CN102296766A - Assembled staircase temporary protective railing - Google Patents

Assembled staircase temporary protective railing Download PDF

Info

Publication number
CN102296766A
CN102296766A CN2011101635681A CN201110163568A CN102296766A CN 102296766 A CN102296766 A CN 102296766A CN 2011101635681 A CN2011101635681 A CN 2011101635681A CN 201110163568 A CN201110163568 A CN 201110163568A CN 102296766 A CN102296766 A CN 102296766A
Authority
CN
China
Prior art keywords
column
adjustable armrest
fixed
stair
connecting bolt
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011101635681A
Other languages
Chinese (zh)
Inventor
高宝俭
马恒晞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Provincial Construction Group Co Ltd
Original Assignee
Jiangsu Provincial Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Provincial Construction Group Co Ltd filed Critical Jiangsu Provincial Construction Group Co Ltd
Priority to CN2011101635681A priority Critical patent/CN102296766A/en
Publication of CN102296766A publication Critical patent/CN102296766A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Steps, Ramps, And Handrails (AREA)

Abstract

The invention relates to an assembled staircase temporary protective railing which is characterized in that the assembled staircase temporary protective railing mainly comprises corner upright posts (1), upright posts (2) and adjustable handrail railings (3), wherein the upright posts (2) are fixed on staircase grounds at the bottom layer and the highest layer through expansion bolts, the corner upright posts (1) are fixed on the staircase grounds except the bottom layer and the top layer through the expansion bolts, one end of each of the adjustable handrail railings (3) at the bottom layer and the top layer is connected with the corner upright post (1) through a connecting bolt, the other end of each is also connected with the upright post (2) through the connecting bolt, and the two ends of each of the adjustable handrail railings (3) except the top layer and the bottom layer are connected with the corresponding corner upright posts (1) through the connecting bolts. The assembled staircase temporary protective railing is good in stability, safe, reliable, convenient to assemble and disassemble and contributed to improving the level of civilized construction on a site.

Description

The interim guard rail of assembly type stair
Technical field
The present invention relates to a kind of building operations facility, the interim balustrade that uses in especially a kind of building operations, specifically a kind of connection is reliable, and construction finishes the interim guard rail of assembly type stair that easily remove the back.
Background technology
At present, in the building operations, balustrade generally is the civil engineering project of last construction, and for the sake of security, the building operations code requirement must install interim guardrail additional behind the stair casting forming.For this reason, most of units in charge of construction are in order to save cost, use scaffolding steel pipe and fastener to build easy balustrade mostly, not only take a large amount of scaffolding steel pipes, and poor stability, especially being easy to make job site invar tube head to expose, meet the eye on every side all is connection fastener, and the pedestrian collides steel pipe or fastener easily, influences civilized construction.If directly with the steel pipe welding, will cause the waste of removing difficulty and a large amount of construction materials after then construction finishes,, still not have good solution at present to this.
Summary of the invention
The objective of the invention is to design a kind of safety standard that both met the interim guard rail of the convenient repeatedly used assembly type stair of neat appearance, and mounting or dismounting again at the interim handrail poor stability of stair in the present building operations, inaesthetic problem.
Technical scheme of the present invention is:
The interim guard rail of a kind of assembly type stair, it is characterized in that it is mainly by turning column 1, column 2 and adjustable armrest railing 3 are formed, column 2 is fixed on bottom and the top stair ground by expansion bolt, turning column 1 is fixed on the stair ground except that bottom and top layer by expansion bolt, one end of the adjustable armrest railing 3 of bottom and top layer links to each other with turning column 1 by connecting bolt, the other end also links to each other with column 2 by connecting bolt, and the two ends of the adjustable armrest railing 3 except that top layer and bottom link to each other with corresponding turning column 1 by connecting bolt respectively.
Described turning column 1 is by left column 101, right column 102, connect cross bar 103 and elongated base plate 104 compositions, thereby elongated base plate 104 is provided with and installs expansion bolt elongated base plate is fixed on the ground through hole of stair, left column 101 and right column 102 are welded on the elongated base plate 104, connect to form doorframe shape structure by connecting cross bar 103 between left column 101 and the right column 102, upper end and/or place, centre position at left column 101 and right column 102 are provided with the brace 105 that links to each other with adjustable armrest railing 3, thereby brace 105 is provided with for the through hole of connecting bolt by adjustable armrest railing 3 is linked to each other with turning column 1.
Described column 2 comprises cylinder 201 and short bottom plate 202, and cylinder 201 is welded on the short bottom plate 202, and expansion bolt is fixed on the ground through hole of stair by making short bottom plate thereby short bottom plate 202 is provided with confession; Upper end and/or middle part at cylinder 201 are connected with brace 203, thereby brace 203 is provided with for the through hole of connecting bolt by realizing linking to each other with adjustable armrest railing 3.
Described adjustable armrest railing 3 is by the tubulose body of rod 301, fixedly connected 302, activity intubate 303 and flexibly connect sheet 304 and form, described fixedly connected 302 end with the tubulose body of rod 301 is weldingly connected, flexibly connect an end of sheet 304 and an end of activity intubate 303 and be weldingly connected, activity intubate 303 is inserted in the other end of the tubulose body of rod 301; Described fixedly connected 302 and flexibly connect and to be equipped with the through hole that passes through for connecting bolt on the sheet 304, and be arranged with the anti-interference structure 305 that connects.
Described anti-connection interference structure 305 is symmetrically arranged chamfering or arc structure.
Be described fixedly connected 302 and be weldingly fixed on fixedly on the intubate 306 that fixedly intubate 306 is fixed in the tubulose body of rod 301.
Beneficial effect of the present invention:
The present invention is simple in structure, and employed raw material are for being the building site common used material.
Good stability of the present invention, safe and reliable, mounting or dismounting are convenient, help improving building site civilized construction level.
Description of drawings
Fig. 1 is a user mode schematic diagram of the present invention.
Fig. 2 is the structural representation of turning of the present invention column.
Fig. 3 is the left view of Fig. 2.
Fig. 4 is the structural representation of column of the present invention.
Fig. 5 is the left TV structure schematic diagram of Fig. 4.
Fig. 6 is the structural representation of adjustable armrest railing of the present invention.
Fig. 7 is the syndeton schematic diagram on turning of the present invention column and stair ground.
Fig. 8 is the syndeton schematic diagram on column of the present invention and stair ground.
The specific embodiment
The present invention is further illustrated below in conjunction with drawings and Examples.
Shown in Fig. 1-8.
The interim guard rail of a kind of assembly type stair, it is mainly lacked one turning column 1 than number of floor levels by quantity, column 2 that bottom and top layer are installed and adjustable armrest railing 3 are formed, column 2 is fixed on bottom and the top stair ground (as Fig. 8) by expansion bolt, turning column 1 is fixed on except that on the stair ground of bottom and top layer (as Fig. 7) by expansion bolt, one end of the adjustable armrest railing 3 of bottom and top layer links to each other with turning column 1 by connecting bolt, the other end also links to each other with column 2 by connecting bolt, and the two ends of the adjustable armrest railing 3 except that top layer and bottom link to each other with corresponding turning column 1 by connecting bolt respectively.As shown in Figure 1.Turning of the present invention column 1 is by left column 101, right column 102, connect cross bar 103 and elongated base plate 104 compositions, as Fig. 2, shown in 3, thereby elongated base plate 104 is provided with and installs expansion bolt elongated base plate is fixed on the ground through hole of stair, left column 101 and right column 102 are welded on the elongated base plate 104, connect to form doorframe shape structure by connecting cross bar 103 between left column 101 and the right column 102, upper end and/or place, centre position at left column 101 and right column 102 are provided with the brace 105 that links to each other with adjustable armrest railing 3, thereby brace 105 is provided with for the through hole of connecting bolt by adjustable armrest railing 3 is linked to each other with turning column 1.Column 2 of the present invention comprises cylinder 201 and short bottom plate 202, and cylinder 201 is welded on the short bottom plate 202, and expansion bolt is fixed on the ground through hole of stair by making short bottom plate thereby short bottom plate 202 is provided with confession; Upper end and/or middle part at cylinder 201 are connected with brace 203, thereby brace 203 is provided with for the through hole of connecting bolt by realizing linking to each other with adjustable armrest railing 3, shown in Fig. 4,5.Adjustable armrest railing 3 of the present invention is by the tubulose body of rod 301, fixedly connected 302, activity intubate 303 and flexibly connect sheet 304 and form, as shown in Figure 6, described fixedly connected 302 end with the tubulose body of rod 301 is weldingly connected, flexibly connect an end of sheet 304 and an end of activity intubate 303 and be weldingly connected, activity intubate 303 is inserted in the other end of the tubulose body of rod 301; Described fixedly connected 302 and flexibly connect and to be equipped with the through hole that passes through for connecting bolt on the sheet 304, and be arranged with the anti-interference structure 305 that connects, as symmetrically arranged chamfering or arc structure.In addition, fixedly connected 302 also can be weldingly fixed on earlier fixedly on the intubate 306 when specifically implementing, and fixedly intubate 306 is fixed by welding in the tubulose body of rod 301 again.
In addition, the intubate at the two ends of adjustable armrest railing 3 also can be designed to be movable structure when specifically implementing, and at this moment, only needs to install dog screw additional on the tubulose body of rod 301 and chute gets final product.
In addition, can the adjustable hand rail of one deck be set according to height of armrests when specifically implementing, also can design two layers or more adjustable hand rail, only need the burn-on brace of respective numbers of column and column corresponding position, turning to get final product.
Using method of the present invention is:
With expansion bolt column and turning column are fixed on the stair ground earlier, shown in Fig. 7,8, then with fixedly connected 302 of the tubulose body of rod 301 1 ends with column or turning column on corresponding brace link to each other, then activity intubate 303 is inserted in the pipe support, the position of adjusting activity intubate 303 in the tubulose body of rod 301 makes to flexibly connect sheet 304 and corresponding column or continuous the getting final product of the usefulness of the brace on the column of turning connection breechblock.During dismounting, unclamp the connecting bolt that connects the tubulose body of rod 301 earlier, take off the tubulose body of rod 301, unclamping column then can be connected base plate with the turning column with column with expansion bolt nut on the column of turning and take out from ground, only stay the expansion breechblock on stair ground, the normal construction that can make expansion bolt not influence balustrade by the method for welding or hammering gets final product, and the column of pulling down, turning column and adjustable armrest railing 3 can be transported to next building site to be continued to use.
The part that the present invention does not relate to prior art that maybe can adopt all same as the prior art is realized.

Claims (6)

1. interim guard rail of assembly type stair, it is characterized in that it is mainly by turning column (1), column (2) and adjustable armrest railing (3) are formed, column (2) is fixed on bottom and the top stair ground by expansion bolt, turning column (1) is fixed on the stair ground except that bottom and top layer by expansion bolt, one end of the adjustable armrest railing (3) of bottom and top layer links to each other with turning column (1) by connecting bolt, the other end also links to each other with column (2) by connecting bolt, and the two ends of the adjustable armrest railing (3) except that top layer and bottom link to each other with corresponding turning column (1) by connecting bolt respectively.
2. the interim guard rail of assembly type stair according to claim 1, it is characterized in that described turning column (1) is by left column (101), right column (102), connecting cross bar (103) and elongated base plate (104) forms, elongated base plate (104) thus be provided with and install expansion bolt elongated base plate is fixed on the ground through hole of stair, left column (101) and right column (102) are welded on the elongated base plate (104), connect to form doorframe shape structure by connecting cross bar (103) between left column (101) and the right column (102), in the upper end of left column (101) and right column (102) and/or the place, centre position be provided with the brace (105) that links to each other with adjustable armrest railing (3), brace (105) thus be provided with the through hole of confession connecting bolt by adjustable armrest railing (3) is linked to each other with turning column (1).
3. the interim guard rail of assembly type stair according to claim 1, it is characterized in that described column (2) comprises cylinder (201) and short bottom plate (202), cylinder (201) is welded on the short bottom plate (202), short bottom plate (202) thus be provided with for expansion bolt and be fixed on the ground through hole of stair by making short bottom plate; Upper end and/or middle part at cylinder (201) are connected with brace (203), brace (203) thus be provided with for the through hole of connecting bolt by realizing linking to each other with adjustable armrest railing (3).
4. the interim guard rail of assembly type stair according to claim 1, it is characterized in that described adjustable armrest railing (3) is by the tubulose body of rod (301), fixedly connected (302), activity intubate (303) with flexibly connect sheet (304) and form, described fixedly connected (302) are weldingly connected with an end of the tubulose body of rod (301), flexibly connect an end of sheet (304) and an end of activity intubate (303) and be weldingly connected, activity intubate (303) is inserted in the other end of the tubulose body of rod (301); Be equipped with the through hole that passes through for connecting bolt on described fixedly connected (302) and the flexible connection sheet (304), and be arranged with the anti-interference structure (305) that connects.
5. the interim guard rail of assembly type stair according to claim 4 is characterized in that described anti-connection interference structure (305) is symmetrically arranged chamfering or arc structure.
6. the interim guard rail of assembly type stair according to claim 4 is characterized in that described fixedly connected (302) are weldingly fixed on fixedly on the intubate (306), and fixedly intubate (306) is fixed in the tubulose body of rod (301).
CN2011101635681A 2011-06-17 2011-06-17 Assembled staircase temporary protective railing Pending CN102296766A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011101635681A CN102296766A (en) 2011-06-17 2011-06-17 Assembled staircase temporary protective railing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011101635681A CN102296766A (en) 2011-06-17 2011-06-17 Assembled staircase temporary protective railing

Publications (1)

Publication Number Publication Date
CN102296766A true CN102296766A (en) 2011-12-28

Family

ID=45357422

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011101635681A Pending CN102296766A (en) 2011-06-17 2011-06-17 Assembled staircase temporary protective railing

Country Status (1)

Country Link
CN (1) CN102296766A (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4255913A (en) * 1979-04-02 1981-03-17 Frank Poma Hollow sleeve brackets
US6279880B1 (en) * 1999-08-20 2001-08-28 Onsite Safety Systems Onsite temporary fall protection system
CN2758372Y (en) * 2004-12-14 2006-02-15 蔡建平 Assembled protective fence
CN2841842Y (en) * 2005-11-11 2006-11-29 张克军 Protective guard
CN201202238Y (en) * 2008-05-30 2009-03-04 浙江省一建建设集团有限公司 Stair temporary guard rail
CN201217950Y (en) * 2008-06-30 2009-04-08 上海市第七建筑有限公司 Temporary protection railing used for stairs
CN201786036U (en) * 2010-08-13 2011-04-06 中国建筑第五工程局有限公司东莞分公司 Temporary protective barrier for building construction
CN202164760U (en) * 2011-06-17 2012-03-14 江苏省建筑工程集团有限公司 Assembled temporary protection railing for stairs

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4255913A (en) * 1979-04-02 1981-03-17 Frank Poma Hollow sleeve brackets
US6279880B1 (en) * 1999-08-20 2001-08-28 Onsite Safety Systems Onsite temporary fall protection system
CN2758372Y (en) * 2004-12-14 2006-02-15 蔡建平 Assembled protective fence
CN2841842Y (en) * 2005-11-11 2006-11-29 张克军 Protective guard
CN201202238Y (en) * 2008-05-30 2009-03-04 浙江省一建建设集团有限公司 Stair temporary guard rail
CN201217950Y (en) * 2008-06-30 2009-04-08 上海市第七建筑有限公司 Temporary protection railing used for stairs
CN201786036U (en) * 2010-08-13 2011-04-06 中国建筑第五工程局有限公司东莞分公司 Temporary protective barrier for building construction
CN202164760U (en) * 2011-06-17 2012-03-14 江苏省建筑工程集团有限公司 Assembled temporary protection railing for stairs

Similar Documents

Publication Publication Date Title
CN202866311U (en) Construction stair protective barrier and veering connecting device
CN209976088U (en) Assembled protection canopy
CN201786036U (en) Temporary protective barrier for building construction
CN202164760U (en) Assembled temporary protection railing for stairs
CN202215006U (en) Tool-type fixed ladder for construction
CN102296766A (en) Assembled staircase temporary protective railing
CN206784977U (en) Construction stair are easily assembled temporary guard rail
CN208056519U (en) A kind of detachable edge protection column
CN110029804A (en) A kind of sizing steel operating platform
CN211639872U (en) Multi-specification PC component placing frame
CN202882352U (en) Multi-layer steel structure connection corridor shaped like Chinese character 'gan' of old commercial and residential building adding elevator
CN210596876U (en) Plank road
CN206418785U (en) Concrete staircase boards face side patch-in formula guardrail
CN201649003U (en) Active powder concrete column and steel pipe combination rail structure
CN218623015U (en) Assembled steel construction stair
CN215484911U (en) Temporary movable stair for assembly type building operation layer
CN205934726U (en) Modular safe work platform
CN205591450U (en) Suspension type stair
CN212984409U (en) Detachable edge-protective guardrail
CN213296937U (en) Steel construction stair that circles round
CN215407555U (en) Interim protective structure of pin-connected panel stair
CN218970474U (en) Assembled concrete stair
CN219261558U (en) Steel concrete integrated stair
CN219196671U (en) Modularized silo construction stair
CN202969972U (en) Tool type safety enclosure guardrail

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20111228