CN102352694A - 一种钢结构柱的加固方法 - Google Patents

一种钢结构柱的加固方法 Download PDF

Info

Publication number
CN102352694A
CN102352694A CN2011102688737A CN201110268873A CN102352694A CN 102352694 A CN102352694 A CN 102352694A CN 2011102688737 A CN2011102688737 A CN 2011102688737A CN 201110268873 A CN201110268873 A CN 201110268873A CN 102352694 A CN102352694 A CN 102352694A
Authority
CN
China
Prior art keywords
steel
column
wing
edge
steel column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2011102688737A
Other languages
English (en)
Other versions
CN102352694B (zh
Inventor
龚顺风
程鹏
许峰
邱鹤
程江敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang University ZJU
Original Assignee
Zhejiang University ZJU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang University ZJU filed Critical Zhejiang University ZJU
Priority to CN 201110268873 priority Critical patent/CN102352694B/zh
Publication of CN102352694A publication Critical patent/CN102352694A/zh
Application granted granted Critical
Publication of CN102352694B publication Critical patent/CN102352694B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Working Measures On Existing Buildindgs (AREA)
  • Rod-Shaped Construction Members (AREA)

Abstract

本发明公开了一种钢结构柱的加固方法,对钢柱卸载后,在柱翼缘外侧点焊和围焊钢板,等焊缝冷却,再逐级恢复荷载。对于梁柱连接处,通过设置加劲板,连接钢板和梁,以有效传递荷载,实现钢柱加固后柱及梁柱节点承载力的提高。该技术不用拆除原有结构,通过焊接钢板,既能利用原有结构,又可以保证新增钢板和原有钢柱的有效连接,最终钢柱能通过焊缝有效传力。

Description

一种钢结构柱的加固方法
技术领域
本发明涉及钢结构加固领域,尤其涉及一种适用于钢结构柱的加固方法。
背景技术
钢结构工程,通常具有高度大、自重大的特点,对于工业厂房,长期承受机械设备动力荷载作用,结构还可能会出现疲劳破坏。因此对于使用多年的钢结构工程,或者在已有结构基础上新建、改建的工程,加固显得尤为重要。
目前钢结构加固方法主要分为三大类,一是改变结构计算图形的加固,二是改变构件截面的加固,三是连接的加固。当前,对于改变构件截面的加固技术,局限在改工字型为箱型、托梁换柱、CFRP技术(碳纤维粘帖钢板)等等。而改工字型为箱型可能需要拆除新增钢板处的斜撑等构件,托梁换柱没有充分利用原有结构,使用碳纤维粘帖对于保持原有钢柱和新增钢板有效连接提出了很大的挑战。
发明内容
本发明的目的在于针对现有技术的不足,提供一种钢结构柱的加固方法。
本发明的目的是通过以下技术方案来实现的:一种钢结构柱的加固方法,该方法包括以下步骤:
(1)对需要加固的钢柱进行卸荷:通过拆除结构上部设备或者通过安装千斤顶等卸载设备,支撑原有结构;
(2)设计外贴钢板和点焊预留孔:外贴钢板厚度相对于钢柱翼缘宽度小100mm;然后在外贴钢板上有序布置点焊预留孔;
(3)加固施工:焊接前,需要清理钢柱翼缘外侧的防锈层,焊接时,首先在点焊预留孔点焊外贴钢板和钢柱翼缘,等焊缝冷却之后,再围焊外贴钢板和钢柱翼缘;对于钢梁与钢柱的连接处,在钢梁上部和下部分别通过两个纵向的加劲板和钢梁翼缘连接,同时钢柱也通过四个加劲板和钢梁翼缘连接,在钢梁的翼缘间通过两个纵向的加劲板将钢柱翼缘和钢梁翼缘连接;
(4)待焊缝冷却之后,再逐级安装结构上部设备或者拆除卸载设备,钢柱加固完成。
本发明的有益效果是,本发明的方法不拆除原结构,对钢柱部分卸荷后在其翼缘外侧焊接钢板。既能充分利用原有结构,又可以保证新增钢板和原有钢柱的有效连接,最终钢柱能通过焊缝有效传力。本发明通过在新增钢板和原有钢柱的关键位置焊接,使得加固后钢柱能承受新增荷载作用,是一种可以广泛应用于钢结构柱加固的技术,具有广阔的应用前景。
附图说明
图1为本发明钢柱加固的示意图;
图2为图1的A-A剖视图;
图3为图1的B-B剖视图;
图4为本发明梁柱连接处的加固示意图;
图5为图4的C-C剖视图;
图中,点焊预留孔1、外贴钢板2、加劲板3、钢柱4、钢梁5。
具体实施方式
如图1-5所示,本发明钢结构柱的加固方法,包括以下步骤:
1、对需要加固的钢柱4进行卸荷。
所需卸荷的大小按照《钢结构加固技术规范》(CECS_77-96)计算确定。常见的卸荷方法主要有拆除结构上部设备,或者通过千斤顶等卸载设备,支撑原有结构。
2、设计外贴钢板2和点焊预留孔1。
外贴钢板2厚度按加固后结构承受的荷载确定,其宽度建议相对于钢柱4翼缘宽度小100mm。考虑到外贴钢板2面积较大,为避免和钢柱4翼缘之间产生空鼓,在外贴钢板2上有序布置点焊预留孔1,孔径大小和间距可按《钢结构设计规范》(GB50017-2003)第七章第二节中螺栓孔径和间距确定。
3、加固施工。
焊接前,需要清理钢柱4翼缘外侧的防锈层,首先在点焊预留孔1点焊外贴钢板2和钢柱4翼缘,等焊缝冷却之后,再围焊外贴钢板2和钢柱4翼缘。
对于钢梁5与钢柱4的连接处,无法直接采用外贴钢板2的方法直接加固,采用如图4所示的加固方法,在钢梁5上部和下部分别通过两个纵向的加劲板3和钢梁翼缘连接,同时钢柱4也通过四个加劲板3和钢梁翼缘连接,在钢梁的翼缘间通过两个纵向的加劲板3将钢柱翼缘和钢梁翼缘连接,有限元分析证明,通过这种处理措施,梁柱连接处的能有效传力,外贴钢板3能充分发挥作用。
4、待焊缝冷却之后,再逐级安装结构上部设备或者拆除卸载设备,钢柱加固完成。

Claims (1)

1.一种钢结构柱的加固方法,其特征在于,该方法包括以下步骤:
(1)对需要加固的钢柱(4)进行卸荷:通过拆除结构上部设备或者通过安装千斤顶等卸载设备,支撑原有结构;
(2)设计外贴钢板(2)和点焊预留孔(1):外贴钢板(2)厚度相对于钢柱(4)翼缘宽度小100mm;然后在外贴钢板(2)上有序布置点焊预留孔(1);
(3)加固施工:焊接前,需要清理钢柱4翼缘外侧的防锈层,焊接时,首先在点焊预留孔(1)点焊外贴钢板(2)和钢柱(4)翼缘,等焊缝冷却之后,再围焊外贴钢板(2)和钢柱(4)翼缘;对于钢梁(5)与钢柱(4)的连接处,在钢梁(5)上部和下部分别通过两个纵向的加劲板(3)和钢梁翼缘连接,同时钢柱(4)也通过四个加劲板(3)和钢梁翼缘连接,在钢梁的翼缘间通过两个纵向的加劲板(3)将钢柱翼缘和钢梁翼缘连接;
(4)待焊缝冷却之后,再逐级安装结构上部设备或者拆除卸载设备,钢柱加固完成。
CN 201110268873 2011-09-13 2011-09-13 一种钢结构柱的加固方法 Expired - Fee Related CN102352694B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201110268873 CN102352694B (zh) 2011-09-13 2011-09-13 一种钢结构柱的加固方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201110268873 CN102352694B (zh) 2011-09-13 2011-09-13 一种钢结构柱的加固方法

Publications (2)

Publication Number Publication Date
CN102352694A true CN102352694A (zh) 2012-02-15
CN102352694B CN102352694B (zh) 2013-09-04

Family

ID=45576325

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201110268873 Expired - Fee Related CN102352694B (zh) 2011-09-13 2011-09-13 一种钢结构柱的加固方法

Country Status (1)

Country Link
CN (1) CN102352694B (zh)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102561522A (zh) * 2012-04-09 2012-07-11 浙江大学 一种钢结构新老结构的连接方法
CN102913001A (zh) * 2012-10-18 2013-02-06 东南大学 一种用于建筑结构构件卸载的支撑机构及其使用方法
CN103015331A (zh) * 2013-01-04 2013-04-03 中国人民解放军军事交通学院 一种站台板主梁与纵梁的过渡结构
CN103741959A (zh) * 2013-12-30 2014-04-23 北京工业大学 外贴装配式pc框架法加固结构的方法
CN103866988A (zh) * 2012-12-18 2014-06-18 武汉倡文科技咨询有限公司 一种h型钢加固方法
CN106149978A (zh) * 2015-03-31 2016-11-23 天津市建工工程总承包有限公司 带有关节型连接装置的钢框柱
CN107143152A (zh) * 2017-07-07 2017-09-08 山东省建筑科学研究院 一种加固h型钢梁柱及方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005139691A (ja) * 2003-11-06 2005-06-02 Sumitomo Forestry Co Ltd 間仕切部分における柱撤去梁補強方法及び梁補強構造
CN101311481A (zh) * 2007-05-25 2008-11-26 贵阳铝镁设计研究院 钢柱脚加固结构
CN101603372A (zh) * 2009-07-01 2009-12-16 四川建筑职业技术学院 高层建筑钢筋砼柱整体置换砼加固方法
CN101839074A (zh) * 2010-06-22 2010-09-22 中国建筑第二工程局有限公司 钢框架加固柱及其加固方法

