Preliminary supporting bag cast isolation wall and placing method thereof Download PDFInfo
- Publication number
- CN102587942A CN102587942A CN2012100689710A CN201210068971A CN102587942A CN 102587942 A CN102587942 A CN 102587942A CN 2012100689710 A CN2012100689710 A CN 2012100689710A CN 201210068971 A CN201210068971 A CN 201210068971A CN 102587942 A CN102587942 A CN 102587942A
- Authority
- CN
- China
- Prior art keywords
- pillar
- flexible membrane
- struts
- casting
- fixed
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Tents Or Canopies (AREA)
Abstract
The invention relates to a preliminary supporting bag cast isolation wall and a placing method thereof. The preliminary supporting bag cast isolation wall consists of struts, flexible membrane bags and cement solidifying materials, the struts are disposed on the outer layer of the preliminary supporting bag cast isolation wall, the flexible membrane bags are fixed on the struts, and the cement solidifying materials are arranged in the flexible membrane bags. The struts are single columns or concrete upright columns or mining anchor columns with upright column supporting performances. During implementation, the struts are punched at designed positions of a top plate and a bottom plate at the rear of a back production support of a coal face at first, and the top plate and the bottom plate are anchored together to realize dual effects including an anchoring effect and a supporting effect. The flexible membrane bags are fixed by the aid of the struts or anchor bolts and anchor cables of the top plate, and the cement solidifying materials are poured in the membrane bags. The isolation wall and the placing method are applicable to quick gob-side entry retaining construction. The invention is particularly suitable for gob-side entry retaining isolation walls of steep seams. More importantly, the shortcoming that an isolation wall in the prior art does not have timing supporting ability is overcome, and the problem that the top plate is unsupported or the top plate is damaged artificially due to the fact that the top plate is supported repeatedly is avoided. Construction speed is fast, efficiency is high, and a construction effect is good.
Description
Technical field
The invention belongs to coal mining engineering field, be specifically related to a kind of preparatory support pouches casting divider wall and placing method thereof.
Background technology
Traditional mining activity face gob-side entry retaining adopts grillage, close standing props, spoil bag, work stone is built a wall or concrete continuous wall as roof supporting.Grillage, close standing props supporting intensity hang down and can not satisfy most of requirement of engineering.Spoil bag, work stone are built a wall can not connect to push up and are caused the excessive sinking of top board to make supporting effect not good.Though high water filling material and gentle mould concrete have solved divider wall and have in time connect the top problem.But can not solve body of wall and in time top board applied support force.Do not cause roof collapse can have a strong impact on production and safety in some cases easily and pay support timely in advance.If adopt traditional hydraulic prop high and have the pressure release situation and take place as the supporting member cost.And the gob side entry retaining divider wall will can be good at adapting to the supporting member that efficient stoping operation just must have certain setting load.
Summary of the invention
The objective of the invention is to be the deficiency to prior art, a kind of safety in production is provided, and supporting effect is good, has the preparatory support pouches casting divider wall and the placing method thereof of timely enabling capabilities.
For realizing above-mentioned purpose, the technical scheme that the present invention adopts is:
A kind of preparatory support pouches casting divider wall is characterized in that by being arranged on outer field pillar, being fixed in flexible membrane bag and the flexible membrane bag on the pillar glued curing materials and forming.
Support pouches is cast the placing method of divider wall in advance, may further comprise the steps:
1) at first at the peripheral mounting column of design isolated wall;
2) the flexible membrane bag is fixed on when pillar is installed on the top board simultaneously or install pillar after be fixed on the pillar;
3), solidify the back and form preparatory support pouches casting divider wall through fill orifice concreting in bag of flexible membrane bag
Said pillar is that monomer column or concrete column or mining anchor post with upright supports performance are processed.
Support pouches is cast the placing method of divider wall in advance, may further comprise the steps:
1) sets anchor pole or anchor cable at the roof and floor design attitude;
2) anchor pole that sets at roof and floor or anchor cable position are provided with pillar and are connected with ground crab-bolt or anchor cable;
3) apply support force to pillar, accomplish pillar and install;
4) the flexible membrane bag is fixed on when pillar is installed on the top board simultaneously or install pillar after be fixed on the pillar;
5), solidify the back and form preparatory support pouches casting divider wall through the glued curing materials of fill orifice placing in bag of flexible membrane bag.
The present invention compared with prior art has the following advantages:
1) the placing method of support pouches casting divider wall is simple, easy to use in advance.
2) with the present invention top board and base plate are anchored at and form anchoring together and support double action.
3) be adapted to the divider wall that sharp gob side entry retaining is constructed, be particularly suitable for the gob side entry retaining divider wall of half-edge coal seam.
Description of drawings
Fig. 1 is a divider wall plan structure sketch map.
Fig. 2 is the partition wall construction view.
Fig. 3 is the pier construction sketch map.
Description of reference numerals:
The 1-top end cover;
The 2-inner carrier;
The 3-outer piston;
The 4-injected hole;
The 5-bottom cover;
The 6-tight locking button;
7-expansion cementitious materials;
The 8-top board;
The 9-anchor pole;
The 10-base plate;
11-flexible membrane bag;
The 12-pillar;
The 13-concrete.
The specific embodiment
Like Fig. 1, a kind of preparatory support pouches casting divider wall shown in 2, it is characterized in that forming by the flexible membrane bag 11 and the flexible membrane bag inner concrete 13 that are arranged on outer field pillar 12, be fixed on the pillar 12.
Support pouches is cast the placing method of divider wall in advance, may further comprise the steps:
1) at first at the peripheral mounting column 12 of design isolated wall;
2) when pillar 12 is installed, be fixed on the top board simultaneously flexible membrane bag 11 or install pillar 12 after be fixed on the pillar 12;
3), solidify the back and form preparatory support pouches casting divider wall through fill orifice concreting 13 in bag of flexible membrane bag 11.
As shown in Figure 3, pillar 12 is by outer field outer piston 3, and inner carrier 2 two parts that are arranged in the outer piston 3 constitute; Inner carrier 2 upper ends are provided with the top end cover 1 that is used to lock the top crab-bolt; Outer piston 3 lower ends are provided with the bottom cover 5 that is used to connect the ground crab-bolt; Outer piston 3 is provided with the tight locking button 6 that is used to prevent the inner carrier downslide with inner carrier 2 contact portions, and outer piston 3 lower ends are provided with injected hole 4.
Said outer piston 3 internal layers are filled with glued curing materials 7.
Support pouches is cast the placing method of divider wall in advance, may further comprise the steps:
6) set anchor pole 9 or anchor cable at the roof and floor design attitude;
7) bottom cover 5 of pillar 12 is connected with ground crab-bolt or anchor cable;
8) utilize grouting equipment to pass through the inner carrier 2 that grouting port 4 reperfusion serosities rise pillar 12;
9) top end cover 1 was connected with top crab-bolt 9 or anchor cable after inner carrier 2 rose;
10) slurry coagulation forming in the outer piston 3, pillar 12 is accomplished and is installed;
11) when pillar 12 is installed, be fixed on the top board simultaneously flexible membrane bag 11 or install pillar 12 after be fixed on the pillar 12;
12), solidify the back and form preparatory support pouches casting divider wall through fill orifice concreting 13 in bag of flexible membrane bag 11.
This divider wall is simple in structure, and is easy to use, and speed of application is fast, and efficiency is high, and supporting effect is good.These apparatus and method can be widely used in colliery, metallurgical mine, water conservancy, underground building, civil engineering industries such as national defence.
Claims (4)
1. preparatory support pouches casting divider wall is characterized in that by being arranged on outer field pillar, being fixed in flexible membrane bag and the flexible membrane bag on the pillar glued curing materials and forming.
2. preparatory support pouches casting divider wall according to claim 1 is characterized in that said pillar is that monomer column or concrete column or the mining anchor post with upright supports performance processed.
3. like the placing method of claim 1,2 described preparatory support pouches casting divider walls, may further comprise the steps:
1) sets anchor pole or anchor cable at the roof and floor design attitude;
2) anchor pole that sets at roof and floor or anchor cable position are provided with pillar and are connected with ground crab-bolt or anchor cable,
3) apply support force to pillar, accomplish pillar and install;
4) the flexible membrane bag is fixed on when pillar is installed on the top board simultaneously or install pillar after be fixed on the pillar;
5), solidify the back and form preparatory support pouches casting divider wall through the glued curing materials of fill orifice placing in bag of flexible membrane bag.
4. the placing method of preparatory support pouches casting divider wall as claimed in claim 1 may further comprise the steps:
1) at first at the peripheral mounting column of design isolated wall;
2) the flexible membrane bag is fixed on when pillar is installed on the top board simultaneously or install pillar after be fixed on the pillar;
3), solidify the back and form preparatory support pouches casting divider wall through fill orifice concreting in bag of flexible membrane bag.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012100689710A CN102587942A (en) | 2012-03-15 | 2012-03-15 | Preliminary supporting bag cast isolation wall and placing method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012100689710A CN102587942A (en) | 2012-03-15 | 2012-03-15 | Preliminary supporting bag cast isolation wall and placing method thereof |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102587942A true CN102587942A (en) | 2012-07-18 |
Family
ID=46477109
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2012100689710A Pending CN102587942A (en) | 2012-03-15 | 2012-03-15 | Preliminary supporting bag cast isolation wall and placing method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102587942A (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103334774A (en) * | 2013-06-05 | 2013-10-02 | 惠兴田 | Externally-anchored mining anchor column and construction method thereof |
