CN102289588A - 上下分层地质条件下盾构刀盘俯仰弯矩的计算方法 - Google Patents

上下分层地质条件下盾构刀盘俯仰弯矩的计算方法 Download PDF

Info

Publication number
CN102289588A
CN102289588A CN2011102371498A CN201110237149A CN102289588A CN 102289588 A CN102289588 A CN 102289588A CN 2011102371498 A CN2011102371498 A CN 2011102371498A CN 201110237149 A CN201110237149 A CN 201110237149A CN 102289588 A CN102289588 A CN 102289588A
Authority
CN
China
Prior art keywords
geological
geology
moment
shield
flexure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2011102371498A
Other languages
English (en)
Other versions
CN102289588B (zh
Inventor
张茜
亢一澜
蔡宗熙
仇巍
王燕群
黄田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin University
Original Assignee
Tianjin University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin University filed Critical Tianjin University
Priority to CN 201110237149 priority Critical patent/CN102289588B/zh
Publication of CN102289588A publication Critical patent/CN102289588A/zh
Application granted granted Critical
Publication of CN102289588B publication Critical patent/CN102289588B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

本发明公开了一种上下分层地质条件下盾构刀盘俯仰弯矩的计算方法,该方法分为三个步骤:1.判定开挖面地质分层情况,开挖面分为上下两个地质层:工况1是指上层地质覆盖深度小于刀盘半径;工况2是指上层地质覆盖深度大于刀盘半径。其它二个步骤分别是:2.若属工况1,则计算工况1下刀盘的俯仰弯矩M1;3.若属工况2,则计算工况2下刀盘的俯仰弯矩M2,不同工况有不同的计算公式。本发明根据地质分层情况预先确定工程全线的俯仰弯矩控制目标,并可随着掘进过程中地质条件和操作状态的改变随时进行调整,改善了原有控制方法的滞后性,为维持盾构高效安全的直线前行提供科学有效的技术指导。

