CN102296813A - Construction method for steel column base and steel column base structure thereof - Google Patents

Construction method for steel column base and steel column base structure thereof Download PDF

Info

Publication number
CN102296813A
CN102296813A CN2010102097821A CN201010209782A CN102296813A CN 102296813 A CN102296813 A CN 102296813A CN 2010102097821 A CN2010102097821 A CN 2010102097821A CN 201010209782 A CN201010209782 A CN 201010209782A CN 102296813 A CN102296813 A CN 102296813A
Authority
CN
China
Prior art keywords
rebound
steel column
crab
bolt
basis
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2010102097821A
Other languages
Chinese (zh)
Other versions
CN102296813B (en
Inventor
宋泽恒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Original Assignee
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guiyang Aluminum Magnesium Design and Research Institute Co Ltd filed Critical Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority to CN201010209782.1A priority Critical patent/CN102296813B/en
Publication of CN102296813A publication Critical patent/CN102296813A/en
Application granted granted Critical
Publication of CN102296813B publication Critical patent/CN102296813B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The invention discloses a construction method for a steel column base and a steel column base structure thereof. A transition plate is welded on an anchor bolt by using a plug welding method; then a bottom plate of a steel column is welded on the transition plate by using triangular welding; and the original threaded connection is changed into welding connection. By adopting the method, the mounting is facilitated; and waste in materials and labor time caused because a concrete foundation is required to be knocked down to newly construct in the case of deviation in the position of the anchor bolt of the steel column base in the prior art is avoided. The steel column base has a simple structure, is low in construction cost and can guarantee safety and reliability during mounting.

Description

A kind of job practices of steel column pin and steel column leg structure thereof
Technical field
The present invention relates to a kind of job practices and steel column leg structure thereof of steel column pin, belong to construction engineering technical field.
Background technology
The job practices of steel column pin is in the construction work at present, and the anchor of pre-buried steel suspension column is fastened in concrete foundation, and the end that anchor is fastened is provided with screw thread.When steel column was installed, the base plate of steel column bottom was fixed on the anchor that exposes basic end face with nut and fixes, and does the back-grouting layer again between base plate bottom steel column and the basic end face then, so just can transmit the superstructure load.But in work progress, the steel column pin anchor that exposes the concrete foundation end face is fastened the position and through regular meeting deviation is taken place, and makes the base plate of steel column bottom that difficulty is installed and maybe can't install.Though steel column pin anchor is fastened the position zero deflection sometimes, when being installed, steel column, heavylier breaks the screw thread that steel column pin anchor is fixed through regular meeting because the steel column quality is big, and nut can't be tightened, safety and reliability that influence connects.
Summary of the invention
The objective of the invention is to, provide a kind of and be convenient to install, simple in structure, operating expenses is low, and the situation that can avoid invar suspension column anchor to fasten needing the dismantling concrete basis to construct again when deviation appears in the position takes place and the job practices and the steel column leg structure thereof of the steel column pin of the safety that can guarantee to install and reliability, thereby overcome the deficiencies in the prior art.
Technical scheme of the present invention: the job practices of a kind of steel column pin of the present invention is, by following step construction,
A, when basis casting pre-buried one group of crab-bolt in the basis, treat that concrete is fixed after, with the crab-bolt levelling, make crab-bolt expose the length unanimity on basis;
B, making rebound with holes, the position in hole is corresponding with the crab-bolt position, crab-bolt is penetrated 1/3-1/2 in the hole of rebound, and make rebound and basic top reserve the gap of back-grouting, with the rebound levelling, and the design elevation between plane and the basis top on the assurance rebound, then in the hole with rebound and crab-bolt plug welding, and the scolder of giving prominence to polished flat;
C, the back-grouting layer of between top, basis and rebound baseplane, casting;
D, treat that the back-grouting layer is fixed after, the base plate on the steel column is seated in plane on the rebound, on the base of steel column base plate steel column base plate and rebound are welded together.
The steel column leg structure of the present invention that makes up by the job practices of above-mentioned steel column pin is: comprise the basis, be embedded with one group of crab-bolt in the basis, crab-bolt upper end and rebound welding are provided with the back-grouting layer between rebound and the basis; The base plate welding of the last plane of rebound and steel column bottom.
In the aforesaid structure, be connected through plug welding on the described crab-bolt with between the rebound.
In the aforesaid structure, last plane three fillet welding of described rebound are connected with the base plate of steel column bottom.
In the aforesaid structure, described back-grouting layer adds that the thickness of rebound equals design elevation.
Compared with prior art, the present invention adopts the mode of plug welding to weld a rebound on crab-bolt, and then adopts the base plate of steel column three fillet welding to be welded on the rebound, changes original being threaded to and is welded to connect.Method of the present invention is convenient to install, and can avoid prior art invar suspension column anchor to fasten the position when deviation takes place, and needs the dismantling concrete basis to construct again, and of the present invention simple in structure, operating expenses is low, and can guarantee the safety and the reliability of installing.
Description of drawings
Fig. 1 is a structural representation of the present invention;
Fig. 2 is the vertical view of Fig. 1.
Being labeled as in the accompanying drawing: 1-basis, 2-crab-bolt, 3-rebound, 4-plug welding, 5-back-grouting layer, 6-steel column, 7-base plate, 8-three fillet welding.
The specific embodiment
The present invention is described in further detail below in conjunction with drawings and Examples.
Embodiment.Structure of the present invention as depicted in figs. 1 and 2.When carrying out the construction of steel column pin, construct by following step,
A, when basis casting pre-buried one group of crab-bolt in the basis, treat that concrete is fixed after, with the crab-bolt levelling, make crab-bolt expose the length unanimity on basis;
B, making rebound with holes, the position in hole is corresponding with the crab-bolt position, crab-bolt is penetrated 1/3-1/2 in the hole of rebound, and make rebound and basic top reserve the gap of back-grouting, with the rebound levelling, and the design elevation between plane and the basis top on the assurance rebound, then in the hole with rebound and crab-bolt plug welding, and the scolder of giving prominence to polished flat;
C, the back-grouting layer of between top, basis and rebound baseplane, casting;
D, treat that the back-grouting layer is fixed after, the base plate on the steel column is seated in plane on the rebound, on the base of steel column base plate steel column base plate and rebound are welded together.
By the steel column leg structure of the present invention that the job practices of above-mentioned steel column pin makes up, comprise basis 1, during making, in basis 1, be embedded with one group of crab-bolt 2, be connected through plug welding 4 between crab-bolt 2 upper ends and the rebound 3; And between rebound 3 and basis 1, back-grouting layer 5 is set; The thickness that makes back-grouting layer 5 add rebound 3 equals design elevation; The last plane trigonometry weldering 8 of rebound 3 is connected with the base plate 7 of steel column 6 bottoms.

Claims (5)

1. the job practices of a steel column pin is characterized in that: by following step construction,
A, when basis casting pre-buried one group of crab-bolt in the basis, treat that concrete is fixed after, with the crab-bolt levelling, make crab-bolt expose the length unanimity on basis;
B, making rebound with holes, the position in hole is corresponding with the crab-bolt position, crab-bolt is penetrated 1/3-1/2 in the hole of rebound, and make rebound and basic top reserve the gap of back-grouting, with the rebound levelling, and the design elevation between plane and the basis top on the assurance rebound, then in the hole with rebound and crab-bolt plug welding, and the scolder of giving prominence to polished flat;
C, the back-grouting layer of between top, basis and rebound baseplane, casting;
D, treat that the back-grouting layer is fixed after, the bottom block on the steel column is dropped on plane on the rebound, on the base of steel column base plate steel column base plate and rebound are welded together.
2. press the steel column leg structure that the described method of claim 1 makes up for one kind, comprise basis (1), it is characterized in that: be embedded with one group of crab-bolt (2) in basis (1), crab-bolt (2) upper end and rebound (3) welding are provided with back-grouting layer (5) between rebound (3) and the basis (1); Base plate (7) welding of the last plane of rebound (3) and steel column (6) bottom.
3. steel column leg structure according to claim 2 is characterized in that: be connected through plug welding (4) on the described crab-bolt (2) with between the rebound (3).
4. steel column leg structure according to claim 2 is characterized in that: last plane three fillet welding (8) of described rebound (3) are connected with the base plate (7) of steel column (6) bottom.
5. steel column leg structure according to claim 2 is characterized in that: the thickness that described back-grouting layer (5) adds rebound (3) equals design elevation.
CN201010209782.1A 2010-06-25 2010-06-25 A kind of construction method of steel kind design and steel column base structure thereof Expired - Fee Related CN102296813B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201010209782.1A CN102296813B (en) 2010-06-25 2010-06-25 A kind of construction method of steel kind design and steel column base structure thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201010209782.1A CN102296813B (en) 2010-06-25 2010-06-25 A kind of construction method of steel kind design and steel column base structure thereof

Publications (2)

Publication Number Publication Date
CN102296813A true CN102296813A (en) 2011-12-28
CN102296813B CN102296813B (en) 2015-09-30

Family

ID=45357469

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201010209782.1A Expired - Fee Related CN102296813B (en) 2010-06-25 2010-06-25 A kind of construction method of steel kind design and steel column base structure thereof

Country Status (1)

Country Link
CN (1) CN102296813B (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102535850A (en) * 2012-03-12 2012-07-04 中天建设集团有限公司 Grouting construction method for steel-structured base
CN102635064A (en) * 2012-04-28 2012-08-15 西安建筑科技大学 Pre-tensioned prestressing steel pipe high-strength concrete superposition bridge pier and construction method thereof
CN102635063A (en) * 2012-04-28 2012-08-15 西安建筑科技大学 Post-tensioned prestressing steel pipe high-strength concrete superposition bridge pier and construction method thereof
CN104234070A (en) * 2014-07-23 2014-12-24 冠鲁建设股份有限公司 Steel structure and foundation pre-burying connection structure and construction method
CN105040826A (en) * 2015-08-05 2015-11-11 中国电建集团贵阳勘测设计研究院有限公司 Standard embedded assembly for structure concrete construction and construction method of standard embedded assembly
CN107604936A (en) * 2017-08-31 2018-01-19 杭萧钢构(河南)有限公司 A kind of means to save the situation of steel column foot crab-bolt dislocation
CN107905452A (en) * 2017-10-25 2018-04-13 重庆建工第三建设有限责任公司 A kind of heavy in section super thick steel reinforced concrete square column construction method
CN108894335A (en) * 2018-07-24 2018-11-27 中建八局第四建设有限公司 A kind of steel plate built-in fitting construction method and steel plate pre-embedded device
CN109440948A (en) * 2018-12-28 2019-03-08 上海建工七建集团有限公司 The connection structure and method of project to be continued steel construction and main structure
CN112144872A (en) * 2019-09-30 2020-12-29 上海宝冶集团有限公司 Rolling/sliding installation method for large steel structure truss
CN114277931A (en) * 2022-01-07 2022-04-05 浙江西子联合工程有限公司 Method for correcting deviation of steel column base node on site

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2861328Y (en) * 2005-12-19 2007-01-24 上海市第二建筑有限公司 Subsectional embedded structure of concrete steel column in reverse construction engineering
CN101105077A (en) * 2006-07-11 2008-01-16 永都建设产业株式会社 Method for connecting reinforced concrete structures
CN201133090Y (en) * 2007-07-09 2008-10-15 李树林 Frame column anti-seismic structure for house floor increasing
CN201406766Y (en) * 2009-05-05 2010-02-17 中冶东方工程技术有限公司上海分公司 Steel column inserted type rigid connection column foot

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2861328Y (en) * 2005-12-19 2007-01-24 上海市第二建筑有限公司 Subsectional embedded structure of concrete steel column in reverse construction engineering
CN101105077A (en) * 2006-07-11 2008-01-16 永都建设产业株式会社 Method for connecting reinforced concrete structures
CN201133090Y (en) * 2007-07-09 2008-10-15 李树林 Frame column anti-seismic structure for house floor increasing
CN201406766Y (en) * 2009-05-05 2010-02-17 中冶东方工程技术有限公司上海分公司 Steel column inserted type rigid connection column foot

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102535850A (en) * 2012-03-12 2012-07-04 中天建设集团有限公司 Grouting construction method for steel-structured base
CN102635064A (en) * 2012-04-28 2012-08-15 西安建筑科技大学 Pre-tensioned prestressing steel pipe high-strength concrete superposition bridge pier and construction method thereof
CN102635063A (en) * 2012-04-28 2012-08-15 西安建筑科技大学 Post-tensioned prestressing steel pipe high-strength concrete superposition bridge pier and construction method thereof
CN104234070A (en) * 2014-07-23 2014-12-24 冠鲁建设股份有限公司 Steel structure and foundation pre-burying connection structure and construction method
CN104234070B (en) * 2014-07-23 2016-08-17 杭州江润科技有限公司 A kind of steel construction and the pre-buried attachment structure in basis and construction method
CN105040826A (en) * 2015-08-05 2015-11-11 中国电建集团贵阳勘测设计研究院有限公司 Standard embedded assembly for structure concrete construction and construction method of standard embedded assembly
CN107604936A (en) * 2017-08-31 2018-01-19 杭萧钢构(河南)有限公司 A kind of means to save the situation of steel column foot crab-bolt dislocation
CN107905452A (en) * 2017-10-25 2018-04-13 重庆建工第三建设有限责任公司 A kind of heavy in section super thick steel reinforced concrete square column construction method
CN108894335A (en) * 2018-07-24 2018-11-27 中建八局第四建设有限公司 A kind of steel plate built-in fitting construction method and steel plate pre-embedded device
CN109440948A (en) * 2018-12-28 2019-03-08 上海建工七建集团有限公司 The connection structure and method of project to be continued steel construction and main structure
CN112144872A (en) * 2019-09-30 2020-12-29 上海宝冶集团有限公司 Rolling/sliding installation method for large steel structure truss
CN114277931A (en) * 2022-01-07 2022-04-05 浙江西子联合工程有限公司 Method for correcting deviation of steel column base node on site
CN114277931B (en) * 2022-01-07 2024-01-02 浙江西子联合工程有限公司 Method for correcting deviation of steel column foot node on site

Also Published As

Publication number Publication date
CN102296813B (en) 2015-09-30

Similar Documents

Publication Publication Date Title
CN102296813A (en) Construction method for steel column base and steel column base structure thereof
CN103422512B (en) Replaceable pre-embedded bolt formula wind generation set concrete foundation and construction method thereof
JP4702862B1 (en) Height adjustment support device for structure and height adjustment method for structure support device
CN203462583U (en) Super high-rise exposed column foot
CN109629424B (en) Cantilever support and construction method of concrete flange of steel-concrete combined bridge using cantilever support
CN102912972B (en) Multifunctional lifting steel platform switching jig and construction method
CN102926504B (en) Construction method of steel and concrete overlapped beam combined part
CN201713940U (en) Steel column base structure
CN113860190B (en) Cantilever crane turnover-free beam rest bracket and installation method
CN201284485Y (en) Fixing device of stone bolt
CN102953344B (en) Climbing cone type triangular cantilever bracket
CN106760014A (en) A kind of board-like adjustable damper embedded part of full assembled and installation method
CN102535507B (en) Combined tower base
CN214574622U (en) PC prefabricated column connection structure
CN204876084U (en) Steel column foot crab -bolt fixed bolster
KR20110088283A (en) Girder having mold supporter and scaffold supporter
CN201915420U (en) Foundation of temporary gate building
CN203320420U (en) Temporary locking structure for corrugated steel webs of steel and concrete combined box girder
CN209941512U (en) Supporting shear part for lower cross beam of inclined tower of cable-stayed bridge
CN210505323U (en) Tower crane anchor foot adjustable support
CN111140010B (en) Vertical connection construction method for upper layer and lower layer of assembled steel-concrete combined pipe
CN108342979B (en) Bridge rapid replacement support and rapid replacement method for bridge support
CN201296995Y (en) Combined connecting structure of corrugated steel web plate in box beam bridge
CN203096625U (en) Suspending basket back pressure slideway anchoring structure
CN201296902Y (en) Bearing anchor ear

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150930

Termination date: 20160625

CF01 Termination of patent right due to non-payment of annual fee