CN102286983B - Split bamboo material soil nail and construction method thereof - Google Patents

Split bamboo material soil nail and construction method thereof Download PDF

Info

Publication number
CN102286983B
CN102286983B CN2011101237311A CN201110123731A CN102286983B CN 102286983 B CN102286983 B CN 102286983B CN 2011101237311 A CN2011101237311 A CN 2011101237311A CN 201110123731 A CN201110123731 A CN 201110123731A CN 102286983 B CN102286983 B CN 102286983B
Authority
CN
China
Prior art keywords
bamboo
bar
split
bamboo bar
locking
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2011101237311A
Other languages
Chinese (zh)
Other versions
CN102286983A (en
Inventor
朱良锋
许明辉
陈伟军
裘国荣
李灿峰
高纪明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHEJIANG BAOYE CONSTRUCTION GROUP CO Ltd
Original Assignee
ZHEJIANG BAOYE CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG BAOYE CONSTRUCTION GROUP CO Ltd filed Critical ZHEJIANG BAOYE CONSTRUCTION GROUP CO Ltd
Priority to CN2011101237311A priority Critical patent/CN102286983B/en
Publication of CN102286983A publication Critical patent/CN102286983A/en
Application granted granted Critical
Publication of CN102286983B publication Critical patent/CN102286983B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The invention relates to a split bamboo material soil nail. The inclined and downward split bamboo material soil nail is inserted into a foundation pit side wall soil layer, the lower parts of at least two split bamboo strips are fixed with a middle bamboo tube at a certain space, lower through holes are perforated at the upper bamboo joints of the split bamboo strips, bamboo fixing pins are inserted into the lower through holes, two vertical locking bamboo strips are bound under the locking bamboo pins, cement mortar or cement slurry is filled in soil layer drill holes, protection slope concrete is divided into two layers, a bamboo strip net piece and a reinforced bamboo strip are placed on the first layer protection slope concrete, and the locking bamboo pins and the vertical locking bamboo strips are buried in the second layer protection slope concrete. When the bottom of a foundation pit is a soft and weak soil layer, downward bamboo pipe piles can be beaten into the soil layer, the middle bamboo joints of the bamboo pipe piles can be in a penetrated way and is filled with concrete for enhancing the rigidity. The split bamboo material soil nail has the advantages that the structure is unique, the construction method is simple, various cheap, environmental-protection and natural bamboo materials can be used for replacing steel bars to be used as a body structure of the deep foundation pit soil nail wall protection, the construction safety of the foundation pit is ensured, and the construction cost is reduced.

Description

Split from bamboo wood soil nailing and job practices thereof
Technical field:
The invention belongs to technical field of civil engineering, split agent structure and the job practices of going along with sb. to guard him as foundation pit side-wall from the soil nailing wall of bamboo wood thereof more specifically to use.
Background technology:
Along with quickening of urbanization process, modern architecture need take full advantage of the underground space, and deep foundation ditch science safety economy excavation is imperative.Deep foundation pit support is the steps necessary of excavation pit, as a temporary structure, must guarantee that safe and reliable prerequisite is issued to the target of most economical environmental protection and energy saving.Existing soil nailing wall all is to cooperate steel mesh reinforcement surface layer, cement mixing pile or timber to do composite soil nailing and advance support wall with steel pipe soil nailing or reinforcing bar soil nailing, after foundation ditch is finished mission, a large amount of reinforcing bars are embedded in underground can't the recovery, soil layer is caused permanent effect, and cause bigger waste, disagree with the environmental protection and energy saving building that country advocates.
Summary of the invention:
Purpose of the present invention is exactly the deficiency at prior art; providing a kind of splits from bamboo wood soil nailing and job practices thereof; it utilizes cheapness, environmental protection, natural 2~3 years living bamboo woods to replace reinforcing bar as the agent structure of deep foundation ditch soil-nail wall support; guarantee security of foundation ditch construction; reduce construction cost, promote the regional economy development.
Technology solution of the present invention is as follows:
Split from the bamboo wood soil nailing, comprise the bamboo trunk stake, split from bamboo bar soil nailing, slope protection concrete, insert splitting from bamboo bar soil nailing under oblique in the foundation pit side-wall soil layer, split from the bottom of bamboo bar at a certain distance fixedly centering thick bamboo tube at least two, split from the perforation down of bamboo bar top ring thorn, insert locking bamboo pin, locking bamboo pin is the vertical locking of binding bamboo bar down, and cement mortar or cement paste are filled in the soil layer boring; Slope protection concrete is divided into two-layer, and bamboo bar net sheet and reinforcement bamboo bar place on the first floor slope protection concrete, and locking bamboo pin and the vertical bamboo bar that locks are embedded in the second layer slope protection concrete.
Squeezing in the described foundation pit side-wall bottom solum fixedly has downward bamboo trunk stake, and the middle ring of bamboo trunk stake connects and be perfused with concrete.
The tail end of described bamboo trunk stake is fined away.
The described fixedly centering thick bamboo tube of splitting from bamboo bar bottom at a certain distance, centering thick bamboo tube and splitting from bamboo piece wedging between bamboo bar side.
Described splitting from the perforation down of bamboo bar top ring thorn inserted locking bamboo pin, and locking bamboo pin must be sidelong, and locking bamboo pin is bound to two vertical locking bamboo bars with iron wire or thin bamboo strips used for weaving, forms " Lv " font tapered end.
Strengthen the parallel placement of bamboo bar, fix by iron wire or thin bamboo strips used for weaving colligation with vertical locking bamboo bar and bamboo bar net sheet for described two.
Split from the job practices of bamboo wood soil nailing:
1), excavation pit, spray the first floor slope protection concrete at the side surface of foundation pit side-wall soil layer;
2), the side surface at the foundation pit side-wall soil layer forms soil layer boring, fixedly centering thick bamboo tube will be split more than two from the bottom of bamboo bar at a certain distance, the centering thick bamboo tube and split between bamboo bar side with the filling of bamboo piece, the side interspaces up and down, splits from the bamboo bar and sends in the soil layer boring and cement injection mortar or cement paste in the soil layer boring;
3), split from the boring in advance down of bamboo bar top ring thorn, insert locking bamboo pin, locking bamboo pin is fixed with the colligation of vertical locking bamboo bar;
4), bamboo bar net sheet is laid on the first floor slope protection concrete, laterally bamboo bar net sheet is sidelong, and strengthens parallel the placing on the bamboo bar net sheet of bamboo bar with two, strengthen the bamboo bar by iron wire or thin bamboo strips used for weaving with bamboo bar net sheet with vertically lock the colligation of bamboo bar and fix;
5), the tail end of bamboo trunk stake fines away, and the bamboo trunk stake is squeezed into downwards in the foundation pit side-wall bottom solum, the ring of bamboo trunk stake can connect and inside concrete perfusion;
6), at first floor slope protection concrete jet surface second layer slope protection concrete.
Beneficial effect of the present invention is:
1, the present invention adopts the bamboo wood soil nailing, utilized the high strength properties of bamboo wood, the safety requirements of bracing of foundation pit is satisfied in design and construction, after treating that the excavation of foundation pit construction is finished, bamboo wood has satisfied useful life, rots automatically, can not leave over impurity in the stratum, exploitation to future can not impact, and solved the problem that soil nailing surmounts the land used red line yet.In weak soil, clay, silt geology, split from putting into hole slip casting after the bamboo bar needs machinery or artificial boring and become soil nailing.In the east of China, southern mountain region, various bamboo groves are extensively distributing, mao bamboon is short growth period, is generally the output height 2 years, low price, the intensity height, the natural durable time can reach 24 months, can satisfy the temporary structure needs of bracing of foundation pit, therefore, adopt all woolen bamboo soil nailing to meet the requirement of national science, economy, energy-saving and environmental protection building.
2, of the present invention splitting from bamboo bar soil nailing fixed form uniqueness adds bamboo trunk stake and bamboo bar net sheet, and whole stability to foundation ditch provides safeguard.
3, the present invention constructs simply, draws materials conveniently, is easy to popularize.
Description of drawings:
Fig. 1 is structural representation of the present invention
Fig. 2 is for splitting from bamboo bar soil nailing schematic diagram
Fig. 3 is the tapered end schematic diagram
Fig. 4 is middle thick bamboo tube schematic diagram
Fig. 5 is bamboo bar net sheet schematic diagram
Among the figure: A, foundation pit side-wall soil layer; 1, bamboo trunk stake; 2, split from bamboo bar soil nailing; 21, split from the bamboo bar; 211, ring thorn; 3, slope protection concrete; 31, first floor slope protection concrete; 32, second layer slope protection concrete; 4, centering thick bamboo tube; 41, bamboo piece; 5, cement mortar or cement paste; 6, bamboo bar net sheet; 61, horizontal bamboo bar net sheet; 62, vertical bamboo bar net sheet; 7, strengthen the bamboo bar; 8, locking bamboo pin; 9, vertically lock the bamboo bar; 11, soil layer boring.
The specific embodiment:
Embodiment: see shown in Fig. 1 to 5, split from the bamboo wood soil nailing, comprise bamboo trunk stake 1, split from bamboo bar soil nailing 2, slope protection concrete 3, insert splitting from bamboo bar soil nailing 2 under oblique among the foundation pit side-wall soil layer A, split from the bottom of bamboo bar 21 at a certain distance fixedly centering thick bamboo tube 4 at least two, split from 211 times perforation of bamboo bar 21 top rings thorns, insert locking bamboo pin 8,8 times vertical lockings of binding of locking bamboo pin bamboo bar 9, cement mortar or cement paste 5 are filled in the soil layer boring 11; Slope protection concrete 3 is divided into two-layer, bamboo bar net sheet 6 and reinforcement bamboo bar 7 place on the first floor slope protection concrete 31, locking bamboo pin 8 and vertical locking bamboo bar 9 are embedded in the second layer slope protection concrete 32, bamboo bar net sheet 6 by horizontal bamboo bar net sheet 61 and vertically bamboo bar net sheet 62 constitute.
Squeezing among the described foundation pit side-wall bottom solum A fixedly has downward bamboo trunk stake 1, and the middle ring of bamboo trunk stake 1 connects and be perfused with concrete.
The tail end of described bamboo trunk stake 1 is fined away.
The described fixedly centering thick bamboo tube 4 of splitting from bamboo bar 21 bottoms at a certain distance, centering thick bamboo tube 4 and splitting from bamboo piece 41 wedgings between bamboo bar 21 sides.
Described splitting from 211 times perforation of bamboo bar 21 top ring thorns inserted locking bamboo pin 8, and locking bamboo pin 8 must be sidelong, and locking bamboo pin 8 usefulness iron wires or thin bamboo strips used for weaving are bound to two vertical locking bamboo bars 9, form " Lv " font tapered end.
Strengthen the 7 parallel placements of bamboo bar, fix by iron wire or thin bamboo strips used for weaving colligation with vertical locking bamboo bar 9 and bamboo bar net sheet 6 for described two.
Split from the job practices of bamboo wood soil nailing:
1), excavation pit, spray first floor slope protection concrete 31 at the side surface of foundation pit side-wall soil layer A;
2), the side surface at foundation pit side-wall soil layer A forms soil layer boring 11, fixedly centering thick bamboo tube 4 will be split more than 2 from the bottom of bamboo bar 21 at a certain distance, centering thick bamboo tube 4 and split between bamboo bar 21 sides with 41 fillings of bamboo piece, the side interspaces up and down, splits from bamboo bar 21 and sends in the soil layer boring 11 and cement injection mortar or cement paste 5 in the soil layer boring 11;
3), split from 211 times boring in advance of bamboo bar 21 top rings thorn, insert locking bamboo pin 8, locking bamboo pin 8 is fixed with 9 colligations of vertical locking bamboo bar;
4), bamboo bar net sheet 6 is laid on the first floor slope protection concrete 31, laterally bamboo bar net sheet 61 should be sidelong, with two reinforcement bamboo bar 7 parallel placing on the bamboo bar net sheet 61,62, strengthen bamboo bar 7 by iron wire or thin bamboo strips used for weaving and bamboo bar net sheet 6 and vertically lock 9 colligations of bamboo bar fixing;
5), the tail end of bamboo trunk stake 1 fines away, and bamboo trunk stake 1 is squeezed into downwards among the foundation pit side-wall bottom solum A, the ring of bamboo trunk stake 1 can connect and inside concrete perfusion;
6), at first floor slope protection concrete 31 jet surface second layer slope protection concretes 32.

Claims (7)

1. split from the bamboo wood soil nailing, comprise bamboo trunk stake (1), split from bamboo bar soil nailing (2), slope protection concrete (3), it is characterized in that: splitting from bamboo bar soil nailing (2) under the middle insertion of foundation pit side-wall soil layer (A) is oblique, split from the bottom of bamboo bar (21) at a certain distance fixedly centering thick bamboo tube (4) at least two, split from bamboo bar (21) top ring thorn (211) perforation down, insert locking bamboo pin (8), locking bamboo pin (8) is the vertical locking of binding bamboo bar (9) down, and cement mortar or cement paste (5) are filled in the soil layer boring (11); Slope protection concrete (3) is divided into two-layer, and bamboo bar net sheet (6) and reinforcement bamboo bar (7) place on the first floor slope protection concrete (31), and locking bamboo pin (8) and vertical locking bamboo bar (9) are embedded in the second layer slope protection concrete (32).
2. according to claim 1 splitting from the bamboo wood soil nailing, it is characterized in that: squeezing in the foundation pit side-wall bottom solum (A) fixedly has downward bamboo trunk stake (1), and the middle ring of bamboo trunk stake (1) connects and also is perfused with concrete.
3. according to claim 2 splitting from the bamboo wood soil nailing is characterized in that: the tail end sharpening of bamboo trunk stake (1).
4. according to claim 1,2 described splitting from the bamboo wood soil nailing, it is characterized in that: split from bamboo bar (21) bottom at a certain distance fixedly centering thick bamboo tube (4), centering thick bamboo tube (4) and splitting from bamboo piece (41) wedging between bamboo bar (21) side.
5. according to claim 1,2 described splitting from the bamboo wood soil nailing, it is characterized in that: split from bamboo bar (21) top ring thorn (211) perforation down, insert locking bamboo pin (8), locking bamboo pin (8) must be sidelong, locking bamboo pin (8) is bound to two vertical locking bamboo bars (9) with iron wire or thin bamboo strips used for weaving, forms " Lv " font tapered end.
6. according to claim 1,2 described splitting from the bamboo wood soil nailing, it is characterized in that: strengthen the parallel placement of bamboo bar (7), fix by iron wire or thin bamboo strips used for weaving colligation with vertical locking bamboo bar (9) and bamboo bar net sheet (6) for two.
7. split from the job practices of bamboo wood soil nailing, it is characterized in that:
1), excavation pit, spray first floor slope protection concrete (31) at the side surface of foundation pit side-wall soil layer (A);
2), the side surface at foundation pit side-wall soil layer (A) forms soil layer boring (11), fixedly centering thick bamboo tube (4) will be split more than 2 from the bottom of bamboo bar (21) at a certain distance, centering thick bamboo tube (4) and split between bamboo bar (21) side with bamboo piece (41) filling, the side interspaces up and down, splits from bamboo bar (21) and sends in the soil layer boring (11) and cement injection mortar or cement paste (5) in the soil layer boring (11);
3), split boring in advance under bamboo bar (21) the top ring thorn (211), insert locking bamboo pin (8), locking bamboo pin (8) is fixed with the colligation of vertical locking bamboo bar (9);
4), bamboo bar net sheet (6) is laid on the first floor slope protection concrete (31), laterally bamboo bar net sheet (61) is sidelong, with two parallel placing on the bamboo bar net sheet (6) of reinforcement bamboo bar (7), strengthen bamboo bar (7) by iron wire or thin bamboo strips used for weaving and bamboo bar net sheet (6) and vertically lock bamboo bar (9) colligation fixing;
5), the tail end of bamboo trunk stake (1) fines away, and bamboo trunk stake (1) is squeezed into downwards in the foundation pit side-wall bottom solum (A), the ring of bamboo trunk stake (1) can connect and inside concrete perfusion;
6), at first floor slope protection concrete (31) jet surface second layer slope protection concrete (32).
CN2011101237311A 2011-05-13 2011-05-13 Split bamboo material soil nail and construction method thereof Active CN102286983B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011101237311A CN102286983B (en) 2011-05-13 2011-05-13 Split bamboo material soil nail and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011101237311A CN102286983B (en) 2011-05-13 2011-05-13 Split bamboo material soil nail and construction method thereof

Publications (2)

Publication Number Publication Date
CN102286983A CN102286983A (en) 2011-12-21
CN102286983B true CN102286983B (en) 2013-08-07

Family

ID=45333713

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011101237311A Active CN102286983B (en) 2011-05-13 2011-05-13 Split bamboo material soil nail and construction method thereof

Country Status (1)

Country Link
CN (1) CN102286983B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104213564A (en) * 2014-09-04 2014-12-17 中建四局第六建筑工程有限公司 Excavation slope supporting structure and construction method thereof
CN108797608B (en) * 2018-06-21 2021-01-01 江苏地基工程有限公司 Assembled bamboo skin foundation pit slope protection and construction method thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201137148Y (en) * 2007-12-25 2008-10-22 杭州南方土木工程咨询有限公司 Double rows bamboo pile composite soil nail defending system
CN201358466Y (en) * 2009-02-25 2009-12-09 福建省建筑科学研究院 Moso bamboo soil nail support wall
KR100956031B1 (en) * 2009-12-03 2010-05-06 주식회사 인우에코텍 Fixing structure for gabion mat
CN202073099U (en) * 2011-05-13 2011-12-14 浙江宝业建设集团有限公司 Split-bamboo soil nail

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201137148Y (en) * 2007-12-25 2008-10-22 杭州南方土木工程咨询有限公司 Double rows bamboo pile composite soil nail defending system
CN201358466Y (en) * 2009-02-25 2009-12-09 福建省建筑科学研究院 Moso bamboo soil nail support wall
KR100956031B1 (en) * 2009-12-03 2010-05-06 주식회사 인우에코텍 Fixing structure for gabion mat
CN202073099U (en) * 2011-05-13 2011-12-14 浙江宝业建设集团有限公司 Split-bamboo soil nail

Also Published As

Publication number Publication date
CN102286983A (en) 2011-12-21

Similar Documents

Publication Publication Date Title
CN101914925B (en) Basement by using optimized composite prefabricated arch wall as external wall
CN102953308B (en) Construction method of bamboo wood reinforcement bidirectional enhanced part-cut and part-fill weak roadbed
CN106869321A (en) The prefabricated regeneration concrete bean column node and its construction method of a kind of reinforcement
CN104234062B (en) A kind of in-situ ionic rare earth soaks the method for ore deposit stope preventing land slide
CN102733827A (en) Tunnel arch exchanging construction method and construction structure in tunnel arch exchanging construction
CN105525627A (en) Two-way anchorage plate retaining wall and construction method thereof
CN205778903U (en) A kind of soft-rock tunnel pucking preventing and treating device
CN111173006B (en) Ecological slope protection method for reinforcing hilly soil by combining permeable retaining wall and sounding type bar planting belt
CN204825928U (en) Excavation supporting
CN104131566B (en) A kind of basement is without the construction method of horizontal support foundation ditch
CN108797578A (en) Crushed stone grouting pile and its construction method with classification enlarged footing
CN102286983B (en) Split bamboo material soil nail and construction method thereof
CN208472592U (en) Close to the steel pipe pile reinforced construction of deep basal pit bridge friction pile
CN203741848U (en) Steel tube plate type retaining structure
CN202073099U (en) Split-bamboo soil nail
CN205576957U (en) Stake end pilework
CN218622201U (en) Hidden reinforced structure system of existing friction pile
CN201605588U (en) Structure for reinforcing and fixing slope surface of prestress anchoring frame beam
CN110889235A (en) Underground pile foundation construction engineering design method
CN207331394U (en) Embedded prefabricated road plate of corner protection assembled
CN102493436A (en) Novel manual tunneling construction method of rectangular anti-slide pile
CN105484270A (en) Reinforcement protection construction method of high steep old rubble retaining wall adjacent to deep foundation pit
CN202673305U (en) Construction structure for use in tunnel arch changing construction
CN206220121U (en) Assembled point anchor barricade
CN202672161U (en) Cement-soil mixing drum sheet-pile united slope structure with soil nails

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant