CN102361315B - 海域地下缆线三同步敷设施工方法 - Google Patents

海域地下缆线三同步敷设施工方法 Download PDF

Info

Publication number
CN102361315B
CN102361315B CN 201110195618 CN201110195618A CN102361315B CN 102361315 B CN102361315 B CN 102361315B CN 201110195618 CN201110195618 CN 201110195618 CN 201110195618 A CN201110195618 A CN 201110195618A CN 102361315 B CN102361315 B CN 102361315B
Authority
CN
China
Prior art keywords
cable
ship
reeler
steel
ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201110195618
Other languages
English (en)
Other versions
CN102361315A (zh
Inventor
葛加君
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Bu Zhenhong
Original Assignee
葛加君
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 葛加君 filed Critical 葛加君
Priority to CN 201110195618 priority Critical patent/CN102361315B/zh
Publication of CN102361315A publication Critical patent/CN102361315A/zh
Application granted granted Critical
Publication of CN102361315B publication Critical patent/CN102361315B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

本发明公开了一种海域地下缆线三同步敷设施工方法,包括敷船制作、缆线盘安装、地纤安装、线纤直接、敷船启动、补埋、注标、缆线连接等步骤。本发明减少了人工操作的比例,基本实施了机械化操作,可靠安全。

Description

海域地下缆线三同步敷设施工方法
技术领域
本发明涉及一种海域地下缆线敷设施工方法。
背景技术
近年来,海滨区域风能建设速度很快,且不断向近海延伸发展。同时海滨基础建设速度加快向近海扩展,由此近海海域地下缆线敷设的施工技术难度越来越大,某种意义上阻碍了风能向近海延伸发展的进程和影响了海滨基础建设的速度,而其安全风险也难以预见。
发明内容
本发明的目的在于提供一种减少人工操作的比例,实行机械化操作,安全可靠的海域地下缆线三同步敷设施工方法。
本发明的技术解决方案是:
一种海域地下缆线三同步敷设施工方法,其特征是:包括下列步骤:
(1)敷船制作
船身制作:选船钢板进行制作,船体尺寸按照承载重量确定;船应用双层船底,船为具有旱行轮胎和水行橹浆的两栖船,共三层平面装载,第一底层平面主要装载车轮、橹浆与压线板;两栖船二层平面布置载体主要动力机械,第三层平面主要装载缆线盘、方向盘;
开槽机安装:开槽机安装在敷船前沿,并用活络连竿进行调节高度,其机头采用环形刀具,用钢板制成宽度为30mm,高度为30cm,长度为15cm;
缆线盘套竿:在敷船中间设置为中舱,其中舱中间船帮下30cm安装金属园环,圆环直径30cm,按照敷船宽度选用实心钢管,其钢管直径为28cm作缆线盘搁置套用;
线眼洞制作:缆线从缆线盘向船前沿放线,在开槽机头后边15cm处设置放线眼,放线眼直径为20cm,眼洞嵌入金属环进行串线;
压线板制作:缆线槽宽度的三分之二为压线板长度,压线板宽度为5cm,压线板厚度为3cm,压线板安装在开槽器与线眼之间进行压线;
(2)缆线盘安装:当材料运至施工现场,用塔机将缆线盘吊至敷船中舱舱位,距三层船面2米距离,由补助工将预先准备的盘竿插入线盘中孔中,然后指挥长指挥塔吊司机徐徐的将线盘下降,直至盘竿两端插入船帮金属环内,并加入锚固方可放下吊钩,拆除缆线线盘包装物;
(3)地纤安装:在施工区域源头处安装地纤,地纤是用直径30mm螺纹钢制作,顶端焊接金属圆环,尾端为纤细状,用重锤打入泥土2.5m深以上,地上部分仅有圆环;
(4)线纤直接:当地纤安装后,缆线从缆盘抽出,经过船体线眼串过,连接纤线;
(5)敷船启动:首先开动发动机,然后以每小时3公里速度进行后推式推进,并实施边开槽边敷线边预埋,特别当敷线盘上缆线即将结束时,及时进行缆线间连接,确保三同步敷线顺利到位;
(6)补埋:由于机械运作可能有部分缆线未能完全埋设,所以在敷船后边距离10米,由2人组合进行缆线补埋;
(7)注标:按照缆线敷设路径及时注入标志,标注为每10米设置一处,转变处设置标识,标识制作采用镀锌直径10cm圆钢,头部制作成尖状,长120cm,在钢纤上连接钢绞线,钢绞线另一端联接浮标,浮标上注明标号,在注标时应距缆线左侧30cm处落桩注标,标纤打入土中,无水区域注标无须连接线,标纤注入土中80cm即可,用不锈钢钢板直接焊接在钢纤上,钢纤注入在缆线左侧30cm处;
(8)缆线连接:当缆线敷设完成后,缆线与上端及下端进行联接,联接前对缆线线路进行全面检验是否路径通畅,检查符合要求后采用机械或人工连接,连接后再次进行检验,检验合格后进行交付使用。
本发明减少了人工操作的比例,基本实施了机械化操作,可靠安全。
下面结合实施例对本发明作进一步说明。
具体实施方式
一种海域地下缆线三同步敷设施工方法,包括下列步骤:
(1)敷船制作
船身制作:选船钢板进行制作,船体尺寸按照承载重量确定;船应用双层船底,船为具有旱行轮胎和水行橹浆的两栖船,共三层平面装载,第一底层平面主要装载车轮、橹浆与压线板;两栖船二层平面布置载体主要动力机械,第三层平面主要装载缆线盘、方向盘;
开槽机安装:开槽机安装在敷船前沿,并用活络连竿进行调节高度,其机头采用环形刀具,用钢板制成宽度为30mm,高度为30cm,长度为15cm;
缆线盘套竿:在敷船中间设置为中舱,其中舱中间船帮下30cm安装金属园环,圆环直径30cm,按照敷船宽度选用实心钢管,其钢管直径为28cm作缆线盘搁置套用;
线眼洞制作:缆线从缆线盘向船前沿放线,在开槽机头后边15cm处设置放线眼,放线眼直径为20cm,眼洞嵌入金属环进行串线;
压线板制作:缆线槽宽度的三分之二为压线板长度,压线板宽度为5cm,压线板厚度为3cm,压线板安装在开槽器与线眼之间进行压线(线从线眼穿出,并经压线板压线);
(2)缆线盘安装:当材料运至施工现场,用塔机将缆线盘吊至敷船中舱舱位,距三层船面2米距离,由补助工将预先准备的盘竿插入线盘中孔中,然后指挥长指挥塔吊司机徐徐的将线盘下降,直至盘竿两端插入船帮金属环内,并加入锚固方可放下吊钩,拆除缆线线盘包装物;
(3)地纤安装:在施工区域源头处安装地纤,地纤是用直径30mm螺纹钢制作,顶端焊接金属圆环,尾端为纤细状,用重锤打入泥土2.5m深以上,地上部分仅有圆环;
(4)线纤直接:当地纤安装后,缆线从缆盘抽出,经过船体线眼串过,连接纤线;
(5)敷船启动:首先开动发动机,然后以每小时3公里速度进行后推式推进,并实施边开槽边敷线边预埋,特别当敷线盘上缆线即将结束时,及时进行缆线间连接,确保三同步敷线顺利到位;
(6)补埋:由于机械运作可能有部分缆线未能完全埋设,所以在敷船后边距离10米,由2人组合进行缆线补埋;
(7)注标:按照缆线敷设路径及时注入标志,标注为每10米设置一处,转变处设置标识,标识制作采用镀锌直径10cm圆钢,头部制作成尖状,长120cm,在钢纤上连接钢绞线,钢绞线另一端联接浮标,浮标上注明标号,在注标时应距缆线左侧30cm处落桩注标,标纤打入土中,无水区域注标无须连接线,标纤注入土中80cm即可,用不锈钢钢板直接焊接在钢纤上,钢纤注入在缆线左侧30cm处;
(8)缆线连接:当缆线敷设完成后,缆线与上端及下端进行联接,联接前对缆线线路进行全面检验是否路径通畅,检查符合要求后采用机械或人工连接,连接后再次进行检验,检验合格后进行交付使用。

Claims (1)

1.一种海域地下缆线三同步敷设施工方法,其特征是:包括下列步骤:
(1)敷船制作
船身制作:选船钢板进行制作,船体尺寸按照承载重量确定;船应用双层船底;船为具有旱行轮胎和水行橹浆的两栖船,共三层平面装载,第一层平面主要装载车轮、橹浆与压线板,两栖船第二层平面布置载体主要动力机械,第三层平面主要装载缆线盘、方向盘;
开槽机安装:开槽机安装在敷船前沿,并用活络连竿进行调节高度,其机头采用环形刀具,用钢板制成,宽度为30mm,高度为30cm,长度为15cm;
缆线盘套竿:在敷船中间设置为中舱,其中舱中间船帮下30cm安装金属圆环,金属圆环直径30cm,按照敷船宽度选用实心钢管,其钢管直径为28cm作缆线盘搁置套用;
线眼洞制作:缆线从缆线盘向船前沿放线,在开槽机头后边15cm处设置放线眼,放线眼直径为20cm,眼洞嵌入金属圆环进行串线;
压线板制作:缆线槽宽度的三分之二为压线板长度,压线板宽度为5cm,压线板厚度为3cm,压线板安装在开槽器与线眼之间进行压线;
(2)缆线盘安装:当材料运至施工现场,用塔机将缆线盘吊至敷船中舱舱位,距三层船面2米距离,由补助工将预先准备的盘竿插入线盘中孔中,然后指挥长指挥塔吊司机将缆线盘下降,直至盘竿两端插入船帮金属圆环内,并锚固,方可放下吊钩,拆除缆线盘包装物;
(3)地纤安装:在施工区域源头处安装地纤,地纤是用直径30mm螺纹钢制作,顶端焊接金属圆环,尾端为纤细状,用重锤打入泥土2.5m深以上,地上部分仅有圆环;
(4)当地纤安装后,缆线从缆线盘抽出,经过船体线眼串过,连接地纤和缆线;
(5)敷船启动:首先开动发动机,然后以每小时3公里速度进行后推式推进,并实施边开槽边敷线边预埋,当缆线盘上缆线即将结束时,及时进行缆线间连接,确保三同步敷线顺利到位;
(6)补埋:由于机械运作可能有部分缆线未能完全埋设,所以在敷船后边距离10米,由2人组合进行缆线补埋;
(7)注标:按照缆线敷设路径及时注入标志,标注为每10米设置一处,转变处设置标识,标识制作采用直径10cm镀锌圆钢,头部制作成尖状,长120cm,在地纤上连接钢绞线,钢绞线一端联接浮标,浮标上注明标号,在注标时应距缆线左侧30cm处落桩注标,地纤打入土中;无水区域注标无须连接钢绞线,用不锈钢钢板直接焊接在地纤上,地纤注入在缆线左侧30cm处,地纤注入土中80cm即可;
(8)缆线连接:当缆线敷设完成后,缆线与上端及下端进行联接,联接前对缆线线路进行全面检验是否路径通畅,检查符合要求后采用机械或人工连接,连接后再次进行检验,检验合格后进行交付使用。
CN 201110195618 2011-07-13 2011-07-13 海域地下缆线三同步敷设施工方法 Expired - Fee Related CN102361315B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201110195618 CN102361315B (zh) 2011-07-13 2011-07-13 海域地下缆线三同步敷设施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201110195618 CN102361315B (zh) 2011-07-13 2011-07-13 海域地下缆线三同步敷设施工方法

Publications (2)

Publication Number Publication Date
CN102361315A CN102361315A (zh) 2012-02-22
CN102361315B true CN102361315B (zh) 2013-08-21

Family

ID=45586580

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201110195618 Expired - Fee Related CN102361315B (zh) 2011-07-13 2011-07-13 海域地下缆线三同步敷设施工方法

Country Status (1)

Country Link
CN (1) CN102361315B (zh)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102856870B (zh) * 2012-08-16 2015-04-01 中英海底系统有限公司 利用通信电缆作业平台进行多根海底电缆同时安装的方法
CN103247977B (zh) * 2013-05-14 2015-11-18 国家电网公司 多相海底电缆横向布置循环敷设施工方法
CN104600652B (zh) * 2014-11-21 2017-11-28 上海市基础工程集团有限公司 基于锚泊系统和动力定位的浅海海缆敷设工艺

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101282028A (zh) * 2008-05-29 2008-10-08 国网武汉高压研究院 水底电缆敷设方法及装置

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0795707A (ja) * 1993-09-24 1995-04-07 Hitachi Cable Ltd ケーブル布設張力分布測定方法

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101282028A (zh) * 2008-05-29 2008-10-08 国网武汉高压研究院 水底电缆敷设方法及装置

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
JP特开平7-95707A 1995.04.07
叶银灿.海底光缆工程发展20 年.《海洋学研究》.2006,第24卷(第3期),1-10.
海底光缆工程发展20 年;叶银灿;《海洋学研究》;20060930;第24卷(第3期);1-10 *

Also Published As

Publication number Publication date
CN102361315A (zh) 2012-02-22

Similar Documents

Publication Publication Date Title
CN103247977B (zh) 多相海底电缆横向布置循环敷设施工方法
CN101280862A (zh) 海底pe管道边敷边埋施工方法
US20110214596A1 (en) Vertically installed spar and construction methods
CN106926978A (zh) 基于浮力的滑道式浮标收放系统
Wang et al. Latest progress in deepwater installation technologies
CN112728211B (zh) 一种污水海域排海管的溜放下水、海上拖运就位施工方法
CN102361315B (zh) 海域地下缆线三同步敷设施工方法
WO2009070034A2 (en) Method for picking up and towing a structure under water
CN205022817U (zh) 适用于圆筒型或多边形fpso/fdpso的外输系统
JP6406665B2 (ja) 浮魚礁の回収装置及び回収方法
JP6985699B2 (ja) 水上架空送電システム、送電塔の設置方法及び水上架空送電システムの設置方法
CN207292328U (zh) 一种布缆船
CN102337746B (zh) 水上风力发电塔架基础和结构的安装施工方法
KR20140120150A (ko) 자력을 이용한 계류 장치 및 방법
CN109901273B (zh) 超深水海底光缆接线盒海上布放的施工方法
CN101837823B (zh) 圆筒型浮式海洋平台水上拖航方法
CN209852529U (zh) 一种海上移动平台原油外输大抓力锚加双缆系泊系统
CN110539853A (zh) 一种长距离沙洲段海缆铺设的铺缆船甲板布置及施工方法
CN103661831B (zh) 艏部具有双锚绞机的全回转拖船
CN211167323U (zh) 一种长距离沙洲段海缆铺设的铺缆船甲板布置
CN210529503U (zh) 一种悬索桥运梁船定位装置
CN203714157U (zh) 艏部具有双锚绞机的全回转拖船
CN207814644U (zh) 海底管道卷管铺设装置
CN206552215U (zh) 一种深水海底电缆敷设船
JP6949690B2 (ja) 浮体係留方法および浮体

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CB03 Change of inventor or designer information

Inventor after: Bu Zhenhong

Inventor before: Ge Jiajun

CB03 Change of inventor or designer information
TR01 Transfer of patent right

Effective date of registration: 20170928

Address after: 063027 No. 2, 101 gate, 18 floor, Guanghua Road, Majiagou Road, Kaiping District, Hebei, Tangshan City

Patentee after: Bu Zhenhong

Address before: Rudong County, Jiangsu province 226400 Nantong juegang Taishan Road East Development Building 1002

Patentee before: Ge Jiajun

TR01 Transfer of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130821

Termination date: 20180713

CF01 Termination of patent right due to non-payment of annual fee