CN102493445A - Treatment method for deep-layer broken pile of prestressed pipe pile - Google Patents

Treatment method for deep-layer broken pile of prestressed pipe pile Download PDF

Info

Publication number
CN102493445A
CN102493445A CN2011104158294A CN201110415829A CN102493445A CN 102493445 A CN102493445 A CN 102493445A CN 2011104158294 A CN2011104158294 A CN 2011104158294A CN 201110415829 A CN201110415829 A CN 201110415829A CN 102493445 A CN102493445 A CN 102493445A
Authority
CN
China
Prior art keywords
pile
millimeters
deep
prestressed pipe
joint bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011104158294A
Other languages
Chinese (zh)
Inventor
宋功业
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Institute of Architectural Technology
Original Assignee
Jiangsu Institute of Architectural Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Institute of Architectural Technology filed Critical Jiangsu Institute of Architectural Technology
Priority to CN2011104158294A priority Critical patent/CN102493445A/en
Publication of CN102493445A publication Critical patent/CN102493445A/en
Pending legal-status Critical Current

Links

Abstract

The invention relates to a building construction technology, in particular to a treatment method for a deep-layer broken pile of a prestressed pipe pile, and belongs to the technical field of building construction. According to the method, a steel dowel is inserted into an inner hole of the pipe pile, and concrete is poured; the steel dowel is a continuous reinforcing steel bar which is made of four secondary reinforcing steel bars of which the diameter is 12 millimeters, and is welded on an iron plate of which the thickness is 3 millimeters, and the diameter is 250 millimeters; a stirrup is bond on a main reinforcement at each interval of 300 millimeters to enhance the whole rigidity of the reinforcing steel bars; superfine grouting materials are poured into drilled holes around the deep-layer broken pipe of the pipe pile; and underground barriers and the pipe pile are integrally connected to bear load together, and the bearing capacity of a pile foundation is enhanced.

Description

A kind of processing method of pile for prestressed pipe deep layer broken pile
Technical field
The present invention relates to a kind of building construction technology, be specifically related to a kind of processing method of pile for prestressed pipe deep layer broken pile, belong to technical field of building construction.
Background technology
In the pile foundation construction process of building operations building site; Often run into the caused fracture accident of underground obstacle; It is the deep layer broken pile of so-called pile for prestressed pipe; Get a probing point because geological prospecting is every separated 20-30 rice, in the geological prospecting report, just do not indicate at the underground obstacles such as boulder in the middle of this.After fracture accident took place, geological prospecting department must verify the position, size, character, proterties of underground obstacle etc. again, submitted to and replenished the geological prospecting report, the foundation of handling as broken pile.Must handle immediately in case broken pile takes place, and must guarantee that bearing capacity reaches designing requirement, otherwise building just there is the danger of toppling.The ring-shaped hollow rod-like structure that pile for prestressed pipe is made up of prestressed reinforcement and C70 concrete mostly, outer dia are generally 300 millimeters to 600 millimeters, and wall thickness is 50 millimeters to 100 millimeters mostly.It is strong that pile for prestressed pipe bears vertical load pressure, bear the horizontal loading ability relatively a little less than.In the piling process, fracture accident then might take place in the underground obstacle of not verifying when the stake end runs into geological prospecting sometimes.This type broken pile generally all occurs near the underground obstacle, so be called the deep layer broken pile.The pile for prestressed pipe broken pile that adopts is now handled pretty troublesome, and following several kinds of processing methods are generally arranged: 1, add stake and handle, behind the broken pile broken pile is passed into disuse, increase by three piles in addition, remodify pile cap.2, add two piles in the both sides of stake and on three piles, add beam to share the bearing capacity of broken pile.Above broken pile processing method is all wanted the pile driving equipment secondary to march into the arena and is mended pile driving construction, and the processing of every broken pile spends several ten thousand yuan at least, spends the handling of hundreds of thousands unit at most, needs human and material resources, the financial resources of labor.
Summary of the invention
The objective of the invention is for overcoming the weak point of above-mentioned prior art; A kind of processing method of pile for prestressed pipe deep layer broken pile is provided; This method is through inserting joint bar and concreting at the pile tube endoporus, and ultra-fine grouting material is injected in boring around pile tube deep layer broken pile, and underground obstacle and pile tube are connected into integral body; Common bearing load, the supporting capacity of enhancing pile foundation.
The present invention realizes with following technical scheme: a kind of processing method of pile for prestressed pipe deep layer broken pile; It is characterized in that: this method is through inserting joint bar and concreting at the pile tube endoporus; Ultra-fine grouting material is injected in boring around pile tube deep layer broken pile, specifically comprises the steps:
(1) holes downwards along the pile for prestressed pipe endoporus; After verifying the character, scope of underground obstacle, hole downwards along the pile for prestressed pipe endoporus, bore diameter equals the pile for prestressed pipe internal diameter again, and drilling depth is not less than 500 millimeters for going deep into underground obstacle inside;
(2) insert joint bar and concreting at the pile tube endoporus; With inserting joint bar in the hole of post, joint bar is processed elongated reinforcing bar for two grade reinforcing steels that adopt 12 millimeters of 4 diameters, is welded on 3 millimeters thick; On the diameter iron plate consistent with the diameter of boring; Be the integral rigidity of reinforcing steel bar, every at a distance from one stirrup of 300 millimeters colligations on main muscle, when iron plate is deep at the bottom of the underground obstacle hole; The stake top should be stretched out and is not less than 420 millimeters joint bar, is deep in the pile foundation support table;
(3) to pouring into the compensation non-shrinkage concrete in the pile for prestressed pipe hole; Concrete strength grade is not less than the concrete strength grade of cushion cap;
(4) around pile tube deep layer broken pile, bore some injected holes, inject ultra-fine grouting material; Grout material adopts superfine cement grouting material, outward appearance: the grey powder, and proportion: 3.0 ± 0.20, unit weight (apparent density kg/L): 0.7 ± 0.20, nonpoisonous and tasteless, fineness. specific area (cm 2/ g):>=8500; Range of grouting comprises in the outer 5 meters scopes of pile tube, the slip casting altitude range from stake hold following 500 millimeters to the scope of broken pile position end face 500-1000 millimeter.
Advantage of the present invention is: this method is holed around pile tube deep layer broken pile and is injected ultra-fine grouting material through at pile tube endoporus insertion joint bar and concreting, and underground obstacle and pile tube are connected into integral body, common bearing load, the supporting capacity of enhancing pile foundation.
The specific embodiment
Embodiment,
Certain engineering construction zone is positioned at the hill slope place, because bearing capacity of foundation soil is inhomogeneous, building adopts the prestressed pipe pile foundation, adopts pressing pile construction.In the pile foundation construction process, have a pile that resistance takes place earlier and increase, then find prominent heavy phenomenon, so stop operation, through the prospecting of geological prospecting unit, the stake position is on the about 15 meters boulder of diameter.After proposing processing scheme, approve jointly, implement through designing institute, Construction Party, management side, construction contractor.
(1) hole downwards along the pile for prestressed pipe endoporus, 250 millimeters of bore diameters, not going down not reaching the about 2 meters ground drill with ferrule in boulder position in the back of spudding in, thinks that possible pile tube fractures at this.More exchange device carries out mud jacking with pile tube fragmentation here, bores under 12 hours continued, until the inner about 500 millimeters places of boulder;
(2) insert joint bar and concreting at the pile tube endoporus; With inserting joint bar in the hole of post; Joint bar adopts two grade reinforcing steels of 12 millimeters of 4 diameters to process elongated reinforcing bar, is welded on 3 millimeters thick, on the iron plate that diameter is 250 millimeters; Be the integral rigidity of reinforcing steel bar, every at a distance from one stirrup of 300 millimeters colligations on main muscle; When iron plate was deep at the bottom of the underground obstacle hole, the stake top should be stretched out and is not less than 420 millimeters joint bar, is deep in the pile foundation support table;
(3) to pouring into C30 compensation non-shrinkage concrete in the pile for prestressed pipe hole, on obstruction, carry out slip casting around the pile tube; The concrete while of construction reinforced bar in pore, around pile tube, evenly choose at 6 as injected hole, every according to 2.5 meters of pile tubes; Be deep into boulder surface beginning slip casting, each injected hole from bottom to top once grouting to 2,5 meters more than the boulder; Make a Zhou Tuyu boulder be coupled to integral body, make the pile foundation load reliable;
(4) grout material adopts superfine cement grouting material, outward appearance: the grey powder, and proportion: 3.0 ± 0.20, unit weight (apparent density kg/L): 0.7 ± 0.20, nonpoisonous and tasteless, fineness. specific area (cm 2/ g):>=8500; Range of grouting comprises in the outer 5 meters scopes of pile tube, the slip casting altitude range from stake hold following 500 millimeters to the scope of broken pile position end face 500-1000 millimeter.
Pile foundation after above-mentioned processing, bearing capacity and integrality have all reached designing requirement.

Claims (1)

1. the processing method of a pile for prestressed pipe deep layer broken pile is characterized in that: this method is through inserting joint bar and concreting at the pile tube endoporus, and ultra-fine grouting material is injected in boring around pile tube deep layer broken pile, specifically comprises the steps:
(1) holes downwards along the pile for prestressed pipe endoporus; After verifying the character, scope of underground obstacle, hole downwards along the pile for prestressed pipe endoporus, bore diameter equals the pile for prestressed pipe internal diameter again, and drilling depth is not less than 500 millimeters for going deep into underground obstacle inside;
(2) insert joint bar and concreting at the pile tube endoporus; With inserting joint bar in the hole of post, joint bar is processed elongated reinforcing bar for two grade reinforcing steels that adopt 12 millimeters of 4 diameters, is welded on 3 millimeters thick; On the diameter iron plate consistent with the diameter of boring; Be the integral rigidity of reinforcing steel bar, every at a distance from one stirrup of 300 millimeters colligations on main muscle, when iron plate is deep at the bottom of the underground obstacle hole; The stake top should be stretched out and is not less than 420 millimeters joint bar, is deep in the pile foundation support table;
(3) to pouring into the compensation non-shrinkage concrete in the pile for prestressed pipe hole; Concrete strength grade is not less than the concrete strength grade of cushion cap;
(4) around pile tube deep layer broken pile, bore some injected holes, inject ultra-fine grouting material; Grout material adopts superfine cement grouting material, outward appearance: the grey powder, and proportion: 3.0 ± 0.20, unit weight (apparent density kg/L): 0.7 ± 0.20, nonpoisonous and tasteless, fineness. specific area (cm 2/ g):>=8500; Range of grouting comprises in the outer 5 meters scopes of pile tube, the slip casting altitude range from stake hold following 500 millimeters to the scope of broken pile position end face 500-1000 millimeter.
CN2011104158294A 2011-12-06 2011-12-06 Treatment method for deep-layer broken pile of prestressed pipe pile Pending CN102493445A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011104158294A CN102493445A (en) 2011-12-06 2011-12-06 Treatment method for deep-layer broken pile of prestressed pipe pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011104158294A CN102493445A (en) 2011-12-06 2011-12-06 Treatment method for deep-layer broken pile of prestressed pipe pile

Publications (1)

Publication Number Publication Date
CN102493445A true CN102493445A (en) 2012-06-13

Family

ID=46185301

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011104158294A Pending CN102493445A (en) 2011-12-06 2011-12-06 Treatment method for deep-layer broken pile of prestressed pipe pile

Country Status (1)

Country Link
CN (1) CN102493445A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106351218A (en) * 2016-08-31 2017-01-25 南京工业大学 Broken pile remedying method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200205765Y1 (en) * 2000-07-05 2000-12-01 주식회사정도엔지니어링 Reinforcing structure of foundation for pier
CN101413265A (en) * 2008-10-07 2009-04-22 天津二十冶建设有限公司 Defect reinforcing and processing construction method of drill filling pile

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200205765Y1 (en) * 2000-07-05 2000-12-01 주식회사정도엔지니어링 Reinforcing structure of foundation for pier
CN101413265A (en) * 2008-10-07 2009-04-22 天津二十冶建设有限公司 Defect reinforcing and processing construction method of drill filling pile

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
《城市道桥与防洪》 20110630 郑利松 桩端存在"孤石"的桩基的优化设计 第173页第2节至第174页第3节 1 , 第6期 *
冒海智: "静压管桩在工程中的应用", 《土工基础》, vol. 21, no. 02, 30 April 2007 (2007-04-30), pages 33 - 1 *
郑利松: "桩端存在"孤石"的桩基的优化设计", 《城市道桥与防洪》, no. 6, 30 June 2011 (2011-06-30) *
黄雄平: "压力注浆处理孤石夹层上PHC管桩基础", 《山西建筑》, vol. 32, no. 15, 31 August 2006 (2006-08-31), pages 84 - 6 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106351218A (en) * 2016-08-31 2017-01-25 南京工业大学 Broken pile remedying method

Similar Documents

Publication Publication Date Title
CN105840207B (en) Construction method for comprehensive tunnel entering structure of large-span tunnel penetrating shallow-buried bias-pressure loose accumulation body
KR101022382B1 (en) Precast horizontality tubular roof and tunnel construction method using the same
CN102828518B (en) Construction method for manual hole digging support pile prestress anchor cable anchoring structure
CN109024651B (en) Steel pipe concrete mixed pile foundation and construction method
CN104452784B (en) Composite bolt pile used for slope strengthening and construction technique of composite bolt pile
CN102926400B (en) Combined earth retaining wall structure and construction method thereof
CN105464074B (en) A kind of artificial digging pile high polymer grouting safeguard structure and its construction method
CN106759376A (en) Anchored Sheet Pile Wall for Excavation system and its construction method for closing on existing underground structure
CN110685286A (en) Deep foundation pit supporting construction process for adjacent road under complex geological condition
CN104790408A (en) Irregular foundation pit construction method
CN107642041A (en) The hollow clump of piles anchorage of super-large diameter
CN111648790B (en) Shallow-buried bias tunnel entry structure and construction method
CN110409525B (en) Soft soil and unfavorable geology composite foundation reinforcing method
CN104131566B (en) A kind of basement is without the construction method of horizontal support foundation ditch
CN206800370U (en) It is a kind of to excavate the continuous side wall supporting and retaining system protective construction in underground without fertile groove
CN111810185B (en) Tunnel bottom pre-reinforcement construction method
CN110080779A (en) Tunnel tunnel bottom karst cave treatment construction method
CN205576957U (en) Stake end pilework
CN105064332A (en) Construction method for bearing base piles of square pile bodies
CN107642040A (en) The construction method heavy stone used as an anchor of the hollow clump of piles anchorage of super-large diameter
CN209339156U (en) The embedding rock foot pilework of anchor tube formula in a kind of Extra-Deep Foundation Pit
CN208472713U (en) A kind of composite structure mini pile for administering small-sized landslide
CN108914947A (en) Foundation pit anchor wall draws the construction method of anchor supporting and its supporting construction of drilling tool and formation
CN102268877A (en) Construction method for great-depth or large-diameter mechanical expanding caisson pile
CN102493445A (en) Treatment method for deep-layer broken pile of prestressed pipe pile

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20120613