CN102312485A - Concrete top plate embedded part and fixing method thereof - Google Patents
Concrete top plate embedded part and fixing method thereof Download PDFInfo
- Publication number
- CN102312485A CN102312485A CN201110197252A CN201110197252A CN102312485A CN 102312485 A CN102312485 A CN 102312485A CN 201110197252 A CN201110197252 A CN 201110197252A CN 201110197252 A CN201110197252 A CN 201110197252A CN 102312485 A CN102312485 A CN 102312485A
- Authority
- CN
- China
- Prior art keywords
- embedded part
- concrete
- concrete top
- part body
- top board
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
The invention discloses a concrete top plate embedded part, which comprises an embedded part body, wherein the embedded part body is provided with at least two fixing holes which are used for being fixed with a mold plate, and the space between the two fixing holes is not larger than 500mm. The invention also discloses a fixing method which comprises the following steps: taking the prepared concrete top part embedded part body, and drilling the fixing holes in the concrete top part embedded part by magnetic force; after being drilled, placing the concrete top plate embedded part body on the top surface of the constructed mold plate according to accurate positions; fixing the concrete top plate embedded part body on the top surface of the mold plate through nails, the nails penetrate through the top surface of the mold plate, and the penetrating length is 25-35mm; bending the nails penetrating through the top surface of the mold plate towards the side; pouring a concrete top plate so that a to-be-embedded part is solidified with concrete; and disassembling the mold plate. The concrete top plate embedded part and fixing method thereof disclosed by the invention effectively solve the deflection problem of the position and the elevation of the top plate embedded part.
Description
Technical field
The present invention relates to a kind of building operations with parts and job practices, especially relate to a kind of concrete top board built-in fitting and fixing means thereof.
Background technology
At present; In the industrial construction construction; Keep somewhere built-in fitting in most of concrete, and the cast-in-situ concrete built-in fitting is easy in construction imbed concrete and cross problems such as dark owing to fixing not firm offset or the embedded part of occurring, and the embedded part position deviation is quality problems very serious in the building operations; Directly influence the construction of next procedure, cause very big loss.
Especially built-in fitting fixing in top board; In the past in construction; Be that the top board built-in fitting is placed directly on the bed die of top board; Embedded part is fixed on the reinforced mesh, because in the concreting process, what be difficult to avoid will occur because personnel walk about and concrete impact and vibrate and cause the variation of embedded part position when toppling over again.
Summary of the invention
The objective of the invention is in order to overcome above-mentioned deficiency of the prior art, a kind of a kind of concrete top board built-in fitting and fixing means thereof that can effectively solve the offset issue of top board built-in fitting position and absolute altitude is provided.
The present invention is achieved through following technical proposals:
A kind of concrete top board built-in fitting comprises embedded part body, and said embedded part body is provided with and is used at least 2 fixing holes fixing with template, and the spacing of said fixing hole is not more than 500mm.
Said embedded part body is of a size of 240-600mm * 160-800mm, and thickness is 10mm.
Another technical scheme of the present invention is the fixing means of concrete top board built-in fitting, comprises the steps:
(1) get the concrete top board embedded part body that has prepared, bore fixing hole with magnetic force, the quantity of said fixing hole is at least 2;
(2) the concrete top board embedded part body after will holing, by the tram be placed on constructed the template end face on;
(3) through fixing hole, concrete top board embedded part body is fixed on the template end face with nail, said nail spigot die plate top surface, penetrating component is 25-35mm;
(4) with the nail of spigot die plate top surface to the side bending;
(5) fluid concrete top board is treated built-in fitting and concrete setting;
(6) stripping.
The invention has the beneficial effects as follows:, be fixed on the template end face, in the concreting process through on the concrete top board embedded part body for preparing, punching; Can avoid with occur because personnel walk about and concrete impact and vibrate when toppling over cause the variation issue of built-in fitting position; And then the deviation of solution top board built-in fitting position and absolute altitude, this method is simple and easy to do in addition, and cost is low; Easy construction, effective.
Description of drawings
Fig. 1 is the present invention's view of constructing.
Fig. 2-1 is the structural representation of different size built-in fitting fixing hole setting of the present invention to 2-3.
Reference numeral: 1 built-in fitting, 2 templates, 3 iron nails, 4 fixing holes, 5 concrete rooves, 6 scaffold tubes, 7 wood are stupefied
The specific embodiment
In order further to understand the present invention, following below in conjunction with the detailed description of the drawings specific embodiment:
Like Fig. 2-2 to shown in the 2-3: a kind of concrete top board of apparatus of the present invention built-in fitting 1, comprise embedded part body, said embedded part body is of a size of between 240-600mm * 160-800mm, thickness is 10mm; Said embedded part body is provided with and is used at least 2 fixing holes 4 of fixing with template 2; Promptly when the size of embedded part body was big, the hole of setting was just some more, on the contrary can be provided with less; But minimumly can not be less than 2, the spacing of said fixing hole is not more than 500mm.
The fixing means of concrete top board built-in fitting 1 of the present invention is made up of following step:
As shown in Figure 1, the work in one early stage is to put up scaffold earlier, sets up its scaffold tubes 6 above the scaffold, on scaffold tubes 6, lays wood stupefied 7; The present invention gets the concrete top board embedded part body that has prepared then, bore fixing hole 4 with magnetic force, bored the hole after; By the tram be placed on constructed template 2 end faces on; Through fixing hole 4, with iron nail 3 concrete top board embedded part body is fixed on the end face of template 2 then, said iron nail will penetrate the end face of template 2; Penetrating component is within 25-35mm, and the part that the present invention penetrates is 30mm; The iron nail 3 that will penetrate template 2 end faces then is to the side bending; Be that built-in fitting just combines with template closely, just can carry out the fluid concrete top board, treat built-in fitting 1 and concrete setting after, just can be earlier that the iron nail sled is straight, again template is pulled down, built-in fitting 1 promptly of the present invention just is arranged in the top board that concrete constitutes.
The above-mentioned specific embodiment of the present invention just schematically; Be not restrictive; Those of ordinary skill in the art is under enlightenment of the present invention; Not breaking away under the scope situation that aim of the present invention and claim protect, can also make the conversion of a lot of forms, these all belong within protection scope of the present invention.
Claims (3)
1. a concrete top board built-in fitting comprises embedded part body, it is characterized in that, said embedded part body is provided with and is used at least 2 fixing holes fixing with template, and the spacing of said fixing hole is not more than 500mm.
2. concrete top board built-in fitting according to claim 1 is characterized in that said embedded part body is of a size of 240-600mm * 160-800mm, and thickness is 10mm.
3. the fixing means of a concrete top board built-in fitting: it is characterized in that comprising the steps:
(1) get the concrete top board embedded part body that has prepared, bore fixing hole with magnetic force, the quantity of said fixing hole is at least 2;
(2) the concrete top board embedded part body after will holing, by the tram be placed on constructed the template end face on;
(3) through fixing hole, concrete top board embedded part body is fixed on the template end face with iron nail, said iron nail spigot die plate top surface, penetrating component is 25-35mm;
(4) with the nail of spigot die plate top surface to the side bending;
(5) fluid concrete top board is treated built-in fitting and concrete setting;
(6) stripping.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201110197252A CN102312485A (en) | 2011-07-14 | 2011-07-14 | Concrete top plate embedded part and fixing method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201110197252A CN102312485A (en) | 2011-07-14 | 2011-07-14 | Concrete top plate embedded part and fixing method thereof |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102312485A true CN102312485A (en) | 2012-01-11 |
Family
ID=45426020
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201110197252A Pending CN102312485A (en) | 2011-07-14 | 2011-07-14 | Concrete top plate embedded part and fixing method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102312485A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108505652A (en) * | 2018-04-02 | 2018-09-07 | 中国十七冶集团有限公司 | A kind of curtain wall embedded member fixing device and installation method |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1236047A (en) * | 1998-05-14 | 1999-11-24 | 许恒嘉 | Mounting and construction method for building built-in part and its auxiliary fixture |
US20050276674A1 (en) * | 2004-06-15 | 2005-12-15 | Pryor John D | Multiple leg concrete anchor |
CN101672038A (en) * | 2009-09-18 | 2010-03-17 | 天津二十冶建设有限公司 | Method for fixing embedded part of large foundation side wall |
CN101787706A (en) * | 2010-03-04 | 2010-07-28 | 中冶实久建设有限公司 | Construction method of installing and fixing equipment basic pre-buried iron elements |
CN201785875U (en) * | 2010-09-28 | 2011-04-06 | 中国十五冶金建设有限公司 | Adjustable type built-in fitting for fixed screw bolt |
-
2011
- 2011-07-14 CN CN201110197252A patent/CN102312485A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1236047A (en) * | 1998-05-14 | 1999-11-24 | 许恒嘉 | Mounting and construction method for building built-in part and its auxiliary fixture |
US20050276674A1 (en) * | 2004-06-15 | 2005-12-15 | Pryor John D | Multiple leg concrete anchor |
CN101672038A (en) * | 2009-09-18 | 2010-03-17 | 天津二十冶建设有限公司 | Method for fixing embedded part of large foundation side wall |
CN101787706A (en) * | 2010-03-04 | 2010-07-28 | 中冶实久建设有限公司 | Construction method of installing and fixing equipment basic pre-buried iron elements |
CN201785875U (en) * | 2010-09-28 | 2011-04-06 | 中国十五冶金建设有限公司 | Adjustable type built-in fitting for fixed screw bolt |
Non-Patent Citations (1)
Title |
---|
银宏义: "预埋件安装的质量控制", 《内蒙古科技与经济》 * |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108505652A (en) * | 2018-04-02 | 2018-09-07 | 中国十七冶集团有限公司 | A kind of curtain wall embedded member fixing device and installation method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207633540U (en) | Vertical between fabricated shear wall is hinged structure more | |
CN203429641U (en) | Single-side supporting formwork reinforcing structure system for building construction | |
CN204983662U (en) | To drawing screw rod and steel pipe framed bent combination unilateral formwork device | |
CN107663903A (en) | The attachment structure and prefabrication and assembly construction method of assembly concrete shear wall and coupling beam | |
CN203270599U (en) | Foundation bolt pre-buried die | |
CN102312485A (en) | Concrete top plate embedded part and fixing method thereof | |
CN105604339B (en) | Secondary structure constructs column reinforcing method | |
CN102425271B (en) | Split head used for building floor | |
CN104947853B (en) | A kind of Inner standpipe formula cast-in-situ reinforced concrete column and construction method | |
CN202247938U (en) | Wedge-shaped foundation bolt preformed hole core formwork device | |
CN107288341A (en) | A kind of reserving hole building mortion and construction method | |
CN202000562U (en) | Multifunctional limiting device for shear wall | |
CN105317230A (en) | Fixing method of beam and wall pre-embedded horizontal sleeve | |
CN101832025A (en) | Sealing up screw | |
CN204238550U (en) | A kind of device for clamping masonry ring beam template | |
CN106284978A (en) | A kind of movement joint both sides shear wall synchronous construction technique and canalization template | |
CN102605945B (en) | Manufacturing method of big wood formwork | |
CN203174625U (en) | Small-section square reserved hole template | |
CN103352568A (en) | Method for building constructional column on foundation pad | |
CN201835524U (en) | Pouring device for concrete beam with top embedded part | |
CN205954854U (en) | Pre -buried device based on template can be dismantled | |
CN208777700U (en) | Cast-in-situ floor hole reserves mold | |
CN203684661U (en) | Advanced location construction device for steel bar planting of constructional columns | |
CN205436766U (en) | Punching device of pre -buried steel sheet of bridge | |
CN202323896U (en) | Accurate positioning device for embedded anchor cone |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20120111 |