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005139691A (ja) * 2003-11-06 2005-06-02 Sumitomo Forestry Co Ltd 間仕切部分における柱撤去梁補強方法及び梁補強構造
CN101311481A (zh) * 2007-05-25 2008-11-26 贵阳铝镁设计研究院 钢柱脚加固结构
CN101603372A (zh) * 2009-07-01 2009-12-16 四川建筑职业技术学院 高层建筑钢筋砼柱整体置换砼加固方法
CN101839074A (zh) * 2010-06-22 2010-09-22 中国建筑第二工程局有限公司 钢框架加固柱及其加固方法

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102561522A (zh) * 2012-04-09 2012-07-11 浙江大学 一种钢结构新老结构的连接方法
CN102561522B (zh) * 2012-04-09 2014-02-19 浙江大学 一种钢结构新老结构的连接方法
CN102913001A (zh) * 2012-10-18 2013-02-06 东南大学 一种用于建筑结构构件卸载的支撑机构及其使用方法
CN102913001B (zh) * 2012-10-18 2015-03-11 东南大学 一种用于建筑结构构件卸载的支撑机构及其使用方法
CN103866988A (zh) * 2012-12-18 2014-06-18 武汉倡文科技咨询有限公司 一种h型钢加固方法
CN103015331A (zh) * 2013-01-04 2013-04-03 中国人民解放军军事交通学院 一种站台板主梁与纵梁的过渡结构
CN103741959A (zh) * 2013-12-30 2014-04-23 北京工业大学 外贴装配式pc框架法加固结构的方法
CN103741959B (zh) * 2013-12-30 2015-10-28 北京工业大学 外贴装配式pc框架法加固结构的方法
CN106149978A (zh) * 2015-03-31 2016-11-23 天津市建工工程总承包有限公司 带有关节型连接装置的钢框柱
CN106149978B (zh) * 2015-03-31 2018-06-01 天津市建工工程总承包有限公司 带有关节型连接装置的钢框柱
CN107143152A (zh) * 2017-07-07 2017-09-08 山东省建筑科学研究院 一种加固h型钢梁柱及方法
CN107143152B (zh) * 2017-07-07 2023-06-27 山东省建筑科学研究院有限公司 一种加固h型钢梁柱及方法

Also Published As

Publication number Publication date
CN102352694B (zh) 2013-09-04

Similar Documents

Publication Publication Date Title
CN102352694B (zh) 一种钢结构柱的加固方法
CN103161168B (zh) 一种可拆卸预应力支撑架系统
CN102251602A (zh) 剪切型开孔软钢建筑结构抗震阻尼器
CN105625585A (zh) 屈曲约束钢结构梁柱连接节点和钢结构建筑
CN103452126A (zh) 一种底板钢材可回收的轻型组合吊箱及其施工工艺
JP4600164B2 (ja) 鉄塔補強工法
CN203361167U (zh) 一种基坑围护用围檩转角构件
CN216616236U (zh) 一种高层建筑抗震型建筑钢结构
CN105604183A (zh) 一种桁架后焊节点的施工方法
CN203238844U (zh) 一种钢桁架节点及钢桁架
CN203420359U (zh) 钢结构支撑系统中承受超大荷载的梁柱连接的刚接节点
CN201400955Y (zh) 一种重型钢结构格构柱
CN209066598U (zh) 双槽钢截面可更换耗能梁段-钢裙梁连接结构
CN106567456A (zh) 一种采用外伸式端板的扩孔型可更换消能梁段连接节点及其施工方法
CN106593006A (zh) 一种采用钢架结构抗连续倒塌加固方法
CN203361165U (zh) 一种建筑基坑围护用支撑梁连接结构
CN108360747A (zh) 用于大吨位双层吊车厂房的钢管砼格构柱
CN105715055B (zh) 一种核电站大型贯穿件可调工装及调节方法
CN104452604B (zh) 一种加固钢结构拱桥中拱肋节段的方法
CN109797854B (zh) 一种大净空的可恢复功能钢框架中心支撑体系
CN101701498A (zh) 一种跨越既有铁路线钢管套接防护棚施工方法
CN208235801U (zh) 用于大吨位双层吊车厂房的钢管砼格构柱
CN207331961U (zh) 一种用于单层网壳的螺栓连接节点
CN206599880U (zh) 剪力钢板与一侧钢筋网的侧立式整体成型结构
CN207331456U (zh) 一种带有横向系梁的正交异性钢桥面板结构

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130904