Overpass concrete outside-hanged cantilever type flower bed and construction method thereof
Technical field
The present invention relates to a kind of partial structurtes of urban interchange, especially a kind of overpass concrete outside-hanged cantilever type flower bed relates to and construction method simultaneously, belongs to technical field of building construction.
Background technology
According to the applicant understood, the flower bed on existing urban interchange mostly adopts and is connected with anti-collision wall rod member, again greening flower case is put into structure wherein hanging case.This structure exists between external hanging type extension case connection bearing and cement the problems such as crack, the perishable rustization of partial fixing bolt are become flexible, plastic containers shell embrittlement breakage, plumbing facility imperfection, has potential safety hazard.
Application number is that the Chinese patent application of CN201010137605.7 discloses a kind of assembled stereoscopic flower bed and preparation method, can realize the assembled stereoscopic flower bed of any regular or irregular surfaces moulding.But this flower bed structure is not also suitable for urban interchange.
Summary of the invention
The object of the invention is to: the problem existing for above-mentioned prior art, propose a kind of with overpass bridge one and there is the overpass concrete outside-hanged cantilever type flower bed that improves drainage, thereby avoid various unsafe factors.Meanwhile, the present invention also will provide its construction method, thereby make it practical.
In order to reach above object, overpass concrete outside-hanged cantilever type flower bed of the present invention comprises by the upwardly extending steel concrete rib in horizontal bridge deck width direction edge, described steel concrete rib bottom is also outwards extended circular arc Wai Tan limit upward, the up big and down small altar chamber that between described Wai Tan limit and described rib, Formation cross-section is approximate trapezoid, bottom, described altar chamber place mat hardcore bed, described hardcore bed upper surface supports the horizontal water-supply-pipe extending along altar cavity length direction, described concrete rib is intervally distributed with the gutter that penetrates that is led to bridge floor tapping pipe by altar chamber hardcore bed upper surface.
Overpass concrete outside-hanged cantilever type flower bed construction method of the present invention comprises following basic step:
The first step, support is set---in position, extrorse beam limit, horizontal bridge deck width side, stone bolt is set, the fixing prefabricated outer tripod of choosing, and the external mold Zhi Li that interior profile shape and Wai Tan limit gabarit shape are matched is fixed on outward and chooses on tripod;
Second step, assembling reinforcement---the Wai Tan limit shape of outwards extending upward according to concrete rib and by its bottom is carried out reinforcing bar binding in external mold;
The 3rd step, security protection pipeline---spaced apart by hardcore bed upper surface position, the predetermined altar chamber fixing longitudinal drainage pipe that leads to bridge floor tapping pipe of arranging at predetermined concrete rib place;
The 4th step, build template---by with altar chamber and concrete rib inside the internal mold Zhi Li that matches of shape be fixed on horizontal bridge deck width direction edge, form pouring concrete shape chamber with external mold;
The 5th step, concreting---concrete is poured into gradually in the cast shape chamber of external mold and internal mold formation;
The 6th step, cleaning completion---after concrete sizing, remove plug-in tripod and interior external mold, by rubble place mat to bottom altar chamber, and by water-supply-pipe along altar cavity length direction lay to hardcore bed.
In overpass concrete outside-hanged cantilever type flower bed of the present invention after planting plants; the outstanding feature of not only there is greening bridge, beautifying city, not taking up an area face; also there is the effect that strengthens overpass bridge intensity and there is anti-collision wall simultaneously, play reliable safeguard protection effect, achieve many things at one stroke.And construction method constructing structure good integrity of the present invention is simple and easy to do, speed is fast, and upper and lower part structure can parallel operations, save space.After completion, do not need again to arrange colored case, economical and practical, safe and reliable, be convenient to virescence maintenance.
Brief description of the drawings
Below in conjunction with accompanying drawing, the present invention is further illustrated.
Fig. 1 is the structural representation of one embodiment of the invention.
Detailed description of the invention
Embodiment mono-
The overpass concrete outside-hanged cantilever type flower bed of the present embodiment as shown in Figure 1, upwards extended spot steel concrete rib 2 of horizontal bridge floor 1 widthwise edges.Steel concrete rib 2 tops are by the fixing anticollision barrier 4 of pre-buried lower margin, and bottom is outwards extended circular arc Wai Tan limit 5 upward.The exterior arc surface on this Wai Tan limit 5 extends the edge end face that is coated to horizontal bridge floor 1, not only makes overpass bridge profile more attractive in appearance, and contributes to strengthen its intensity.The up big and down small altar chamber 6 that between Wai Tan limit 5 and steel concrete rib 2, Formation cross-section is approximate trapezoid.Owing to adopting concreting to form, therefore form one with bridge, overall structure is good, has strengthened the function of anti-collision wall simultaneously, safer, reliable.Altar chamber 6 bottom place mat hardcore beds 7, hardcore bed 7 upper surfaces support the horizontal water-supply-pipe 8 extending along altar cavity length direction, on horizontal water-supply-pipe 8, have water seepage hole.Concrete rib 2 be intervally distributed with lead to bridge floor tapping pipe by altar chamber hardcore bed 7 upper surfaces penetrate gutter 9, thereby make internal drainage pipe in altar chamber be connected supporting with overpass bridge drainage.
The overpass concrete outside-hanged cantilever type flower bed construction sequence of the present embodiment is:
The first step, support is set---in position, extrorse beam limit, horizontal bridge deck width side, stone bolt is set, the fixing prefabricated outer tripod of choosing, and the external mold Zhi Li that interior profile shape and Wai Tan limit gabarit shape are matched is fixed on outward and chooses on tripod;
Second step, assembling reinforcement---the Wai Tan limit shape of outwards extending upward according to concrete rib and by its bottom is carried out reinforcing bar binding in external mold; Bar splice lap length is 32-36 times of bar diameter, conventionally gets 36d.For ensureing thickness of protection tier, reinforcing bar bottommost is lined with the mortar pad suitable with predetermined protective layer thickness with the distance interval of 1 meter of spacing;
The 3rd step, security protection pipeline---spaced apart by hardcore bed upper surface position, the predetermined altar chamber fixing longitudinal drainage pipe that leads to bridge floor tapping pipe of arranging at predetermined concrete rib place;
The 4th step, build template---by with altar chamber and concrete rib inside the internal mold Zhi Li that matches of shape be fixed on horizontal bridge deck width direction edge, form pouring concrete shape chamber with external mold; Plug-in cantilever type flower bed is clear-water concrete, does not allow to carry out any repairing, so template and support are most important to concrete presentation quality;
The 5th step, concreting---concrete is poured into gradually in the cast shape chamber of external mold and internal mold formation; The concrete slump is controlled at 12-14cm, and building stones particle diameter is 5-25mm; Preferably adopt concreting in lifts, first floor is built to altar chamber bottom, carries out concrete and shakes again, drives as far as possible the second layer concreting on carrying out again after the bubble accumulating;
The 6th step, cleaning completion---after concrete sizing, remove plug-in tripod and interior external mold, by rubble place mat to bottom altar chamber, and by water-supply-pipe along altar cavity length direction lay to hardcore bed.
Compared with the mode that extension case is connected with anti-collision wall rod member, adopt structure and the method for the present embodiment, because adopting concreting, flower bed forms, form entirety with bridge, flower bed gutter is easily connected with overpass bridge drainage, not only strengthen collision prevention function, also contribute to strengthen the intensity of overpass bridge, hang between case connection bearing and cement and have crack at the external hanging type of having properly settled prior art existence, partial fixing bolt corrosion rustization is loosening, plastic containers shell embrittlement breakage, when the problems such as plumbing facility imperfection, also make bridge more attractive in appearance, the virescence maintenance work in later stage becomes safety, convenient, economical.
In addition to the implementation, the present invention can also have other embodiments.All employings are equal to the technical scheme of replacement or equivalent transformation formation, all drop on the protection domain of requirement of the present invention.