CN102444276A - Auxiliary adjusting device and method for hydraulic climbing template - Google Patents

Auxiliary adjusting device and method for hydraulic climbing template Download PDF

Info

Publication number
CN102444276A
CN102444276A CN2011104297028A CN201110429702A CN102444276A CN 102444276 A CN102444276 A CN 102444276A CN 2011104297028 A CN2011104297028 A CN 2011104297028A CN 201110429702 A CN201110429702 A CN 201110429702A CN 102444276 A CN102444276 A CN 102444276A
Authority
CN
China
Prior art keywords
climbing
base plate
screw rod
hydraulic
adjusting device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2011104297028A
Other languages
Chinese (zh)
Other versions
CN102444276B (en
Inventor
周厚贵
戴志清
詹剑霞
刘晓华
马少甫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Gezhouba Group Co Ltd
Original Assignee
China Gezhouba Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Gezhouba Group Co Ltd filed Critical China Gezhouba Group Co Ltd
Priority to CN201110429702.8A priority Critical patent/CN102444276B/en
Publication of CN102444276A publication Critical patent/CN102444276A/en
Application granted granted Critical
Publication of CN102444276B publication Critical patent/CN102444276B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The invention relates to an auxiliary adjusting device for a hydraulic climbing template, comprising the hydraulic climbing template. A bottom plate is arranged on a climbing frame steel beam and is positioned below a bolt base of the climbing template; the bottom plate is provided with a sleeve which is in thread matching with a screw; and one end of the screw is contacted with the bolt base. According to the invention, by the auxiliary adjusting device arranged under the bolt base, an operator leads the climbing template to move vertically by rotating the screw, so that the purposes of accurately aligning and positioning are achieved. The auxiliary adjusting device is simple in structure, low in cost and convenience in operation, and not only is the labor intensity reduced, and is the construction time of aligning the template shortened, but also safe construction is benefitted.

Description

Hydraulic climbing shuttering auxiliary adjusting device and method
Technical field
The present invention relates to a kind of auxiliary adjusting device and method of concrete blinding, particularly a kind of hydraulic climbing shuttering auxiliary adjusting device and method.
Background technology
In certain engineering king-post tubular construction concrete construction, adopted hydraulic climbing shuttering to carry out the formwork erection construction.This cover template is mainly formed (seeing accompanying drawing 1) by climbing scaffold system and template system; Wherein that to be the M30 locating cone be connected with pouring concrete metope climbing scaffold system is fixing through anchor device, and jumping formwork then adopts the climbing frame girder steel of special bolt and climbing scaffold system to be slidingly connected.Because after former jumping formwork adopts hydraulic-driven preliminary in place; Need take the method for artificial adjustment that it is accurately adjusted the location; But a whole set of template weight is big; Therefore the time of wanting the manpower of labor and growing is the control template height accurately, reaches pinpoint purpose, has also strengthened the security risk of work high above the ground simultaneously.
Summary of the invention
Technical problem to be solved by this invention provides a kind of hydraulic climbing shuttering auxiliary adjusting device and method; Can solve and need the manpower of labor and long time control template height accurately in the original template system adjustment construction; Reach pinpoint purpose, also reduced the security risk of work high above the ground simultaneously.
For solving the problems of the technologies described above; The technical scheme that the present invention adopted is: a kind of hydraulic climbing shuttering auxiliary adjusting device, comprise hydraulic climbing shuttering, and base plate is installed on the climbing frame girder steel; Be positioned at the below of jumping formwork bolt base; Base plate is provided with sleeve, and sleeve cooperates with screw flight, and described screw rod one end contacts with the bolt base.
Described screw rod is provided with at least one place clamping head.
Described base plate is provided with a plurality of bolts hole.
A kind of hydraulic climbing shuttering is assisted method of adjustment, may further comprise the steps:
One, on the climbing frame girder steel of climbing scaffold system, the processing bolt hole, below of bolt base;
Two, make base plate, the bolt hole that the bolt hole size of preprocessing is complementary on processing and climbing frame girder steel on the base plate;
Three, the sleeve of welding band entire body internal thread on base plate is installed the screw rod that cooperates with bush whorl in the sleeve;
Four, behind the climbing scaffold system installation in position, the hydraulic-driven jumping formwork is tentatively in place, base plate is installed to the climbing frame girder steel, the screw rod jacking bolt base in the turnbarrel;
Realize accurate adjustment through above-mentioned steps to jumping formwork.
In the scheme of optimizing, in the step 4, the driving jumping formwork is tentatively in place when being lower than design attitude 0-20cm.
Described screw rod is provided with the clamping head that is used for the tool using rotary screw, and the external diameter of clamping head circumscribed circle is less than or equal to circular diameter at the bottom of the screw flight.
A kind of hydraulic climbing shuttering auxiliary adjusting device provided by the invention and method, through the auxiliary adjusting device that below the bolt base, is provided with, the operating personnel moves up and down jumping formwork through rotary screw, thereby reaches the purpose of accurate adjustment location.Apparatus structure of the present invention is simple, and cost is easy and simple to handle, has not only alleviated labour intensity, has shortened the engineering time of adjustment template, and has helped safe construction.
Description of drawings
Below in conjunction with accompanying drawing and embodiment the present invention is described further:
Fig. 1 is an overall structure sketch map of the present invention.
Fig. 2 is the main TV structure sketch map of auxiliary adjusting device among the present invention.
Fig. 3 is the plan structure sketch map of auxiliary adjusting device among the present invention.
The specific embodiment
In Fig. 1-Fig. 3; Comprise hydraulic climbing shuttering; The climbing frame girder steel 2 of climbing scaffold system 5 is that locating cone is installed on the concrete surface through a plurality of anchor devices 4, and jumping formwork 6 is connected with climbing frame girder steel 2 through bolt base 3, can be up and down along climbing frame girder steel 2 by hydraulically powered jumping formwork 6.Base plate 11 is installed on the climbing frame girder steel 2, is positioned at the below of jumping formwork 6 bolt bases 3, and base plate 11 is provided with sleeve 12, sleeve 12 and screw rod 13 threaded engagement, and described screw rod 13 1 ends contact with bolt base 3.
Described screw rod 13 is provided with at least one place clamping head 14.This clamping head 14 is used for tool using clamping rotary screw 13, is arranged on the two ends of screw rod 13 usually.
Described base plate 11 is provided with a plurality of bolts hole.
A kind of hydraulic climbing shuttering is assisted method of adjustment, may further comprise the steps:
One, on the climbing frame girder steel 2 of climbing scaffold system 5, the processing bolt hole, below of bolt base 3;
Two, make base plate 11, the bolt hole that the bolt hole size of preprocessing is complementary on processing and climbing frame girder steel 2 on the base plate; The hydraulic climbing shuttering auxiliary adjusting device is made in processing factory.The steel plate that base plate 11 adopts thickness to be not less than 1cm is processed, and on base plate 11, bolt hole is set, and the bolt hole size of reserving on the climbing frame girder steel 2 of the size of bolt hole and climbing scaffold system 5 is complementary;
Three, the sleeve 12 of welding band entire body internal thread on base plate 11 is installed the screw rod 13 with sleeve 12 threaded engagement in the sleeve 12; Sleeve 12 is processed by 1.5 cun thick walled steel tubes, in establish the entire body screw thread, sleeve of machine-shaping 12 and base plate 11 firm welding.The screw rod 13 that is used to support adopts φ 36 round steel to process, and the outside is the entire body screw thread, and two ends is established square clamping head.Described screw rod 13 is provided with the clamping head 14 that is used for tool using rotary screw 13, and the external diameter of clamping head 14 circumscribed circles is less than or equal to circular diameter at the bottom of screw rod 13 screw threads.
Four, as shown in Figure 1, climbing scaffold system 5 is that anchor device 4 is fixed on the concrete wall surface of having built through a plurality of M30 locating cones, is slidingly fitted with the special bolt base 3 of a plurality of connection jumping formworks 6 on the climbing frame girder steel 2 of climbing scaffold system 5.When hydraulic climbing shuttering 6 under the hydraulic-driven preliminary in place after, drive be when jumping formwork 6 is lower than design attitude 0-20cm tentatively in place.
Whole auxiliary adjusting device is installed in the bottom of each special bolt base 3; Adopt instrument rotation studdle 13 jacking special bolt bases 3 such as spanner; Hydraulic climbing shuttering 6 is moved up and down; Thereby reach the accurate adjustment to climbing scaffold system 5, it is fixing after meeting the requirements, to adopt a plurality of special bolts that jumping formwork 6 is connected with climbing frame girder steel 2.
Realize accurate adjustment through above-mentioned steps to jumping formwork 6.

Claims (6)

1. hydraulic climbing shuttering auxiliary adjusting device; Comprise hydraulic climbing shuttering; It is characterized in that: base plate (11) is installed on the climbing frame girder steel (2), is positioned at the below of jumping formwork (6) bolt base (3), and base plate (11) is provided with sleeve (12); Sleeve (12) and screw rod (13) threaded engagement, described screw rod (13) one ends contact with bolt base (3).
2. a kind of hydraulic climbing shuttering auxiliary adjusting device according to claim 1 is characterized in that: described screw rod (13) is provided with at least one place clamping head (14).
3. a kind of hydraulic climbing shuttering auxiliary adjusting device according to claim 1 is characterized in that: described base plate (11) is provided with a plurality of bolts hole.
4. a hydraulic climbing shuttering is assisted method of adjustment, it is characterized in that may further comprise the steps:
One, on the climbing frame girder steel (2) of climbing scaffold system (5), the processing bolt hole, below of bolt base (3);
Two, make base plate (11), the bolt hole that the bolt hole size of the last preprocessing of processing and climbing frame girder steel (2) is complementary on base plate;
Three, go up the sleeve (12) of welding band entire body internal thread at base plate (11), the screw rod (13) with sleeve (12) threaded engagement is installed in the sleeve (12);
Four, behind climbing scaffold system (5) installation in position, hydraulic-driven jumping formwork (6) is tentatively in place, base plate (11) is installed to climbing frame girder steel (2), screw rod (13) the jacking bolt base (3) in the turnbarrel (12);
Realize accurate adjustment through above-mentioned steps to jumping formwork (6).
5. a kind of hydraulic climbing shuttering according to claim 4 is assisted method of adjustment, it is characterized in that: in the step 4, driving jumping formwork (6) is tentatively in place when being lower than design attitude 0-20cm.
6. a kind of hydraulic climbing shuttering according to claim 4 is assisted method of adjustment; It is characterized in that: described screw rod (13) is provided with the clamping head (14) that is used for tool using rotary screw (13), and the external diameter of clamping head (14) circumscribed circle is less than or equal to circular diameter at the bottom of screw rod (13) screw thread.
CN201110429702.8A 2011-12-20 2011-12-20 Auxiliary adjusting method for hydraulic climbing template Active CN102444276B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110429702.8A CN102444276B (en) 2011-12-20 2011-12-20 Auxiliary adjusting method for hydraulic climbing template

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110429702.8A CN102444276B (en) 2011-12-20 2011-12-20 Auxiliary adjusting method for hydraulic climbing template

Publications (2)

Publication Number Publication Date
CN102444276A true CN102444276A (en) 2012-05-09
CN102444276B CN102444276B (en) 2014-03-05

Family

ID=46007180

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110429702.8A Active CN102444276B (en) 2011-12-20 2011-12-20 Auxiliary adjusting method for hydraulic climbing template

Country Status (1)

Country Link
CN (1) CN102444276B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105003075A (en) * 2015-08-07 2015-10-28 俊川建筑科技有限公司 Building construction system
CN105155844A (en) * 2015-08-07 2015-12-16 俊川建筑科技有限公司 Building constructive system

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4062513A (en) * 1975-09-11 1977-12-13 Lawrence Edwin Lindell Vertically adjustable wall forms
CA2260364A1 (en) * 1999-01-27 2000-07-27 Peter Vladikovic Concrete form suspension system and method
CN1912314A (en) * 2006-08-28 2007-02-14 杨秋利 Automatic hydraulic climbing shuttering
CN201962944U (en) * 2010-12-20 2011-09-07 江苏南通三建集团第十六建设发展有限公司 Hydraulic climbing formwork for building construction
CN202248860U (en) * 2011-10-12 2012-05-30 四川路桥建设股份有限公司 Hydraulic climbing formwork system
CN202370247U (en) * 2011-12-20 2012-08-08 中国葛洲坝集团股份有限公司 Auxiliary adjusting device for hydraulic climbing formwork

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4062513A (en) * 1975-09-11 1977-12-13 Lawrence Edwin Lindell Vertically adjustable wall forms
CA2260364A1 (en) * 1999-01-27 2000-07-27 Peter Vladikovic Concrete form suspension system and method
CN1912314A (en) * 2006-08-28 2007-02-14 杨秋利 Automatic hydraulic climbing shuttering
CN201962944U (en) * 2010-12-20 2011-09-07 江苏南通三建集团第十六建设发展有限公司 Hydraulic climbing formwork for building construction
CN202248860U (en) * 2011-10-12 2012-05-30 四川路桥建设股份有限公司 Hydraulic climbing formwork system
CN202370247U (en) * 2011-12-20 2012-08-08 中国葛洲坝集团股份有限公司 Auxiliary adjusting device for hydraulic climbing formwork

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105003075A (en) * 2015-08-07 2015-10-28 俊川建筑科技有限公司 Building construction system
CN105155844A (en) * 2015-08-07 2015-12-16 俊川建筑科技有限公司 Building constructive system

Also Published As

Publication number Publication date
CN102444276B (en) 2014-03-05

Similar Documents

Publication Publication Date Title
CN203603586U (en) Equipment support regulating device
CN101892812B (en) Reciprocating drill or electric drill support
CN202370247U (en) Auxiliary adjusting device for hydraulic climbing formwork
CN202370104U (en) Butted installing device for steel lattice column
CN112324160A (en) Temporary support frame for mounting assembly lattice type steel structure and use method
CN103912137A (en) Lifting device for lifting construction for buildings
CN203546728U (en) Improved installation fixing device of top-down steel pipe column
CN102496771B (en) Method and device for installing large-sized steel structural antenna
CN102444276A (en) Auxiliary adjusting device and method for hydraulic climbing template
CN202265778U (en) High-precision precast-beam positioning structure
CN210684499U (en) Hydraulic jacking device for pier column
CN102392540B (en) High-precision method and structure for positioning high-precision precast beam
CN215907403U (en) Fine adjustment tool for supporting large steel formwork
CN115492403A (en) Combined type precise positioning construction device for tower footing steel latticed column
CN214994011U (en) Municipal construction is with supporting location bed-jig
CN202100018U (en) High-precision positioning fixture for large-scale pre-buried bolts
CN211666301U (en) Steel constructs straightness control stop device that hangs down of post
CN107740583B (en) Beam bottom bar planting and feeding device and using method thereof
CN113309085A (en) Building foundation construction pouring construction method
CN108840234B (en) Hoisting device for prefabricated section and hoisting method thereof
CN202323896U (en) Accurate positioning device for embedded anchor cone
CN210224904U (en) Tunnel cable trench template mounting support
CN113385795B (en) Positioning device for cutting elliptical groove of cable guide pipe
CN212027098U (en) Portal system with leveling device
CN220099899U (en) Positioning device for reinforcing prestressed hollow floating square pile

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant