagging jacks Download PDF

Info

Publication number
CN102606174A
CN102606174A CN2012101130501A CN201210113050A CN102606174A CN 102606174 A CN102606174 A CN 102606174A CN 2012101130501 A CN2012101130501 A CN 2012101130501A CN 201210113050 A CN201210113050 A CN 201210113050A CN 102606174 A CN102606174 A CN 102606174A
Authority
CN
China
Prior art keywords
bow member
junction plate
connection plate
preliminary bracing
steel support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012101130501A
Other languages
Chinese (zh)
Other versions
CN102606174B (en
Inventor
陈长强
陈海军
荆永军
李永纯
韩冰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Tunnel Stock Co Ltd
Original Assignee
China Railway Tunnel Stock Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Tunnel Stock Co Ltd filed Critical China Railway Tunnel Stock Co Ltd
Priority to CN201210113050.1A priority Critical patent/CN102606174B/en
Publication of CN102606174A publication Critical patent/CN102606174A/en
Application granted granted Critical
Publication of CN102606174B publication Critical patent/CN102606174B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention belongs to the technical field of tunnel construction, and provides a four-direction connection box for lagging jacks. The four-direction connection box for the lagging jacks comprises two cambered plates (12) and four connection plates, namely a connection plate I (8) connected with an outer-layer preliminary supporting lagging jack, a connection plate II (9) connected with a temporary steel support as well as a connection plate III (10) and a connection plate IV (11) which are connected with an inner-layer preliminary supporting lagging jack, wherein the connection plate I (8) and the connection plate II (9) are positioned on the inner sides and outer sides of the two cambered plates (12); and the connection plate III (10) and the connection plate IV (11) are positioned at the upper ends and lower ends of the two cambered plates. Under the condition that a stressed system consisting of the outer-layer preliminary supporting lagging jack and the temporary steel support is not damaged, the inner-layer preliminary supporting lagging jack is erected; and the four-direction connection box has the characteristics of high safety performance and convenience in operation.

Description

Bow member four-way connecting box
Technical field
The invention belongs to the tunnel construction technology field, relate generally to a kind of bow member four-way connecting box.
Background technology
At present, the tunnel preliminary bracing is mostly two-layer or multilayer bow member+sprayed mortar structure is formed, and in the tunnel excavation process, is provided with temporary steel support; How to guarantee that preliminary bracing bow member and smooth connection between the temporary steel support are the key factors of safety for tunnel engineering.Traditional connected mode is to be connected with temporary steel support immediately after outer preliminary bracing bow member sets up completion; When setting up internal layer preliminary bracing bow member, earlier temporary steel support is separated with outer preliminary bracing bow member, treat again temporary steel support and internal layer preliminary bracing bow member to be linked together after internal layer preliminary bracing bow member has set up.Traditional method bring great hidden danger to safety for tunnel engineering, and efficiency of construction is lower owing to will remove temporary steel support earlier before setting up internal layer preliminary bracing bow member.
Summary of the invention
In order to overcome the deficiency of prior art middle arch rack connected mode, the objective of the invention is to propose a kind of bow member four-way connecting box.
The present invention adopts following technical scheme for accomplishing the foregoing invention task:
A kind of bow member four-way connecting box, described bow member four-way connecting box includes two arcs and four junction plates; Described four junction plates are respectively: in order to the junction plate I that is connected with outer preliminary bracing bow member, junction plate II and junction plate III, the junction plate IV in order to be connected with internal layer preliminary bracing bow member in order to be connected with temporary steel support; Described junction plate I, junction plate II are positioned at the inside and outside both sides of two arcs, and described junction plate III, junction plate IV are positioned at the two ends up and down of two arcs.
The use of described bow member four-way connecting box is: after the installation of outer preliminary bracing bow member, bow member four-way connecting box is connected one with outer preliminary bracing bow member, again bow member four-way connecting box is connected one with temporary steel support; When internal layer preliminary bracing bow member is installed, directly internal layer preliminary bracing bow member is connected with bow member four-way connecting box and get final product.
A kind of bow member four-way connecting box that the present invention proposes; Overcome the deficiency of prior art middle arch rack connected mode; Under the situation of not destroying outer preliminary bracing bow member and the formed stress system of temporary steel support; Carry out setting up of internal layer preliminary bracing bow member, have security performance height, convenience operation.
Description of drawings
Fig. 1 is user mode figure of the present invention.
Among the figure: 1, outer preliminary bracing bow member, 2, temporary steel support, 3, bow member four-way connecting box; 4, internal layer preliminary bracing bow member, 5, outer preliminary bracing bow member junction plate, 6, internal layer preliminary bracing bow member junction plate; 7, temporary steel support junction plate, 8, the junction plate I, 9, the junction plate II; 10, junction plate III, 11, the junction plate IV, 12, arc.
The specific embodiment
In conjunction with accompanying drawing and specific embodiment the present invention is explained;
As shown in Figure 1, a kind of bow member four-way connecting box, described bow member four-way connecting box is arranged between outer preliminary bracing bow member 1 and the temporary steel support 2; Include two arcs 12 and four junction plates; Described four junction plates are respectively: in order to the junction plate I 8 that is connected with outer preliminary bracing bow member 1, junction plate II 9 and junction plate III 10, the junction plate IV 11 in order to be connected with internal layer preliminary bracing bow member 4 in order to be connected with temporary steel support 2; Described junction plate I 8, junction plate II 9 are positioned at the inside and outside both sides of two arcs 12, and described junction plate III 10, junction plate IV 11 are positioned at the two ends up and down of two arcs 12.
The present invention in use; After outer preliminary bracing bow member 1 installation; Use high-strength bolt that the junction plate I 8 of bow member four-way connecting box 3 is connected one with outer preliminary bracing bow member junction plate 5, pass through high-strength bolt again the junction plate II 9 of bow member four-way connecting box 3 is connected one with temporary steel support junction plate 7; When internal layer preliminary bracing bow member 4 is installed, through high-strength bolt internal layer preliminary bracing junction plate 6 is connected with junction plate III 10, the junction plate IV 11 of bow member four-way connecting box and to get final product.Under the situation of not removing already installed temporary steel support 2, still can reach the purpose of smooth installation internal layer preliminary bracing bow member 4 like this.

Claims (1)

1. bow member four-way connecting box, it is characterized in that: described bow member four-way connecting box includes two arcs (12) and four junction plates; Described four junction plates are respectively: in order to the junction plate I (8) that is connected with outer preliminary bracing bow member (1), junction plate II (9) and junction plate III (10), the junction plate IV (11) in order to be connected with internal layer preliminary bracing bow member (4) in order to be connected with temporary steel support (2); Described junction plate I (8), junction plate II (9) are positioned at the inside and outside both sides of two arcs (12), and described junction plate III (10), junction plate IV (11) are positioned at the two ends up and down of two arcs (12).
CN201210113050.1A 2012-04-18 2012-04-18 Four-direction connection box for lagging jacks Expired - Fee Related CN102606174B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210113050.1A CN102606174B (en) 2012-04-18 2012-04-18 Four-direction connection box for lagging jacks

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210113050.1A CN102606174B (en) 2012-04-18 2012-04-18 Four-direction connection box for lagging jacks

Publications (2)

Publication Number Publication Date
CN102606174A true CN102606174A (en) 2012-07-25
CN102606174B CN102606174B (en) 2014-07-02

Family

ID=46523894

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210113050.1A Expired - Fee Related CN102606174B (en) 2012-04-18 2012-04-18 Four-direction connection box for lagging jacks

Country Status (1)

Country Link
CN (1) CN102606174B (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0092307A1 (en) * 1982-03-24 1983-10-26 Caledonian Mining Company Limited Improvements in and relating to support arches for colliery tunnels
CN101832141A (en) * 2009-03-11 2010-09-15 中铁十三局集团有限公司 Method for connecting temporary supports of tunnel
CN201810323U (en) * 2010-10-21 2011-04-27 中铁三局集团有限公司 Bolt connection plate for connecting tunnel inverted arch steel frame with arch angle steel frame
CN202578717U (en) * 2012-04-18 2012-12-05 中铁隧道股份有限公司 Four-direction connection box for arch frame

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0092307A1 (en) * 1982-03-24 1983-10-26 Caledonian Mining Company Limited Improvements in and relating to support arches for colliery tunnels
CN101832141A (en) * 2009-03-11 2010-09-15 中铁十三局集团有限公司 Method for connecting temporary supports of tunnel
CN201810323U (en) * 2010-10-21 2011-04-27 中铁三局集团有限公司 Bolt connection plate for connecting tunnel inverted arch steel frame with arch angle steel frame
CN202578717U (en) * 2012-04-18 2012-12-05 中铁隧道股份有限公司 Four-direction connection box for arch frame

Also Published As

Publication number Publication date
CN102606174B (en) 2014-07-02

Similar Documents

Publication Publication Date Title
CN103572763B (en) Large-span steel supports pattern foundation pit supporting structure Demolition Construction method
US20120205336A1 (en) crane jib transition structure
CN204139459U (en) Regeneration concrete hetermorphiscal column
CN109747775A (en) The parallel building technology of FPSO modular unitization
CN103410101A (en) Tower crane conversion method for construction of parabola-shaped ultrahigh pier
CN205475854U (en) Roof beam wall composite external wall component
CN202250098U (en) Pipe piece lining structure capable of providing continuous counterforce action face used for shield tunnel
CN202578717U (en) Four-direction connection box for arch frame
CN203531483U (en) Tower body connection structure of single-pipe tower and single-pipe tower
CN206457955U (en) A kind of oblique close rib composite wall board structure
CN102606174B (en) Four-direction connection box for lagging jacks
CN204434123U (en) Tower body in tower crane resistance to deformation
CN204571353U (en) A kind of building structure single tube bracing or strutting arrangement
CN104440766B (en) A kind of disassembling fixture of interference bolt and method
CN202672484U (en) Steel pipe single-post structure
CN202440851U (en) Structure for supporting construction elevator foundation on basement top plate
CN104358355A (en) Detachable column base fixing device and construction method thereof
CN206092009U (en) A convenient to detach component for underground works prefab
CN100585113C (en) The method of climbing system for building construction throwing over barrier
CN203452056U (en) Diversion tunnel gate lifting device
CN204238951U (en) Three-dimensional space curved surface combined type top die set device
CN202006362U (en) Special dismounting tool for high-pressure upper inner casing of steam turbine
CN103132495B (en) Integral building and carrying method for drilling platform
CN204238830U (en) A kind of gate, assembly type building site
CN204060733U (en) One is applicable to embedded portal section of jurisdiction, shield construction tunnel plucking device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140702

CF01 Termination of patent right due to non-payment of annual fee