CN207017708U - Piping lane formula computer room - Google Patents
Piping lane formula computer room Download PDFInfo
- Publication number
- CN207017708U CN207017708U CN201720934749.2U CN201720934749U CN207017708U CN 207017708 U CN207017708 U CN 207017708U CN 201720934749 U CN201720934749 U CN 201720934749U CN 207017708 U CN207017708 U CN 207017708U
- Authority
- CN
- China
- Prior art keywords
- computer room
- concatenation unit
- box concatenation
- box
- main body
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Abstract
This application discloses a kind of piping lane formula computer room, including backing plate, the computer room main body being arranged on backing plate and the roof being arranged on above computer room main body, computer room main body includes multiple box concatenation units, the rear ends of box concatenation unit are outward extended with a circle split side respectively, the split side alignment of rear and front end, front and rear adjacent box concatenation unit is bolted, after the completion of box concatenation unit splicing, offset to form groove between two split sides of two adjacent box concatenation units, in a groove provided with waterproof construction.The utility model has easy for installation, the high beneficial effect of installation effectiveness.
Description
Technical field
It the utility model is related to a kind of assembled computer room, more particularly to the piping lane formula computer room that length is larger.
Background technology
Traditional machine room needs to excavate by civil engineering, pours maintenance etc., long construction period, cost are big, efficiency is low, traditional machine room
It can not meet that steel tower company quickly builds a station demand.
For piping lane formula computer room, because its volume is larger, the length of in general piping lane formula computer room can reach more than ten meters to two
More than ten meters, directly pour it is very inconvenient, in the form of wallboard is spliced install, assembled efficiency is low, and the wall during assembly
The position alignment of plate is extremely difficult.
The content of the invention
In order to solve the above problems, it is an object of the invention to provide a kind of easy to assembly, be advantageous to improve efficiency of construction
Piping lane formula computer room.
In order to realize above-mentioned purpose, present invention employs following technical scheme:
A kind of piping lane formula computer room, including backing plate, the computer room main body being arranged on backing plate and are arranged on above computer room main body
Roof, computer room main body includes multiple box concatenation units, and box concatenation unit is by epipleural, bottom plate, left plate and right side
The case structure of the front and rear insertion of plate composition, the rear ends of box concatenation unit are outward extended with a circle split side respectively, preceding
The split side alignment at both ends afterwards, the rear and front end of box concatenation unit is respectively equipped with multiple bolted connections, the spiral shell of rear and front end
Socket part is tethered to be oppositely arranged, front and rear adjacent box concatenation unit is bolted, after the completion of box concatenation unit splicing, phase
Offset to form groove between two split sides of two adjacent box concatenation units, it is thick poly- by being set gradually outside Intranet in a groove
Ester waterproof coating, solid cement mortar levelling layer, fibrous mesh cloth and solid cement mortar cover, and in the box splicing list at both ends
Splice prefabricated panel with the rear ends of closing machine house-owner's body in the rear and front end of member.Computer room main body is used as using box concatenation unit
Minimum concatenation unit, be advantageous to improve splicing efficiency.The structure of the splicing edge of the rear ends of box concatenation unit is identical, builds
It is convenient to pour mould, and above-mentioned waterproof construction is set, advantageously ensures that computer room main body has good water proofing property.
Preferably, the installation position of machine room door is reserved with prefabricated panel or box concatenation unit.
It is arranged on as the preferred bolted connection at the corner connection of box two adjacent side plates of concatenation unit.
In summary, above-mentioned piping lane formula computer room, there is easy for installation, the high beneficial effect of installation effectiveness.
Brief description of the drawings
Fig. 1 is the side structure schematic diagram on the utility model length direction.
Fig. 2 is the side structure schematic diagram on the utility model width.
The splicing construction schematic diagram of two neighboring box-type unit in Fig. 3 the utility model.
Fig. 4 is the sealed structural representation after the completion of two neighboring box-type unit splicing in the utility model.
Wherein:1st, backing plate, 2, computer room main body, 21, box concatenation unit, 211, split side, 212, bolted connection, 22,
Prefabricated panel, 3, roof, 4, high-strength bolt, 51, solid cement mortar cover, 52, fibrous mesh cloth, 53, solid cement mortar
Screed-coat, 54, thick polyester waterproof film.
Embodiment
The preferred embodiment of this patent is described in further detail below in conjunction with the accompanying drawings.
A kind of piping lane formula computer room as shown in Figure 1-Figure 3, including backing plate 1, the computer room main body 2 being arranged on backing plate and set
Put the roof 3 above computer room main body.
Computer room main body includes multiple box concatenation units 21, and box concatenation unit is poured using armored concrete at the construction field (site)
Build to be formed, box-type unit presets heat-insulation layer in pouring molding process, and the heat-insulation layer uses EPS warming plates, has good
Good function of heat insulation.Box concatenation unit 21 is the front and rear insertion being made up of epipleural, bottom plate, left plate and right plate
Rectangular configuration, the front and rear insertion of box concatenation unit, the rear ends of box concatenation unit are outward extended with a circle split respectively
Side 211, the structure on the split side of front and back end are identical.The thickness on split side is less than the thickness of the side plate of box concatenation unit, split
Step is formed between the respective side panels of side and box concatenation unit.The thickness on the split side is respective side panels on box concatenation unit
Thickness half, the width on split side is also the half of the thickness of respective side panels on box concatenation unit.Box concatenation unit
Rear and front end be respectively equipped with multiple bolted connections 212, the bolted connection 212 of rear and front end is oppositely arranged, the bolt
Connecting portion is arranged at the corner connection of two adjacent side plates of box-type unit, and adjacent two box concatenation units pass through high-strength bolt
4 connections, and offset to form groove between two split sides of adjacent two box concatenation units, after the completion of strengthening splicing
Computer room main body water proofing property, in a groove by setting gradually thick polyester waterproof film 54, solid cement mortar levelling layer outside Intranet
53rd, fibrous mesh cloth 52 and solid cement mortar cover 51.Using the box concatenation unit direct splicing of case structure into computer room
Main body 2, splicing is convenient, is advantageous to improve efficiency of construction.And using box concatenation unit 21 as minimum concatenation unit, compared to
Two wallboards are as concatenation unit, it is easier to alignment and splicing.Because the weight of box concatenation unit 21 itself is larger, during construction
Directly build at the construction field (site) and coordinate pouring molding with haydite concrete after mould, be then lifted into specified location carry out it is assembled.
Before computer room main body 2 is spliced, first specified location lay backing plate 1, computer room main body 2 be arranged on backing plate 1 with
Ensure that computer room main body is in plane.After the completion of box concatenation unit 21 splices, two before and after the box concatenation unit at both ends
End matching is connected prefabricated panel 22 and is provided with and the bolted connection with the rear ends of closing machine house-owner's body, prefabricated panel 22
The screw 221 matched somebody with somebody, is connected between prefabricated panel 22 and box concatenation unit 21 by high-strength bolt 4.Prefabricated panel 22
Or the installation position of machine room door is reserved with box concatenation unit 21.The length, width and height size of box concatenation unit in the present embodiment is
3m*5m*3m, the computer room of random length can be spliced into according to the actual requirements.After the completion of computer room main body is built, in computer room main body
Side is provided with roof 3.Roof can be flat two kinds of forms in roof or pitched roof, and during using flat roof, roof structure looks for slope to be equipped with room
Face waterproof.During using pitched roof, Sloping roof is equipped with color steel using lightgage steel joist and set up, and structure is more attractive in appearance.The roofing on roof
Also prefabricated roof-top unit spicing forming type is used, is easy to build and pours, the roof uses armored concrete at the construction field (site)
Pouring molding.After the completion of computer room is built, the outer on roof is located at the outside of computer room main body.