Description

上下分层地质条件下盾构刀盘俯仰弯矩的计算方法
技术领域
本发明属于盾构机械施工技术,具体涉及一种在某种地质条件下预测盾构机刀盘俯仰弯矩的计算方法。
背景技术
近年来,随着许多城市逐步发展地下交通建设,盾构施工法作为一种暗挖隧道的工程方法,以其对周围环境扰动小等优点被越来越广泛的应用于地铁工程施工。在绝大多数隧道工程中,开挖面土体由于自然沉积等原因自上而下分为不同地质层,并且由于土体的自重会引起土体压力梯度随着埋深的增大而逐渐加大。因此当盾构机在上下分层地质中掘进时,由于刀盘前方待开挖土体的不均匀分布,以及沿埋深方向土体压力梯度的逐渐增大,会引起盾构的掘进轨迹在深度方向发生向上或向下的偏移。为保证盾构直线前进,避免盾首抬起或俯下,其驱动系统需要给刀盘施加一个俯仰弯矩。目前,该弯矩的施加主要依靠盾构机操纵人员的经验,在掘进过程中一旦发现盾首发生偏移,立即对弯矩进行调整,当然就存在一定的滞后。特别是在某些地质条件变化剧烈的施工段,由于缺乏预先的调整依据,常常会造成不必要的损失。因此,提出一种盾构在上下分层地质中掘进时刀盘俯仰弯矩的计算方法,是盾构施工领域亟待解决的问题。
发明内容
本发明的目的是,提出一种盾构在上下分层地质条件中掘进时刀盘俯仰弯矩的计算方法,为盾构施工提供有效的参数调整依据。
本发明的计算方法分为以下三个步骤:
(1)判定开挖面地质情况;
判定的开挖面地质情况包括地质工况1和地质工况2两种:工况1是指开挖面分上下两个地质层,上层地质覆盖深度小于刀盘半径,下层地质覆盖深度大于刀盘半径;工况2也是指开挖面分上下两个地质层,但上层地质覆盖深度大于刀盘半径,而下层地质覆盖深度小于刀盘半径。
(2)若属于地质分层工况1,则计算工况1下刀盘的俯仰弯矩M1
(3)若属于地质分层工况2,则计算工况2下刀盘的俯仰弯矩M2
具体计算式为:
M 1 = ( 1 - η ) [ δ π ( E 1 1 - μ 1 2 - E 2 1 - μ 2 2 ) + K 1 γ 1 ( 4 HR 3 π - R 2 4 ) - K 2 γ 2 ( 4 HR 3 π + R 2 4 ) ]
· [ R 2 arccos ( R - a R ) - R ( R - a ) 2 Ra - a 2 ]
M 2 = ( 1 - η ) [ δ π ( E 1 1 - μ 1 2 - E 2 1 - μ 2 2 ) + K 1 γ 1 ( 4 HR 3 π - R 2 4 ) - K 2 γ 2 ( 4 HR 3 π + R 2 4 ) ]
· [ R 2 arccos ( a - R R ) - R ( a - R ) 2 Ra - a 2 ]
式中各参数定义:a为上层土质的覆盖深度(m),E1、E2分别为上下两层土体的弹性模量(MPa),μ1、μ2分别为上下两层土体的泊松比,K1、K2分别为上下两层土体的静止土压力系数,γ1、γ2分别为上下两层土体的容重(kN/m3),δ为刀盘每转切入深度(m/r),R为刀盘半径(m),η为刀盘开口率,H为地表至盾构中心轴线处埋深(m)。
上述M1与M2两个公式的计算结果为正值时,表示需要给盾构刀盘施加一个使其下俯的弯矩以保证盾构直线掘进,弯矩的大小为|M1|或|M2|,当计算结果为负值时,则表示需要施加一个使其上仰的弯矩,弯矩的大小亦为|M1|或|M2|。
本发明的特点以及产生的积极效果是,当盾构机在上下分层地质条件中掘进时,可根据地质分层情况预先确定工程全线的俯仰弯矩控制目标,并可随着掘进过程中地质条件和操作状态的改变随时进行调整,改善了原有控制方法的滞后性,为维持盾构高效安全的直线前行提供科学有效的技术指导。
具体实施方式
以下通过具体实施例对本发明的计算过程作进一步的说明,需要说明的是本实施例是叙述性的,而不是限定性的,不以此限定本发明的保护范围。
本实施例结合某地铁工程施工过程。该工程采用盾构施工法,共掘进800环,任意选取其中的第20环和第50环为例,给出盾构掘进到这两环时刀盘俯仰弯矩的详细计算步骤,其他各环均可按照相同的方法进行计算。
盾构在上下分层地质条件中掘进时刀盘俯仰弯矩的计算方法
(1)判定开挖面地质情况;
(2)若属于地质分层工况1,则计算工况1下刀盘的俯仰弯矩M1
(3)若属于地质分层工况2,则计算工况2下刀盘的俯仰弯矩M2
首先确定目标工程的地质情况属于分层工况1还是分层工况2:
由地质报告获取目标工程的地质分层情况及地质参数,该工程第20环处地质条件属于工况1。上层为粉质粘土下层为粉砂,上层土体厚度a1=2m。
该工程第50环处地质条件属于工况2,上层为粉质粘土下层为粉砂,上层土体厚度a2=4m。
具体地质参数为(粉质粘土对应参数下标为1,粉砂对应参数下标为2):弹性模量E1=8.2MPa,E2=18.0MPa;泊松比μ1=0.30,μ2=0.23;容重γ1=20.0kN/m3,γ2=24.20kN/m3;静止土压力系数K1=0.40,K2=0.30。
第二步,计算工况1下第20环处的刀盘俯仰弯矩M1
盾构机刀盘结构参数如下:刀盘直径R=3.10m,刀盘开口率η=30%;
在掘进过程中,由盾构机自动采集到第20环处时,刀盘每转切入深度δ=0.02m/r,刀盘中心线埋深H=11.50m,
根据
M 1 = ( 1 - η ) [ δ π ( E 1 1 - μ 1 2 - E 2 1 - μ 2 2 ) + K 1 γ 1 ( 4 HR 3 π - R 2 4 ) - K 2 γ 2 ( 4 HR 3 π + R 2 4 ) ]
· [ R 2 arccos ( R - a R ) - R ( R - a ) 2 Ra - a 2 ]
计算得到M1=-107.66kNm,计算结果为负值,说明(掘进到20环时)需要给刀盘施加一个使其上仰的弯矩,具体数值为107.66kNm。
第三步,计算工况2下,第50环处的刀盘俯仰弯矩M2
刀盘结构参数与第二步中结构参数相同,盾构掘进到第50环处时,刀盘每转切入深度δ=0.03m/r,刀盘中心线埋深H=11.80m,
根据
M 2 = ( 1 - η ) [ δ π ( E 1 1 - μ 1 2 - E 2 1 - μ 2 2 ) + K 1 γ 1 ( 4 HR 3 π - R 2 4 ) - K 2 γ 2 ( 4 HR 3 π + R 2 4 ) ]
· [ R 2 arccos ( a - R R ) - R ( a - R ) 2 Ra - a 2 ]
计算得到M2=-336.71kNm,计算结果仍为负值,说明(掘进到50环时)需要给刀盘施加一个使其上仰的弯矩,具体数值为336.71kNm。
至此,为保证盾构直线掘进,已预先计算出该地铁工程掘进至第20环和第50环处时,盾构刀盘需要调整俯仰弯矩的具体参数。其余各环均可按照相同方法确定,由此可预先获得盾构在整个施工过程中,掘进到不同地质条件时的刀盘俯仰弯矩,为盾构施工提供科学有效的施工技术指导。

Claims (1)

1.上下分层地质条件下盾构刀盘俯仰弯矩的计算方法,其特征在于计算需要以下几个步骤:
(1)判定开挖面地质情况;
所述步骤(1)中判定的地质情况包括两种:地质工况1是指开挖面分上下两个地质层,上层地质覆盖深度小于刀盘半径,下层地质覆盖深度大于刀盘半径;地质工况2是指开挖面分上下两个地质层,上层地质覆盖深度大于刀盘半径,下层地质覆盖深度小于刀盘半径;
(2)若属于地质工况1,则计算工况1下刀盘的俯仰弯矩M1
M 1 = ( 1 - η ) [ δ π ( E 1 1 - μ 1 2 - E 2 1 - μ 2 2 ) + K 1 γ 1 ( 4 HR 3 π - R 2 4 ) - K 2 γ 2 ( 4 HR 3 π + R 2 4 ) ]
· [ R 2 arccos ( R - a R ) - R ( R - a ) 2 Ra - a 2 ]
式中:a为上层土质的覆盖深度(m),E1、E2分别为上下两层土体的弹性模量(MPa),μ1、μ2分别为上下两层土体的泊松比,K1、K2分别为上下两层土体的静止土压力系数,γ1、γ2分别为上下两层土体的容重(kN/m3),δ为刀盘每转切入深度(m/r),R为刀盘半径(m),η为刀盘开口率,H为地表至盾构中心轴线处埋深(m);
(3)若属于地质工况2,则计算工况2下刀盘的俯仰弯矩M2
M 2 = ( 1 - η ) [ δ π ( E 1 1 - μ 1 2 - E 2 1 - μ 2 2 ) + K 1 γ 1 ( 4 HR 3 π - R 2 4 ) - K 2 γ 2 ( 4 HR 3 π + R 2 4 ) ]
· [ R 2 arccos ( a - R R ) - R ( a - R ) 2 Ra - a 2 ]
式中各参数定义同前;
上述M1与M2两个公式的计算结果为正值时,表示需要给盾构刀盘施加一个使其下俯的弯矩,弯矩的大小为|M1|或|M2|,当计算结果为负值时,则表示需要施加一个使其上仰的弯矩,弯矩的大小亦为|M1|或|M2|。
CN 201110237149 2011-08-18 2011-08-18 上下分层地质条件下盾构刀盘俯仰弯矩的计算方法 Active CN102289588B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201110237149 CN102289588B (zh) 2011-08-18 2011-08-18 上下分层地质条件下盾构刀盘俯仰弯矩的计算方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201110237149 CN102289588B (zh) 2011-08-18 2011-08-18 上下分层地质条件下盾构刀盘俯仰弯矩的计算方法

Publications (2)

Publication Number Publication Date
CN102289588A true CN102289588A (zh) 2011-12-21
CN102289588B CN102289588B (zh) 2013-03-27

Family

ID=45336010

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201110237149 Active CN102289588B (zh) 2011-08-18 2011-08-18 上下分层地质条件下盾构刀盘俯仰弯矩的计算方法

Country Status (1)

Country Link
CN (1) CN102289588B (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102562086A (zh) * 2012-01-17 2012-07-11 天津大学 盾构掘进左右转向时回转弯矩的计算方法
CN102562079A (zh) * 2012-01-17 2012-07-11 天津大学 盾构掘进中沿深度方向调向时俯仰弯矩的计算方法
CN103899328A (zh) * 2014-03-10 2014-07-02 天津大学 曲面型土压平衡盾构刀盘正面扭矩的计算方法
CN104632239A (zh) * 2015-01-12 2015-05-20 天津大学 分层地质中盾构机推进油缸垂直分区压力配比的确定方法

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101182772A (zh) * 2007-11-20 2008-05-21 中铁二局股份有限公司 两线立交小半径、浅覆土、大纵坡复杂线型盾构施工方法
CN102129499A (zh) * 2011-03-15 2011-07-20 天津大学 隧道掘进机刀盘驱动载荷计算方法
CN102147826A (zh) * 2011-03-15 2011-08-10 天津大学 隧道掘进机在不同地质下最优掘进速度的计算方法

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101182772A (zh) * 2007-11-20 2008-05-21 中铁二局股份有限公司 两线立交小半径、浅覆土、大纵坡复杂线型盾构施工方法
CN102129499A (zh) * 2011-03-15 2011-07-20 天津大学 隧道掘进机刀盘驱动载荷计算方法
CN102147826A (zh) * 2011-03-15 2011-08-10 天津大学 隧道掘进机在不同地质下最优掘进速度的计算方法

Non-Patent Citations (5)

* Cited by examiner, † Cited by third party
Title
QIAN ZHANG ET AL: "Mechanical Model for Operational Loads Prediction on Shield Cutter Head during Excavation", 《2010 IEEE/ASME INTERNATIONAL CONFERENCE ON ADVANCED INTELLIGENT MECHATRONICS》, 9 July 2010 (2010-07-09), pages 1252 - 1256, XP031855744 *
刘建虎 等: "复合地层中盾构机外载荷模型研究", 《机械设计与制造》, no. 5, 31 May 2011 (2011-05-31), pages 1 - 3 *
张莹等: "盾构机掘进参数的关联分析与地质特征识别", 《哈尔滨工程大学学报》, vol. 32, no. 4, 30 April 2011 (2011-04-30), pages 476 - 480 *
苏健行 等: "土压平衡盾构掘进总推力的计算与试验研究", 《工程机械》, vol. 39, 31 January 2008 (2008-01-31), pages 13 - 16 *
苏翠侠等: "盾构刀盘掘进载荷的数值模拟", 《天 津 大 学 学 报》, vol. 44, no. 6, 30 June 2011 (2011-06-30), pages 522 - 528 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102562086A (zh) * 2012-01-17 2012-07-11 天津大学 盾构掘进左右转向时回转弯矩的计算方法
CN102562079A (zh) * 2012-01-17 2012-07-11 天津大学 盾构掘进中沿深度方向调向时俯仰弯矩的计算方法
CN102562086B (zh) * 2012-01-17 2013-11-13 天津大学 盾构掘进左右转向时回转弯矩的计算方法
CN103899328A (zh) * 2014-03-10 2014-07-02 天津大学 曲面型土压平衡盾构刀盘正面扭矩的计算方法
CN103899328B (zh) * 2014-03-10 2015-12-02 天津大学 曲面型土压平衡盾构刀盘正面扭矩的计算方法
CN104632239A (zh) * 2015-01-12 2015-05-20 天津大学 分层地质中盾构机推进油缸垂直分区压力配比的确定方法
CN104632239B (zh) * 2015-01-12 2017-05-17 天津大学 分层地质中盾构机推进油缸垂直分区压力配比的确定方法

Also Published As

Publication number Publication date
CN102289588B (zh) 2013-03-27

Similar Documents

Publication Publication Date Title
CN102262712B (zh) 上下分层地质条件下盾构刀盘正面载荷的计算方法
CN107842368B (zh) 城市隧道钻凿铣机械组合非爆开挖工艺
CN100580220C (zh) 三线并行下穿铁路干线隧道的盾构施工方法
CN108241780B (zh) 复合盾构在岩土混合地质中掘进刀盘扭矩的计算方法
CN107489424A (zh) 一种盾构地铁施工诱发地层变形及对古建筑影响的预估方法
Bergeson Review of long drive microtunneling technology for use on large scale projects
CN108268709B (zh) 复合盾构在岩土混合地质中掘进总推力的计算方法
CN101215969A (zh) 大直径盾构近距离下穿小直径地铁隧道的变形控制方法
CN102289588B (zh) 上下分层地质条件下盾构刀盘俯仰弯矩的计算方法
CN109056746A (zh) 一种柔性复合装配式可回收矩形工作井支护结构的设计施工方法
CN104455726A (zh) 一种管道底部注浆加固的顶管施工方法
CN102129499B (zh) 隧道掘进机刀盘驱动载荷计算方法
CN110259467A (zh) 泥水平衡盾构下穿江河施工方法
CN104100272A (zh) 一种隧道穿越不良地质的快速施工方法
CN102562079B (zh) 盾构掘进中沿深度方向调向时俯仰弯矩的计算方法
CN110984132B (zh) 复杂地质条件下地下连续墙成槽的施工方法
CN102147826A (zh) 隧道掘进机在不同地质下最优掘进速度的计算方法
CN103899328B (zh) 曲面型土压平衡盾构刀盘正面扭矩的计算方法
AU2021101945A4 (en) A Construction Control Method for Shield Tunneling Through Existing Operating Lines
CN103352705A (zh) 盾构机刀盘系统推力的计算方法
Liu et al. Subgrade settlements of existing railway lines and operational parameters of shield machine induced by twin shield tunnel excavations: A case study
CN111305847B (zh) 一种城市地下工程超浅埋暗挖施工动态极限强度控制方法
CN103437774A (zh) 一种盾构掘进的加工方法
CN102562086B (zh) 盾构掘进左右转向时回转弯矩的计算方法
CN108798704A (zh) 一种适用于地下工程施工的岩层主动托换方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant