CN102129499B - 隧道掘进机刀盘驱动载荷计算方法 - Google Patents

隧道掘进机刀盘驱动载荷计算方法 Download PDF

Info

Publication number
CN102129499B
CN102129499B CN2011100616503A CN201110061650A CN102129499B CN 102129499 B CN102129499 B CN 102129499B CN 2011100616503 A CN2011100616503 A CN 2011100616503A CN 201110061650 A CN201110061650 A CN 201110061650A CN 102129499 B CN102129499 B CN 102129499B
Authority
CN
China
Prior art keywords
cutterhead
soil
soil body
torque
determining
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2011100616503A
Other languages
English (en)
Other versions
CN102129499A (zh
Inventor
亢一澜
张茜
蔡宗熙
黄干云
仇巍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin University
Original Assignee
Tianjin University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin University filed Critical Tianjin University
Priority to CN2011100616503A priority Critical patent/CN102129499B/zh
Publication of CN102129499A publication Critical patent/CN102129499A/zh
Application granted granted Critical
Publication of CN102129499B publication Critical patent/CN102129499B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

一种包含地质参数、操作参数以及刀盘结构参数对刀盘载荷影响的驱动载荷计算方法,可以为刀盘设计及施工参数调整提供准确的依据。隧道掘进机刀盘驱动载荷包括推力和扭矩,其计算方法为:(1)确定开挖面静止土压力F1;(2)确定刀盘掘进推力F2;(3)根据F1和F2的和确定刀盘总的驱动推力;(4)确定刀盘侧面与周围土体间的摩擦扭矩T1;(5)确定密封舱内搅拌扭矩T2;(6)确定刀盘掘进扭矩T3;(7)由T1、T2、T3之和确定刀盘总的驱动扭矩。本方法可以快速计算出隧道掘进机刀盘驱动载荷,由于综合考虑了各核心要素对刀盘载荷的影响规律,因而计算结果更加准确,并能随时根据地质条件与操作状态的改变灵活调整载荷参数,实现了掘进机施工过程中载荷的科学设定与调整。

Description

隧道掘进机刀盘驱动载荷计算方法
技术领域
本发明属于隧道掘进机械施工技术,具体涉及一种隧道掘进机刀盘驱动载荷的计算方法。
背景技术
近年来,随着我国城市地下交通的迅速发展,铁路、输运管道等隧道工程项目逐渐增多,围绕隧道掘进机设计与施工的相关技术也得到快速发展。其中隧道掘进机刀盘驱动载荷的确定是其设计及施工环节的核心技术之一。准确计算隧道掘进机在掘进过程中刀盘所需要的驱动载荷值,是掘进机刀盘及动力系统设计的理论基础,也是施工过程中掘进状态实时调整的重要依据。掘进机在隧道掘进过程中,刀盘与掘进界面土体所构成的复杂力学系统包含:法向挤压、旋转摩擦、切削破坏等多种形式耦合作用。因此,其驱动载荷(包括推力与扭矩)与地质条件、刀盘结构以及操作状态等多种因素密切相关。目前实际工程中的隧道掘进机载荷计算多采用经验公式,但其仅给出一个较大的载荷估算区间,且经验系数缺乏明确的取值依据。国内外已有的刀盘载荷相关计算多为静态载荷分析,未考虑操作参数对载荷的影响。因此提出一种对刀盘驱动载荷的计算方法,成为本行业之急需。
发明内容
本发明的目的是,提出一种包含地质参数、操作参数以及刀盘结构参数对刀盘载荷影响的驱动载荷计算方法,为刀盘设计及施工参数调整提供准确的依据。
本发明的目的是这样实现的:隧道掘进机刀盘驱动载荷包括推力和扭矩,其计算确定方法,主要分为以下几个步骤:
(1)确定开挖面静止土压力F1
(2)确定刀盘掘进推力F2
(3)根据F1和F2的和确定刀盘总的驱动推力;
(4)确定刀盘侧面与周围土体间的摩擦扭矩T1
(5)确定密封舱内搅拌扭矩T2
(6)确定刀盘掘进扭矩T3
(7)根据T1、T2、T3之和确定刀盘总的驱动扭矩;
其中所述步骤(1)中的开挖面静止土压力,是指掘进界面前方土体在自然状态下由自身重力引起的土压力,与掘进过程无关,由如下公式确定:
F 1 = π D 2 4 K 0 γH
式中,D(m)为刀盘直径,K0为开挖面静止土压力系数,γ(kN/m3)为土体容重,H(m)为地表至掘进机中心线埋深。
其中所述步骤(2)中的刀盘掘进推力,是指掘进过程中由于刀盘挤压土体引起的,用以保证掘进机推进以及维持开挖面稳定的推进载荷,由如下公式确定:
F 2 = E 1 - μ 2 δD
式中,E(kPa)为土体弹性模量,μ为土体泊松比,δ(m/r)为刀盘每转切入深度。
然后根据所述步骤(1)、(2)将F1与F2之和确定为刀盘总的驱动推力。
其中所述步骤(4)中刀盘侧面与周围土体间的摩擦扭矩由如下公式确定:
T1=π·D·t·f1·Pm
式中,t(m)为刀盘厚度,f1为刀盘与土体间摩擦系数,Pm(kPa)为作用在刀盘侧面上的平均土压力。
其中所述步骤(5)中的密封舱内搅拌扭矩指刀盘后方密封舱内搅拌土体产生的扭矩,由如下公式确定:
T2=m·πDa·La·b·f2·pm
式中,m为搅拌棒个数,Da(m)为搅拌棒直径,La(m)为搅拌棒长度;b(m)为搅拌棒与刀盘中心轴线之间的平均距离;f2为搅拌棒与土体间摩擦系数;pm(kPa)为密封舱平均土压力。
其中所述步骤(6)中的掘进扭矩指在掘进界面上由于刀盘旋转摩擦土体及切削破坏土体所引起的扭转载荷,由如下公式确定:
T 3 = Eπ f 1 η 8 ( 1 - μ 2 ) δ D 2 + 1 12 πηc D 3
式中,η为刀盘开口率,c(kPa)为土体内聚力。
最后根据所述步骤(4)、(5)、(6)将T1、T2、T3之和确定为刀盘总的驱动扭矩。
本发明的特点以及产生的有益效果是,可以快速计算出隧道掘进机刀盘驱动载荷,由于综合考虑了地质条件、操作状态以及刀盘结构等核心要素对刀盘载荷的影响规律,因而计算结果比较准确,并能随时根据地质条件与操作状态的改变灵活调整载荷参数,为掘进机的刀盘设计以及施工过程中载荷参数的设定与实时调整提供科学依据。
具体实施方式
以下通过具体实施例对本发明的计算过程作进一步的说明,需要说明的是本实施例是叙述性的,不以此限定本发明的保护范围。
本实施例结合某地铁工程施工过程。该工程所使用的掘进机刀盘结构参数如下:刀盘直径D=6.34m,刀盘厚度t=0.475m,刀盘开口率η=44%,搅拌棒直径Da=0.162m,搅拌棒长度La=0.538m,搅拌棒个数m=4,搅拌棒与刀盘中心轴线之间的平均距离b=0.7m。以下将以该工程掘进到第50环的地质条件与操作状态为例,给出计算掘进到该环时掘进机刀盘所需驱动载荷值的详细步骤,其他各环均可按照相同的方法进行计算。
第一步确定开挖面静止土压力F1
由地质报告获取所需地质参数。根据该地铁工程第50环处的地质条件可知:开挖面静止土压力系数K0=0.5,土体容重γ=18.2kN/m3,地表至掘进机中心线埋深H=144m,
得到F1=4134.78kN。
第二步确定刀盘掘进推力F2
由掘进机上附带传感器获取操作参数。当掘进机掘进到第50环处时,刀盘每转切入深度δ=0.035m/r,土体弹性模量E=8200kPa,土体泊松比μ=0.35,
Figure BDA0000050236610000032
得到F2=2073.60kN。
第三步根据F1和F2的和确定刀盘总的驱动推力,该工程隧道掘进机在掘进至第50环时所需的驱动推力值为F=F1+F2=6208.38kN。
第四步确定刀盘侧面与周围土体间的摩擦扭矩T1
刀盘厚度t=0.475m,刀盘与土体间摩擦系数f1=0.25,刀盘侧面平均土压力Pm=197.2kPa
由T1=π·D·t·f1·Pm,得到T1=466.19kN·m。
第五步确定密封舱内搅拌扭矩T2
搅拌棒个数m=4,搅拌棒直径Da=0.162m,搅拌棒长度La=0.538m,搅拌棒与土体间摩擦系数f2=0.2,密封舱平均土压力pm=230kPa;搅拌棒与刀盘中心轴线之间的平均距离b=0.7m
由T2=m·πDa·La·b·f2·pm,得到T2=35.25kN·m。
第六步确定刀盘掘进扭矩T3
刀盘开口率η=44%,内聚力c=10kPa,其它参数同前,
Figure BDA0000050236610000041
得到T3=861.01kN·m。
第七步求和,掘进至第50环时所需的驱动扭矩值为T=T1+T2+T3=1362.45kN·m。至此,已计算出此隧道工程第50环处掘进机所需驱动载荷值,其余各环均可按照相同方法确定,由此可获得掘进机在整个施工过程中在不同地质条件和操作状态下所需的驱动载荷值。

Claims (1)

1.隧道掘进机刀盘驱动载荷计算方法,其特征在于计算分为以下几个步骤:
(1)确定开挖面静止土压力F1
所述开挖面静止土压力是指掘进界面前方土体在自然状态下由自身重力引起的土压力,由如下公式确定:
F 1 = πD 2 4 K 0 γH
式中,D为刀盘直径,K0为开挖面静止土压力系数,γ为土体容重,H为地表至掘进机中心线埋深;
(2)确定刀盘掘进推力F2
所述刀盘掘进推力是指掘进过程中,由刀盘挤压土体引起的,用以维持掘进机推进及开挖面稳定的推进载荷,由如下公式确定:
F 2 = E 1 - μ 2 δD
式中,E为土体弹性模量,μ为土体泊松比,δ为刀盘每转切入深度;
(3)根据F1和F2的和确定刀盘总的驱动推力为F1+F2
(4)确定刀盘侧面与周围土体间的摩擦扭矩T1
所述摩擦扭矩T1由如下公式确定:
T1=π·D·t·f1·Pm
式中,t为刀盘厚度,f1为刀盘与土体间摩擦系数,Pm为作用在刀盘侧面上的平均土压力;
(5)确定密封舱内搅拌扭矩T2
所述密封舱内搅拌扭矩是指刀盘后方密封舱内搅拌土体产生的扭矩,T2由如下公式确定:
T2=m·πDa·La·b·f2·pm
式中,m为搅拌棒个数,Da为搅拌棒直径,La为搅拌棒长度;b为搅拌棒与刀盘中心轴线之间的平均距离;f2为搅拌棒与土体间摩擦系数;pm为密封舱平均土压力;
(6)确定刀盘掘进扭矩T3
所述刀盘掘进扭矩是指在掘进界面上由刀盘旋转摩擦以及切削破坏土体所引起的扭转载荷,T3由如下公式确定:
T 3 = Eπ f 1 η 8 ( 1 - μ 2 ) δ D 2 + 1 12 πηc D 3
式中,η为刀盘开口率,c为土体内聚力;
(7)由所述步骤(4)、(5)和(6)将T1、T2、T3之和,确定为刀盘总的驱动扭矩。
CN2011100616503A 2011-03-15 2011-03-15 隧道掘进机刀盘驱动载荷计算方法 Active CN102129499B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011100616503A CN102129499B (zh) 2011-03-15 2011-03-15 隧道掘进机刀盘驱动载荷计算方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011100616503A CN102129499B (zh) 2011-03-15 2011-03-15 隧道掘进机刀盘驱动载荷计算方法

Publications (2)

Publication Number Publication Date
CN102129499A CN102129499A (zh) 2011-07-20
CN102129499B true CN102129499B (zh) 2012-07-11

Family

ID=44267581

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011100616503A Active CN102129499B (zh) 2011-03-15 2011-03-15 隧道掘进机刀盘驱动载荷计算方法

Country Status (1)

Country Link
CN (1) CN102129499B (zh)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102262712B (zh) * 2011-08-18 2013-03-27 天津大学 上下分层地质条件下盾构刀盘正面载荷的计算方法
CN102289588B (zh) * 2011-08-18 2013-03-27 天津大学 上下分层地质条件下盾构刀盘俯仰弯矩的计算方法
CN106383931A (zh) * 2016-08-31 2017-02-08 广州市市政集团有限公司 基于csm模型的隧道掘进机刀盘有效推力和扭矩计算方法
CN106777568B (zh) * 2016-11-29 2020-09-01 天津大学 全断面岩石掘进机刀盘掘进载荷的确定方法
CN108241780B (zh) * 2017-12-29 2021-06-08 天津大学 复合盾构在岩土混合地质中掘进刀盘扭矩的计算方法
CN109766621B (zh) * 2019-01-03 2020-08-21 天津大学 一种tbm刀盘扭矩确定方法及系统
CN113283106B (zh) * 2021-06-10 2024-02-13 中铁九局集团有限公司 一种顶管掘进机施工对上覆管线安全性影响预测方法

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
Qian Zhang 等.Mechanical Model for Operational Loads Prediction on Shield Cutter Head during Excavation.《2010 IEEE/ASME International Conference on Advanced Intelligent Mechatronics》.2010,1252-1256. *
吕强 等.土压平衡盾构掘进机刀盘扭矩模拟试验研究.《岩石力学与工程学报》.2006,第25卷(第增1期),3137-3143. *
邓立营 等.盾构机刀盘扭矩及盾体推力计算方法研究.《矿山机械》.2010,第38卷(第17期),13-16. *

Also Published As

Publication number Publication date
CN102129499A (zh) 2011-07-20

Similar Documents

Publication Publication Date Title
CN102129499B (zh) 隧道掘进机刀盘驱动载荷计算方法
CN102262712B (zh) 上下分层地质条件下盾构刀盘正面载荷的计算方法
CN108241780B (zh) 复合盾构在岩土混合地质中掘进刀盘扭矩的计算方法
CN108268709B (zh) 复合盾构在岩土混合地质中掘进总推力的计算方法
CN107165648A (zh) 用于盾构机的刀盘设计方法
CN107747488B (zh) 大断面马蹄形盾构始发的施工方法
CN110874512A (zh) 基于能耗的盾构机掘进效率计算方法
CN102538741A (zh) 考虑注浆压力的顶管施工引起土体变形的确定方法
CN103352705A (zh) 盾构机刀盘系统推力的计算方法
CN105926589B (zh) 适应于珊瑚礁地质的钢管桩及其注浆方法
AU2021101945A4 (en) A Construction Control Method for Shield Tunneling Through Existing Operating Lines
CN102562079B (zh) 盾构掘进中沿深度方向调向时俯仰弯矩的计算方法
Li et al. Observed ground pressure acting on the lining of a large-diameter shield tunnel in sandy stratum under high water pressure
CN102289588B (zh) 上下分层地质条件下盾构刀盘俯仰弯矩的计算方法
Tao et al. Pasternak model-based tunnel segment uplift model of subway shield tunnel during construction
Hsiung A case record of bored tunnels in sand based on the Kaohsiung mass rapid transit system project
Peng et al. Stress Performance Evaluation of Shield Machine Cutter Head during Cutting Piles under Masonry Structures
Zhang et al. Construction applicability of mechanical methods for connecting aisle in the bohai mudstone stratum with high water pressure
Li et al. Observed ground pressures and internal forces of the Shanghai Yangtze river tunnel
Bineshian (I)-TM: I-System’s Tunnelling Method–An Introduction
Kwak et al. Numerical simulation for surface settlement considering face vibration of TBM tunnelling in mixed-face condition
Liu et al. Subgrade settlements of existing railway lines and operational parameters of shield machine induced by twin shield tunnel excavations: A case study
Zhu et al. Research studies on the thrust of special-shaped full-sectional cutterheads of quasirectangular shield
CN202284448U (zh) 杂填土层钻孔引孔钻具
CN113775349B (zh) 一种小曲率半径盾构隧道推进参数确定方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant