CN202100018U - High-precision positioning fixture for large-scale pre-buried bolts - Google Patents
High-precision positioning fixture for large-scale pre-buried bolts Download PDFInfo
- Publication number
- CN202100018U CN202100018U CN2011201928476U CN201120192847U CN202100018U CN 202100018 U CN202100018 U CN 202100018U CN 2011201928476 U CN2011201928476 U CN 2011201928476U CN 201120192847 U CN201120192847 U CN 201120192847U CN 202100018 U CN202100018 U CN 202100018U
- Authority
- CN
- China
- Prior art keywords
- bolts
- bolt
- positioning
- location
- fixture
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 230000007246 mechanism Effects 0.000 claims abstract description 16
- 238000010276 construction Methods 0.000 abstract description 2
- 238000000034 method Methods 0.000 abstract description 2
- 238000003466 welding Methods 0.000 abstract description 2
- 230000002787 reinforcement Effects 0.000 abstract 1
- 239000004575 stone Substances 0.000 description 13
- 229910000831 Steel Inorganic materials 0.000 description 5
- 239000010959 steel Substances 0.000 description 5
- 238000006073 displacement reaction Methods 0.000 description 3
- 230000007812 deficiency Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000002513 implantation Methods 0.000 description 1
- 230000002093 peripheral effect Effects 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model discloses a high-precision positioning fixture for large-scale pre-buried bolts. The high-precision positioning fixture for large-scale pre-buried bolts comprises four adjusting mechanisms and a positioning plate, wherein positioning holes are formed on the positioning plate; the internal diameters of the positioning holes are larger than the external diameters of the pre-buried bolts by 0.7 mm to 0.9 mm; and each adjusting mechanism comprises a base, wherein a set screw nut is fixedly connected onto the base, an adjusting bolt is in threaded connection with the set screw nut in the vertical direction; and the positioning plate is arranged at the top of the adjusting screw in a supporting manner. Through the adoption of the fixture, the leveling and the positioning of the bolts can be guaranteed; and during the using process, the upper parts of the bolts are fastened through screw caps, the middle and the bottoms of the bolts adopt horizontal and inclined spot welding through corresponding reinforcement bars, so that the bolts can not displace vertically and horizontally, and the pre-control parameter requirements for construction are ensured.
Description
Technical field
The utility model relates to positioning fixture, relates in particular to the high-precision fixed position fixture of large-scale pre-embedded bolt.
Background technology
Solve the hi-Fix problem of large-scale pre-embedded bolt in work progress, absolute altitude, the location of adjusting large-scale bolt are difficult point, the emphasis in work progress.The patent No. is that the Chinese patent of CN200410058289.9 discloses " sleeve is used in a kind of stone bolt location ", and this location in the position, bottom that outer peripheral face has the main body of all faces of polygon that rotate usefulness, is provided with the stone bolt screwed hole that screws togather with stone bolt with sleeve; In top bit; Be received in the set bolt that end face has the polygonal hole of rotation usefulness with screw-in version), between stone bolt screwed hole and set bolt, be provided with pressing body, in pressing body; Screwing togather between foot bolt screwed hole and the stone bolt concomitantly; Contact with the bottom face of the threaded shank of set bolt with the top end face of stone bolt, make stone bolt and main body be in the stationary state of double nut effect, in addition; In pressing body, the top end face of stone bolt and the bottom face of set bolt) the contact site be dome shape.This device is used for the individually implantation of foot bolt, can not carry out hi-Fix.The patent No. is that the Chinese patent of CN201020267898.6 discloses " stone bolt positioner "; This device comprises rigid platfor, fixing steel plate, pad; Fixing steel plate is fixed on the rigid platfor; Fixing steel plate is provided with locating hole, and the upper end of stone bolt is fixed by nut after passing locating hole on the fixing steel plate, pad successively.This device can easily not dismantled because rigid platfor and fixing steel plate are one, has reduced operating efficiency, and the while can not be according to the situation at the scene verticality to stone bolt, and absolute altitude is accurately adjusted the location.This device is used for the location of group's bolt, is not suitable for single bolt location.
Summary of the invention
The purpose of the utility model is to overcome the deficiency of prior art, provide a kind of can be well with the pre-embedded bolt location and guarantee that the large-scale pre-embedded bolt of its levelness, absolute altitude uses high-precision fixed position fixture.
The large-scale pre-embedded bolt of the utility model is used high-precision fixed position fixture; It comprises four guiding mechanisms and location-plate, on described location-plate, is provided with locating hole, and the internal diameter of described locating hole is than the big 0.7mm-0.9mm of external diameter of pre-embedded bolt; Each described guiding mechanism comprises base; On described base, be fixedly connected with hold-down nut, the adjustment screw rod that on described hold-down nut, vertically has been threaded, location-plate supports the top that is arranged on described adjustment screw rod.
Adopt these anchor clamps can guarantee bolt level and location, in use bolt top adopts that nut is fastening, bolt middle part and bottom adopt corresponding reinforcing bar level and oblique spot welding, makes it not produce displacement with level up and down, has guaranteed that construction controls parameter request in advance.
Description of drawings
Fig. 1 is the location-plate structural representation of the large-scale pre-embedded bolt of the utility model with high-precision fixed position fixture;
Fig. 2 is the structural representation of the large-scale pre-embedded bolt of the utility model with the guiding mechanism of high-precision fixed position fixture;
Fig. 3 is used for the sketch map of pre-embedded bolt location for location-plate shown in Figure 1.
The specific embodiment
Below in conjunction with accompanying drawing and specific embodiment the utility model is done to describe in detail.
The large-scale pre-embedded bolt of the utility model is used high-precision fixed position fixture shown in accompanying drawing; It comprises location-plate 1 and four guiding mechanisms; On described location-plate 1, be provided with locating hole 2; The internal diameter of described locating hole 2 is than the big 0.7mm-0.9mm of external diameter of pre-embedded bolt 3, and each described guiding mechanism comprises base 4, on described base, is fixedly connected with hold-down nut 5; On described hold-down nut, vertically be threaded and adjusted screw rod 6, location-plate supports the top that is arranged on described adjustment screw rod.
The method for using of these anchor clamps is following:
(internal diameter is only than design bolt external diameter big 0.7-0.9mm to utilize the locating hole of special fixture location-plate; And its center is consistent with design) pre-embedded bolt is positioned; When stone bolt was placed in wherein, the maximum displacement deviation that each bolt can produce was 0.35-0.45mm, and the maximum displacement deviation that any two bolts can produce is 0.7-0.9mm just; Characteristics based on special fixture itself; Precision control better, therefore as long as special fixture is installed with guiding mechanism and employing level and vertical guiding mechanism accurately after the adjustment, just can guarantee that the stone bolt precision of being inserted in the anchor clamps is controlled within the scope of design to pre-embedded bolt through total powerstation.
Anchor clamps are installed by guiding mechanism independently in advance, and four jiaos are adopted guiding mechanisms, regulate the guiding mechanism on four jiaos; Spirit level through being provided with at the anchor clamps periphery is a benchmark, makes anchor clamps on same horizontal plane, then guiding mechanism is fixed; Again pre-embedded bolt only is inserted in the locating hole than the big 0.7mm-0.9mm of its external diameter; The pre-embedded bolt bottom is provided with the vertical guiding mechanism jack of bolt (being used to regulate the bolt absolute altitude), and level gauge or total powerstation control bolt top mark height are adopted in the bolt top, and it is controlled within the same design elevation; Top, bolt top nut is fastening, it is not produced move up.
Claims (1)
1. large-scale pre-embedded bolt is used high-precision fixed position fixture; It is characterized in that: it comprises four guiding mechanisms and location-plate, on described location-plate, is provided with locating hole, and the internal diameter of described locating hole is than the big 0.7mm-0.9mm of external diameter of pre-embedded bolt; Each described guiding mechanism comprises base; On described base, be fixedly connected with hold-down nut, the adjustment screw rod that on described hold-down nut, vertically has been threaded, location-plate supports the top that is arranged on described adjustment screw rod.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011201928476U CN202100018U (en) | 2011-06-09 | 2011-06-09 | High-precision positioning fixture for large-scale pre-buried bolts |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011201928476U CN202100018U (en) | 2011-06-09 | 2011-06-09 | High-precision positioning fixture for large-scale pre-buried bolts |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202100018U true CN202100018U (en) | 2012-01-04 |
Family
ID=45386036
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011201928476U Expired - Fee Related CN202100018U (en) | 2011-06-09 | 2011-06-09 | High-precision positioning fixture for large-scale pre-buried bolts |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202100018U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105654995A (en) * | 2014-12-04 | 2016-06-08 | 中国核工业二四建设有限公司 | Nuclear power plant curved-surface high-precision pre-embedded sleeve fixing device |
CN114127367A (en) * | 2019-07-04 | 2022-03-01 | 维斯塔斯风力系统有限公司 | Method of forming a wind turbine foundation |
CN118327160A (en) * | 2024-06-12 | 2024-07-12 | 中建五局第三建设有限公司 | A method for installing embedded bolts of steel structure |
-
2011
- 2011-06-09 CN CN2011201928476U patent/CN202100018U/en not_active Expired - Fee Related
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105654995A (en) * | 2014-12-04 | 2016-06-08 | 中国核工业二四建设有限公司 | Nuclear power plant curved-surface high-precision pre-embedded sleeve fixing device |
CN105654995B (en) * | 2014-12-04 | 2017-12-15 | 中国核工业二四建设有限公司 | A kind of nuclear power station curved surface high accuracy embedded sleeve barrel fixing device |
CN114127367A (en) * | 2019-07-04 | 2022-03-01 | 维斯塔斯风力系统有限公司 | Method of forming a wind turbine foundation |
CN114127367B (en) * | 2019-07-04 | 2023-11-17 | 维斯塔斯风力系统有限公司 | Method of forming a wind turbine foundation |
US12018448B2 (en) | 2019-07-04 | 2024-06-25 | Vestas Wind Systems A/S | Method of forming a wind turbine foundation |
CN118327160A (en) * | 2024-06-12 | 2024-07-12 | 中建五局第三建设有限公司 | A method for installing embedded bolts of steel structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204040056U (en) | A kind of location and installation support of pre-embedded anchoring bolts | |
CN201649690U (en) | Height adjustable support of steel-tube back shore | |
CN102061746B (en) | Steel structure assembled embedded part and construction method thereof | |
CN203783165U (en) | Multi-directional accurate adjusting device for embedded part | |
CN203625921U (en) | Precision control device for pre-embedded mounting of foundation bolts | |
CN202100018U (en) | High-precision positioning fixture for large-scale pre-buried bolts | |
CN104032969A (en) | Precise positioning and process regulation and control device for vibration isolation support embedded plate | |
CN205776306U (en) | Steel column base bolt positioning device and steel column base structure | |
CN201059070Y (en) | Locating formwork for steelwork pole bottom embedded bolt group | |
CN202000651U (en) | Adjustable wall-mounted supporting device for reinforcing upright columns | |
CN102829287B (en) | Supporting and levelling device and test stand using same | |
CN202000727U (en) | Steel tube upright column adjusting base | |
CN204151820U (en) | Stone bolt location and installation support | |
CN105370051A (en) | Concrete stand column adjusting bracket | |
CN101492967A (en) | Steel column error-correcting method | |
CN203347249U (en) | Perpendicularity adjusting device applied to steel column mounting | |
CN205000354U (en) | Rim of a cup basis steel column installation elevation control structure | |
CN109972847A (en) | A positioning and vertical adjustment device for a structural column | |
CN102423846A (en) | Assembly device for cam shaft | |
CN202280074U (en) | Foundation bolt positioning sleeve | |
CN202370247U (en) | Auxiliary adjusting device for hydraulic climbing formwork | |
CN211114901U (en) | Bracket device convenient to precast beam is under construction fast | |
CN205224569U (en) | Template steel pipe support support structure | |
CN210622214U (en) | Overhead ground support adjusting foot | |
CN102444276B (en) | Auxiliary adjusting method for hydraulic climbing template |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20120104 Termination date: 20150609 |
|
EXPY | Termination of patent right or utility model |