CN102582631A - Fast transiting method for two or more temporary ropeways - Google Patents
Fast transiting method for two or more temporary ropeways Download PDFInfo
- Publication number
- CN102582631A CN102582631A CN2012100378213A CN201210037821A CN102582631A CN 102582631 A CN102582631 A CN 102582631A CN 2012100378213 A CN2012100378213 A CN 2012100378213A CN 201210037821 A CN201210037821 A CN 201210037821A CN 102582631 A CN102582631 A CN 102582631A
- Authority
- CN
- China
- Prior art keywords
- transportation
- cableway
- interim
- shelf
- rope
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
- Ropes Or Cables (AREA)
Abstract
The invention discloses a fast transiting method for two or more temporary ropeways. The method comprises the construction steps of (1) building temporary ropeways; (2) paving tracks among the temporary ropeways; (3) arranging vehicle transmitting and running goods shelves; and (4) transmitting and turnovering devices and materials. According to the fast transiting method, fast connection among the temporary ropeways is realized, midway turnover time of the materials and the devices is reduced, manual cost is reduced, and the temporary ropeway transmitting efficiency is improved.
Description
Technical field
The invention belongs to the bigger material of physical features drop, equipment transportation resources, especially relate to the transportation resources of construction material, equipment on the dangerously steep massif.
Background technology
At present; When carrying out engineering construction on the bigger massif of physical features drop, the mode of interim cableway transportation is progressively adopted in the conveying of material, equipment, but some massif transportation environment is relatively harsher; Because of obstacle on the massif more; Interim cableway transportation crossing ability traffic condition out of reach, an interim cableway has realized that not material, equipment are transported to the requirement of assigned address, and adopts many interim cableway transportations can realize the transportation of material installation.But many interim cableway transportations; The form of transportation mostly is a single-stop-type types of transportation now; Promptly be transported on this cableway and through manual work material, equipment unloaded from cableway conveyor behind the station through an interim cableway; Lift through manual work then and be transported to second transportation cableway place, through manual work material, equipment are placed on the cableway conveyor again, realize the transportation of the interim cableway of second; Connect many interim cableway transportation functions by that analogy, realize that material, equipment are transported to assigned address.It is many that this kind form not only drops into manual work, and between the two interim cableways turn round time longer, entire equipment transport of materials efficient is not high, has not only increased the construction speed that engineering cost of labor input is also directly restricting engineering.
Summary of the invention
The objective of the invention is to propose a kind of two and above interim cableway quick transportation method, realized the quick connection between the interim cableway, reduce the turn round time midway of material installation, reduce cost of labor, improve interim cableway conveying efficiency.
The objective of the invention is to realize like this: a kind of two and above interim cableway quick transportation method are on the bad massif of interim cableway sighting condition; Set up two or above interim cableway and carry out the transportation of material, equipment; Distance shortens spacing as much as possible according to the condition of massif between cableway and the cableway; Between two interim cableways, set up and be made into conveying track with channel-section steel; Sport car is connected with chain block on purpose made transportation shelf and the steel rope, and the material of coming when transportation, when equipment transportation shelf arrive last station is placed on the track of previous arrangement after with chain block shelf being unloaded; Adopt manual work to push to the interim cableway of second; After through chain block on the interim cableway sport car of second the shelf of material, equipment being promoted then, be transported on this cableway with the interim cableway of second and stand, realize that by that analogy cableway directly connects fast.
These two and above interim cableway quick transportation method, its construction procedure is: 1, set up interim cableway, 2, lay track between interim cableway, 3, transportation sport car shelf are set, 4, equipment and materials transportation and turnover.
Wherein:
1) set up interim cableway:
By Fig. 1, Fig. 3: drafting on the circuit that the transportation trafficability characteristic satisfies, set up interim cableway A and B (transporting cableways with two is example),, select interim ropeway supporting trestle point and support number temporarily based on the length and the physical features discrepancy in elevation condition of interim cableway according to the pattern among the figure.Interim ropeway supporting trestle 7 and support cable rope 8 have been installed; All interim ropeway supporting trestles 7 of fixation lay and carry rope 5 and hauling rope 10, install and improve traction return sheave 12, traction track adjusting wheel 13, traction drive strand mill winch 11; And two ropeway carrying-ropes 5 of every interim cableway of difference tensioning; In the anchoring honest 9 of passenger station, every interim ropeway hauling rope 10 is implemented in drives under 11 effects of strand mill winch, reciprocating type traction about being fixed in; Arrive the condition that interim cableway transportation is carried after ropeway carrying-rope 5 tensionings, the condition and the function of every interim cableway transportation realized in comprehensive back.
2) lay track between interim cableway:
According to Fig. 1, Fig. 4:
With the last station of cableway A and the following station of cableway B, according to the massif condition, the transition route of optimum design is provided with transition conveying track 6 respectively, and track 6 gauges are according to the distance setting of the travelling wheel 2 of transportation under the shelf 1, and with two tracks carry out reliably, firm connection.
3) transportation sport car shelf are set:
According to Fig. 1, Fig. 2, Fig. 3:
Carry on the rope 5 at the interim cableway that has installed; Two sport cars 4 are set; To transport shelf 1 through chain block 3 again and be connected,, realize the reciprocal transportation function of sport car 4 through hauling rope 10 and carrying rope 5 again at the firm hauling rope 10 of transportation sport car 4 places of hanging binding with transportation sport car 4.
4) equipment and materials transportation and turnover:
Equipment, the material of need transportation are placed on the transportation shelf 1 that possess transportation function; Driving strand mill winch 11 through the A cableway drives; Driving hauling rope 5 is transferred to transportation power on the transportation sport car 4; With the last website of equipment, transport of materials to the interim cableway of A, will transport shelf 1 through chain block 3 again and be unloaded on the conveying track 6 with goods integral body, make that travelling wheel 2 is placed in the conveying track 6 on the shelf 1; (ability that at present interim cableway transports is 3t to website under defeated shelf 1 of artificial promotion and goods to the B cableway; Manual work can easily realize moving), will move defeated shelf 1 with the chain block 3 on the B cableway sport car 4 and rise with goods, drive the transportation that strand mill winch 11 is realized goods through the B cableway again.
The characteristics of proposed by the invention a kind of two and above interim cableway quick transportation method are:
1) selects best interim cableway haulway respectively and the connection track between interim carrying cable duct device and the cableway is set like Fig. 1;
2) like Fig. 2,3, shown in 4, shelf 1 can be realized rising and descending through chain block 3, and the roller under the shelf 12 can cooperate shelf 1 to realize that the level between the cableway transports with twilight orbit 6.Roller 2 is welded on the shelf 1.
The form of 3) on many interim cableways, transporting is identical with the interim cableway transportation of wall scroll principle.
Article two, interim cableway types of transportation fundamental principle is consistent with two that are introduced interim cableway types of transportations more than.
A kind of two and above interim cableway quick transportation method and device thereof proposed by the invention, easy to use reliable, lowered the difficulty of equipment, transport of materials on the dangerously steep massif, reduce construction cost, improve interim cableway conveying efficiency.
Now with instance a kind of two and above interim cableway quick transportation method and device thereof are explained in conjunction with the accompanying drawings.
Description of drawings
Fig. 1 is a kind of two and an above interim cableway quick transportation method layout scheme drawing proposed by the invention.
Among Fig. 1: 5, carry that rope 6, twilight orbit 7, interim ropeway supporting trestle 8, ropeway supporting trestle cable rope 9, anchoring are honest 10, hauling rope 12, return sheave 13, track adjusting wheel.
Fig. 2 be Fig. 1 analyse and observe the transportation scheme drawing.
Among Fig. 2: 1, transportation shelf 2, shelf pulley 3, chain block 4, transportation sport car 5, carrying rope 7, interim ropeway supporting trestle 8, ropeway supporting trestle cable rope 10, hauling rope.
Fig. 3 is that the C of Fig. 2 is to view.
Among Fig. 3: 1, transportation shelf 2, shelf pulley 3, chain block 4, transportation sport car 5, carrying rope 10, hauling rope.
Fig. 4 connects track to analyse and observe the transportation scheme drawing between the cableway of Fig. 1.
Among Fig. 4: 2, shelf pulley 6, twilight orbit.
The specific embodiment
1. the new cloud valley cable in Mount Huang road installation work
1.1 project profile
New cloud valley cable road, Mount Huang in; The ropeway line length of this project is 2476 meters; 740 meters of the discrepancy in elevation, the Austrian haulage cradle cableway technology of introduction is in order to ensure the steel structure at circuit and last station, the transportation of equipment; Utilize the cableway line of centers to set up interim cableway, facing the rope form is that two-wire carries circulation traction cableway.
1.2 condition of construction
Based on the actual conditions of engineering, select this construction method, in 2 months, accomplished whole aerial cableway transport, transport 230 tons in station, line facility and steel construction.
2 Jiuhuashans flower platform passenger ropeway project
2.1 project profile
Jiuhuashan flower platform passenger aerial ropeway in; This project ropeway line length is 2756 meters, 860 meters of the discrepancy in elevation, Austrian many Bei Maya haulage cradle cableway technology of introduction; Transportation for the building materials, steel structure and the equipment that satisfy last station, circuit utilizes the cableway line of centers to set up interim cableway.
2.2 condition of construction
According to the actual conditions of engineering, select this construction method, in 5 months, accomplished whole cableway engineering construction material, equipment transport, the building materials of transportation is 2900 tons, the steel structure of transportation and equipment are 210 tons.
Claims (3)
1. one kind two and above interim cableway quick transportation method, its construction procedure is: one, set up interim cableway, two, lay track between interim cableway, three, transportation sport car shelf are set, four, equipment and materials transportation and turnover, wherein:
One, set up interim cableway:
Drafting on the satisfied circuit of transportation trafficability characteristic, set up interim cableway A and B, based on the length and the physical features discrepancy in elevation condition of interim cableway, select interim ropeway supporting trestle point and support number; Interim ropeway supporting trestle (7) and support cable rope (8) have been installed; All interim ropeway supporting trestles (7) of fixation lay carrying rope (5) and pull rope (10), install and improve traction return sheave (12), traction directive wheel (13), traction drive strand mill hoist engine (11); And two ropeway carrying-ropes (5) of every interim cableway of difference tensioning; In the anchoring of passenger station honest (9), make every interim ropeway hauling rope (10) be implemented in driving strand mill hoist engine (11) and act on down reciprocating type traction about being fixed in; Arrive the condition of interim cableway transportation carrying after ropeway carrying-rope (5) tensioning, the condition and the function of every interim cableway transportation realized in comprehensive back;
Two, lay track between interim cableway:
With the last station of cableway A and the following station of cableway B; Based on the massif condition, the transition route of optimal design is provided with transition conveying track (6) respectively; Track (6) gauge is set based on the distance of the travelling wheel (2) under the transportation shelf (1), and two tracks are carried out reliably, firmly connect;
Three, transportation sport car shelf are set:
Carry on the rope (5) at the interim cableway that has installed; Two sport cars (4) are set; To transport shelf (1) through chain block (3) again is connected with transportation sport car (4); At transportation sport car (4) place's of hanging binding firm hauling rope (10), realize the reciprocal transportation function of sport cars (4) through hauling rope (10) and carrying rope (5) again;
Four, equipment and materials transportation and turnover:
Equipment, the material of need transportation are placed on the transportation shelf (1) that possess transportation function; Driving strand mill winch (11) through the A cableway drives; Driving hauling rope (5) is transferred to transportation power on the transportation sport car (4); With the last website of equipment, transport of materials to the interim cableway of A, (1 is unloaded on the conveying track (6) with goods integral body, makes shelf (1) go up travelling wheel (2) and is placed in the conveying track (6) will to transport shelf through chain block (3) again; (ability of at present interim cableway transportation is 3t to website under defeated shelf (1) of artificial promotion and goods to the B cableway; Manual work can easily realize moving), will move defeated shelf (1) and goods rise with the chain block (3) on the B cableway sport car (4), drive the transportation that strand mill winch (11) is realized goods through the B cableway again.
2. a kind of two and above interim cableway quick transportation method according to claim 1; It is characterized in that: drafting on the satisfied circuit of transportation crossing ability; Set up the interim cableway more than two; According to the length and the physical features discrepancy in elevation condition of interim cableway, select interim ropeway supporting trestle point and support number; Article two, interim cableway types of transportation fundamental principle is consistent with two that are introduced interim cableway types of transportations more than.
3. a kind of two and above interim cableway quick transportation method according to claim 1; It is characterized in that: shelf (1) can pass through chain block (3) to be realized rising and descending, and the roller (2) under the shelf (1) can cooperate shelf (1) to realize the level transportation between the cableway with twilight orbit (6); Roller (2) is welded on the shelf (1).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210037821.3A CN102582631B (en) | 2012-02-20 | 2012-02-20 | Fast transiting method for two or more temporary ropeways |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210037821.3A CN102582631B (en) | 2012-02-20 | 2012-02-20 | Fast transiting method for two or more temporary ropeways |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102582631A true CN102582631A (en) | 2012-07-18 |
CN102582631B CN102582631B (en) | 2014-08-06 |
Family
ID=46472039
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201210037821.3A Active CN102582631B (en) | 2012-02-20 | 2012-02-20 | Fast transiting method for two or more temporary ropeways |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102582631B (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104133976A (en) * | 2014-08-25 | 2014-11-05 | 国家电网公司 | Stress calculation method for cableway type crossing structure bearing rope |
CN108408403A (en) * | 2018-04-10 | 2018-08-17 | 苏州康弗士科技有限公司 | A kind of automatic dischargingapparatus |
CN109677423A (en) * | 2019-01-04 | 2019-04-26 | 扬州市百思特机械设备有限公司 | A kind of coal mine mixing tunnel enclosed systemic circulation overhead passenger cableway |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3922970A (en) * | 1971-04-15 | 1975-12-02 | Mij Voor Ind Research En Ontwi | Railway transportation system |
CN86104381A (en) * | 1985-06-27 | 1986-12-24 | 韦维机械制造厂(有限) | The mass transportation facility that on the guide rail that is hanging, moves |
KR20080109663A (en) * | 2007-06-13 | 2008-12-17 | 이병철 | Transferring apparatus using transfer wire |
CN201808908U (en) * | 2010-09-30 | 2011-04-27 | 安徽意通电力设备有限公司 | Steering device for light rail suspension conveying track |
-
2012
- 2012-02-20 CN CN201210037821.3A patent/CN102582631B/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3922970A (en) * | 1971-04-15 | 1975-12-02 | Mij Voor Ind Research En Ontwi | Railway transportation system |
CN86104381A (en) * | 1985-06-27 | 1986-12-24 | 韦维机械制造厂(有限) | The mass transportation facility that on the guide rail that is hanging, moves |
KR20080109663A (en) * | 2007-06-13 | 2008-12-17 | 이병철 | Transferring apparatus using transfer wire |
CN201808908U (en) * | 2010-09-30 | 2011-04-27 | 安徽意通电力设备有限公司 | Steering device for light rail suspension conveying track |
Non-Patent Citations (1)
Title |
---|
刘丹清等: "索道运输", 《黑龙江科技信息》, 25 February 2008 (2008-02-25) * |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104133976A (en) * | 2014-08-25 | 2014-11-05 | 国家电网公司 | Stress calculation method for cableway type crossing structure bearing rope |
CN104133976B (en) * | 2014-08-25 | 2017-04-12 | 国家电网公司 | Stress calculation method for cableway type crossing structure bearing rope |
CN108408403A (en) * | 2018-04-10 | 2018-08-17 | 苏州康弗士科技有限公司 | A kind of automatic dischargingapparatus |
CN109677423A (en) * | 2019-01-04 | 2019-04-26 | 扬州市百思特机械设备有限公司 | A kind of coal mine mixing tunnel enclosed systemic circulation overhead passenger cableway |
CN109677423B (en) * | 2019-01-04 | 2024-05-28 | 扬州市百思特机械设备有限公司 | Closed type large-circulation overhead man-riding cableway for coal mine mixed roadway |
Also Published As
Publication number | Publication date |
---|---|
CN102582631B (en) | 2014-08-06 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201494438U (en) | Simple and fast installation cableway for maintenance and rush repair of mountain pipeline | |
CN202864283U (en) | Band type belt conveyor | |
CN103097610B (en) | Rail conveyor system | |
CN106352158B (en) | Piping lane pipeline transportation installation method | |
CN103661408B (en) | Station for a cable railway system | |
CN102602398B (en) | Quick-transporting method and quick-transport device for foldable temporary cableways | |
CN104265334A (en) | Fast unloading device for segments of shield machine | |
CN103277582A (en) | Method for mounting inclined shaft internal pressure steel tube | |
CN102582631B (en) | Fast transiting method for two or more temporary ropeways | |
CN103362546A (en) | Material transporting device for inclined shaft and material transporting method thereof | |
CN206592150U (en) | Monorail crane winch transportation system | |
CN202829249U (en) | Mechanical system of continuous rope mechanical speed-adjusting winch system | |
CN102745205A (en) | Mechanical system of endless rope mechanical speed regulating winch system | |
CN204506935U (en) | Mining cross-country traveling ability heavier load transport hutching | |
CN103523667A (en) | Mining steel rope traction monorail crane transportation system and transportation method thereof | |
CN213976674U (en) | Lifting beam for monorail crane | |
CN106348183A (en) | Multi-track cable lift and transport device | |
CN106335514B (en) | Duplex type draws overhead trolley system | |
CN105358400A (en) | Device for replacing roller sets | |
CN201941770U (en) | Curve transport cableway system | |
CN203667819U (en) | Large-dip angle lane monorail crane transporting device | |
CN201254385Y (en) | Roller conveying apparatus for belt conveyor maintenance | |
CN204506903U (en) | Rail transport quick despatch car device | |
CN201249761Y (en) | High-tension transmission line mountain area construction two-way circulating freight cableway | |
CN211769633U (en) | Material conveying system of subway station access & exit |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |