A kind of totally-enclosed building energy conservation door window auxiliary frame
Technical field
The present invention relates to window frame, relate in particular to a kind of outer door window auxiliary frame.
Background technology
Along with the development of Building Trade in China technology, construction engineering quality is corresponding to be greatly improved, but building doors and windows is installed but still according to outmoded a set of installation way: with reference to architectural design door and window hole dimensional requirement, take first box out mouth, rear mounting door-window housing, carry out door and window peripheral joint filling again and whitewash, assemble the technological process of bar and complete erection of doors and windows engineering.At this point, the impact of all many factors of construction formwork, cast, building block etc. while being subject to civil engineering due to the standardization at hole and can not one-time-reach-place, need to smear and be solved by artificial powder, the so not only time-consuming expense material of taking a lot of work, and door and window hole inside and outside surrounding whitewash while construct with joint filling, multiplex (MUX) plants cooperation and unavoidably can cause serious secondary pollution and the damages of generation such as door and window housing to having installed.Even if the door and window of having installed is also of no avail through second protection.Also easily produce because door and window peripheral is filled out and met leakiness to cause the problems such as seepage.Also there is at present application steel auxiliary frame to want to solve hole standardization issue, still, also can be due to sealing in actual application, preservative treatment is not in place, easily produces seepage, corrosion, forms the problems such as potential safety hazard, cost is also higher in addition.Particularly now general housing construction all will adopt architectural exterior insulation, and installation steel auxiliary frame can not solve energy saving door and window " cold bridge " problem of heat-insulation and heat-preservation.Current building needs external wall body thermal insulation and erection of doors and windows hole to comprise side Full enclosed integrated, realizes building doors and windows energy conservation standard in addition.
Summary of the invention
Goal of the invention: the object of the invention is to solve the problems such as the seepage that exists in building doors and windows installation in prior art, burn into cost, a kind of simple in structure, heat-insulation and heat-preservation, environmental protection and energy saving, cost economy, easy for installation are provided, realize building doors and windows completely the standardized secondary frame in hole is installed, this secondary frame can totally-enclosed building doors and windows installation hole, realize completely full building doors and windows brand-new, that be not subject to any pollution paid to user; Thoroughly solve current building outer wall insulation and erection of doors and windows vertical side Full enclosed integrated; Thoroughly solve erection of doors and windows and be connected contradiction and seepage problem with the construction at civil engineering hole; Greatly shortened " cold bridge " problem of erection of doors and windows duration and building energy conservation door and window; Fire protection flame retarding, improves safety and effectiveness.
Technical scheme: in order to solve the problems of the technologies described above, the present invention has adopted the totally-enclosed door window auxiliary frame of such one, comprise corner brace, the material modified secondary deckle board piece of making of environmental friendly regenerated composite plastic wood, this pair deckle board piece connects to form totally-enclosed secondary frame by corner brace, at described totally-enclosed secondary frame medial surface, be provided with a communication groove, described totally-enclosed secondary frame is connected by the fixed installation of primary and secondary fastener with door and window, in described communication groove, coupling has secondary frame fastener for installing, described secondary frame fastener for installing is fixedly connected with erection of doors and windows fastener, described door and window dress fastener is connected on building doors and windows section bar.
Totally-enclosed secondary frame of the present invention is comprised of lower secondary deckle board piece, the secondary deckle board piece of side and upper secondary deckle board piece, the secondary deckle board piece of described lower secondary deckle board piece, side and upper secondary deckle board piece are cavity plate, and described totally-enclosed secondary frame and wall connecting one side are vertical bar kerve shape.
Lower secondary deckle board piece of the present invention is outer lateral incline in the plane one end at described communication groove place, and described outer lateral incline and described plane junction are cambered surface.
The secondary deckle board piece of secondary deckle board piece of the present invention and side is the secondary deckle board piece of decorating surface brick or the secondary deckle board piece of common facing.
The secondary deckle board piece of decorating surface brick of the present invention is outer lateral incline in the plane one end at described communication groove place.
The secondary deckle board piece of common facing of the present invention is horizontal plane at the plane two ends at described communication groove place.
Communication groove of the present invention is arranged on the middle part of described totally-enclosed secondary frame medial surface.
Secondary frame fastener for installing of the present invention forms one by a level board and a vertical panel, has at least one group of connecting hole on described level board, has an installing hole being connected with described erection of doors and windows fastener on described vertical panel.
Erection of doors and windows fastener of the present invention forms one by a level board and a vertical panel, at described level board two ends, is provided with U-shaped interface, and on described vertical panel, has an installing hole being connected with described secondary frame fastener for installing.
Beneficial effect: the totally-enclosed building energy conservation door window auxiliary frame of the present invention, simple in structure, heat-insulation and heat-preservation, environmental protection and energy saving, cost economy, easy for installation, realize building doors and windows completely hole standardization is installed, thoroughly solve the construction integrated of current building outer wall insulation and erection of doors and windows hole, thoroughly solved erection of doors and windows and be connected contradiction and seepage problem with the construction at civil engineering hole; Greatly shortened " cold bridge " problem of erection of doors and windows duration and building energy conservation door and window; Fire protection flame retarding, improves safety and effectiveness.Change traditional erection of doors and windows technique, realize completely full building doors and windows brand-new, that be not subject to any pollution is paid to user.
Accompanying drawing explanation
Fig. 1 is secondary frame connection layout of the present invention;
Fig. 2 is the structural representation of upper secondary deckle board piece, the secondary deckle board piece of side and lower secondary deckle board piece;
Fig. 3 is the structural representation of secondary frame fastener for installing and erection of doors and windows fastener;
Fig. 4 is the secondary deckle board piece of common facing scheme of installation;
Fig. 5 is the secondary deckle board piece of decorating surface brick scheme of installation;
Fig. 6 is lower secondary deckle board piece and wall connecting schematic diagram.
The specific embodiment
Embodiment 1: as shown in Figure 1, Figure 2, shown in Fig. 3, Fig. 4, Fig. 6, totally-enclosed building energy conservation door window auxiliary frame, by the secondary deckle board piece 24 of common facing and the secondary deckle board piece 27 of blanking, formed, described secondary deckle board piece 10, the secondary deckle board piece 9 of side are the secondary deckle board piece of common facing 24 materials, and described lower secondary deckle board piece 8 is the secondary deckle board piece of blanking 27 materials; It comprises corner brace 1, the material modified secondary deckle board piece 2 of making of environmental friendly regenerated composite plastic wood, the material modified secondary deckle board piece 2 of making of this environmental friendly regenerated composite plastic wood connects to form totally-enclosed secondary frame 3 by corner brace 1, totally-enclosed secondary frame 3 medial surfaces that are formed by connecting by the material modified secondary deckle board piece 2 of making of described environmental friendly regenerated composite plastic wood are provided with a communication groove 4, in the interior coupling of described communication groove 4, there is secondary frame fastener for installing 5, described secondary frame fastener for installing 5 is fixedly connected with door window section fastener for installing 6, and described erection of doors and windows fastener 6 is connected on building doors and windows section bar 7; Described totally-enclosed secondary frame 3 is comprised of lower secondary deckle board piece 8, the secondary deckle board piece 9 of side and upper secondary deckle board piece 10, described lower secondary deckle board piece 8, the secondary deckle board piece 9 of side and upper secondary deckle board piece 10 are cavity plate, being convenient to end face adopts corner brace 1 to connect, and described totally-enclosed secondary frame 3 is connected a side with body of wall 11 be that totally-enclosed secondary frame 3 adopts vertical bar kerve shape by body of wall 11 one sides, make whole totally-enclosed secondary frame 3 there is better mechanical property, resistance to deformation, nail-holding ability is strong, and cost is low; Described communication groove 4 is arranged on the middle part of described totally-enclosed secondary frame 3 medial surfaces; Described secondary frame fastener for installing 5 is comprised of a level board 12 and a vertical panel 13, on described level board 12, has at least one group of connecting hole 14, has an installing hole 15 being connected with described erection of doors and windows fastener 6 on described vertical panel 13; Described erection of doors and windows fastener 6 comprises a level board 16 and a vertical panel 17, at described level board 16 two ends, is provided with U-shaped interface 18, and on described vertical panel 17, has an installing hole 19 being connected with described secondary frame fastener for installing 5; Described lower secondary deckle board piece 8 is outer lateral incline 21 in plane 20 one end at described communication groove 4 places, and in order to rainwater water conservancy diversion, described outer lateral incline 21 is cambered surface 22 with described plane 20 junctions; The secondary frame 24 of described common facing is horizontal plane 26 at the plane two ends at described communication groove 4 places, whole totally-enclosed secondary frame 3 and materials for wall, comprise that cement slurry, coating, glue etc. have good adhesion stress, there is good heat-proof quality, hole is totally-enclosed, saved the wall thermal insulating of building doors and windows vertical side, solved the integrated of building outer wall insulation and erection of doors and windows hole, thoroughly solved erection of doors and windows and be connected contradiction and seepage problem with the construction at civil engineering hole; Greatly shortened " cold bridge " problem of erection of doors and windows duration and building energy conservation door and window; Fire protection flame retarding, improves safety and effectiveness.Change traditional erection of doors and windows technique, realize completely full building doors and windows brand-new, that be not subject to any pollution is paid to user.
Embodiment 2: as shown in Figure 1, Figure 2, shown in Fig. 3, Fig. 5, Fig. 6, totally-enclosed building energy conservation door window auxiliary frame, by the secondary deckle board piece 23 of decorating surface brick and the secondary deckle board piece 27 of blanking, formed, described secondary deckle board piece 10, the secondary deckle board piece 9 of side are the secondary deckle board piece of decorating surface brick 23 materials, and described lower secondary deckle board piece 8 is the secondary deckle board piece of blanking 27 materials; It comprises corner brace 1, the material modified secondary deckle board piece 2 of making of environmental friendly regenerated composite plastic wood, the material modified secondary deckle board piece 2 of making of this environmental friendly regenerated composite plastic wood connects to form totally-enclosed secondary frame 3 by corner brace 1, totally-enclosed secondary frame 3 medial surfaces that are formed by connecting by the material modified secondary deckle board piece 2 of making of described environmental friendly regenerated composite plastic wood are provided with a communication groove 4, in the interior coupling of described communication groove 4, there is secondary frame fastener for installing 5, described secondary frame fastener for installing 5 is fixedly connected with erection of doors and windows fastener 6, and described erection of doors and windows fastener 6 is connected on building doors and windows section bar 7; Described totally-enclosed secondary frame 3 is comprised of lower secondary deckle board piece 8, the secondary deckle board piece 9 of side and upper secondary deckle board piece 10, described lower secondary deckle board piece 8, the secondary deckle board piece 9 of side and upper secondary deckle board piece 10 are cavity plate, being convenient to end face adopts corner brace 1 to connect, and described totally-enclosed secondary frame 3 is connected a side with body of wall 11 be that totally-enclosed secondary frame 3 adopts vertical bar kerve shape by body of wall 11 one sides, make whole totally-enclosed secondary frame 3 there is better mechanical property, resistance to deformation, nail-holding ability is strong, and cost is low; Described communication groove 4 is arranged on the middle part of described totally-enclosed secondary frame 3 medial surfaces; Described secondary frame fastener for installing 5 is comprised of a level board 12 and a vertical panel 13, on described level board 12, has at least one group of connecting hole 14, has an installing hole 15 being connected with described erection of doors and windows fastener 6 on described vertical panel 13; Described erection of doors and windows fastener 6 comprises a level board 16 and a vertical panel 17, at described level board 16 two ends, is provided with U-shaped interface 18, and on described vertical panel 17, has an installing hole 19 being connected with described secondary frame fastener for installing 5; Described lower secondary deckle board piece 8 is outer lateral incline 21 in plane 20 one end at described communication groove 4 places, and described outer lateral incline 21 is cambered surface 22 with described plane 20 junctions; The secondary deckle board piece 23 of described decorating surface brick is outer lateral incline 25 in the plane one end at described communication groove 4 places, whole totally-enclosed secondary frame 3 and materials for wall, comprise that cement slurry, coating, glue etc. have good adhesion stress and good thermal process performance, coefficient of thermal conductivity is low, saved the wall thermal insulating of building doors and windows vertical side and solved the integrated of building outer wall insulation and erection of doors and windows hole, thoroughly solved erection of doors and windows and be connected contradiction and seepage problem with the construction at civil engineering hole; Greatly shortened " cold bridge " problem of erection of doors and windows duration and building energy conservation door and window; Fire protection flame retarding, improves safety and effectiveness, changes traditional erection of doors and windows technique, realizes completely full building doors and windows brand-new, that be not subject to any pollution is paid to user.