CN102583163A - Steel wire rope symmetrically disassembling process flow for tower crane attachment device - Google Patents
Steel wire rope symmetrically disassembling process flow for tower crane attachment device Download PDFInfo
- Publication number
- CN102583163A CN102583163A CN2012100727229A CN201210072722A CN102583163A CN 102583163 A CN102583163 A CN 102583163A CN 2012100727229 A CN2012100727229 A CN 2012100727229A CN 201210072722 A CN201210072722 A CN 201210072722A CN 102583163 A CN102583163 A CN 102583163A
- Authority
- CN
- China
- Prior art keywords
- steel rope
- tower
- attachment device
- attached wall
- crane
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Working Measures On Existing Buildindgs (AREA)
- Jib Cranes (AREA)
Abstract
The invention provides steel wire rope symmetrically disassembling process flow for tower crane attachment device and relates to the technical field of constructional engineering. The process flow comprises the following steps: disassembling a wall attached device on the side of a lifting arm by using a crampon; disassembling the attached wall on the side of a balancing arm by a back rolling symmetrical steel wire rope device; and clearing and inspecting mechanical parts. The process flow is safe, practical, scientific and efficient and can guarantee construction safety and avoid the damage on the wall of a building to the maximum degree.
Description
Technical field:
The present invention relates to construction engineering technical field, be specifically related to a kind of steel rope symmetry dismantle processes flow process of tower crane attachment device.
Background technology:
Perfect day by day along with the development of society and Building technology; High-storey business has become the favorite in market at present; The construction characteristic of this type building is generally to adopt the reinforced concrete shear wall structure technology, and main body construction speed is fast, and the material and the member single-piece weight of palpus vertical transport are big; The vertical transportation machinery full-load operation, this has just proposed challenge for the vertical transport in the work progress; Fixedly the hoisting capacity of attached tower crane, operational height, construction cost can both satisfy the construction needs; In order to accomplish economical rationality, guarantee construction speed, to guarantee safety; Fixedly attached tower crane becomes the first-selection of each unit in charge of construction; But; The demolishing process of tower crane but exists a lot of potential safety hazards, and the therefore perfect fixedly dismounting construction method of attached tower crane has just become a new problem, has very realistic meanings.
Fixedly attached tower crane often adopts the method for the auxiliary suspention dismounting of tower machine suspension hook when attachment device is removed, and the method existence swing when removing the half of adhering member of equilibrium arm direction is big, operating personal is subject to injure shortcomings such as destruction metope finished product.
Summary of the invention:
The steel rope symmetry dismantle processes flow process that the purpose of this invention is to provide a kind of tower crane attachment device, is prone to row, science, efficient at its safety, has guaranteed that to greatest extent civilized construction and environment avoid pollution.
In order to solve the existing problem of background technology; The present invention adopts following technological process: at first use load hook that the wall-attaching equipment of crane arm side is removed; Prick symmetrical wire rope device through the back of the body then the attached wall of equilibrium arm side is removed, the component of machine of arrangement inspection at last.
Dead work before removing mainly contains the situation of understanding the camp site, the cleaning obstacle; Carry out the safety method work of telling somebody what one's real intentions are to participating in dismounting tower machine personnel, and the tower machine of being dismantled is carried out complete machine inspection work; Check no potential safety hazard, be equipped with the wheel crane of a 25T under the normal at the construction field (site) condition, required instrument and fragment data when being ready to dismantle.
Fall standard knot and be the standard knot that falls more than the first road attached wall, the process of falling standard knot is opposite with the process that the body of the tower standard knot is installed.
For safety and protection building finished product, use following method for dismounting: the utilization suspension hook is removed the attached wall of crane arm one side earlier when removing attached wall, apart from equilibrium arm and cat head frame hinged place middle part, about 1.5 meters a fixed pulley is being installed again.Suspension hook drops down onto apart from ground about 1 meter, and steel rope and the master winch steel rope of φ 9 is locked, passes pulley and drops down onto lifting rope on the Ground lock, and the suspension hook that hoists hangs the attached wall of equilibrium arm one side and removes with the steel rope of φ 9.The ring beam framework that hangs equilibrium arm one side with the steel rope of φ 9 is again removed.Dismantle the at last steel rope of φ 9 is removed the ring beam framework of crane arm one side with the crane arm suspension hook.One attached wall removed and finished.Repeat above-mentioned steps the tower machine is reduced to height of foundation.
The present invention has following beneficial effect: its safety, be prone to row, science, efficient, guaranteed that to greatest extent civilized construction and environment avoid pollution.
The specific embodiment:
This specific embodiment adopts following technological process: at first, use load hook that the wall-attaching equipment of crane arm side is removed, prick symmetrical wire rope device through the back of the body then the attached wall of equilibrium arm side is removed, the component of machine of arrangement inspection at last.
Dead work before removing mainly contains the situation of understanding the camp site, the cleaning obstacle; Carry out the safety method work of telling somebody what one's real intentions are to participating in dismounting tower machine personnel, and the tower machine of being dismantled is carried out complete machine inspection work; Check no potential safety hazard, be equipped with the wheel crane of a 25T under the normal at the construction field (site) condition, required instrument and fragment data when being ready to dismantle.
Fall standard knot and be the standard knot that falls more than the first road attached wall, the process of falling standard knot is opposite with the process that the body of the tower standard knot is installed.
For safety and protection building finished product, use following method for dismounting: the utilization suspension hook is removed the attached wall of crane arm one side earlier when removing attached wall, apart from equilibrium arm and cat head frame hinged place middle part, about 1.5 meters a pulley is being installed again.Suspension hook drops down onto apart from ground about 1 meter, and steel rope and the master winch steel rope of φ 9 is locked, passes pulley and drops down onto lifting rope on the Ground lock, and the suspension hook that hoists hangs the attached wall of equilibrium arm one side and removes with the steel rope of φ 9.The ring beam framework that hangs equilibrium arm one side with the steel rope of φ 9 is again removed.Dismantle the at last steel rope of φ 9 is removed the ring beam framework of crane arm one side with the crane arm suspension hook.One attached wall removed and finished.Repeat above-mentioned steps the tower machine is reduced to height of foundation.
The technological principle of this specific embodiment is: at first with after the tower machine adjustment balance; Remove the ring beam framework and the strut of the half of attachment device of crane arm direction with the suspention of tower machine suspension hook in advance; When the ring beam framework of the half of attachment device of removing the crane arm direction; The ring beam framework of wanting earlier the equilibrium arm direction to be adhered to ties with three boomers and standard knot, comes off when preventing the removal flange bolt.The back of the body is pricked steel rope on the master winch rope then, and ring beam framework and strut that the mode that makes the back of the body prick steel rope and the synchronized operation of master winch rope is adhered to the equilibrium arm direction are removed.
This specific embodiment safety, be prone to row, science, efficient, guaranteed that to greatest extent civilized construction and environment avoid pollution.
Claims (4)
1. the steel rope of tower crane attachment device symmetry dismantle processes flow process; It is characterized in that its technological process is: at first use load hook that the wall-attaching equipment of crane arm side is removed; Through being pricked symmetrical wire rope device the attached wall of equilibrium arm side is removed the component of machine of arrangement inspection at last then.
2. the steel rope symmetry dismantle processes flow process of a kind of tower crane attachment device according to claim 1, the dead work before it is characterized in that removing mainly contains: understand the situation of camp site, the cleaning obstacle; Carry out the safety method work of telling somebody what one's real intentions are to participating in dismounting tower machine personnel, and the tower machine of being dismantled is carried out complete machine inspection work; Check no potential safety hazard, be equipped with the wheel crane of a 25T under the normal at the construction field (site) condition, required instrument and fragment data when being ready to dismantle.
3. the steel rope symmetry dismantle processes flow process of a kind of tower crane attachment device according to claim 1 is characterized in that falling standard knot and is the standard knot that falls more than the first road attached wall, and the process of falling standard knot is opposite with the process that the body of the tower standard knot is installed.
4. the steel rope symmetry dismantle processes flow process of a kind of tower crane attachment device according to claim 1; When it is characterized in that removing attached wall for safety and protection building finished product; Use following method for dismounting: the utilization suspension hook is removed the attached wall of crane arm one side earlier, apart from equilibrium arm and cat head frame hinged place middle part, about 1.5 meters a fixed pulley is being installed again.Suspension hook drops down onto apart from ground about 1 meter, and steel rope and the master winch steel rope of φ 9 is locked, passes pulley and drops down onto lifting rope on the Ground lock, and the suspension hook that hoists hangs the attached wall of equilibrium arm one side and removes with the steel rope of φ 9.The ring beam framework that hangs equilibrium arm one side with the steel rope of φ 9 is again removed.Dismantle the at last steel rope of φ 9 is removed the ring beam framework of crane arm one side with the crane arm suspension hook.One attached wall removed and finished.Repeat above-mentioned steps the tower machine is reduced to height of foundation.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012100727229A CN102583163A (en) | 2012-03-20 | 2012-03-20 | Steel wire rope symmetrically disassembling process flow for tower crane attachment device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012100727229A CN102583163A (en) | 2012-03-20 | 2012-03-20 | Steel wire rope symmetrically disassembling process flow for tower crane attachment device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102583163A true CN102583163A (en) | 2012-07-18 |
Family
ID=46472536
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2012100727229A Pending CN102583163A (en) | 2012-03-20 | 2012-03-20 | Steel wire rope symmetrically disassembling process flow for tower crane attachment device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102583163A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104692261A (en) * | 2015-03-24 | 2015-06-10 | 启东建筑集团有限公司 | Symmetrical dismounting construction method for attachment device of tower crane |
CN105060138A (en) * | 2015-09-07 | 2015-11-18 | 鞍钢房产建设有限公司 | Disassembling and installation method for tower crane attachment |
CN106829739A (en) * | 2017-03-01 | 2017-06-13 | 南通庞源机械工程有限公司 | A kind of method that utilization suspension bridge dismantles tower crane attached wall pull bar |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0912274A (en) * | 1995-06-27 | 1997-01-14 | Matsuda Eng Kk | Crane capable of assembling and disassembling small-scale steel tower |
US6702132B1 (en) * | 1999-03-19 | 2004-03-09 | Link-Belt Construction Equipment Company, L.P., Lllp | Crane self-assembly system |
CN101214908A (en) * | 2007-12-29 | 2008-07-09 | 中建二局第二建筑工程有限公司 | Gin pole integrated dismounting method for tower crane |
CN201914868U (en) * | 2011-02-23 | 2011-08-03 | 刘福元 | Tower crane attached mounting-demounting hoisting device |
CN202390113U (en) * | 2011-12-16 | 2012-08-22 | 西安市第四建筑工程公司 | Hoisting and demounting device attached to tower crane for building |
-
2012
- 2012-03-20 CN CN2012100727229A patent/CN102583163A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0912274A (en) * | 1995-06-27 | 1997-01-14 | Matsuda Eng Kk | Crane capable of assembling and disassembling small-scale steel tower |
US6702132B1 (en) * | 1999-03-19 | 2004-03-09 | Link-Belt Construction Equipment Company, L.P., Lllp | Crane self-assembly system |
CN101214908A (en) * | 2007-12-29 | 2008-07-09 | 中建二局第二建筑工程有限公司 | Gin pole integrated dismounting method for tower crane |
CN201914868U (en) * | 2011-02-23 | 2011-08-03 | 刘福元 | Tower crane attached mounting-demounting hoisting device |
CN202390113U (en) * | 2011-12-16 | 2012-08-22 | 西安市第四建筑工程公司 | Hoisting and demounting device attached to tower crane for building |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104692261A (en) * | 2015-03-24 | 2015-06-10 | 启东建筑集团有限公司 | Symmetrical dismounting construction method for attachment device of tower crane |
CN105060138A (en) * | 2015-09-07 | 2015-11-18 | 鞍钢房产建设有限公司 | Disassembling and installation method for tower crane attachment |
CN105060138B (en) * | 2015-09-07 | 2017-04-19 | 鞍钢房产建设有限公司 | Disassembling and installation method for tower crane attachment and device thereof |
CN106829739A (en) * | 2017-03-01 | 2017-06-13 | 南通庞源机械工程有限公司 | A kind of method that utilization suspension bridge dismantles tower crane attached wall pull bar |
CN106829739B (en) * | 2017-03-01 | 2017-12-29 | 南通庞源机械工程有限公司 | A kind of method that tower crane attached wall pull bar is dismantled using suspension bridge |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201228206Y (en) | Self-made small-sized hoisting machine | |
CN202416183U (en) | Bent cap collar-clamp type cast support | |
CN206328678U (en) | Steel box-girder chooses arm and steel guard rail installs dual-purpose type Mobile operating platform | |
CN102900021B (en) | Split mounting type bridge wet joint construction method | |
CN201635020U (en) | Bridge floor dismantling crane for large and medium concrete bridges | |
CN100519396C (en) | Gin pole integrated dismounting method for tower crane | |
CN208120594U (en) | A kind of section of jurisdiction for subway work vertical transport system automatically grabs handler | |
CN104692261A (en) | Symmetrical dismounting construction method for attachment device of tower crane | |
CN102583163A (en) | Steel wire rope symmetrically disassembling process flow for tower crane attachment device | |
CN205973523U (en) | Super high -rise building is special to be hung from tearing formula roofing open | |
CN205188839U (en) | Movably -assembled anti -collision bridge wall construction hanging basket | |
CN208120584U (en) | It is a kind of to turn over slag device for subway work vertical transport system | |
CN105133499A (en) | Movable hanging basket trolley for bridge concrete anti-collision guardrail construction | |
CN204418013U (en) | Bridge flange plate is constructed self-propelled cantilever hanging basket | |
CN107720569B (en) | A kind of dismounting inner climbing crane tower is hung with masts type roofing | |
CN202114446U (en) | Tool for mounting and demounting of horizontal equipment in frame | |
CN103882852A (en) | Rammer release device of dynamic compactor | |
CN103979442B (en) | The method of 6400 tons of Hydraulic double-type crane lifting cost tropsch reactors | |
CN202744961U (en) | Lifting mechanism for anti-falling beam check block | |
CN106121254B (en) | The construction method of heavy component transportation system after a kind of disassembly of contrary sequence method | |
CN201722937U (en) | Sliding platform for installation of net rack | |
CN213202204U (en) | Overhead hoist is demolishd to real abdomen section limit case of truss-like combination arched bridge | |
CN211198328U (en) | Fabricated bridge lower pier column lifting appliance | |
CN203834458U (en) | Hammer dropping device of dynamic compaction machine | |
CN102733612B (en) | Mounting method of electric hoist orbit |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20120718 |