Claims (3)
1. a kind of piping lane formula computer room, including backing plate(1), the computer room main body that is arranged on backing plate(2)And it is arranged on computer room main body
The roof of top(3), it is characterised in that computer room main body includes multiple box concatenation units(21), box concatenation unit(21)For
The case structure for the front and rear insertion being made up of epipleural, bottom plate, left plate and right plate, the front and back end part of box concatenation unit
A circle split side is not outward extended with(211), the split side alignment of rear and front end, the rear and front end of box concatenation unit is set respectively
There are multiple bolted connections(212), the bolted connection of rear and front end(212)It is oppositely arranged, front and rear adjacent box splicing list
Member is bolted, box concatenation unit(21)After the completion of splicing, two split sides of adjacent two box concatenation units
Between offset to form groove, in a groove by setting gradually thick polyester waterproof film outside Intranet(54), solid cement mortar levelling layer
(53), fibrous mesh cloth(52)With solid cement mortar cover(51), and the rear and front end of the box concatenation unit at both ends is spelled
Connect prefabricated panel(22)With the rear ends of closing machine house-owner's body.
A kind of 2. piping lane formula computer room according to claim 1, it is characterised in that prefabricated panel(22)Or box concatenation unit
(21)On be reserved with the installation position of machine room door.
A kind of 3. piping lane formula computer room according to claim 1, it is characterised in that the bolted connection(212)It is arranged on
Box concatenation unit(21)At the corner connection of two adjacent side plates.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720934749.2U CN207017708U (en) | 2017-07-28 | 2017-07-28 | Piping lane formula computer room |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720934749.2U CN207017708U (en) | 2017-07-28 | 2017-07-28 | Piping lane formula computer room |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207017708U true CN207017708U (en) | 2018-02-16 |
Family
ID=61482031
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720934749.2U Expired - Fee Related CN207017708U (en) | 2017-07-28 | 2017-07-28 | Piping lane formula computer room |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207017708U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114439281A (en) * | 2022-02-25 | 2022-05-06 | 江苏惠民交通设备有限公司 | Assembled bus stop service room |
-
2017
- 2017-07-28 CN CN201720934749.2U patent/CN207017708U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114439281A (en) * | 2022-02-25 | 2022-05-06 | 江苏惠民交通设备有限公司 | Assembled bus stop service room |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107190884A (en) | A kind of new many high-rise hot-rolled steel section composite light-weight steel shear wall combined structure systems | |
CN103993679A (en) | Bolt connecting joint structure of low-rise fabricated composite wall house | |
CN105178502A (en) | Novel light composite batten exterior wall and assembling method thereof | |
KR101079646B1 (en) | A construction method for inside and outside insulation of structure using hybrid panel and formwork | |
CN106522359A (en) | Total-prefabricated rural residential class composite wall structure system and construction method thereof | |
CN206053106U (en) | A kind of precast concrete external wall panel | |
CN103352569A (en) | Construction method of integrally-poured architecture building | |
CN207017708U (en) | Piping lane formula computer room | |
CN207017440U (en) | Assembled computer room | |
CN108729692A (en) | A kind of method of construction of assembled Low-rise Lightweight system of steel residential structure | |
CN108643585A (en) | Precast concrete sandwich heat preservation Side fascia and its preparation construction method | |
CN205677114U (en) | Installation node for assembled inside casing light partition wall | |
CN207988131U (en) | A kind of integrated house | |
CN203412143U (en) | Wall body structure of integrally poured building house | |
CN207017705U (en) | A kind of piping lane formula computer room | |
CN103362235B (en) | Integrally-poured building house with wallboards integrating thermal insulating and templates | |
CN206205140U (en) | A kind of full assembled villages and small towns local-style dwelling houses class composite wall structure system | |
CN203412312U (en) | Thermal-insulating integrated template wallboard construction building | |
CN210529947U (en) | Assembled building body with external hanging plate | |
CN209011405U (en) | Keep the temperature floor support plate and floor system | |
CN207905160U (en) | A kind of bindiny mechanism at prefabricated buildings corner | |
CN203113514U (en) | Combined split-mounting-type house device | |
CN203626133U (en) | Thermal-insulating external wall panel with steel frame | |
CN103498512B (en) | A kind of assembled architecture wall beam stablizes syndeton | |
CN207934315U (en) | Assembled architecture multifunctional wall body plate |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180216 Termination date: 20190728 |
|
CF01 | Termination of patent right due to non-payment of annual fee |