CN102456418B - 一种核反应堆冷却剂泵机械密封泄漏量异常的预防方法 - Google Patents

一种核反应堆冷却剂泵机械密封泄漏量异常的预防方法 Download PDF

Info

Publication number
CN102456418B
CN102456418B CN201010514552.6A CN201010514552A CN102456418B CN 102456418 B CN102456418 B CN 102456418B CN 201010514552 A CN201010514552 A CN 201010514552A CN 102456418 B CN102456418 B CN 102456418B
Authority
CN
China
Prior art keywords
filtrator
boron concentration
loop
row
standby
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201010514552.6A
Other languages
English (en)
Other versions
CN102456418A (zh
Inventor
王勤湖
刘军生
洪振旻
张朝文
曹智鹏
侯晔
王春
毛文军
安建军
袁建春
张兰岐
任合斌
何继强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China General Nuclear Power Corp
Guangdong Nuclear Power Joint Venture Co Ltd
Original Assignee
China General Nuclear Power Corp
Daya Bay Nuclear Power Operations and Management Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China General Nuclear Power Corp, Daya Bay Nuclear Power Operations and Management Co Ltd filed Critical China General Nuclear Power Corp
Priority to CN201010514552.6A priority Critical patent/CN102456418B/zh
Publication of CN102456418A publication Critical patent/CN102456418A/zh
Application granted granted Critical
Publication of CN102456418B publication Critical patent/CN102456418B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E30/00Energy generation of nuclear origin
    • Y02E30/30Nuclear fission reactors

Landscapes

  • Structures Of Non-Positive Displacement Pumps (AREA)

Abstract

本发明涉及一种核反应堆冷却剂泵机械密封泄漏量异常的预防方法,冷却剂泵的1号轴封注入水回路中设置有两列并联的过滤器,其中一列过滤器在线运行,另一列过滤器备用,该预防方法包括如下步骤:S1检测一回路的硼浓度;S2将一回路的硼浓度与备用列的过滤器的硼浓度作比较;S3当备用列的过滤器的硼浓度与一回路的硼浓度的差值超过预设值时,将备用列的过滤器切换至在线运行,将在线运行列的过滤器切换至备用。在本发明的预防方法中,当备用列过滤器的硼浓度与一回路的硼浓度之差大于预设值时,进行过滤器切换,可以利用备用列过滤器内相对高硼浓度的轴封注入水及时地对1号轴封密封面进行冲洗,可以及时有效的改善1号轴封密封面的密封状况。

Description

一种核反应堆冷却剂泵机械密封泄漏量异常的预防方法
技术领域
本发明涉及核电站的安全维护方法,更具体地说,涉及一种核反应堆冷却剂泵机械密封泄漏流量异常的预防方法。
背景技术
反应堆冷却剂系统(以下称RCP系统)即核电站一回路的主回路,其主要功能是使冷却剂循环流动,将堆芯中核裂变产生的热量通过蒸发器传输给二回路,同时冷却堆芯,防止燃料元件烧毁或毁坏。反应堆冷却剂泵简称主泵,一回路的每一条主环路有一台主泵,用于驱动冷却剂在RCP系统内循环。轴封组件(也称轴封系统)是核反应堆一回路主泵的关键部件,其性能的好坏直接影响泵的安全工作。
轴封系统由三道串联的轴封组成,位于泵轴末端,它的作用是保证在电厂正常运行期间从RCP系统沿泵轴向安全壳的泄漏量基本为零。第一道轴封是可控制的液膜密封,第二和第三道轴封是摩擦面密封。
第一道密封即1号密封,位于轴承上面,其结构如图1所示,它是流体静力平衡式、依靠液膜悬浮的受控泄漏轴封,其主要部件是一个随轴一起转动的动环和一个与密封外罩固定的静环(可上下移动)。动环和静环的不锈钢圈上喷涂氧化铝覆面,这样密封覆面很耐腐蚀,而且它的膨胀系数和不锈钢圈基本相同。在运转中两个环的表面并不接触,有一层液膜隔开,否则就会磨损,从而发生泄露。
参看图2,在正常运行中,温度为55摄氏度的轴封注入水以高于RCP系统绝对压力(约15.8Mp)进入泵中,流量约为1.8m3/h,在1号轴封内产生15.5Mp的压降。此注入水中大约11m3/h经泵轴和热屏向下流动,并进入RCP系统,这就防止一回路冷却剂进入泵轴和轴封区。其余0.7m3/h的注入水通过1号轴封,被第二道轴封即2号轴封阻挡,一小部分流过2号轴封,其余流入1号轴封泄漏管线,与RCP过剩下斜管线汇合后回到化学和容积控制系统(下称RCV系统)上冲泵入口处。
由于1号轴封是依靠液膜密封,系统在运行的过程中产生的杂质会对液膜密封造成破坏,造成泄漏量异常,泄漏量异常情况严重时会导致机组的核安全及运行安全事故。参看图3,为保障系统的安全运行,在1号轴封注入水回路上设置有并联的两列过滤器,一列在线运行,另一列备用,备用列过滤器内封有含硼酸的轴封注入水。当系统出现紧急情况或在线运行的过滤器两端的压差超过额定值时,将备用切入到系统中,将原来在线运行列切换至备用列。当过滤器两端的压差超过额定值时,意味着过滤器中已经积攒了大量的杂质,可能已经导致1号轴封已经产生的了破坏,不利于1号轴封泄漏的预防。
发明内容
本发明的目的在于提供一种核反应堆冷却剂泵机械密封泄漏量异常的预防方法,该方法可以预防核反应堆冷却剂泵机械密封泄流量异常的发生,延长主泵的工作寿命,保证核反应堆的正常运行。
本发明解决其技术问题所采用的技术方案是:构造种核反应堆冷却剂泵机械密封泄漏量异常的预防方法,所述冷却剂泵的1号轴封注入水回路中设置有两列并联的过滤器,其中一列过滤器在线运行,另一列过滤器备用,其特征在于,所述预防方法包括如下步骤:
S1检测一回路的硼浓度;
S2将一回路的硼浓度与备用列的过滤器的硼浓度作比较;
S3当备用列的过滤器的硼浓度与一回路的硼浓度的差值超过预设值时,将备用列的过滤器切换至在线运行,将在线运行列的过滤器切换至备用。
在本发明所述的核反应堆冷却剂泵机械密封泄漏量异常的预防方法中,所述预设值的范围为50~150ppm。
在本发明所述的核反应堆冷却剂泵机械密封泄漏量异常的预防方法中,所述预设值为100ppm。
在本发明所述的核反应堆冷却剂泵机械密封泄漏量异常的预防方法中,所述步骤S3中,当备用列的过滤器的硼浓度与一回路的硼浓度的差值超过预设值时,首先将备用列的过滤器切换至在线运行,两列过滤器短时并联运行,然后将原在线运行列的过滤器切换至备用。
在本发明所述的核反应堆冷却剂泵机械密封泄漏量异常的预防方法中,该预防方法还包括将切换至备用列的过滤器更换的步骤。
实施本发明的核反应堆冷却剂泵机械密封泄漏量异常的预防方法,具有以下有益效果:在本发明的预防方法中,当备用列过滤器的硼浓度与一回路的硼浓度之差大于预设值时,就将备用列过滤器和在线运行列过滤器进行切换,可以利用备用列过滤器内相对高硼浓度的轴封注入水及时地对1号轴封密封面进行冲洗,可以及时有效的改善1号轴封密封面的密封状况,有利于延长冷却剂泵的寿命,有利于系统安全可靠的运行。
附图说明
下面将结合附图及实施例对本发明作进一步说明,附图中:
图1是核反应堆冷却剂泵轴封结构示意图;
图2是核反应堆冷却剂泵轴封水流程图;
图3是核反应堆冷却剂泵轴封水注入、泄漏流程图;
具体实施方式
下面结合具体实施例详细介绍本发明的核反应堆冷却剂泵机械密封泄漏量异常的预防方法是如何实施的。
由于轴封注入水回路的部分水流入到一回路,另外一部分水和轴封泄漏水一起回流到轴封注入水回路中,稳定运行时,在线运行列滤网的硼浓度和一回路的硼浓度是一致的,所以检测一回路的硼浓度即可得到在线运行列的过滤器的硼浓度,一回路的硼浓度可以由一回路的硼浓度表读出;得到一回路硼浓度后和备用列的过滤器的硼浓度做比较,当备用列的过滤器的硼浓度与备用列的过滤器的硼浓度之差超高预设值时,将备用列的过滤器切换至运行列,两列过滤器短时并联运行,然后将原在线运行列过滤器切换至备用。与现有的过滤器切换流程相比,本发明的预防方法及早的切换了滤网,可以利用备用列过滤器内相对高硼浓度的轴封注入水及时地对1号轴封密封面进行冲洗,可以及时有效的改善1号轴封密封面的密封状况,有利于延长冷却剂泵的寿命,有利于系统安全可靠的运行,也使备用列过滤器得到充分的利用。
备用列过滤器的硼浓度可以通过以下方式获得,如果是新的过滤器,其硼浓度为封入到过滤器的轴封注入水的硼浓度;如果是运行过程中切换至备用列的过滤器的硼浓度,其硼浓度为切换时一回路的硼浓度。
备用列的过滤器的硼浓度与备用列的过滤器的硼浓度之差的预设值可以为50ppm、100ppm或150ppm,或者50~100ppm范围的任意值,优选100ppm。
当切换至备用列的过滤器,如果硼浓度已降至比较低的程度,可以将其更换为新的过滤器。
上面结合附图对本发明的实施例进行了描述,但是本发明并不局限于上述的具体实施方式,上述的具体实施方式仅仅是示意性的,而不是限制性的,本领域的普通技术人员在本发明的启示下,在不脱离本发明宗旨和权利要求所保护的范围情况下,还可做出很多形式,这些均属于本发明的保护之内。

Claims (4)

1.一种核反应堆冷却剂泵机械密封泄漏量异常的预防方法,所述冷却剂泵的1号轴封注入水回路中设置有两列并联的过滤器,其中一列过滤器在线运行,另一列过滤器备用,其特征在于,所述预防方法包括如下步骤:
S1检测一回路的硼浓度;
S2将一回路的硼浓度与备用列的过滤器的硼浓度作比较;
S3当备用列的过滤器的硼浓度与一回路的硼浓度的差值超过预设值时,将备用列的过滤器切换至在线运行,将在线运行列的过滤器切换至备用,所述预设值的范围为50~150ppm;
所述备用列的过滤器的硼浓度可以通过以下方式获得,如果是新的过滤器,其硼浓度为封入到过滤器的轴封注入水的硼浓度;如果是运行过程中切换至备用列的过滤器的硼浓度,其硼浓度为切换时一回路的硼浓度。
2.根据权利要求1所述的核反应堆冷却剂泵机械密封泄漏量异常的预防方法,其特征在于,所述预设值为100ppm。
3.根据权利要求1或2所述的核反应堆冷却剂泵机械密封泄漏量异常的预防方法,其特征在于,所述步骤S3中,当备用列的过滤器的硼浓度与一回路的硼浓度的差值超过预设值时,首先将备用列的过滤器切换至在线运行,两列过滤器短时并联运行,然后将原在线运行列的过滤器切换至备用。
4.根据权利要求3所述的核反应堆冷却剂泵机械密封泄漏量异常的预防方法,其特征在于,该预防方法还包括将切换至备用列的过滤器更换的步骤。
CN201010514552.6A 2010-10-21 2010-10-21 一种核反应堆冷却剂泵机械密封泄漏量异常的预防方法 Active CN102456418B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201010514552.6A CN102456418B (zh) 2010-10-21 2010-10-21 一种核反应堆冷却剂泵机械密封泄漏量异常的预防方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201010514552.6A CN102456418B (zh) 2010-10-21 2010-10-21 一种核反应堆冷却剂泵机械密封泄漏量异常的预防方法

Publications (2)

Publication Number Publication Date
CN102456418A CN102456418A (zh) 2012-05-16
CN102456418B true CN102456418B (zh) 2014-04-30

Family

ID=46039503

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201010514552.6A Active CN102456418B (zh) 2010-10-21 2010-10-21 一种核反应堆冷却剂泵机械密封泄漏量异常的预防方法

Country Status (1)

Country Link
CN (1) CN102456418B (zh)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104005946B (zh) * 2014-05-13 2016-07-06 哈尔滨电气动力装备有限公司 反应堆冷却剂泵流速控制器
CN105448367B (zh) * 2014-08-19 2017-09-08 中国广核集团有限公司 核电站主泵泄漏异常的处理方法
CN105179223B (zh) * 2015-09-07 2017-06-30 中广核核电运营有限公司 反应堆主泵的机械密封组件鉴定系统
FR3075450B1 (fr) * 2017-12-15 2019-12-27 Electricite De France Procede d'identification de l'unite a l'origine d'une fuite d'eau brute dans un condenseur d'une centrale thermique
CN112283096B (zh) * 2020-10-23 2023-03-10 岭东核电有限公司 核电站主泵密封泄漏干预方法、装置、设备及介质
CN112682327B (zh) * 2020-12-24 2022-05-24 中广核核电运营有限公司 一种主泵检修方法
CN113090552A (zh) * 2021-04-15 2021-07-09 苏州热工研究院有限公司 核电站主泵一号轴封泄漏量干预方法
CN116201722A (zh) * 2021-11-30 2023-06-02 福建福清核电有限公司 核电站主泵机械密封泄漏量高故障缓解方法

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4560529A (en) * 1983-02-01 1985-12-24 The United States Of America As Represented By The United States Department Of Energy Fuel washout detection system
CN101211674A (zh) * 2006-12-30 2008-07-02 大亚湾核电运营管理有限责任公司 核反应堆冷却剂泵机械密封泄漏量异常的快速处理方法

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4560529A (en) * 1983-02-01 1985-12-24 The United States Of America As Represented By The United States Department Of Energy Fuel washout detection system
CN101211674A (zh) * 2006-12-30 2008-07-02 大亚湾核电运营管理有限责任公司 核反应堆冷却剂泵机械密封泄漏量异常的快速处理方法

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
岭澳核电站反应堆冷却剂泵机械密封泄漏量异常的处理实践及原因初探;毛文军 等;《机械》;20091231;第36卷(第S1期);第125页第2栏,第126第3.1节-127页第4节,图4 *
毛文军 等.岭澳核电站反应堆冷却剂泵机械密封泄漏量异常的处理实践及原因初探.《机械》.2009,第36卷(第S1期),第125页第2栏,第126第3.1节-127页第4节,图4.
轻水堆核电站主冷却剂泵的发展动向;黄成铭;《核动力工程》;19880430;第9卷(第2期);28-34 *
黄成铭.轻水堆核电站主冷却剂泵的发展动向.《核动力工程》.1988,第9卷(第2期),28-34.

Also Published As

Publication number Publication date
CN102456418A (zh) 2012-05-16

Similar Documents

Publication Publication Date Title
CN102456418B (zh) 一种核反应堆冷却剂泵机械密封泄漏量异常的预防方法
US8817941B2 (en) Pressurized water reactor plant
KR101242746B1 (ko) 원자력 발전소의 격납건물 외부 통합피동안전계통 시스템
KR101234570B1 (ko) 냉각재 상실사고 완화가 가능한 일체형 원자로 및 그 완화방법
CN111540487A (zh) 一种蒸汽发生器传热管破事故后反应堆冷却处理方法
US11043310B2 (en) Valve assembly with isolation valve vessel
CN111081399B (zh) 核电厂应急堆芯冷却系统
WO2014048290A1 (zh) 一种能动与非能动相结合的堆腔注水冷却系统
EP3907743B1 (en) Passive pulse cooling method and system for nuclear power plant
CN104332206A (zh) 一种压水堆核电站启/停堆工况的超压保护方法
CN202887747U (zh) 一种能动与非能动相结合的堆腔注水冷却系统
KR102552914B1 (ko) 가압수형 핵 원자로의 정지를 관리하기 위한 방법
Xu et al. Transient Analysis of Dedicated Pressure Relief Valve Under High-Pressure Condition in Severe Accident for Tianwan 56 Nuclear Power Plant
Li et al. Nuclear Power Plant Design Optimization Based on Risk-Informed Method
CN116201722A (zh) 核电站主泵机械密封泄漏量高故障缓解方法
JP2016194419A (ja) 原子炉の安全システム
Shirahama et al. 2.3 Reactor coolant system and connected
JP3984038B2 (ja) 沸騰水型原子力発電所
Mitenkov et al. VPBER-600 conceptual features and safety analysis results
Baranaev et al. Emergency heat removal in the integral water cooled ABV-6 reactor for the Volnolom floating nuclear power plant
CN116344076A (zh) 一种用于严重事故缓解的海水淹没系统
JP2023124344A (ja) 高速炉の崩壊熱除去系熱交換器構造
Raflis Regulatory Challenges of Filtered Containment Venting in Indonesia
Beck Power reactor accidents in perspective
JPH055318B2 (zh)

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent for invention or patent application
CB02 Change of applicant information

Address after: Shenzhen science and technology building, No. 1001 Futian District Road, Shenzhen city in Guangdong province 518031 17-19 floor

Applicant after: China General Nuclear Power Corporation

Applicant after: Dayawan Nuclear Power Running Management Co., Ltd.

Address before: Shenzhen science and technology building, No. 1001 Futian District Road, Shenzhen city in Guangdong province 518031 17-19 floor

Applicant before: China Guangdong Nuclear Power Group Co., Ltd.

Applicant before: Dayawan Nuclear Power Running Management Co., Ltd.

COR Change of bibliographic data

Free format text: CORRECT: APPLICANT; FROM: CHINA GUANGDONG NUCLEAR POWER GROUP CO., LTD. TO: CHINA GENERAL NUCLEAR GROUP CO., LTD.

C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: CHINA GENERAL NUCLEAR GROUP CO., LTD.

Free format text: FORMER OWNER: DAYAWAN NUCLEAR POWER RUNNING MANAGEMENT CO., LTD.

Effective date: 20141212

Owner name: GUANGDONG NUCLEAR POWER JOINT CO., LTD.

Free format text: FORMER OWNER: CHINA GENERAL NUCLEAR GROUP CO., LTD.

Effective date: 20141212

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20141212

Address after: 518031 Guangdong city of Shenzhen province Futian District science and technology building, Shangbu Road 15

Patentee after: Guangdong Nuclear Power Joint Venture Co., Ltd

Patentee after: China General Nuclear Power Corporation

Address before: Shenzhen science and technology building, No. 1001 Futian District Road, Shenzhen city in Guangdong province 518031 17-19 floor

Patentee before: China General Nuclear Power Corporation

Patentee before: Dayawan Nuclear Power Running Management Co., Ltd.