CN102495413B - Method for acquiring transmission line tower coordinate - Google Patents

Method for acquiring transmission line tower coordinate Download PDF

Info

Publication number
CN102495413B
CN102495413B CN201110377888.7A CN201110377888A CN102495413B CN 102495413 B CN102495413 B CN 102495413B CN 201110377888 A CN201110377888 A CN 201110377888A CN 102495413 B CN102495413 B CN 102495413B
Authority
CN
China
Prior art keywords
shaft tower
transmission line
coordinate
angle
horizontal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201110377888.7A
Other languages
Chinese (zh)
Other versions
CN102495413A (en
Inventor
张焕杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Electric Power Construction Group Hebei electric survey and Design Research Institute Co., Ltd.
Original Assignee
Hebei Electric Power Design and Research Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hebei Electric Power Design and Research Institute filed Critical Hebei Electric Power Design and Research Institute
Priority to CN201110377888.7A priority Critical patent/CN102495413B/en
Publication of CN102495413A publication Critical patent/CN102495413A/en
Application granted granted Critical
Publication of CN102495413B publication Critical patent/CN102495413B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Position Fixing By Use Of Radio Waves (AREA)

Abstract

The invention discloses a method for acquiring a transmission line tower coordinate. In the method, based on a computer technology, a lead adjustment calculation technology and a GPS measurement technology, one transmission line is taken as one control measurement lead; information, such as an apparatus, a measuring method, a horizontal angle, a horizontal distance and the like, is obtained through data mining. A few field GPS measuring points are reasonably arranged. The GPS is used to acquire national coordinates of the field GPS measuring points. Computer software is controlled and measured to calculate the national coordinates of the whole towers. Precision assessment is performed and measurement precision can be guaranteed. Compared to the current general method for acquiring the national coordinates of the tower through the GPS measuring method, by using the method of the invention, cost is low; a working efficiency is high; labor intensity is low; personnel needed in the method is few; quality is reliable; it is convenient for popularization and application; economic benefits and social benefits are remarkable.

Description

The preparation method of transmission line tower coordinate
Technical field
The invention belongs to field of computer technology, particularly a kind of method that obtains transmission line tower coordinate by computing machine.
Background technology
Power grid GIS is the computer system of a theory with GIS and management by methods topomap, the relevant space of remote sensing images and transmission line of electricity, electric substation and generating plant and attribute data, is planning, survey and design, construction and the operation service of power transmission network.Data are the blood of generalized information system, and in the whole life cycle of generalized information system, data account for 70% of whole investment.Electric network data is the core of power grid GIS, and electrical network spatial data is the basis of attribute data location.
Transmission line of electricity is comprised of a series of bars, tower and the wire that is connected between shaft tower, and wherein the national coordinate of shaft tower is the sterically defined foundation of transmission line of electricity, is the basic data of carrying out space querying, spatial analysis.Transmission line of electricity has the advantages that quantity is many, space distribution is wide, so the collecting work amount of transmission line tower coordinate is huge.At present, the method that conventionally adopts GPSRTK technology field to measure by tower.GPSRTK technology is to obtain in real time the measuring method of centimetre-sized positioning precision in the wild, it has adopted carrier phase dynamic real-time difference method, the great milestone of GPS application, for engineering setting out, topographic mapping, various control survey have brought very big facility.But the method somewhat expensive, and Measuring Time is longer.
The design of transmission line of electricity is mainly completed by power survey and design institutes at different levels, so in the reference room of each power survey and design institute, has just accumulated the data of many existing circuits: such as measurement report, flat section location map, location outcome table, shaft tower detail list etc.Wherein in measurement report article the surveying instrument that uses of tower spotting, method, time etc.; Location outcome table mainly comprises the information such as shaft tower number, mileage, elevation, the deflection angle number of degrees, uses optical theodolite, stadimeter, total station survey, and mileage, span fetch bit be to rice, deflection angle fetch bit to minute; Use in the recent period GPS to measure, mileage, span fetch bit are to cm, and deflection angle fetch bit is to second.
Be no matter adopt optical theodolite, stadimeter, total powerstation or adopt GPS to measure, due to the impact of precision, human factor and the external condition of surveying instrument, measuring error is always inevitable.In order to improve the quality of achievement, handle the error problem that these exist in measuring well, the number of observed reading often will, more than the number of determining that unknown quantity institute must observe, namely will be carried out redundant observation.Had redundant observation, certainly will between observed result, produce contradiction, the object of measurement adjustment is tried to achieve the reliable results of observed quantity and is evaluated the precision of Measurement results with regard to being to eliminate these contradictions.Control survey adjustment Software, for control survey precision, is widely applied in fields of measurement.
Summary of the invention
The technical issues that need to address of the present invention are to provide and a kind ofly can improve field work efficiency and measuring accuracy, reduce the transmission line tower coordinate preparation method of Measuring Time and surveying work amount.
For solving the problems of the technologies described above, the technical solution adopted in the present invention is:
The preparation method of transmission line tower coordinate, the method is based on computer technology, traverse adjustment computing technique and GPS measuring technique, and its feature comprises the following steps being:
A. by consulting transmission line of electricity archives material, gather the basic parameter of every transmission line of electricity, form the data text of this transmission line of electricity;
B. according to steps A, obtain the horizontal angle of shaft tower in transmission line of electricity and the horizontal range between adjacent shaft tower;
C. according to steps A and B, according to the fetch bit of power grid GIS accuracy requirement and mileage, deflection angle, the two base shaft towers of transmission line of electricity starting point and terminal of take are known point, arrange field GPS measurement point;
D. the field GPS measurement point that adopts GPSRTK technology to arrange step C carries out obtaining of national coordinate;
E. by the data input lead compensating computation software of step B and D acquisition, carry out calculating, the input judgement of rough error and the judgement of coordinate precision of every base shaft tower coordinate;
F. shaft tower coordinate step e being obtained imports Microsoft Excel, generates shaft tower coordinate warehouse-in data file.
Described step e comprises the following steps:
A. the mis-tie of the mis-tie of computer azimuth angle and shaft tower coordinate, judges whether to exist input rough error, if there is input rough error, rejects;
B. fixing known point, weighs surely according to the fetch bit of the measuring method of location, surveying instrument equipment, horizontal angle, horizontal range, carries out compensating computation, calculates the coordinate of every base shaft tower, and judges whether the precision of every base shaft tower coordinate meets the demands; If do not met the demands, return to step C.
The computing method of described every base shaft tower coordinate are: the horizontal angle obtaining by step B, and calculate the position angle of shaft tower, then by position angle and span, calculated respectively the coordinate of every base shaft tower.
The basic parameter of data text described in described steps A mainly comprises title, starting point, terminal, surveying instrument equipment, shaft tower number, mileage, the deflection angle of transmission line of electricity.
In described steps A, also comprise the step of rule file being inputted to computer system, the input rule that described rule file is deflection angle, when the straight line pole deflection angle number of degrees are zero, left-hand rotation deflection angle is negative value, right-hand rotation deflection angle be on the occasion of.
Horizontal angle described in described step B adopts following formula to calculate:
L 1=L 2+180°
Wherein: L 1: horizontal angle
L 2: deflection angle;
Described horizontal range adopts following formula to calculate:
D=S n+1—S n
Wherein: S n+1: n+1 shaft tower mileage
S n: n shaft tower mileage.
Owing to having adopted technique scheme, the technical progress that the present invention obtains is:
The present invention is by carrying out data mining to Electric Power Survey design and research institute archives material, utilize existing EXCEL, SURVEYING CONTROL NETWORK adjustment Software, obtain by experiment layout principle and experimental formula that field GPS measures, finally to obtain the national coordinate of electric power line pole tower.Adopt the present invention to carry out the national coordinate collection of electric power line pole tower, can reduce field and use GPS eyeball quantity 60%-80%, not only work efficiency significantly improves, and effectively reduces the labour intensity of field process, and the duration is reduced by the impact of the extraneous factors such as weather, traffic, vegetation.Compare with conventional operation method, the duration shortens approximately 80%, and measuring accuracy improves greatly, for the power grid GIS create beneficial result that puts into operation early provides condition.
Take Southern Hebei Power Network as example, have 500kV circuit 2277km the end of the year 2010,220kV circuit 8118km.500kV circuit is pressed 500m span (standard file is apart from 450m) Conservative estimation, and steel tower approximately has 4554 bases; 220kV circuit is pressed 400m(standard file apart from 350m) span Conservative estimation, steel tower approximately has 20295 bases, adds up to 24849 bases.If the collection expense of every base steel tower is roughly equal to 100 yuan of Renminbi, Southern Hebei Power Network 220kV, 500kV circuit adopt the present invention to compare with classic method so, can save 156.549 ten thousand yuans of collection expenses.There will be transmission line of electricity 618837km the end of the year 2010 in State Grid Corporation of China, by 500m span, calculate conservative estimation and have shaft tower 1237674 bases, the collection expense of every base steel tower is by 100 yuans of Conservative estimations, adopt invention to compare with classic method, can save 7797.346 ten thousand yuans of collection expenses, remarkable in economical benefits improves.
Accompanying drawing explanation
Fig. 1 is process flow diagram of the present invention.
Embodiment
Below in conjunction with the drawings and specific embodiments, the present invention is described in further details:
The preparation method of transmission line tower coordinate, the process flow diagram of the method as shown in Figure 1.The method is based on computer technology, traverse adjustment computing technique and GPS measuring technique, while being specifically applied in electrical network, take Southern Hebei Power Network region 220kV and above transmission line of electricity is example, relate to altogether 283 transmission lines of electricity, the acquisition methods of every transmission line tower coordinate all adopts method of the present invention.The transmission line of electricity of take is below example, illustrates that the present invention obtains all shaft towers on this transmission line of electricity and sits calibration method.
A. by consulting transmission line of electricity archives material, each circuit is used as to a single-measurement wire, every grade of shaft tower is measured reference mark as one, gather the basic parameter of every transmission line of electricity, basic parameter comprises the information such as title, starting point, terminal, geographic position, surveying instrument equipment, shaft tower number, mileage, the deflection angle of transmission line of electricity, and the basic parameter of transmission line of electricity is input in the Microsoft Excel of computer system, form and take a data text that transmission line of electricity is unit.Form altogether 283 shaft tower 11345 bases of data file.
While inputting deflection angle information in this step, the needs basis in advance rule file of input computer system is inputted.Here said rule file is the input rule of deflection angle: when the straight line pole deflection angle number of degrees are zero, left-hand rotation deflection angle is negative value, right-hand rotation deflection angle be on the occasion of.
B. according to the basic parameter in steps A, obtain the horizontal angle of shaft tower in transmission line of electricity and the horizontal range between adjacent shaft tower.
The horizontal angle of shaft tower adopts following formula to calculate:
L 1=L 2+180°
Wherein: L 1: horizontal angle
L 2: deflection angle;
Horizontal range between adjacent shaft tower adopts following formula to calculate:
D=S n+1—S n
Wherein: S n+1: n+1 shaft tower mileage
S n: n shaft tower mileage.
C. according to steps A and B, obtain parameter, according to the fetch bit of power grid GIS accuracy requirement and mileage, deflection angle, the two base shaft towers of transmission line of electricity starting point and terminal of take are known point, arrange field GPS measurement point;
The starting point of transmission line of electricity and terminal turnover power plant or electric substation in electrical network, circuit is intensive, and outlet planning needs precision higher, and the center section of transmission line of electricity is relatively low.In the present embodiment, assign each transmission line of electricity as a measure traverse line, according to measuring error propagation law, meet wire error the weakest point in middle theory, therefore, two base shaft towers of transmission line of electricity starting point, terminal are as the Fixed Initial Point of GPS measurement point, then according to the accuracy requirement of power grid GIS, in the increase of transmission line of electricity interlude, layout.
The cardinal rule of layouting is as follows:
A. transmission line of electricity circuit starting point, terminal respectively arrange two base shaft towers and layout;
B. for adopting GPSRTK method to measure, and mileage, deflection angle fetch bit are respectively centimetre and second situation, the centre that line length is less than or equal to 50km can not increase and layout, and increases a point as check point in the middle of consideration more than 50km, guarantees data reliability;
C. for being no matter to adopt optical theodolite, total station survey, still adopt GPSRTK method to measure, if mileage, deflection angle fetch bit be respectively rice and minute situation, by following formula estimation error,
Δd=0.5+1.2×S/10000
Δ d wherein: Horizontal position errors
S: line length, unit rice
Then, according to increasing and layout in the middle of the accuracy requirement of power grid GIS.Adopt this principle to there is directive significance for reasonable Arrangement GPS measurement point in step C, can avoid a large amount of duplication of labour, guarantee one-shot measurement success ratio.
According to arranging altogether 1731 of field survey points in mentioned above principle the present embodiment.
D. the field GPS measurement point that adopts GPSRTK technology to arrange step C carries out obtaining of national coordinate;
E. by the data input lead compensating computation software of step B and D acquisition, carry out calculating, the input judgement of rough error and the judgement of coordinate precision of every base shaft tower coordinate.Detailed process is:
A. the mis-tie of the mis-tie of computer azimuth angle and shaft tower coordinate, judges whether to exist input rough error, if there is input rough error, rejects; Mis-tie refers to the total error between transmission line of electricity terminal and starting point.
B. fixing known point, weighs surely according to the fetch bit of the measuring method of location, surveying instrument equipment, horizontal angle, horizontal range, carries out compensating computation, calculates the coordinate of every base shaft tower.
Principle is weighed in fetch bit surely: when deflection angle fetch bit divides, tires out apart from fetch bit rice, priori mean square error of angle observation and mean square distance error are respectively 30 seconds and 0.5 meter; Deflection angle fetch bit second, tired during apart from fetch bit centimetre, priori mean square error of angle observation and mean square distance error are respectively 5 seconds and 0.05 meter.Tired distance is every base shaft tower to the distance between starting point.
The computing method of every base shaft tower coordinate are: the horizontal angle obtaining by step B, and calculate the position angle of shaft tower, then by the horizontal range between position angle and adjacent shaft tower, calculated respectively the coordinate of every base shaft tower.
Azimuthal computing formula is:
L 3=L 0+180°+L 1
L wherein 0: initial known azimuth;
L 1: horizontal angle;
L 3: position angle;
The computing formula of shaft tower coordinate is:
X=X 0+S×cos(L 3)
Y=Y0+S×sin(L 3)
X wherein 0: initial known ordinate
Y 0: initial known horizontal ordinate
S: the horizontal range between adjacent shaft tower
L 3: position angle
X: shaft tower ordinate
Y: shaft tower horizontal ordinate
After coordinate has calculated, judge whether the precision of every base shaft tower coordinate meets the demands.If do not met the demands, return to step C and rearrange GPS measurement point, carry out field survey.
F. shaft tower coordinate step e being obtained imports Microsoft Excel, generates shaft tower coordinate warehouse-in data file, so that power grid GIS platform directly reads in.

Claims (3)

1. the preparation method of transmission line tower coordinate, the method is based on computer technology, traverse adjustment computing technique and GPS measuring technique, and its feature comprises the following steps being:
A. by consulting transmission line of electricity archives material, gather the basic parameter of every transmission line of electricity, form the data text of this transmission line of electricity; The basic parameter of described data text comprises title, starting point, terminal, surveying instrument equipment, shaft tower number, mileage, the deflection angle of transmission line of electricity;
B. according to steps A, obtain the horizontal angle of shaft tower in transmission line of electricity and the horizontal range between adjacent shaft tower;
Described horizontal angle adopts following formula to calculate:
L 1=L 2+180°
Wherein: L 1: horizontal angle
L 2: deflection angle;
Described horizontal range adopts following formula to calculate:
D=S n+1-S n
Wherein: S n+1: n+1 shaft tower mileage
S n: n shaft tower mileage;
C. according to steps A and B, according to the fetch bit of power grid GIS accuracy requirement and mileage, deflection angle, the two base shaft towers of transmission line of electricity starting point and terminal of take are known point, arrange field GPS measurement point; The arrangement principle of described field GPS measurement point is:
C1. transmission line of electricity circuit starting point, terminal respectively arrange two base shaft towers and layout;
C2. for adopting GPSRTK method to measure, and mileage, deflection angle fetch bit are respectively centimetre and second situation, the centre that line length is less than or equal to 50km does not increase and layouts, line length increases a point as check point in the middle of when 50km is above;
C3. for adopting optical theodolite, total station survey or adopt GPSRTK method when wherein any mode being measured, when mileage, deflection angle fetch bit be respectively rice and minute situation time, by following formula estimation error,
Δd=0.5+1.2×S/10000
Δ d wherein: Horizontal position errors
S: line length, unit rice;
C4. according to increasing and layout in the middle of the accuracy requirement of power grid GIS;
D. the field GPS measurement point that adopts GPSRTK technology to arrange step C carries out obtaining of national coordinate;
E. by the data input lead compensating computation software of step B and D acquisition, carry out calculating, the input judgement of rough error and the judgement of coordinate precision of every base shaft tower coordinate;
E1. the mis-tie of the mis-tie of computer azimuth angle and shaft tower coordinate, judges whether to exist input rough error, if there is input rough error, rejects;
E2. fixing known point, weighs surely according to the fetch bit of the measuring method of location, surveying instrument equipment, horizontal angle, horizontal range, carries out compensating computation, calculates the coordinate of every base shaft tower, and judges whether the precision of every base shaft tower coordinate meets the demands; If do not met the demands, return to step C;
F. shaft tower coordinate step e being obtained imports Microsoft Excel, generates shaft tower coordinate warehouse-in data file.
2. the preparation method of transmission line tower coordinate according to claim 1, it is characterized in that: in described step e2, the computing method of every base shaft tower coordinate are, the horizontal angle obtaining by step B, calculates the position angle of shaft tower, then by position angle and span, is calculated respectively the coordinate of every base shaft tower;
Calculate as follows at described position angle:
L 3=L 0+180°+L 1
L wherein 0: initial known azimuth;
L 1: horizontal angle;
L 3: position angle;
The computing formula of shaft tower coordinate is:
X=X 0+S×cos(L 3)
Y=Y 0+S×sin(L 3)
X wherein 0: initial known ordinate;
Y 0: initial known horizontal ordinate;
S: the horizontal range between adjacent shaft tower;
L 3: position angle;
X: shaft tower ordinate;
Y: shaft tower horizontal ordinate.
3. the preparation method of transmission line tower coordinate according to claim 1, it is characterized in that: described steps A comprises the step of rule file being inputted to computer system, described rule file is the input rule of deflection angle, when the straight line pole deflection angle number of degrees are zero, left-hand rotation deflection angle is negative value, right-hand rotation deflection angle be on the occasion of.
CN201110377888.7A 2011-11-24 2011-11-24 Method for acquiring transmission line tower coordinate Active CN102495413B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110377888.7A CN102495413B (en) 2011-11-24 2011-11-24 Method for acquiring transmission line tower coordinate

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110377888.7A CN102495413B (en) 2011-11-24 2011-11-24 Method for acquiring transmission line tower coordinate

Publications (2)

Publication Number Publication Date
CN102495413A CN102495413A (en) 2012-06-13
CN102495413B true CN102495413B (en) 2014-03-26

Family

ID=46187253

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110377888.7A Active CN102495413B (en) 2011-11-24 2011-11-24 Method for acquiring transmission line tower coordinate

Country Status (1)

Country Link
CN (1) CN102495413B (en)

Families Citing this family (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102901451B (en) * 2011-07-26 2015-10-21 上海市电力公司 A kind of accurately quick method for the measuring and calculating of transmission and transformation engineering wire and device
CN104200046B (en) * 2014-09-18 2018-08-14 国家电网公司 A kind of three-dimensional power transmission line corridor band design method based on GIS
CN105804472B (en) * 2014-12-31 2018-01-12 浙江大华系统工程有限公司 A kind of localization method and device of shaft tower position
CN104850596B (en) * 2015-04-28 2018-01-02 国家电网公司 A kind of distribution data processing method based on mobile GIS and RTK positioning
KR20180018251A (en) * 2015-06-05 2018-02-21 파나소닉 아이피 매니지먼트 가부시키가이샤 Content displaying system
CN105738933B (en) * 2016-02-16 2017-11-24 国网山东省电力公司经济技术研究院 A kind of construction stake position repetition measurement method and device
CN108805336B (en) * 2018-05-18 2020-05-22 云南电网有限责任公司电力科学研究院 Method and device for selecting shared tower based on power grid geographic information system
CN110207638A (en) * 2019-05-20 2019-09-06 中国核工业华兴建设有限公司 A kind of on-fixed survey station purlin track road position inspecting method
CN111238627B (en) * 2020-01-20 2022-03-15 南京法艾博光电科技有限公司 Geographic information calibration method for strain tower in overhead transmission line
CN112163055B (en) * 2020-09-09 2023-11-21 成都深瑞同华科技有限公司 Tower labeling method
CN112698375B (en) * 2020-12-14 2023-10-20 国网辽宁省电力有限公司鞍山供电公司 Circuit drawing method for eliminating multi-domain double positioning errors
CN113884072B (en) * 2021-07-30 2023-09-01 山东电力工程咨询院有限公司 Automatic lofting method and system for line and tower foundation

Also Published As

Publication number Publication date
CN102495413A (en) 2012-06-13

Similar Documents

Publication Publication Date Title
CN102495413B (en) Method for acquiring transmission line tower coordinate
CN101825662B (en) Short-distance measurement method and structure of grounding resistance of grounding network
CN102721371B (en) Method for calculating sag of power transmission line
CN104698313B (en) DC magnetic bias current influences the Forecasting Methodology of website under many direct current grounding pole different running methods
CN108801141B (en) Intelligent debugging and calibrating system for ultrahigh-voltage isolating switch based on laser measurement technology
CN107462910A (en) A kind of field data measurement and real-time processing method based on high in the clouds fusion
CN102590701B (en) Coordinate calibration method for power transmission line towers
CN103954842B (en) Method for determining grounding resistance value of large-scale grounding system
CN109784540A (en) A kind of water supply layout optimization system and optimization method based on DMA subregion
CN110375711A (en) Ring network trackless measurement construction method in a kind of subway tunnel
CN102750413A (en) Data processing and mapping method of topographic surveying of electric transmission line tower positions
CN105844038B (en) A kind of highway polymorphic type traffic detector Combinatorial Optimization distribution method
CN110501612A (en) A kind of distributed power transmission state monitoring system and method
CN110070282A (en) A kind of low-voltage platform area line loss analysis of Influential Factors method based on Synthesis Relational Grade
CN103645490A (en) Method for monitoring attitude of continuous operating reference station (CORS) of global navigation satellite system (GNSS)
CN107393006A (en) A kind of method for weighing tunnel overall deformation
CN107084676A (en) A kind of method of phase spacing at the position for the anti-dancing device for obtaining transmission line of electricity
CN108151766A (en) Localization method, magnetic nail positioning navigation error correcting method and the positioning device of magnetic nail
CN107063207A (en) A kind of method that Multistage Control net measures power transmission cable tunnel axis
CN102590686B (en) A kind of method for determining radio interference of bipolar direct current transmission line
CN114491928A (en) Transformer magnetic bias direct current calculation method caused by subway stray current based on complex soil model
CN113513052A (en) BDS + BIM-based intelligent foundation pit monitoring system and method
CN105651311A (en) Method for measuring satellite navigation autopilot accuracy of agricultural machinery operation
CN106199202A (en) A kind of line steel tower grounded screen Transient grounding resistance measuring instrument
CN101403775B (en) Short-distance test method for grounding impedance of large grounding network

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 050031 No. 6 Jianhua Street, Shijiazhuang City, Hebei Province

Patentee after: China Electric Power Construction Group Hebei electric survey and Design Research Institute Co., Ltd.

Address before: 050031 No. 6 Jianhua Street, Shijiazhuang City, Hebei Province

Patentee before: Hebei Province Power Surveying Design & Research Institute