CN103603681A (en) * | 2013-11-06 | 2014-02-26 | 神华集团有限责任公司 | Support separation wall and construction method thereof |
CN104405404A (en) * | 2014-11-14 | 2015-03-11 | 山东科技大学 | Mine gas tail roadway reservation method |
CN106285738A (en) * | 2016-09-28 | 2017-01-04 | 山东科技大学 | A kind of " steel reinforced concrete hydraulic pressure " roadside support device for deep tunnel and method for protecting support |
CN106870001A (en) * | 2017-02-21 | 2017-06-20 | 长沙矿山研究院有限责任公司 | Tunnel is layered pocket type self-support filling counterfort construction method |
CN107524470A (en) * | 2017-08-21 | 2017-12-29 | 长沙有色冶金设计研究院有限公司 | A kind of method of geotechnical fabric bag and rapid build artificial ore pillar |
CN109057829A (en) * | 2018-09-06 | 2018-12-21 | 山东科技大学 | A kind of the siccative finished bag and method of built-in water pocket group |
-
2012
- 2012-03-15 CN CN2012100689710A patent/CN102587942A/en active Pending
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103334774A (en) * | 2013-06-05 | 2013-10-02 | 惠兴田 | Externally-anchored mining anchor column and construction method thereof |
CN103603681A (en) * | 2013-11-06 | 2014-02-26 | 神华集团有限责任公司 | Support separation wall and construction method thereof |
CN103603681B (en) * | 2013-11-06 | 2016-08-17 | 神华集团有限责任公司 | A kind of support divider wall and construction method thereof |
CN104405404A (en) * | 2014-11-14 | 2015-03-11 | 山东科技大学 | Mine gas tail roadway reservation method |
CN106285738A (en) * | 2016-09-28 | 2017-01-04 | 山东科技大学 | A kind of " steel reinforced concrete hydraulic pressure " roadside support device for deep tunnel and method for protecting support |
CN106285738B (en) * | 2016-09-28 | 2018-10-16 | 山东科技大学 | A kind of " steel reinforced concrete-hydraulic pressure " roadside support device and method for protecting support for deep tunnel |
CN106870001A (en) * | 2017-02-21 | 2017-06-20 | 长沙矿山研究院有限责任公司 | Tunnel is layered pocket type self-support filling counterfort construction method |
CN106870001B (en) * | 2017-02-21 | 2019-05-21 | 长沙矿山研究院有限责任公司 | Tunnel is layered pocket type self-support filling counterfort construction method |
CN107524470A (en) * | 2017-08-21 | 2017-12-29 | 长沙有色冶金设计研究院有限公司 | A kind of method of geotechnical fabric bag and rapid build artificial ore pillar |
CN107524470B (en) * | 2017-08-21 | 2020-02-11 | 长沙有色冶金设计研究院有限公司 | Geotechnical formwork bag and method for quickly constructing artificial ore pillar |
CN109057829A (en) * | 2018-09-06 | 2018-12-21 | 山东科技大学 | A kind of the siccative finished bag and method of built-in water pocket group |
CN109057829B (en) * | 2018-09-06 | 2023-12-15 | 山东科技大学 | Dry material finished product bag with built-in water bag group and method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102587942A (en) | Preliminary supporting bag cast isolation wall and placing method thereof | |
CN103321654B (en) | The method of flexible air-bag process coal mine roadway roof collapse | |
CN203756206U (en) | Novel soft-rock roadway floor heave governing structure | |
CN205530247U (en) | Prebored hole bag slip casting stock structure | |
CN103485349B (en) | Lime nail composite frame prestressed anchor tube structure and construction method for reinforcing weak slope | |
CN205025479U (en) | Administer bottom plate support system of soft rock tunnel pucking | |
CN203755334U (en) | Single-pipe tower prefabricated spiral steel pipe pile foundation | |
CN203213136U (en) | Caisson and pile combined foundation of consolidated subsoil | |
CN102352601A (en) | Tunnel type composite anchorage | |
CN103758549A (en) | Sequential filling-anchoring prestress full-length anchorage supporting method on basis of paste materials | |
CN111022085A (en) | Pre-empty soft rock roadway supporting structure and construction method thereof | |
CN2926319Y (en) | Rooted foundation and anchored topped-push construction set apparatus | |
CN102852551A (en) | Gob-side entry retaining method using high-water material filling columns | |
CN105019924A (en) | Strong roof support pier column and method for protecting section coal pillar | |
CN201486566U (en) | Device for pouring concrete continuous wall through gob-side entry retaining of mining working surface | |
CN101967983A (en) | Method for over-dredging, anchoring, backfilling and controlling deep well rock roadway floor heave | |
CN103215889A (en) | Arch bridge foundation used on bad geological conditions and construction method of arch bridge foundation | |
CN105114099B (en) | A kind of weak consolidated formation laneway support method and support system | |
CN201835869U (en) | Gob-side retained entry reinforcing fill structure | |
CN209260749U (en) | A kind of prefabricated Rock Bolt Foundation of mountain area iron tower of power transmission line half | |
CN202578720U (en) | Mining anchor post | |
CN105696620A (en) | Earth-retaining wall structure composed of waste tire-broken concrete, and construction method | |
CN101806040B (en) | Underpinning device and method for bridge and building | |
CN205444236U (en) | Retaining wall structure that broken concrete of junked tire - constitutes | |
CN203049577U (en) | Complete recovery type non-grouting anchor grasping anchor cable timbering structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20120718 |