CN102418525B - 软煤层长壁大采高综合机械化采煤末采方法 - Google Patents

软煤层长壁大采高综合机械化采煤末采方法 Download PDF

Info

Publication number
CN102418525B
CN102418525B CN201110334117.XA CN201110334117A CN102418525B CN 102418525 B CN102418525 B CN 102418525B CN 201110334117 A CN201110334117 A CN 201110334117A CN 102418525 B CN102418525 B CN 102418525B
Authority
CN
China
Prior art keywords
mining
coal
height
working face
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201110334117.XA
Other languages
English (en)
Other versions
CN102418525A (zh
Inventor
杨文斌
王永革
张育恒
王家学
田书龙
胡红伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanxi Jincheng Anthracite Mining Group Co Ltd
Original Assignee
Shanxi Jincheng Anthracite Mining Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanxi Jincheng Anthracite Mining Group Co Ltd filed Critical Shanxi Jincheng Anthracite Mining Group Co Ltd
Priority to CN201110334117.XA priority Critical patent/CN102418525B/zh
Publication of CN102418525A publication Critical patent/CN102418525A/zh
Application granted granted Critical
Publication of CN102418525B publication Critical patent/CN102418525B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

本发明涉及一种煤矿井下末采技术,具体为一种软煤层长壁大采高综合机械化采煤末采方法。解决现有技术在长壁大采高软煤层的工作面的条件下末采带来的煤壁垮塌的问题。大采高长壁工作面采高大于3.5米以上,至少采用一进一回的工作面布置方式,工作面推进到末采线后,支架停止前移,然后在工作面机尾安装掘进机,采用综掘工艺将撤架通道做出,完成末采。本明所述的工艺适应复杂地质条件的能力强。可以根据地质条件和顶板压力的变化规律,灵活选择末采的地点和时间,安全系数高。

Description

软煤层长壁大采高综合机械化采煤末采方法
技术领域
本发明涉及一种煤矿井下末采技术,具体为一种软煤层长壁大采高综合机械化采煤末采方法。
背景技术
目前,我国煤矿综合机械采煤工作面末采主要采用两种方式:第一种为综采工作面末采一直沿用的距终采线一定距离铺网,支架尾梁后的网下实后,停止拉架,然后将支架和溜子的框架摘开,用采煤机将撤出通道割出,然后进行支护撤架通道。第二种为我国神东矿区综采工作面采用的多辅巷多通道式胶轮搬运车回撤安装工艺。即在回采工作面停采线处,预先掘出两条平行于回采工作面的辅助巷道,然后在两条辅巷之间,掘出若干条联巷,就构成了“回撤通道”系统。靠工作面停采线的第一条辅巷,是作为回采工作面液压支架回撤时的调向通道,称为“主回撤通道”,工作面要与此巷道采通;外侧一条铺巷是作为工作面液压支架撤出时的辅助运输通道,两辅巷之间的联巷则成为工作面采取多头作业、分段放顶的安全出口。然后工作面和主回撤通道平行贯通,贯通后该通道就作为回撤支架的空间。
采用以上两种末采方法,在坚硬煤层下基本能满足大采高工作面末采做通道技术生产需要。但是在软煤层条件下,采用以上的末采方法存在顶板难以控制的弊端,非常容易造成人员伤亡。如图1、2所示意,撤架通道4为提前施工好的,停采线和撤架通道4还有一定的距离,该距离一般都比较短,最后形成一个薄煤壁3,而软煤层的特点是煤层脆性大,尤其是在采高大于3.5米的条件下,特别容易在采煤机的震动下突然垮塌,给作业人员造成危险,损坏机械设备。
发明内容
本发明为了解决现有技术在长壁大采高软煤层的工作面的条件下末采带来的煤壁垮塌的问题而提供了一种软煤层长壁大采高综合机械化采煤末采方法。
本发明是由以下技术方案实现的,一种软煤层长壁大采高综合机械化采煤末采方法,大采高长壁工作面采高大于3.5米以上,至少采用一进一回的工作面布置方式,工作面推进到末采线后,支架停止前移,然后在工作面机尾安装掘进机,采用综掘工艺将撤架通道做出,完成末采。
与现有的末采技术相比本发明专利的优点是:
1、工作面采用此方法做末采做撤架通道时,工作面控顶面积较小,支护简单、强度高,撤架通道不容易发生顶板下沉等矿压显现。
2、撤架通道采用了综掘机组进行施工作业,撤架通道的支护不需要搭脚手架,施工人员不需要高空作业,安全系数高。
3、做撤架通道时,不需要降低采高,工作面的资源回收率较高。
4、该方法不要与撤架通道对接,更不需要提前施工撤架通道,适应复杂地质条件的能力强。可以根据地质条件和顶板压力的变化规律,灵活选择末采的地点和时间。
附图说明
图1为现有末采技术的俯视图
图2为现有末采技术的侧视图
图3为本发明所述工艺的俯视图
图4为本发明所述工艺的侧视图。
具体实施方式
如图3、4所示意,在硬度系数小于1.5的软煤层长壁3.5米以上的大采高下综合机械化采煤末采方法,步骤为:
1、综合机械化大采高采煤工作面的布置采用超过一百米的长壁式开采,至少采用一进一回的工作面布置方式,并且用全部跨落法管理顶板。
2、从开始末采上网到支架1停止前移的末采阶段和正常末采过程一致,即在回采工作面距离停采线一段(20m)距离开始在支架1顶部上第一趟网,在第三趟开始上双网并开始上钢丝绳,最后支架尾梁后的金属网7压实后,达到末采线,停止割煤及前移拉架。(如图1、2所示意)
3、在工作面机尾辅助运输顺槽内安装掘进机5等设备,然后开始利用掘进机5割煤将撤架通道6做出,工艺过程为:割煤,装煤,临时支护,永久支护,清煤。
撤架通道内的割煤:将撤架通道割出,割煤方式为:通过升降摇臂从靠工作面侧顶板往煤壁里然后向下或从工作面侧底板下向上称“正S或倒S”行割煤(如图4所示意)。以上割煤方式的选择可以根据撤架通道高度大小合理选择,以工人进行永久护不进行高空作业为原则。
装煤:利用工作面已经安装好的刮板输送机将撤架通道的煤运出。
临时支护:可以采用前探梁、单体柱等多种形式。
永久支护:撤架通道采用高强度锚杆、高强度玻纤树脂锚杆、钢筋托梁、金属网、混合支护。即巷道采用高强度锚杆树脂加长锚固锚杆组合支护系统,并进行锚索补强。

Claims (2)

1.一种软煤层长壁大采高综合机械化采煤末采方法,其特征是大采高长壁工作面采高大于3.5米,至少采用一进一回的工作面布置方式,工作面推进到末采线后,支架停止前移,然后在工作面机尾安装掘进机,采用综掘工艺将撤架通道做出,完成末采。
2.根据权利要求1所述的软煤层长壁大采高综合机械化采煤末采方法,其特征是综掘工艺为,割煤,装煤,临时支护,永久支护,清煤。
CN201110334117.XA 2011-10-28 2011-10-28 软煤层长壁大采高综合机械化采煤末采方法 Active CN102418525B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110334117.XA CN102418525B (zh) 2011-10-28 2011-10-28 软煤层长壁大采高综合机械化采煤末采方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110334117.XA CN102418525B (zh) 2011-10-28 2011-10-28 软煤层长壁大采高综合机械化采煤末采方法

Publications (2)

Publication Number Publication Date
CN102418525A CN102418525A (zh) 2012-04-18
CN102418525B true CN102418525B (zh) 2014-07-09

Family

ID=45943145

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110334117.XA Active CN102418525B (zh) 2011-10-28 2011-10-28 软煤层长壁大采高综合机械化采煤末采方法

Country Status (1)

Country Link
CN (1) CN102418525B (zh)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102777182B (zh) * 2012-08-11 2014-04-16 山西晋城无烟煤矿业集团有限责任公司 大采高工作面快速末采方法
CN103016008B (zh) * 2012-12-20 2015-04-15 大同煤矿集团有限责任公司 煤层群下行式开采下部煤层的停采方法
CN104453966B (zh) * 2014-10-24 2016-05-18 山西晋城无烟煤矿业集团有限责任公司 大采高末采综掘机做撤架通道过陷落柱架无腿棚施工方法
CN108825235B (zh) * 2018-05-04 2020-01-10 内蒙古伊泰煤炭股份有限公司 煤矿开采高向位置标志方法及结构以及煤矿末采方法
CN110454163B (zh) * 2019-08-30 2024-03-26 陕煤集团神木红柳林矿业有限公司 一种综采工作面快速末采回撤及淸煤工艺
CN112879008B (zh) * 2021-01-26 2022-03-15 中国矿业大学 适用于自掘通道式回撤工艺的支护系统及支护方法
CN114776355B (zh) * 2022-04-18 2023-08-22 内蒙古满世煤炭集团罐子沟煤炭有限责任公司 一种煤层破碎带回撤通道加强支护确定方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1865657A (zh) * 2005-05-19 2006-11-22 兖矿集团有限公司 长壁采煤法综采工艺
CN1888390A (zh) * 2006-07-12 2007-01-03 山西潞安矿业(集团)有限责任公司 高瓦斯松软厚煤层准大采高综采低位放顶煤开采技术
CN101126316A (zh) * 2007-09-19 2008-02-20 中国矿业大学 一种长壁综采回收房式开采煤柱的方法
CN101876248A (zh) * 2009-04-30 2010-11-03 乔伊·姆·特拉华公司 用于保持长壁开采工作面对准的方法及设备
CN101970795A (zh) * 2008-02-19 2011-02-09 拉格股份公司 控制长壁开采作业的方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1865657A (zh) * 2005-05-19 2006-11-22 兖矿集团有限公司 长壁采煤法综采工艺
CN1888390A (zh) * 2006-07-12 2007-01-03 山西潞安矿业(集团)有限责任公司 高瓦斯松软厚煤层准大采高综采低位放顶煤开采技术
CN101126316A (zh) * 2007-09-19 2008-02-20 中国矿业大学 一种长壁综采回收房式开采煤柱的方法
CN101970795A (zh) * 2008-02-19 2011-02-09 拉格股份公司 控制长壁开采作业的方法
CN101876248A (zh) * 2009-04-30 2010-11-03 乔伊·姆·特拉华公司 用于保持长壁开采工作面对准的方法及设备

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
优化撤架通道支护实现综采快速搬家;李建胜等;《山西科技报》;20050621;第006版,1-3页 *
李建胜等.优化撤架通道支护实现综采快速搬家.《山西科技报》.2005,

Also Published As

Publication number Publication date
CN102418525A (zh) 2012-04-18

Similar Documents

Publication Publication Date Title
CN102418525B (zh) 软煤层长壁大采高综合机械化采煤末采方法
CN104533416B (zh) 极厚大矿体大规模机械化无底柱分段崩落采矿方法
CN102493838B (zh) 一种急倾斜煤层综采连续充填采煤方法
CN104405437B (zh) 一种固体充填与综采混合式工作面开采方法
CN103742148B (zh) 一种急倾斜煤层柔掩支护下行矸石充填的采煤法
CN104234749B (zh) 一种综采工作面大断面回撤通道围岩控制方法
CN102644476B (zh) 保护层机巷高位钻场穿层钻孔抽采被保护层瓦斯的方法
CN104481578B (zh) 一种高瓦斯煤层大采高工作面瓦斯治理方法
CN103485786B (zh) 一种急倾斜煤层走向长壁机械化开采方法
CN102900444B (zh) 改进型综采工作面液压支架回撤工艺
CN103104260B (zh) 复杂地质条件下综—机对拉面采煤方法
CN105626071A (zh) 一种缓倾斜薄矿体采矿方法
CN102943690A (zh) 采煤工作面顶板离层水的防治方法
CN106522953B (zh) 一种急倾斜厚煤层走向长壁综放开采动态分段采放工艺
CN104632220A (zh) 缓倾斜中厚矿体条柱再造采场结构尺寸可调可控采矿方法
CN103206215A (zh) 一种预控顶上向进路充填采矿法
CN105736044A (zh) 一种急倾斜煤层综采工作面设备快速回撤方法
CN103939135A (zh) 一种综采工作面撤架通道快速施工方法
CN105863639A (zh) 松散煤层的采煤方法
CN106089234B (zh) 一种长距离辅巷多通道快速回撤综采工作面的方法
CN105134212B (zh) 一种三软厚煤层巷道沿顶掘进综放开采保证回采率的方法
CN109252863A (zh) 一种利用煤巷掘进机开采破碎型厚矿体的方法
CN104533419A (zh) 一种部分回收大煤柱残煤的方法
CN105240012A (zh) 一种实现煤柱同采的f型区段采煤方法
CN104405392A (zh) 三软厚煤层巷道托顶留底锚网索主动支护综放开采方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant