CN102522781B - 风火统一建模参与ace控制方法 - Google Patents
风火统一建模参与ace控制方法 Download PDFInfo
- Publication number
- CN102522781B CN102522781B CN201110440155.3A CN201110440155A CN102522781B CN 102522781 B CN102522781 B CN 102522781B CN 201110440155 A CN201110440155 A CN 201110440155A CN 102522781 B CN102522781 B CN 102522781B
- Authority
- CN
- China
- Prior art keywords
- control
- wind
- energy turbine
- ace
- turbine set
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/70—Wind energy
- Y02E10/76—Power conversion electric or electronic aspects
Landscapes
- Supply And Distribution Of Alternating Current (AREA)
- Wind Motors (AREA)
Abstract
Description
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201110440155.3A CN102522781B (zh) | 2011-12-26 | 2011-12-26 | 风火统一建模参与ace控制方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201110440155.3A CN102522781B (zh) | 2011-12-26 | 2011-12-26 | 风火统一建模参与ace控制方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102522781A CN102522781A (zh) | 2012-06-27 |
CN102522781B true CN102522781B (zh) | 2014-03-26 |
Family
ID=46293604
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201110440155.3A Active CN102522781B (zh) | 2011-12-26 | 2011-12-26 | 风火统一建模参与ace控制方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102522781B (zh) |
Families Citing this family (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103779860B (zh) * | 2012-10-18 | 2016-03-02 | 中国电力科学研究院 | 发电厂的有功功率的控制系统及控制方法 |
CN103066620B (zh) * | 2012-12-24 | 2014-10-22 | 中国电力科学研究院 | 间歇能源并网下的自动发电控制模型的设计方法 |
CN103208086B (zh) * | 2013-01-21 | 2016-03-16 | 云南电网公司电网规划研究中心 | 一种准确计及风电贡献的电力电量平衡方法 |
CN103390905B (zh) * | 2013-07-30 | 2015-07-22 | 国家电网公司 | 一种考虑风电接纳的多元能源自动发电控制方法 |
CN103439962B (zh) * | 2013-08-06 | 2015-09-23 | 国家电网公司 | 一种电网自动发电控制闭环检测验证方法 |
CN104092248B (zh) * | 2014-06-17 | 2016-01-20 | 国家电网公司 | 一种风火打捆外送容量协调优化配置方法 |
CN104300535B (zh) * | 2014-10-17 | 2016-09-07 | 华中电网有限公司 | 一种大功率缺额事故后网内快速备用的协调优化调度方法 |
CN104767205B (zh) * | 2015-01-29 | 2017-02-22 | 国家电网公司 | 基于风电场接入的电力系统自动发电控制系统的建立方法 |
CN105207264B (zh) * | 2015-10-22 | 2017-07-25 | 南京国电南自电网自动化有限公司 | 计及风电机组并网要求的孤立局域网频率优化控制方法 |
CN106160000B (zh) * | 2016-08-02 | 2018-12-04 | 国电南瑞科技股份有限公司 | 一种分调-省调两级协调的风电增发控制方法 |
CN106253353B (zh) * | 2016-08-29 | 2018-07-03 | 国电南瑞科技股份有限公司 | 一种动态区域控制偏差分配策略的改进优化方法 |
CN106505636B (zh) * | 2016-11-02 | 2018-11-13 | 南京南瑞继保电气有限公司 | 一种基于分组控制的电力系统自动发电控制方法 |
CN107276127B (zh) * | 2017-08-18 | 2019-10-11 | 西安交通大学 | 考虑联络线电力交易计划的多区域互联电力系统的风电消纳优化方法 |
CN107749645B (zh) * | 2017-09-26 | 2019-05-03 | 国网辽宁省电力有限公司 | 一种控制高压大容量储热供暖装置的方法 |
WO2019165637A1 (zh) * | 2018-03-02 | 2019-09-06 | 国网冀北电力有限公司 | 风电场群有功功率的控制方法及装置 |
CN111030194B (zh) * | 2019-12-25 | 2021-01-12 | 东南大学 | 一种含风电机组互联电网的自动发电控制方法 |
Family Cites Families (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20090212563A1 (en) * | 2008-02-21 | 2009-08-27 | General Electric Company | System and method for improving performance of power constrained wind power plant |
JP2011103736A (ja) * | 2009-11-11 | 2011-05-26 | Mitsubishi Heavy Ind Ltd | 風力発電システム |
CN201750218U (zh) * | 2010-07-16 | 2011-02-16 | 北京中科伏瑞电气技术有限公司 | 一种风电自动发电控制系统 |
-
2011
- 2011-12-26 CN CN201110440155.3A patent/CN102522781B/zh active Active
Also Published As
Publication number | Publication date |
---|---|
CN102522781A (zh) | 2012-06-27 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102522781B (zh) | 风火统一建模参与ace控制方法 | |
CN102003337B (zh) | 风电并网后主站端风电场有功功率控制方法 | |
CN106160000B (zh) | 一种分调-省调两级协调的风电增发控制方法 | |
CN108092324B (zh) | 一种风电参与调峰调频的agc控制系统和控制方法 | |
CN108039736A (zh) | 一种提高风电接纳能力的大容量储热储电协调调度方法 | |
Zhang et al. | Deloading power coordinated distribution method for frequency regulation by wind farms considering wind speed differences | |
CN107332286B (zh) | 一种含储热的热电联产与风电协调调度方法 | |
CN107958300A (zh) | 一种考虑互动响应的多微网互联运行协调调度优化方法 | |
CN107069829B (zh) | 一种场站级虚拟同步机控制系统、方法及其应用 | |
CN106602613B (zh) | 一种省地两级调度断面协调控制方法 | |
CN112838603B (zh) | 一种风光储抽多源能源agc协调互补控制方法和装置 | |
CN106026198B (zh) | “风-水”打捆外送的agc协调控制系统及控制方法 | |
CN110380438A (zh) | 一种考虑储能动作边界的快速调频控制方法 | |
CN103545849A (zh) | 风电参与系统调频控制的架构 | |
CN112865139B (zh) | 储能电站安全参与电网一次调频的优化控制策略 | |
CN107968443A (zh) | 一种风光火打捆直流外送的agc控制方法 | |
CN104253439B (zh) | 电池储能电站无功功率分配与控制方法 | |
CN105678394A (zh) | 一种多源多周期发电计划制定方法 | |
CN111525625A (zh) | 一种考虑燃气机组的日前计划制定方法及系统 | |
CN107968442A (zh) | 一种基于滚动优化策略的新能源区域的功率预测方法 | |
CN116316884A (zh) | 一种适用于高比例新能源电网多源协同的调频控制方法 | |
CN110443470A (zh) | 基于生成式对抗网络的风光水联合调度方法及装置 | |
CN108718093A (zh) | 一种高载能负荷参与风电消纳的有功-无功协调控制方法 | |
Zhang et al. | Research on active power automatic control strategy of wind farm energy station access system | |
CN104933534B (zh) | 一种考虑风电有功降载能力的两阶段系统备用优化评估方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
ASS | Succession or assignment of patent right |
Owner name: NORTH CHINA GRID CO., LTD. NARI NANJING CONTROL SY Free format text: FORMER OWNER: NORTH CHINA GRID CO., LTD. Effective date: 20141205 |
|
C41 | Transfer of patent application or patent right or utility model | ||
TR01 | Transfer of patent right |
Effective date of registration: 20141205 Address after: High road high tech Development Zone Nanjing city Jiangsu province 210061 No. 20 Patentee after: NARI Technology Development Co., Ltd. Patentee after: North China Grid Co., Ltd. Patentee after: SGCC NARI Nanjing Control System Co., Ltd. Address before: High road high tech Development Zone Nanjing city Jiangsu province 210061 No. 20 Patentee before: NARI Technology Development Co., Ltd. Patentee before: North China Grid Co., Ltd. |