CN102278140A - Gob-side entry retaining method for solid filling coal mining building gangue wall - Google Patents
Gob-side entry retaining method for solid filling coal mining building gangue wall Download PDFInfo
- Publication number
- CN102278140A CN102278140A CN2011101999298A CN201110199929A CN102278140A CN 102278140 A CN102278140 A CN 102278140A CN 2011101999298 A CN2011101999298 A CN 2011101999298A CN 201110199929 A CN201110199929 A CN 201110199929A CN 102278140 A CN102278140 A CN 102278140A
- Authority
- CN
- China
- Prior art keywords
- entry retaining
- wall
- pack wall
- side entry
- retaining method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
Abstract
The invention relates to a gob-side entry retaining method for a solid filling coal mining building gangue wall. The method comprises the following steps of: building the gangue wall on one side of a filling body in a gob of a filling coal mining surface, and filling coal gangue into a weaving bag or a snakeskin bag and building to form the gangue wall, wherein filling gangue of the filling coal mining surface can be used as the coal gangue directly; and pretightening and timbering the built gangue wall by using a single-layer metal net, a 'W'-shaped steel belt, a ladder beam and a double-ended anchor rod with threads. With the advance of a working surface, the gob-side entry retaining method preserves the complete gangue wall for the mining of the next working surface. The entry retaining method is simple, practical, high in timbering strength and low in cost.
Description
Technical field
The present invention relates to a kind of solid filling coal mining and assemble pack wall gob side entry retaining method, being particularly useful for the filling coal mining work plane does not have the coal column gob side entry retaining.
Background technology
Along with the solid filling coal-mining technique develops gradually, liberated " three times " and pressed coal, improve mine resource recovery ratio, realized the needs of mining area resource and environment harmonic extraction.But the protection pillar about in the filling coal mining between section two stopes stays and establishes width is 20~30m, has caused the loss of a large amount of coal resources, has become the bottleneck that improves the coal resources rate of extraction in the filling coal mining technology.Existing gob-side entry retaining method and relevant patented technology great majority are to adopt the roadside packing technology to carry out on the basis of conventional coal mining activity, the construction technology complexity, need expend more manpower and materials, and this kind mode can to cause inter process to influence each other very serious, inefficiency.
At above problem, a kind of solid filling of the present invention is mined and is assembled pack wall gob side entry retaining method, improved the rate of extraction of coal resources greatly, can increase an escape way for this work plane, can prepare stope drift active workings for next work plane again, can save the tunnelling expense, can alleviate the coal mine excavation imbalance and the nervous situation that continues again, the condition of " Y " type ventilation is provided for high Gassy Coal Face again simultaneously, and on the basis of goaf filling, stay the lane difficulty low, method is simple, and is easy and simple to handle, has important practical significance and wide application prospect.
Summary of the invention
Technical problem: it is simple to the purpose of this invention is to provide a kind of method, and easy construction is safe and reliable, and the solid filling coal mining that has than strong support force assembles pack wall gob side entry retaining method.
Technical scheme: solid filling of the present invention is mined and is assembled pack wall gob side entry retaining method, is to assemble pack wall in filling coal mining face goaf obturation one side, and the width that assembles pack wall is 1.5m~3m, and it is identical with the work plane mining height to assemble the pack wall height; Pack wall is coal mine waste rock is filled and to be assembled and be body of wall with encapsulation bag, and the spoil encapsulation bag of employing is common woven bag or snakeskin bag, and coal mine waste rock directly adopts the filing gangue in mined-out area of even proportioning, and particle diameter is less than 50mm; Adopt single-layer metal net, " W " steel band of model, ladder beam and the supporting of anchor pole pretension then, array pitch is 600mm * 800mm between anchor pole, and " W " steel band of model and ladder beam are right-angled intersection and arrange.
Beneficial effect: the invention solves " three times " and press coal to reach the loss of coal pillar between section two stopes up and down, improved the rate of extraction of coal resources greatly, can increase an escape way for this work plane, can prepare stope drift active workings for next work plane again, can save the tunnelling expense, can alleviate the coal mine excavation imbalance and the pressure that continues again, the condition of " Y " type ventilation is provided for high Gassy Coal Face again simultaneously, and on the basis of goaf filling, stay the lane difficulty low, its method method is simple, practical, the supporting intensity height, cost is low, has practicality widely.
Description of drawings
Fig. 1 is that work plane of the present invention is arranged schematic diagram;
Fig. 2 is the schematic side view that the A-A structure of Fig. 1 assembles the supporting of spoil body of wall;
Fig. 3 is the B-B structure gob side entry retaining schematic diagram of Fig. 1.
Among the figure: 1-goaf filling body, 2-pack wall, 3-encapsulate bag, 4-wire lath, 5-" W " steel band of model, 6-ladder beam, 7-anchor pole.
The specific embodiment
Below in conjunction with accompanying drawing one embodiment of the present of invention are further described:
Figure 1 shows that work plane layout schematic diagram of the present invention, along with work plane is pushed ahead, form the goaf, filling is carried out with spoil in the goaf, form goaf filling body 1, and then goaf filling body 1 one sides assemble pack wall 2, and the width that assembles pack wall 2 is 1.5m~3m, and it is identical with the work plane mining height to assemble pack wall 2 height; Pack wall 2 is coal mine waste rock is filled and to be assembled and be body of wall with encapsulation bag 3, and the spoil encapsulation bag 3 of employing is common woven bag or snakeskin bag, and coal mine waste rock directly adopts the filing gangue in mined-out area of even proportioning, and the spoil particle diameter is less than 50mm; The support pattern of pack wall 2 as shown in Figure 2, adopt single-layer metal net 4, " W " steel band of model 5, ladder beam 6 and anchor pole 7 to carry out the composite reinforcement supporting, array pitch is 600mm * 800mm between anchor pole, wherein " W " steel band of model 5 and ladder beam 6 are " ten " word arranged crosswise, and the final gob side entry retaining lateral view of the present invention that forms as shown in Figure 3.
Claims (7)
1. a solid filling is mined and is assembled pack wall gob side entry retaining method, it is characterized in that assembling pack wall (2) in filling coal mining face goaf obturation (1) one side, and described pack wall is coal mine waste rock is filled and to be assembled and be body of wall with encapsulation bag (3).
2. solid filling according to claim 1 is mined and is assembled pack wall gob side entry retaining method, it is characterized in that the described width that assembles pack wall is 1.5m~3m, and it is identical with the work plane mining height to assemble the pack wall height.
3. solid filling according to claim 1 is mined and is assembled pack wall gob side entry retaining method, it is characterized in that described pack wall both sides employing single-layer metal net (4), " W " steel band of model (5), ladder beam (6) and the threaded anchor pole of double end (7) pretension supporting.
4. array pitch is 600mm * 800mm between anchor pole according to claim 3.
5. " W " steel band of model according to claim 3 and ladder beam are right-angled intersection and arrange.
6. solid filling according to claim 1 is mined and is assembled pack wall gob side entry retaining method, it is characterized in that described spoil encapsulation bag is common woven bag or snakeskin bag.
7. solid filling according to claim 1 is mined and is assembled pack wall gob side entry retaining method, it is characterized in that described coal mine waste rock directly adopts the filing gangue in mined-out area of even proportioning, and particle diameter is less than 50mm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011101999298A CN102278140A (en) | 2011-07-05 | 2011-07-05 | Gob-side entry retaining method for solid filling coal mining building gangue wall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011101999298A CN102278140A (en) | 2011-07-05 | 2011-07-05 | Gob-side entry retaining method for solid filling coal mining building gangue wall |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102278140A true CN102278140A (en) | 2011-12-14 |
Family
ID=45103828
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011101999298A Pending CN102278140A (en) | 2011-07-05 | 2011-07-05 | Gob-side entry retaining method for solid filling coal mining building gangue wall |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102278140A (en) |
Cited By (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102661169A (en) * | 2012-04-28 | 2012-09-12 | 山东科技大学 | Gob-side entry retaining method for anchor bolt network gangue bag wall body for coal mining without pillars |
CN102720498A (en) * | 2012-06-20 | 2012-10-10 | 鄂托克前旗长城煤矿有限责任公司 | Gob-side entry retaining mining process for coal face |
CN102733820A (en) * | 2012-07-05 | 2012-10-17 | 山东新阳能源有限公司 | Gob-side entry retaining support wall and integrated construction method thereof |
CN103147793A (en) * | 2013-02-22 | 2013-06-12 | 山东科技大学 | Non-chain-pillar roadway protection method adopting filling beside thin coal seam roadway |
CN103334769A (en) * | 2013-06-18 | 2013-10-02 | 中国矿业大学 | Cross building block wall supporting method for reinforcing empty roadway of advanced working face |
CN103967519A (en) * | 2014-05-15 | 2014-08-06 | 山东科技大学 | Method for reinforcing gob-side entry retaining through fallen gangue in gob of composite top board inclined seam |
CN104088662A (en) * | 2014-06-25 | 2014-10-08 | 中国矿业大学 | Construction method of gob-side entry retaining wall of solid filling coal mining |
CN104612729A (en) * | 2014-11-27 | 2015-05-13 | 中国矿业大学(北京) | Asymmetric anchor beam structure and supporting method for goaf-side roadway roof |
CN105351004A (en) * | 2015-12-04 | 2016-02-24 | 山东科技大学 | Bagged gangue concrete united roadside supporting method |
CN105422172A (en) * | 2015-12-25 | 2016-03-23 | 山东科技大学 | Waste rock bag roadside support method for anchoring low coal seam with strong roof |
CN105756702A (en) * | 2016-03-18 | 2016-07-13 | 安徽理工大学 | Roadway-side mesh cage filling supporting gob-side entry retaining method |
CN108590655A (en) * | 2018-03-27 | 2018-09-28 | 山东科技大学 | Assemble the method that wall realizes gob side entry retaining |
CN109098752A (en) * | 2018-10-15 | 2018-12-28 | 中国矿业大学 | A kind of trapezoidal ruggedized construction of filling mining roadside support body and method |
CN109209485A (en) * | 2018-11-02 | 2019-01-15 | 中国矿业大学 | A kind of trapezoidal roadside support body of filling mining and method for protecting support |
CN109915138A (en) * | 2019-03-26 | 2019-06-21 | 中国矿业大学(北京) | Spontaneous fire seam cuts top self-contained lane without pillar mining method |
CN109973094A (en) * | 2019-03-05 | 2019-07-05 | 中国矿业大学 | Recovery method is filled by a kind of coplanar full office of adopting of mine resources |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4340254A (en) * | 1979-02-14 | 1982-07-20 | Tatabanyai Szenbanyak | Method of mining heavy coal seams in two or more benches |
CN201363157Y (en) * | 2009-03-17 | 2009-12-16 | 天地科技股份有限公司 | Gauge protecting member combined by steel bar supporting beam and W steel protecting plate |
CN101864987A (en) * | 2010-06-13 | 2010-10-20 | 中国矿业大学 | Building method of filled wall body for gob-side entry retaining of large-inclination coal seam |
CN101949301A (en) * | 2010-08-30 | 2011-01-19 | 山东新矿赵官能源有限责任公司 | Different-strength bearing roadway-beside filling body of gob-side entry under coal mine |
CN201826891U (en) * | 2010-09-17 | 2011-05-11 | 山东新矿赵官能源有限责任公司 | Unequal-strength bearing roadside filling body for no coal pillar mining of thin coal seam |
-
2011
- 2011-07-05 CN CN2011101999298A patent/CN102278140A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4340254A (en) * | 1979-02-14 | 1982-07-20 | Tatabanyai Szenbanyak | Method of mining heavy coal seams in two or more benches |
CN201363157Y (en) * | 2009-03-17 | 2009-12-16 | 天地科技股份有限公司 | Gauge protecting member combined by steel bar supporting beam and W steel protecting plate |
CN101864987A (en) * | 2010-06-13 | 2010-10-20 | 中国矿业大学 | Building method of filled wall body for gob-side entry retaining of large-inclination coal seam |
CN101949301A (en) * | 2010-08-30 | 2011-01-19 | 山东新矿赵官能源有限责任公司 | Different-strength bearing roadway-beside filling body of gob-side entry under coal mine |
CN201826891U (en) * | 2010-09-17 | 2011-05-11 | 山东新矿赵官能源有限责任公司 | Unequal-strength bearing roadside filling body for no coal pillar mining of thin coal seam |
Cited By (24)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102661169B (en) * | 2012-04-28 | 2015-05-06 | 山东科技大学 | Gob-side entry retaining method for anchor bolt network gangue bag wall body for coal mining without pillars |
CN102661169A (en) * | 2012-04-28 | 2012-09-12 | 山东科技大学 | Gob-side entry retaining method for anchor bolt network gangue bag wall body for coal mining without pillars |
CN102720498A (en) * | 2012-06-20 | 2012-10-10 | 鄂托克前旗长城煤矿有限责任公司 | Gob-side entry retaining mining process for coal face |
CN102720498B (en) * | 2012-06-20 | 2015-06-17 | 鄂托克前旗长城煤矿有限责任公司 | Gob-side entry retaining mining process for coal face |
CN102733820A (en) * | 2012-07-05 | 2012-10-17 | 山东新阳能源有限公司 | Gob-side entry retaining support wall and integrated construction method thereof |
CN103147793A (en) * | 2013-02-22 | 2013-06-12 | 山东科技大学 | Non-chain-pillar roadway protection method adopting filling beside thin coal seam roadway |
CN103147793B (en) * | 2013-02-22 | 2016-01-20 | 山东科技大学 | Girdle roadside packing non chain pillar entryprotection method |
CN103334769A (en) * | 2013-06-18 | 2013-10-02 | 中国矿业大学 | Cross building block wall supporting method for reinforcing empty roadway of advanced working face |
CN103967519A (en) * | 2014-05-15 | 2014-08-06 | 山东科技大学 | Method for reinforcing gob-side entry retaining through fallen gangue in gob of composite top board inclined seam |
CN104088662A (en) * | 2014-06-25 | 2014-10-08 | 中国矿业大学 | Construction method of gob-side entry retaining wall of solid filling coal mining |
CN104088662B (en) * | 2014-06-25 | 2016-08-31 | 中国矿业大学 | A kind of construction method of solid filling coal mining gob-side entry retaining support body of wall |
CN104612729A (en) * | 2014-11-27 | 2015-05-13 | 中国矿业大学(北京) | Asymmetric anchor beam structure and supporting method for goaf-side roadway roof |
CN105351004A (en) * | 2015-12-04 | 2016-02-24 | 山东科技大学 | Bagged gangue concrete united roadside supporting method |
CN105422172A (en) * | 2015-12-25 | 2016-03-23 | 山东科技大学 | Waste rock bag roadside support method for anchoring low coal seam with strong roof |
CN105756702A (en) * | 2016-03-18 | 2016-07-13 | 安徽理工大学 | Roadway-side mesh cage filling supporting gob-side entry retaining method |
CN105756702B (en) * | 2016-03-18 | 2018-10-19 | 安徽理工大学 | A kind of lane side cylinder mould filling and support gob-side entry retaining method |
CN108590655A (en) * | 2018-03-27 | 2018-09-28 | 山东科技大学 | Assemble the method that wall realizes gob side entry retaining |
CN108590655B (en) * | 2018-03-27 | 2019-05-31 | 山东科技大学 | Assemble the method that wall realizes gob side entry retaining |
CN109098752A (en) * | 2018-10-15 | 2018-12-28 | 中国矿业大学 | A kind of trapezoidal ruggedized construction of filling mining roadside support body and method |
CN109209485A (en) * | 2018-11-02 | 2019-01-15 | 中国矿业大学 | A kind of trapezoidal roadside support body of filling mining and method for protecting support |
CN109209485B (en) * | 2018-11-02 | 2020-05-08 | 中国矿业大学 | Filling mining trapezoid roadside support body and support method |
CN109973094A (en) * | 2019-03-05 | 2019-07-05 | 中国矿业大学 | Recovery method is filled by a kind of coplanar full office of adopting of mine resources |
CN109973094B (en) * | 2019-03-05 | 2020-01-21 | 中国矿业大学 | Mine resource same-face full-mining local-filling mining method |
CN109915138A (en) * | 2019-03-26 | 2019-06-21 | 中国矿业大学(北京) | Spontaneous fire seam cuts top self-contained lane without pillar mining method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102278140A (en) | Gob-side entry retaining method for solid filling coal mining building gangue wall | |
CN202215249U (en) | Layering pack wall along for hollow entry retaining in solid filling coal mining | |
CN101761338B (en) | Gob-side entry retaining method of a solid filling coal mining half-section one-leg shed | |
CN101514633B (en) | Non-roadside supporting gob-side entry retaining process | |
CN101864956B (en) | Sectional coal pillar-free exploitation method | |
CN102383857A (en) | Gob-side entry retaining process for solid-filling, coal-mining and laying gangue wall | |
CN107905790B (en) | Broadwall N00 engineering method | |
CN103410515B (en) | It is a kind of that three-soft seam is reciprocating combines mining method without coal column | |
CN102661169B (en) | Gob-side entry retaining method for anchor bolt network gangue bag wall body for coal mining without pillars | |
CN103233751B (en) | Double-layer anchoring and balancing arch supporting system for coal roadway with extremely-weak top plates | |
CN107829742B (en) | Caving-filling-open stope-caving mining method | |
CN103557000B (en) | Method for preventing gob-side entry rock burst through side-drawing filling | |
CN102900449B (en) | Support method for underground goaf roof of coal mine | |
CN102587914A (en) | Strip-type Wongawilli mining method of coal buried under building | |
CN104088638B (en) | Large-inclination-angle coal bed longwell large-mining-height working surface coal wall caving and roof fall control technology | |
CN101881167B (en) | Coal face stump mining method | |
EA037966B1 (en) | Fractured roof mining method | |
CN103742171A (en) | Mining roadway coal pillar reinforcing method | |
CN102733836A (en) | Roadway support method for fully mechanized caving mining of weak extra-thick coal seam | |
CN104847406A (en) | Method for fracturing retained filled wall of adjacent coal face | |
CN104863588A (en) | Advanced pier column pre-arranging gob-side entry retaining method | |
CN112610258A (en) | Impact mine stoping roadway advanced support method applied to smart mine | |
CN205172609U (en) | Asymmetric supporting device in tunnel | |
CN104074534A (en) | Gob-side entry retaining method of fully-mechanized mining/full-mechanized caving mining working face | |
CN106285692B (en) | A kind of construction method of gob side entry retaining |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20111214 |