CN102562068B - Mine subsequent cemented and non-cemented filling mining method - Google Patents

Mine subsequent cemented and non-cemented filling mining method Download PDF

Info

Publication number
CN102562068B
CN102562068B CN2012100257844A CN201210025784A CN102562068B CN 102562068 B CN102562068 B CN 102562068B CN 2012100257844 A CN2012100257844 A CN 2012100257844A CN 201210025784 A CN201210025784 A CN 201210025784A CN 102562068 B CN102562068 B CN 102562068B
Authority
CN
China
Prior art keywords
filling
mining
mineral building
cemented
concentration
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2012100257844A
Other languages
Chinese (zh)
Other versions
CN102562068A (en
Inventor
何克舰
黄光柱
周文勇
袁旗
张秋炜
甄云军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wengfu Group Co Ltd
Original Assignee
Wengfu Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wengfu Group Co Ltd filed Critical Wengfu Group Co Ltd
Priority to CN2012100257844A priority Critical patent/CN102562068B/en
Publication of CN102562068A publication Critical patent/CN102562068A/en
Application granted granted Critical
Publication of CN102562068B publication Critical patent/CN102562068B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Curing Cements, Concrete, And Artificial Stone (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention discloses a mine subsequent cemented and non-cemented filling mining method, comprising the following steps: (1) preparing chambers; (2) preparing for chamber filling; (3) preparing for filling: making tailing, cement, super-micro powder and aggregate made from mining waste rock into a filling slurry with the concentration of larger than 70 %, carrying out cemented filling by applying pressure or flowing automatically to the prepared mining chambers, and carrying out non-cemented filling only by directly filling the mining chambers with high-concentration tailing having the concentration of larger than 65 % and mining waste rock having the particle size of less than 2 cm; (4) stoping and filling the chambers: stoping and filling the next adjacent chamber in every four chambers, wherein the cemented and non-cemented filling modes are carried out alternately between the adjacent chambers; and (5) managing after filling. The invention has significant economic social benefits, and is suitable for mining with the filling mining method, especially for the mid-low grade phosphate rock.

Description

A kind of mining is cementing and Non cemented filling mining methods afterwards
Technical field
The present invention relates to the method for mining by the way of filling, furthermore, relate to afterwards cementing and Non cemented filling mining methods of a kind of mining.
Background technology
The technology close with the present invention is Chinese patent ZL200710077624.3 " phosphogypsum cementing and post-filling mining method and pulping process thereof ", it is take ardealite, flyash or dolomite and cement as filling the material of slip that this patent discloses pulping process, after adding water, by complete mixing plant, make filling slurry; Filling slurry is adopted accurate level through the input of filling borehole or pumping plant, then outside filling pipeline inclined shaft enters the higher slice arteries and veins of filling stope the layering gallery, be filled with stope by the higher slice mineral building connecting taxiway of filling stope.This invention can guarantee arrival at mine full capacity and stable yields, improves ore recovery ratio, and phosphate rock resource is recycled fully, remarkable in economical benefits; Can also effectively protect mine environment; the mining of solution open-stope method forms geological disaster, mine produces dangerous; bring the problem of threat for earth's surface industrial facility, highway and house; but the shortcoming that it is maximum or weak point are directly to use to the huge industrial residue phosphogypsum of environmental hazard as main filler filling in underground, and its harm to underground Environmental Water system will be huge.Secondly, it adopts full consolidated fill must be directed at the increase of filling cost, and this, for the exploitation of the poor mid low grade phosphate rock district ore of ore quality, is extremely disadvantageous on cost of winning.
A large amount of rejects-mine tailings that mid low grade phosphate rock stone produces through the ore-dressing technique enrichment, ore-dressing technique tailings concentration out is about 20%, and mine tailing is sent into Tailings Dam.And the accumulation of mine tailing and management belong to China's Management of Major Risk scope.
Summary of the invention
The objective of the invention is in order to overcome the defect of prior art, afterwards cementing and Non cemented filling mining codes of phosphorus tailings are provided.In order to realize this purpose, a kind of mining of the present invention afterwards cementing and particular contents Non cemented filling mining methods comprises:
(1), mineral building is prepared:, according to the requirement of mining codes, adopt every four mineral buildings, the mode of a mineral building of exploitation is exploited;
(2), the mineral building filling is prepared: will form 25000 meters of 45 meters to 120 meters, interval after the mineral building exploitation 3With 30000 meters 3Mined area, mineral building has been adopted the plank shutoff of the rear route of ore removal to polycrystalline substance, reserves the deep water hole, mined area starts filling after soakaway trench is installed;
(3), filling is prepared:
Requirement by application number 201210008744.9 " casting resin oar of a kind of method of mining by the way of filling and preparation method thereof ", the aggregate that mine tailing, cement, Ultramicro-powder and mining barren rock are made is prepared into casting resin oar greater than 70% concentration and pressurizes by pipeline or flow automatically to the ready sky mineral building of adopting and carry out consolidated fill, that is:
By press filtration or deeply to bore dense mode dense for the high-concentration tailings of concentration more than 65% with the milltailings of 20% concentration, the water of separation is back to beneficiation flowsheet;
Again by pipeline with the dense casting resin oar preparation station that is transported to mine cave mouth for the above mine tailing of concentration 65%, stand in the preparation of casting resin oar, press each material formula by weight by mixing plant: cement: Ultramicro-powder=0.8~0.3:0.2~0.7; Aggregate-to-cement ratio is 4~12; Debris is the particle less than 2cm, and debris is unfixing with the ratio of mine tailing, is prepared into concentration and is equal to or greater than 70% casting resin oar; Pressurize or flow automatically to the ready sky mineral building of adopting by pipeline and carry out consolidated fill;
Non cemented filling only is the high-concentration tailings more than 65% and less than the particle of 2cm, digs up mine the direct filling of barren rock in adopting the sky mineral building with dense;
(4), back production and mineral building filling:
Mined area starts filling after soakaway trench is installed, polycrystalline substance partly carries out the high strength filling with the casting resin oar that aggregate-to-cement ratio is 4, and each packed height can not, greater than 60 centimeters, be carried out the mineral building filling subsequently, be 10~12 casting resin oar low-intensity filling with aggregate-to-cement ratio, until complete dead zone of filling; After obturation reaches and solidifies requirement, then every four mineral buildings, to exploiting adjacent next mineral building back production and filling;
The adjacent mines room adopts staggered the carrying out of cementing mode with Non cemented filling;
Stage casing mainstay on starting to reclaim after mineral building exploitation in whole stage casing finishes, casting resin oar at the aggregate-to-cement ratio 4 that mainstay dead zone part is adopted carries out the high strength filling, sprayed mortar knot top is adopted on the knot top of obturation, wherein for strengthening the stability of obturation, in high strength obturation part, the split anchor pole of constructing is in advance strengthened obturation and roof and floor to connect;
(5), the management after filling:
In the process of carrying out filling, the cemented filling material oar of different proportion is prepared the pressure testing standard component, after meeting, final setting time carries out pressure testing check intensity, every day fill area is patrolled and examined and is made a report on simultaneously patrol record;
The water that obturation is oozed out, carries out after corresponding physical chemistry is processed discharging according to result of laboratory test after sample examination to shaft bottom special use sump by the pipeline centralized recovery;
Set up surface displacement deformation monitoring management system, grasp at any time the earth's surface situation of change, with this, instruct and adjust underground filling work.
Economic and social benefit of the present invention is remarkable:
1, realized the safety in production of mining process.
2, mining recovery is brought up to more than 90% from 70%.
3, carry out Balancing Analysis of Charges from the output capacity of mine tailing and the expense of filling, the output capacity of mine tailing is 30%, and the demand in goaf is 40%, therefore, the mine tailing total amount can not satisfy the demands, and the barren rock (different mining methods have different digging ratios) that the construction of recycling mine tunnel engineering produces can be realized overall material balance substantially.Like this, eliminate this major hazard source of Tailings Dam fully, realized the exploration without waster in mine.
4,, by after the filling to underground goaf, effectively reduce the destruction to earth's surface, avoided the generation of geological disaster, realized Green Mine, harmonious development.Be mainly to reach national requirements for environmental protection, do not produce secondary harm;
5, reduced filling cost, this has realistic meaning for promote the use of filling method in the enterprise of mid low grade phosphate rock mountain.
The present invention is the concrete application of application number 201210008744.9 " casting resin oar of a kind of method of mining by the way of filling and preparation method thereof ", is applicable to method of mining by the way of filling mining, low-grade phosphorus ore mountain in being particularly useful for.
The specific embodiment
The invention will be further described below in conjunction with embodiment.
Embodiment:
Enforcement in the urn good fortune Da Tang of group ore deposit section:
The occurrence condition of ore body: ore body average thickness: 30 meters; Inclination angle 70-90 degree, rock consolidating coefficient 6-8, country rock be take dolomite as main, rock consolidating coefficient 8-12, ore average grade 22%, 1,500,000 ton/years of mine capacities;
(1), mineral building is prepared: mining methods are " VCR " method and " separative production and separative delivery mining codes ",, according to the requirement of mining codes, adopt every four mineral buildings, the mode of a mineral building of exploitation is exploited, wherein the stope size of " VCR " method is: long for the ore body horizontal breadth, wide 15 meters, high 70 meters; " separative production and separative delivery mining codes " stope size is: long 40 meters, wide is the ore body horizontal breadth, and stage casing is high 70 meters, and segmentation is high 18 meters, and ore pillar is wide is 8 meters;
(2), the mineral building filling is prepared: will form 25000 meters of 45 meters to 120 meters, interval after the mineral building exploitation 3With 30000 meters 3Mined area; Mineral building has been adopted the plank shutoff of the rear route of ore removal to polycrystalline substance, reserves the deep water hole, and mined area starts filling after soakaway trench is installed;
(3), filling is prepared:
Build the ore dressing plant of processing one year 3500000 tons of abilities of raw ore for seven kilometers apart from mine, have between mine and selected scenes
Belt porch transportation ore; Milltailings is dense is 20%; Mode by press filtration with the milltailings of 20% concentration dense be the high-concentration tailings of concentration more than 65%, the water of separation is back to beneficiation flowsheet;
Again by pipeline with the dense casting resin oar preparation station that is transported to mine cave mouth for the above mine tailing of concentration 65%, stand in the preparation of casting resin oar, press each material formula by weight by mixing plant: cement: Ultramicro-powder=0.8~0.3:0.2~0.7; Aggregate-to-cement ratio is 4~12; Debris is the particle less than 2cm, and debris is unfixing with the ratio of mine tailing, is prepared into concentration and is equal to or greater than 70% casting resin oar; Be pressurized to the ready sky mineral building of adopting by pipeline and carry out consolidated fill;
Non cemented filling only with mine tailing and the direct filling of barren rock of digging up mine in adopting the sky mineral building;
(4), back production and mineral building filling:
Mined area starts filling after soakaway trench is installed, polycrystalline substance partly carries out the high strength filling with the casting resin oar that aggregate-to-cement ratio is 4, and each packed height can not, greater than 60 centimeters, be carried out the mineral building filling subsequently, be 10~12 casting resin oar low-intensity filling with aggregate-to-cement ratio, until complete dead zone of filling; After obturation reaches and solidifies requirement, then every four mineral buildings, to exploiting adjacent next mineral building back production and filling;
The adjacent mines room adopts staggered the carrying out of cementing mode with Non cemented filling;
Stage casing mainstay on starting to reclaim after mineral building exploitation in whole stage casing finishes, casting resin oar at the aggregate-to-cement ratio 4 that mainstay dead zone part is adopted carries out the high strength filling, sprayed mortar knot top is adopted on the knot top of obturation, for strengthening the stability of obturation, in high strength obturation part, the split anchor pole of constructing is in advance strengthened obturation and roof and floor to connect;
(5), the management after filling:
In the process of carrying out filling, the cemented filling material oar of different proportion is prepared the pressure testing standard component, after meeting, final setting time carries out pressure testing check intensity, every day fill area is patrolled and examined and is made a report on simultaneously patrol record;
The water that obturation is oozed out, carries out after corresponding physical chemistry is processed discharging according to result of laboratory test after sample examination to shaft bottom special use sump by the pipeline centralized recovery;
Set up surface displacement deformation monitoring management system, grasp at any time the earth's surface situation of change, with this, instruct and adjust underground filling work.

Claims (1)

1. a mining cementing and Non cemented filling mining methods afterwards, its feature comprises:
(1), mineral building is prepared:, according to the requirement of mining codes, adopt every four mineral buildings, the mode of a mineral building of exploitation is exploited;
(2), the mineral building filling is prepared: will form 25000 meters of 45 meters to 120 meters, interval after the mineral building exploitation 3With 30000 meters 3Mined area, mineral building has been adopted the plank shutoff of the rear route of ore removal to polycrystalline substance, reserves the deep water hole, mined area starts filling after soakaway trench is installed;
(3), filling is prepared:
The aggregate that mine tailing, cement, Ultramicro-powder and mining barren rock are made is prepared into the casting resin oar that is equal to or greater than 70% concentration and pressurizes by pipeline or flow automatically to the ready sky mineral building of adopting and carry out consolidated fill, that is:
By press filtration or deeply to bore dense mode dense for the high-concentration tailings of concentration more than 65% with the milltailings of 20% concentration, the water of separation is back to beneficiation flowsheet;
Again by pipeline with the dense casting resin oar preparation station that is transported to mine cave mouth for the above mine tailing of concentration 65%, stand in the preparation of casting resin oar, press each material formula by weight by mixing plant: cement: Ultramicro-powder=0.8~0.3:0.2~0.7; Aggregate-to-cement ratio is 4~12; Debris is the particle less than 2cm, and debris is unfixing with the ratio of mine tailing, is prepared into concentration and is equal to or greater than 70% casting resin oar; Pressurize or flow automatically to the ready sky mineral building of adopting by pipeline and carry out consolidated fill;
Non cemented filling only is the high-concentration tailings more than 65% and less than the particle of 2cm, digs up mine the direct filling of barren rock in adopting the sky mineral building with dense;
(4), back production and mineral building filling:
Mined area starts filling after soakaway trench is installed, polycrystalline substance partly carries out the high strength filling with the casting resin oar that aggregate-to-cement ratio is 4, and each packed height can not, greater than 60cm, be carried out the mineral building filling subsequently, be 10~12 casting resin oar low-intensity filling with aggregate-to-cement ratio, until complete dead zone of filling; After obturation reaches and solidifies requirement, then every four mineral buildings, to exploiting adjacent next mineral building back production and filling;
The adjacent mines room adopts staggered the carrying out of cementing mode with Non cemented filling;
Stage casing foundation on starting to reclaim after mineral building exploitation in whole stage casing finishes, casting resin oar at the aggregate-to-cement ratio 4 that foundation dead zone part is adopted carries out the high strength filling, sprayed mortar knot top is adopted on the knot top of obturation, wherein for strengthening the stability of obturation, in high strength obturation part, the split anchor pole of constructing is in advance strengthened obturation and roof and floor to connect;
(5), the management after filling:
In the process of carrying out filling, the cemented filling material oar of different proportion is prepared the pressure testing standard component, after meeting, final setting time carries out pressure testing check intensity, every day fill area is patrolled and examined and is made a report on simultaneously patrol record;
The water that obturation is oozed out, carries out after corresponding physical chemistry is processed discharging according to result of laboratory test after sample examination to shaft bottom special use sump by the pipeline centralized recovery;
Set up surface displacement deformation monitoring management system, grasp at any time the earth's surface situation of change, with this, instruct and adjust underground filling work.
Figure FDA0000351977740000041
CN2012100257844A 2012-02-07 2012-02-07 Mine subsequent cemented and non-cemented filling mining method Active CN102562068B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012100257844A CN102562068B (en) 2012-02-07 2012-02-07 Mine subsequent cemented and non-cemented filling mining method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012100257844A CN102562068B (en) 2012-02-07 2012-02-07 Mine subsequent cemented and non-cemented filling mining method

Publications (2)

Publication Number Publication Date
CN102562068A CN102562068A (en) 2012-07-11
CN102562068B true CN102562068B (en) 2013-11-13

Family

ID=46408502

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012100257844A Active CN102562068B (en) 2012-02-07 2012-02-07 Mine subsequent cemented and non-cemented filling mining method

Country Status (1)

Country Link
CN (1) CN102562068B (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103643992B (en) * 2013-12-10 2016-04-13 中国恩菲工程技术有限公司 Mining placement method
CN104314613B (en) * 2014-08-26 2016-06-01 中煤科工集团重庆研究院有限公司 The method of chemistry grouting filling colliery caving place
CN105041318B (en) * 2015-08-07 2017-11-28 辽宁科技大学 A kind of closed barnyard mining afterwards filling method
CN105777014B (en) * 2016-03-30 2017-12-12 武汉工程大学 A kind of high pumping phosphate mine packing material and preparation method thereof
CN106014477A (en) * 2016-06-15 2016-10-12 山东华联矿业股份有限公司 Stable filler filling method
CN107500634A (en) * 2017-10-13 2017-12-22 中南大学 A kind of application of cemented filling material containing polypropylene fibre in mining with stowing
CN111088979B (en) * 2019-12-03 2021-05-04 南华大学 Downward access filling mining method
WO2024082011A1 (en) * 2022-10-19 2024-04-25 Gazmick Pty Ltd Method of mining in underground mines including disposal of tailings

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6322292B1 (en) * 1997-01-29 2001-11-27 Lloyd P. Zenari Backfilling underground voids
RU2213868C1 (en) * 2002-06-19 2003-10-10 Михайлов Юрий Васильевич Method of mining with filling of permafrost mineral deposits
CN101818643A (en) * 2010-05-18 2010-09-01 中南大学 Stepped non-pillar continuous filling mining method for deep well super high large breaking ore body panel
CN101858217A (en) * 2010-05-18 2010-10-13 中南大学 House pillar changeable panel upward demix filling mining method
CN102251773A (en) * 2011-06-22 2011-11-23 大冶有色金属股份有限公司 Route type upward horizontal layered filling mining method suitable for extremely complex ore body mining

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6322292B1 (en) * 1997-01-29 2001-11-27 Lloyd P. Zenari Backfilling underground voids
RU2213868C1 (en) * 2002-06-19 2003-10-10 Михайлов Юрий Васильевич Method of mining with filling of permafrost mineral deposits
CN101818643A (en) * 2010-05-18 2010-09-01 中南大学 Stepped non-pillar continuous filling mining method for deep well super high large breaking ore body panel
CN101858217A (en) * 2010-05-18 2010-10-13 中南大学 House pillar changeable panel upward demix filling mining method
CN102251773A (en) * 2011-06-22 2011-11-23 大冶有色金属股份有限公司 Route type upward horizontal layered filling mining method suitable for extremely complex ore body mining

Also Published As

Publication number Publication date
CN102562068A (en) 2012-07-11

Similar Documents

Publication Publication Date Title
CN102562068B (en) Mine subsequent cemented and non-cemented filling mining method
CN101858217B (en) House pillar changeable panel upward demix filling mining method
CN101818643B (en) Stepped non-pillar continuous filling mining method for deep well super high large breaking ore body panel
CN103437769B (en) Combination is reproduced structure medium-length hole ore blast and is worked in coordination with cable bolting afterwards filling mining method
CN102678121B (en) Layered top-controlling filling mining method for residual ores in deep hole in diskless area
CN101775985B (en) Deeply buried iron mineral resource underground mining and concentrating integration system
CN102392644A (en) Stripped fluid expansion filling mining method for below middle thick coal seam
CN102155228A (en) Fully-segmented presplitting squeezing primary-blasting mining method
CN105587318A (en) Filling mining method for continuous backstoping of gently inclined parallel medium thick ore body group
CN102168579A (en) Rib-pillar-free continuous sublevel filling method for mining preparation in medium-thickness slope crushed ore body vein
CN105041314A (en) Method for united mining of deep subsequent stoping chamber and layered stoping jamb
CN102261262B (en) High-performance foam mortar filling method for mine stope
CN102531482B (en) Filling slurry for filling mining method and preparation method for filling slurry
CN103437768B (en) Pre-set space filling mining method without top column and bottom column
CN110924967B (en) Fine control construction method for shield proximity sensitive building in water-rich sandy gravel stratum
CN102071940A (en) Construction method for mine shaft through multilayer goaf
CN105971606A (en) Extremely-thick coal seam longwall working face mining method
CN105317458A (en) Grading zonal paste backfilling system and method for total tailings of metal minerals
CN114472462B (en) Underground-aboveground linkage coal gangue disposal system and disposal method
CN109209379A (en) A kind of mine, which picks up, fills+X exploitation pattern
CN107975044B (en) Method for backfilling collapse method mine by utilizing tailing surface collapse pits
CN104453900A (en) Filling mining method of near-horizontal ore body
CN101892862A (en) Full tailing filling method in large goafs
CN111042817A (en) Partition cemented prop wall-cutting filling mining method
CN103557003A (en) Iron ore body safety pillar mining method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP02 Change in the address of a patent holder

Address after: 550500 Guizhou Province, Qiannan Buyei and Miao Autonomous Prefecture Fuquan Racecourse town Yingbin Road No. 1 Wengfu group

Patentee after: WENGFU GROUP Co.,Ltd.

Address before: 23, 550002 floor, International Building, No. 57, South City Road, Nanming District, Guiyang, Guizhou

Patentee before: WENGFU GROUP Co.,Ltd.

CP02 Change in the address of a patent holder