CN102330872A - Anti-freezing method for buried pipeline - Google Patents
Anti-freezing method for buried pipeline Download PDFInfo
- Publication number
- CN102330872A CN102330872A CN201110210794A CN201110210794A CN102330872A CN 102330872 A CN102330872 A CN 102330872A CN 201110210794 A CN201110210794 A CN 201110210794A CN 201110210794 A CN201110210794 A CN 201110210794A CN 102330872 A CN102330872 A CN 102330872A
- Authority
- CN
- China
- Prior art keywords
- pipeline
- insulating material
- thermal insulating
- backfill
- buried pipeline
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
Abstract
The invention discloses an anti-freezing method for a buried pipeline. In the method, a heat insulating material is completely or partially filled in a backfill region or a fill region around the pipeline. In the method, the material is completely or partially filled in the backfill region around the pipeline. In the method, the material is completely or partially filled in the fill region around the pipeline. The method has the advantage of greatly saving manual labor and material resources to achieve an anti-freezing effect for the pipeline.
Description
Technical field:
The invention belongs to the engineering field, relate to a kind of buried pipeline means to prevent freezing, especially a kind of around the pipeline back filled region/embankment district partly or entirely adopt the method for backfill thermal insulating material.
Background technique:
Extreme weather conditions phenomenon took place in recent years often; For example on-the-spot actual frost line has often been broken through the frost line data that record is arranged in the past; Cause the pipeline below the former frost line that come into operation and be laid in that freezing phenomenon has still taken place thus; If excavation reduces the pipe laying absolute altitude again once more, will bring great inconvenience and very big manpower, financial resources input; If only change the pipeline earthing into thermal insulating material (like lime-ash), then can save a lot of inputs.
For the buried pipeline engineering of construction not, in order to reduce investment outlay, speed up the work, often hope buried depth of pipeline try one's best more shallow, possibly will make pipe laying more than frost line.
Summary of the invention:
The objective of the invention is to overcome the shortcoming of above-mentioned existing technology; Provide a kind of and freeze dangerous or frozen pipeline for actual the having below the frost line that be laid in; A kind of method that pipeline freezes that prevents of simple possible is proposed; Promptly the method for back filled region/embankment district part employing backfill thermal insulating material (like lime-ash) around pipeline plays the effect that prevents that pipeline from freezing.
The objective of the invention is to solve through following technological scheme:
A kind of buried pipeline means to prevent freezing, said method are that back filled region or the embankment district around pipeline partly or entirely adopts the backfill thermal insulating material.
Said method is all or part of backfill thermal insulating material in back filled region around pipeline.
Said method is all or part of backfill thermal insulating material in embankment district around pipeline.
Said thermal insulating material is a lime-ash.
Advantage of the present invention is: can greatly save the man power and material, play the effect that prevents that pipeline from freezing.
Description of drawings:
Fig. 1 is embodiments of the invention 1 schematic representation;
Fig. 2 is embodiments of the invention 2 schematic representation;
Wherein: 1 is pipeline; 2 is terrace; 3 is thermal insulating material.
Embodiment:
Below in conjunction with accompanying drawing the present invention is done and to describe in further detail:
Referring to Fig. 1 and Fig. 2, buried pipeline means to prevent freezing of the present invention is all or part of backfill thermal insulating material in back filled region or embankment district around pipeline.
Said method is all or part of backfill thermal insulating material in back filled region around pipeline.
Said method is all or part of backfill thermal insulating material in embankment district around pipeline.
Said thermal insulating material is a lime-ash
Need be under the situation more than the frost line for some with pipe laying; A kind of method that pipeline freezes that prevents of simple possible is proposed; Promptly the method for the back filled region/all or part of employing backfill in embankment district thermal insulating material (like lime-ash) around pipeline plays the effect that prevents that pipeline from freezing.
Above content is to combine concrete preferred implementation to further explain that the present invention did; Can not assert that embodiment of the present invention only limits to this; Those of ordinary skill for technical field under the present invention; Under the prerequisite that does not break away from the present invention's design, can also make some simple deduction or replace, all should be regarded as belonging to the present invention and confirm scope of patent protection by claims of being submitted to.
Claims (4)
1. buried pipeline means to prevent freezing is characterized in that: said method is back filled region or the embankment district backfill thermal insulating material around pipeline.
2. a kind of according to claim 1 buried pipeline means to prevent freezing is characterized in that: said method is all or part of backfill thermal insulating material in back filled region around pipeline.
3. a kind of according to claim 1 buried pipeline means to prevent freezing is characterized in that: said method is all or part of backfill thermal insulating material in embankment district around pipeline.
4. like claim 1,2 or 3 said a kind of buried pipeline means to prevent freezings, it is characterized in that: said thermal insulating material is a lime-ash.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201110210794A CN102330872A (en) | 2011-07-27 | 2011-07-27 | Anti-freezing method for buried pipeline |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201110210794A CN102330872A (en) | 2011-07-27 | 2011-07-27 | Anti-freezing method for buried pipeline |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102330872A true CN102330872A (en) | 2012-01-25 |
Family
ID=45482759
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201110210794A Pending CN102330872A (en) | 2011-07-27 | 2011-07-27 | Anti-freezing method for buried pipeline |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102330872A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113330242A (en) * | 2018-12-06 | 2021-08-31 | 瑞典意昂公司 | Method for filling a trench comprising a pair of conduits and filled trench |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4142555A (en) * | 1976-01-19 | 1979-03-06 | Sumitomo Kinzoku Kogyo Kabushiki Kaisha | Corrosion preventive, coated metal pipe |
JPH0238A (en) * | 1987-10-19 | 1990-01-05 | Konica Corp | Silver halide photographic sensitive material having high contrast |
JPH112038A (en) * | 1997-06-11 | 1999-01-06 | Nippon Pane Heater Kogyo Kk | Concrete floor heating structure |
CN2842150Y (en) * | 2005-10-24 | 2006-11-29 | 孙启玉 | Steam pipeline for heating and power plant |
CN1884888A (en) * | 2005-06-20 | 2006-12-27 | 吕迎智 | Steam pipeline laying method for thermoelectric plant |
CN201007416Y (en) * | 2007-02-07 | 2008-01-16 | 孙启玉 | Underground steam conduit with thermal insulation waterproof jacket |
-
2011
- 2011-07-27 CN CN201110210794A patent/CN102330872A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4142555A (en) * | 1976-01-19 | 1979-03-06 | Sumitomo Kinzoku Kogyo Kabushiki Kaisha | Corrosion preventive, coated metal pipe |
JPH0238A (en) * | 1987-10-19 | 1990-01-05 | Konica Corp | Silver halide photographic sensitive material having high contrast |
JPH112038A (en) * | 1997-06-11 | 1999-01-06 | Nippon Pane Heater Kogyo Kk | Concrete floor heating structure |
CN1884888A (en) * | 2005-06-20 | 2006-12-27 | 吕迎智 | Steam pipeline laying method for thermoelectric plant |
CN2842150Y (en) * | 2005-10-24 | 2006-11-29 | 孙启玉 | Steam pipeline for heating and power plant |
CN201007416Y (en) * | 2007-02-07 | 2008-01-16 | 孙启玉 | Underground steam conduit with thermal insulation waterproof jacket |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113330242A (en) * | 2018-12-06 | 2021-08-31 | 瑞典意昂公司 | Method for filling a trench comprising a pair of conduits and filled trench |
CN113330242B (en) * | 2018-12-06 | 2023-02-21 | 瑞典意昂公司 | Method for filling a trench comprising a pair of conduits and filled trench |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106677229B (en) | The pipe network system and its construction method of Tailings Dam frozen soil are administered in conjunction with water seepage drainage facility | |
CN201982890U (en) | Prefabricated polyurethane foam insulating pipe for trenches | |
CN102322276A (en) | Tunneling engineering freeze-proofing structure in seasonally frozen ground region | |
CN204023628U (en) | A kind of water-stopping structure | |
CN103061230B (en) | Construction method of technology utilizing ground source heat pump to cool and melt frozen road surfaces and drain boards for construction | |
CN103938658A (en) | Structure capable of avoiding cold damage to high-temperature and unstable freeze soil area tunnel portal side slope | |
CN202188269U (en) | Insulation pipe | |
CN106088115A (en) | The method increasing Stability of Soil of High Side Slopes | |
CN102330872A (en) | Anti-freezing method for buried pipeline | |
CN210263089U (en) | Highway side slope protection structure for frozen soil area | |
CN204492745U (en) | Between monitoring two-layer compound Shaft Linings, hydraulic pressure is to determine the device of best time for injecting | |
CN204691792U (en) | A kind of tunnel in cold area anti-freezing and heat-insulating system | |
CN203685289U (en) | High-altitude severe cold rich water channel permanent and temporary combined freeze-proofing drainage structure | |
CN204402513U (en) | A kind of device solving the infiltration of underground chamber lining cutting surface and leak | |
CN108166455B (en) | Construction method and structure for preventing frost heaving of excavation channel in high and cold area | |
CN105649394A (en) | Anti-freezing structure for iron tower and foundation of transmission line in deep-water area of severe cold region | |
CN205445088U (en) | A anti -icing freezing is constructed that is used for cold area profundal zone transmission line iron tower and basis | |
CN207003157U (en) | A kind of roadbed material of energy saving and environment friendly highway | |
CN204703363U (en) | Energy-saving wall heat insulation building block | |
CN205026223U (en) | Direct -burried steam conduit is at waterproof connection structure of valve inspection shaft department | |
CN203429591U (en) | Ground surface deicing device | |
CN203878541U (en) | Ice blocking dam device | |
CN104234725A (en) | Method for preventing tunnel freezing damage of seasonally frozen regions | |
CN203821188U (en) | Frost heave resistant structure of subgrade surrounding transverse building in severe cold area | |
CN204825930U (en) | Sunshade net of slope and cutting section is faced upward on tunnel limit in ever -frozen ground district |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20120125 |