CN101787706A - Construction method of installing and fixing equipment basic pre-buried iron elements - Google Patents

Construction method of installing and fixing equipment basic pre-buried iron elements Download PDF

Info

Publication number
CN101787706A
CN101787706A CN 201010118955 CN201010118955A CN101787706A CN 101787706 A CN101787706 A CN 101787706A CN 201010118955 CN201010118955 CN 201010118955 CN 201010118955 A CN201010118955 A CN 201010118955A CN 101787706 A CN101787706 A CN 101787706A
Authority
CN
China
Prior art keywords
buried iron
iron parts
embedded iron
fixing
iron elements
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 201010118955
Other languages
Chinese (zh)
Inventor
马会军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC Shijiu Construction Co Ltd
Original Assignee
MCC Shijiu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC Shijiu Construction Co Ltd filed Critical MCC Shijiu Construction Co Ltd
Priority to CN 201010118955 priority Critical patent/CN101787706A/en
Publication of CN101787706A publication Critical patent/CN101787706A/en
Pending legal-status Critical Current

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

Thee invention relates to a construction method of installing and fixing equipment basic pre-buried iron elements, which comprises the following steps: processing and manufacturing the pre-buried iron elements according to a design drawing; processing fixing holes on the pre-buried iron elements; welding pre-buried iron element anchoring ribs; installing the pre-buried iron elements in correct positions after the formwork completion of a basic template; drilling holes on a template sleeve; fixing the pre-buried iron elements to the template through fixing screw bolts; casting concrete; after completion, releasing the fixing screw bolts of the pre-buried iron elements; cutting exposed screw bolts; and grinding the screw bolts to obtain the smooth appearance. The invention changes the traditional pre-buried iron element fixing method on the basis of summarizing the defects of the existing pre-buried iron element fixing method, and the screw bolts are adopted for positioning and fixing, so the installation positions of the pre-buried iron elements are accurate. When the method of the invention is adopted, the positioning accuracy of the installation positions of the pre-buried iron elements is greatly improved, the rework and repair loss is reduced, good construction conditions are created for the subsequent work, and the effect is obvious.

Description

The job practices that a kind of equipment basic pre-buried iron elements installs and fixes
Technical field
The present invention relates to the job practices that a kind of equipment basic pre-buried iron elements installs and fixes.
Background technology
In the construction of metallurgical engineering Equipment Foundations, the installation of embedded iron parts is very general, behind traditional embedded iron parts location, usually adopts the inner support steel reinforcing, fixes to guarantee the embedded iron parts installation site.Yet, influence of various factors in owing to constructed, embedded iron parts installing and locating effect is unsatisfactory, usually after form removal, embedded iron parts caves in, verticality, planeness are not enough etc., and problem emerges in an endless stream, and badly influences follow-up engineering, construction as follow-up support of pipelines installation, cable testing bridge installation etc., usually need to take to add remedial measures such as backing plate, both wasted manpower, also strengthened material cost.This is the persistent ailment that perplexs the Equipment Foundations construction for a long time.
Summary of the invention
The objective of the invention is at above-mentioned present situation, aim to provide and a kind ofly can fundamentally solve the excessive job practices of equipment basic pre-buried iron elements installing and locating deviation.
The implementation of the object of the invention is, the job practices that a kind of equipment basic pre-buried iron elements installs and fixes, and concrete steps are as follows:
1) processing and fabricating of embedded iron parts
1. according to design drawing processing and fabricating embedded iron parts,
2. on embedded iron parts, pass through drilling machine or other boring bar tools, the fixing hole of processing and fabricating requirement,
3. weld the embedded iron parts anchor rib,
2) installation of embedded iron parts
1. after the foundation forms formwork finishes, embedded iron parts is in place,
2. adopt power drill to template carry out with embedded iron parts on the cover of fixing hole bore;
3. the supporting set bolt of fixing hole on employing and the embedded iron parts is fixed together embedded iron parts and template,
4. concreting, reach the form removal condition after, unclamp the embedded iron parts set bolt, excision exerted bolt, and polishing flat.
The present invention is summing up on the basis of embedded iron parts fixing means deficiency in the past, is changing traditional embedded iron parts fixing means, adopts the bolt positioning and fixing, makes that embedded iron parts installation forming position is accurate.Adopt this method, improved the accurate location of embedded iron parts installation site greatly, having reduced does over again reprocesses loss, has created good execution conditions for follow-up work, and effect is remarkable.
The specific embodiment
Concrete steps of the present invention are as follows:
1) processing and fabricating of embedded iron parts
1. according to design drawing processing and fabricating embedded iron parts,
2. according to embedded iron parts size and deadweight, fixing hole position, aperture, quantity are set, general aperture is set to about 8mm, by drilling machine or other boring bar tools, processing and fabricating fixing hole;
3. weld the embedded iron parts anchor rib, guarantee weldquality, flame smoothing embedded iron parts plate face, planeness meets the job specfication requirement;
2) installation of embedded iron parts
1. after the foundation forms formwork finishes, according to construction drawing, embedded iron parts is in place, guarantees that the embedded iron parts position is accurate, verticality meets the requirements;
2. utilize the fixing hole on the embedded iron parts, instruments such as employing power drill overlap brill to template;
3. according to the fixing hole pore size, adopt supporting with it plain bolt, embedded iron parts and template are fixed together;
4. concreting finish reach the form removal condition after, unclamp the embedded iron parts set bolt, adopt sanding machine excision exerted bolt, and polish flat.

Claims (1)

1. job practices that equipment basic pre-buried iron elements installs and fixes is characterized in that concrete steps are as follows:
1) processing and fabricating of embedded iron parts
1. according to design drawing processing and fabricating embedded iron parts,
2. on embedded iron parts, pass through drilling machine or other boring bar tools, the fixing hole of processing and fabricating requirement,
3. weld the embedded iron parts anchor rib,
2) installation of embedded iron parts
1. after the foundation forms formwork finishes, embedded iron parts is in place,
2. adopt power drill to template carry out with embedded iron parts on the cover of fixing hole bore;
3. the supporting set bolt of fixing hole on employing and the embedded iron parts is fixed together embedded iron parts and template,
4. concreting after finishing, unclamps the embedded iron parts set bolt, the excision exerted bolt, and polish flat.
CN 201010118955 2010-03-04 2010-03-04 Construction method of installing and fixing equipment basic pre-buried iron elements Pending CN101787706A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201010118955 CN101787706A (en) 2010-03-04 2010-03-04 Construction method of installing and fixing equipment basic pre-buried iron elements

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201010118955 CN101787706A (en) 2010-03-04 2010-03-04 Construction method of installing and fixing equipment basic pre-buried iron elements

Publications (1)

Publication Number Publication Date
CN101787706A true CN101787706A (en) 2010-07-28

Family

ID=42531073

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201010118955 Pending CN101787706A (en) 2010-03-04 2010-03-04 Construction method of installing and fixing equipment basic pre-buried iron elements

Country Status (1)

Country Link
CN (1) CN101787706A (en)

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102095052A (en) * 2010-11-25 2011-06-15 华锐风电科技(集团)股份有限公司 Installing method of foundation bolt anchoring system and method for installing industrial equipment
CN102312485A (en) * 2011-07-14 2012-01-11 天津二十冶建设有限公司 Concrete top plate embedded part and fixing method thereof
CN103276747A (en) * 2013-06-26 2013-09-04 陕西建工集团第十一建筑工程有限公司 One-time high-accuracy pre-burying construction method for large equipment base guide rails
CN103590416A (en) * 2013-11-01 2014-02-19 浙江水利水电学院 Pre-buried construction method for high-precision foundation bolts
CN103711141A (en) * 2013-12-17 2014-04-09 攀钢集团工程技术有限公司 Construction method for equipment installation without sizing block
CN103835308A (en) * 2012-11-23 2014-06-04 江西昌河航空工业有限公司 Method for installing embedded base plate of machine tool
CN104818730A (en) * 2015-05-26 2015-08-05 中国化学工程第三建设有限公司 Equipment base top embedded part and mounting method thereof
CN105133556A (en) * 2015-09-01 2015-12-09 中国电建集团贵阳勘测设计研究院有限公司 Pre-embedded steel plate applicable to wood formwork
CN106760707A (en) * 2016-11-21 2017-05-31 常州第建筑集团有限公司 Trench abnormity branch mouthful embedded iron construction method
CN107447773A (en) * 2017-07-14 2017-12-08 中国能源建设集团浙江省电力设计院有限公司 A kind of main transformer basis manufacture method for being used to discharge data constraint
CN107780432A (en) * 2016-08-27 2018-03-09 上海宝冶集团有限公司 Improve the construction method of the medium-and-large-sized installation of embedded parts precision of Equipment Foundations
CN109057102A (en) * 2018-09-20 2018-12-21 中国二十二冶集团有限公司 The installation method of slag processing wall protection board
CN111155549A (en) * 2019-12-27 2020-05-15 绍兴宝城建筑工业化制造有限公司 Construction method of steel structure combined embedded part
CN111851568A (en) * 2020-07-31 2020-10-30 无锡市政设计研究院有限公司 Method for remedying foundation embedded plate and embedded plate used by same

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101250881A (en) * 2008-01-21 2008-08-27 武汉冶建安装工程有限责任公司 Method for installation of seat slurry method construction packing plate
CN201406691Y (en) * 2009-04-13 2010-02-17 中冶实久建设有限公司 Positioning structure for ground bolt

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101250881A (en) * 2008-01-21 2008-08-27 武汉冶建安装工程有限责任公司 Method for installation of seat slurry method construction packing plate
CN201406691Y (en) * 2009-04-13 2010-02-17 中冶实久建设有限公司 Positioning structure for ground bolt

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
《内蒙古科技与经济》 20090615 银宏义 预埋件安装的质量控制 130、132 1 , 第11期 *

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102095052B (en) * 2010-11-25 2013-06-12 华锐风电科技(集团)股份有限公司 Installing method of foundation bolt anchoring system and method for installing industrial equipment
CN102095052A (en) * 2010-11-25 2011-06-15 华锐风电科技(集团)股份有限公司 Installing method of foundation bolt anchoring system and method for installing industrial equipment
CN102312485A (en) * 2011-07-14 2012-01-11 天津二十冶建设有限公司 Concrete top plate embedded part and fixing method thereof
CN103835308A (en) * 2012-11-23 2014-06-04 江西昌河航空工业有限公司 Method for installing embedded base plate of machine tool
CN103276747A (en) * 2013-06-26 2013-09-04 陕西建工集团第十一建筑工程有限公司 One-time high-accuracy pre-burying construction method for large equipment base guide rails
CN103590416B (en) * 2013-11-01 2016-03-16 浙江水利水电学院 Foot bolt Embedment Construction engineering method accurately
CN103590416A (en) * 2013-11-01 2014-02-19 浙江水利水电学院 Pre-buried construction method for high-precision foundation bolts
CN103711141A (en) * 2013-12-17 2014-04-09 攀钢集团工程技术有限公司 Construction method for equipment installation without sizing block
CN104818730A (en) * 2015-05-26 2015-08-05 中国化学工程第三建设有限公司 Equipment base top embedded part and mounting method thereof
CN105133556A (en) * 2015-09-01 2015-12-09 中国电建集团贵阳勘测设计研究院有限公司 Pre-embedded steel plate applicable to wood formwork
CN107780432A (en) * 2016-08-27 2018-03-09 上海宝冶集团有限公司 Improve the construction method of the medium-and-large-sized installation of embedded parts precision of Equipment Foundations
CN106760707A (en) * 2016-11-21 2017-05-31 常州第建筑集团有限公司 Trench abnormity branch mouthful embedded iron construction method
CN106760707B (en) * 2016-11-21 2019-01-29 常州第一建筑集团有限公司 Trench abnormity branch mouth embedded iron construction method
CN107447773A (en) * 2017-07-14 2017-12-08 中国能源建设集团浙江省电力设计院有限公司 A kind of main transformer basis manufacture method for being used to discharge data constraint
CN109057102A (en) * 2018-09-20 2018-12-21 中国二十二冶集团有限公司 The installation method of slag processing wall protection board
CN111155549A (en) * 2019-12-27 2020-05-15 绍兴宝城建筑工业化制造有限公司 Construction method of steel structure combined embedded part
CN111851568A (en) * 2020-07-31 2020-10-30 无锡市政设计研究院有限公司 Method for remedying foundation embedded plate and embedded plate used by same

Similar Documents

Publication Publication Date Title
CN101787706A (en) Construction method of installing and fixing equipment basic pre-buried iron elements
CN203684398U (en) Device for positioning embedded parts in reinforced concrete structure
CN103243911A (en) Integral setting and one-step in-position construction method for steel sleeves of inner pipelines of vertical shaft of building
CN106320715B (en) A kind of construction method of installation of the I-shaped inclined-plane built-in fitting of large size
CN103206089A (en) Fabricated aluminum alloy formwork system construction method
CN103758348B (en) Profile steel framework structure concrete floor slab suspension mould pouring construction method
CN102764956A (en) Production process of steel moulding plate
CN103835373B (en) The construction method of a kind of annular cap built-in fitting and annular concrete cap
CN108678004A (en) A kind of installation method of Urban Underground pipe gallery built-in groove
CN208733666U (en) A kind of fixing bolt preformed hole template tool
CN110820794B (en) Integrated construction method for equipment base and foundation embedded part
CN201908439U (en) Reserved embedded grouting die for floor sleeve holes
CN104612175A (en) Device and method used for guaranteeing levelness of installation plane of precise equipment
CN211258625U (en) Tunnel secondary lining platform truck end template
JP2012154040A (en) Ruler for spray of mortar and the like
CN100507174C (en) Pre-embedded construction method for PVC casing pipe of prestressed hollow slab hanger rod
CN108049639B (en) Method for connecting ring crane rail bearing beam and bracket
JP2019155659A (en) Drilling machine
CN104074320A (en) Method for fast mounting handrails
CN103866770B (en) A kind of combined steel formwork and mounting method thereof
CN205343431U (en) Prefabricated wall body grout sleeve strip solid matter exposes accurate positioning die of reinforcing bar
CN103556825A (en) Construction method for reserved pipe sleeve in concrete of structural layers of high-rise building
CN103276840A (en) Nuclear power plant composite floor slab module and construction method thereof
CN219317838U (en) Hanging rod embedded mounting structure capable of fine adjustment of position
CN204899241U (en) Built -in fitting center positioner for downcomer

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Open date: 20100728