CN102190459A CN 201010122059 CN201010122059A CN102190459A CN 102190459 A CN102190459 A CN 102190459A CN 201010122059 CN201010122059 CN 201010122059 CN 201010122059 A CN201010122059 A CN 201010122059A CN 102190459 A CN102190459 A CN 102190459A
Authority
CN
China
Prior art keywords
cold
emulsified bitumen
repairing material
preparation
building stones
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 201010122059
Other languages
Chinese (zh)
Other versions
CN102190459B (en
Inventor
刘艳
马庆丰
张烨
马志君
张生泉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Petroleum and Natural Gas Co Ltd
Petrochina Fuel Oil Co Ltd
Original Assignee
China Petroleum and Natural Gas Co Ltd
Petrochina Fuel Oil Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Petroleum and Natural Gas Co Ltd, Petrochina Fuel Oil Co Ltd filed Critical China Petroleum and Natural Gas Co Ltd
Priority to CN 201010122059 priority Critical patent/CN102190459B/en
Publication of CN102190459A publication Critical patent/CN102190459A/en
Application granted granted Critical
Publication of CN102190459B publication Critical patent/CN102190459B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention relates to a storable emulsified asphalt cold-patch mixture and a preparation method and application thereof. The storable emulsified asphalt cold-patch mixture consists of the following components in percentage by weight: 7 to 8 percent of emulsified asphalt, 5 to 6 percent of water, 1 to 2 percent of reinforcing agent, 1 to 3 percent of thixotropic agent and the balance of stone, wherein the emulsified asphalt consists of the following components in percentage by weight: 1.0 to 1.5 percent of emulsifying agent, 1 to 3 percent of thickening agent, 26.5 to 36.5 percent of water and the balance of No.70 asphalt. The storable emulsified asphalt cold-patch mixture has the advantages of convenience of manufacture, long storage time, no environmental pollution, convenience of construction, capacity of opening the traffic after construction and the like, and is suitable for repairing pot holes of asphalt pavements.

Description

A kind of emulsified bitumen cold-repairing material and its production and application that stores
Technical field
The present invention relates to a kind of emulsified bitumen cold-repairing material and its production and application that stores, belong to the cold-repairing material of emulsified bitumen class.
Background technology
According to agglutinate kind difference, to mainly contain with the polymkeric substance performed polymer be the compound of main additive and with the compound two big classes of lightweight oil content (mostly being diesel oil greatly) fluxed asphalt as agglutinate to cold repairing asphalt mixture on the present stage market.For example mention a kind of regenerated type road cold-repairing material among the CN 101008172A, adopt express highway pavement to wash to dig material, a small amount of new building stones, cold repairing additive, diesel oil and polymer to activate property-modifying additive and heat according to a certain ratio to mix and stir and form.Asphalt cold repairing additive among the CN 1810885A comprises styrene-butadiene-styrene block copolymer, resin, and solvent, mineral oil, vinylbenzene, diesel oil, pitch is formed.CN 1667045A mentions the solvent composition of a kind of cold-patch liquid by pitch, adhesion resin and solvent pitch and adhesion resin, is equipped with building stones and forms cold-repairing material.
With the polymkeric substance performed polymer be main additive compound and all mostly with fluxed asphalt as the compound of agglutinate be to contain lightweight oil content (mostly being diesel oil greatly), though this cold-repairing material has good construction workability, water stability, and the storage time is also long, but owing to contain more lightweight oil content in the compound, it is very slow to volatilize, and can bring disadvantageous effect to the intensity and the weather resistance of compound.Emulsified bitumen class cold-repairing material can overcome this shortcoming.
Traditional Emulsified Asphalt Mixture is at the scene with emulsified bitumen, and mineral aggregate, powder etc. are mixed and made into Emulsified Asphalt Mixture by a certain percentage, after having constructed, must wait for emulsion breaking after, could open to traffic, and require disposable using.
Summary of the invention
The purpose of this invention is to provide a kind of emulsified bitumen cold-repairing material and its production and application that stores, the existing good construction workability of this cold-repairing material, anti-water damage ability, and also the storage time is longer, gets final product open to traffic behind the compaction moulding.
A kind of emulsified bitumen cold-repairing material that stores of the present invention adopts emulsified bitumen as agglutinate, is made of following component by weight percentage:
Emulsified bitumen 7~10%
Water 5~6%
Toughener 1~2%
Thixotropic agent 1~3%
The building stones surplus;
Described emulsified bitumen is made up of following compositions in weight percentage:
No. 70 pitch surpluses
Emulsifying agent 1.0~1.5%
Thickening material 1~3%
Water 26.5~36.5%
Described emulsifying agent is for splitting the type anionic emulsifier slowly.
Described thickening material can obviously increase the viscosity of emulsified bitumen, guarantees the stability of emulsified bitumen.
Described thickening material is one or more of sodium cellulosate, sodium polyacrylate, polyacrylamide, sodium alginate.
Described toughener is a lignin fibre, trevira, one or more of polyacrylonitrile fibre.
Described thixotropic agent can strengthen the denseness of emulsified bitumen cold-repairing material in storage process, prevent precipitated and separated, can make the emulsified bitumen cold-repairing material have flowability under external force again, guarantees construction workability.
Described thixotropic agent is the emulsion method polyoxyethylene, aerosil, diatomaceous one or more, preferred emulsion method polyoxyethylene and aerosil.
Described building stones are one or more in basalt, limestone, diabase, the grouan etc.
Technical process preparation and use:
1) Production Flow Chart
With toughener, thixotropic agent, building stones mixed and stirred 1~2 minute, added entry, stirred 0.5~1 minute, and building stones are fully wetting, added emulsified bitumen then by prescription, stirred to seal after 1 minute to pack promptly to get the emulsified bitumen cold-repairing material.
2) use
Rubble around reaching in the hole groove to be repaired, waste residue, ponding, dust etc. are cleaned out, evenly sprayed one deck sticking layer oil then.Take out an amount of emulsified bitumen cold-repairing material, pour in the groove of hole, the cold-repairing material outline is above ground level.After laying evenly,, select suitable compactor and method compacting for use, get final product open to traffic according to repairing environment on the spot, repairing the area size and the degree of depth.
The performance test of cold-repairing material of the present invention:
(1) cohesiveness test
Get the part cold-repairing material, make marshal piece according to JTJ 052-2000 " highway asphalt and asphalt experiment rules ", being placed on diameter then is 200 millimeters, and the aperture is to erect on 25 millimeters the sieve to roll 20 times, observes its intact situation.Cold-repairing material of the present invention can reach more than 80% intact.
(2) immersion Marshall stability
Make marshal piece according to JTJ 052-2000 " highway asphalt and asphalt experiment rules ", the demoulding after room temperature is placed 24h then places test specimen 15 ℃ of water temperature insulations 30 minutes again, measures Marshall stability.Immersion stability of the present invention can reach more than the 3KN.
(3) Marshall residual stability
Make marshal piece according to JTJ 052-2000 " highway asphalt and asphalt experiment rules ", the demoulding after room temperature is placed 24h then, after the demoulding test specimen is divided into two groups, one group of test specimen is placed 15 ℃ of water temperature insulations 30 minutes, measure Marshall stability 1; Another group test specimen places 15 ℃ of water temperature insulations 48 hours, measures Marshall stability 2.Residual stability is: stability 2/ stability 1 * 100%.Residual stability of the present invention can reach more than 75%.
The invention has the beneficial effects as follows on the existing achievement of present stage cold-repairing material, overcome the existence of lightweight oil content and caused forming intensity shortcoming slowly.Simultaneously, reduce the waste of material, improved maintenance of surface efficient widely.
Emulsified bitumen cold-repairing material among the present invention is different from traditional Emulsified Asphalt Mixture, but be single component storage type emulsified bitumen cold-repairing material, pass through emulsified bitumen, water, toughener, the accurate measurement control of thixotropic agent, under the state of sealing, can guarantee that Emulsified Asphalt Mixture is in metastable condition in the regular hour scope, destroy this metastable condition by the effect of external force and the volatilization of moisture during use, reach fast emulsion breaking, form the purpose of intensity.
Embodiment
Embodiment 1
The preparation method of the emulsified bitumen cold-repairing material in the present embodiment is as follows.Get 1% trevira, 1% emulsion method polyoxyethylene and surplus building stones mixed in mixing machine 1~2 minute, add 6% water again, stirred 0.5~1 minute, building stones are fully wetting, add 7% part of emulsified bitumen then, stir after 1 minute the sealing pack and promptly get the emulsified bitumen cold-repairing material.Wherein each component composition weight ratio of emulsified bitumen is: No. 70 pitch surpluses, GYM-02 emulsifying agent 1% (Henan Province Wei Sende pavement material company limited), sodium cellulosate 1%, 26.5 parts in water.During use cold-repairing material is taken out, pour in the groove of hole, after the compacting, get final product open to traffic.Performance index see Table 1.
Embodiment 2
The preparation method of the emulsified bitumen cold-repairing material in the present embodiment is as follows.Get 2% lignin fibre, 3% aerosil and surplus building stones mixed in mixing machine 1~2 minute, add 5% water again, stirred 0.5~1 minute, building stones are fully wetting, add 10% emulsified bitumen then, stir after 1 minute the sealing pack and promptly get the emulsified bitumen cold-repairing material.Wherein each component composition weight ratio of emulsified bitumen is: No. 70 pitch surpluses, UCAN-58 emulsifying agent 1.26% (phenolic ether sulphate class, the loyal Fine Chemical Co., Ltd in Shanghai), sodium polyacrylate 1.08%, water 29.16%.During use cold-repairing material is taken out, pour in the groove of hole, after the compacting, get final product open to traffic.Performance index see Table 1.
Embodiment 3
The preparation method of the emulsified bitumen cold-repairing material in the present embodiment is as follows.Get 1% lignin fibre, 2% aerosil and surplus building stones mixed in mixing machine 1~2 minute, add 5.5% water again, stirred 0.5~1 minute, building stones are fully wetting, add 8% part of emulsified bitumen then, stir after 1 minute the sealing pack and promptly get the emulsified bitumen cold-repairing material.Wherein each component composition weight ratio of emulsified bitumen is: No. 70 pitch surpluses, UCAN-58 emulsifying agent 1.5% (phenolic ether sulphate class, the loyal Fine Chemical Co., Ltd in Shanghai), sodium cellulosate 2%, water 30.32%.During use cold-repairing material is taken out, pour in the groove of hole, after the compacting, get final product open to traffic.Performance index see Table 1.
Table 1 emulsified bitumen cold-repairing material performance index
Figure GSA00000057293700061
Emulsified bitumen cold-repairing material cohesiveness test of the present invention can reach more than 80%, and the immersion stability can reach more than the 3KN, and residual stability can reach more than 75%.Compare with traditional cold-repairing material, various aspects of performance can meet and exceed the traditional cold feed supplement.

Claims (4)

1. preparation method that can store the emulsified bitumen cold-repairing material is characterized in that: be grouped into by following one-tenth by weight percentage:
Emulsified bitumen 7~10%
Water 5~6%
Toughener 1~2%
Thixotropic agent 1~3%
The building stones surplus;
Described emulsified bitumen is made up of following composition by weight percentage:
No. 70 pitch surpluses
Emulsifying agent 1.0~1.5%
Thickening material 1~3%
Water 26.5~36.5%;
Described emulsifying agent is for splitting the type anionic emulsifier slowly;
Described thickening material is one or more of sodium cellulosate, sodium polyacrylate, polyacrylamide, sodium alginate;
Described toughener is a lignin fibre, trevira, one or more of polyacrylonitrile fibre;
Described thixotropic agent is the emulsion method polyoxyethylene, aerosil, diatomaceous one or more;
Production Flow Chart:
With toughener, thixotropic agent, building stones mixed and stirred 1~2 minute, added entry, stirred 0.5~1 minute, and building stones are fully wetting, added emulsified bitumen then by prescription, stirred to pack after 1 minute to seal promptly to get the emulsified bitumen cold-repairing material.
2. the preparation method who stores the emulsified bitumen cold-repairing material according to claim 1 is characterized in that: described building stones are one or more in basalt, limestone, diabase, the grouan.
3. one kind can store the emulsified bitumen cold-repairing material, it is characterized in that: the preparation method who stores the emulsified bitumen cold-repairing material according to claim 1 prepares.
4. application that can store the emulsified bitumen cold-repairing material is characterized in that: be used for the asphalt pavement pit cold repair and mend.
CN 201010122059 2010-03-10 2010-03-10 Storable emulsified asphalt cold-patch mixture and preparation method and application thereof Active CN102190459B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201010122059 CN102190459B (en) 2010-03-10 2010-03-10 Storable emulsified asphalt cold-patch mixture and preparation method and application thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201010122059 CN102190459B (en) 2010-03-10 2010-03-10 Storable emulsified asphalt cold-patch mixture and preparation method and application thereof

Publications (2)

Publication Number Publication Date
CN102190459A true CN102190459A (en) 2011-09-21
CN102190459B CN102190459B (en) 2013-07-03

Family

ID=44599435

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201010122059 Active CN102190459B (en) 2010-03-10 2010-03-10 Storable emulsified asphalt cold-patch mixture and preparation method and application thereof

Country Status (1)

Country Link
CN (1) CN102190459B (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102532658A (en) * 2011-12-16 2012-07-04 陈达溪 Asphalt modifier suitable for rainy region and preparation method and application process thereof
CN102826792A (en) * 2012-09-13 2012-12-19 安徽路达泰克沥青新材料有限公司 Preparation method of LB cold patch material
CN103979896A (en) * 2014-05-15 2014-08-13 中国石油大学(华东) Highly anti-rutting emulsified asphalt mixture for treating rutting on asphalt pavement and preparation method of emulsified asphalt mixture
CN106477974A (en) * 2016-09-29 2017-03-08 长安大学 A kind of glass fibre and water-base epoxy emulsified asphalt material for road repair
CN106633952A (en) * 2016-10-19 2017-05-10 天津佰思特新材料科技有限公司 Novel asphalt road pavement cracking repair material and preparation method thereof
CN108467700A (en) * 2018-03-29 2018-08-31 宁夏睿泰天成新材料科技有限公司 A kind of SMC pitches cold-patch agent and preparation method thereof
CN110804317A (en) * 2019-12-06 2020-02-18 长安大学 Storable composite modified emulsified asphalt pavement pit cold patching material and preparation method thereof
CN114230236A (en) * 2021-09-23 2022-03-25 临沂市公路事业发展中心费县中心 Cold repairing agent and application thereof in pavement construction

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4018730A (en) * 1975-06-06 1977-04-19 Mcdonald Charles H Method for emulsifying asphalt-rubber paving material and a stable thixotropic emulsion of said material
CN1396213A (en) * 2002-06-10 2003-02-12 中油销售江苏公司兴能沥青厂 Polymer emulsified and re-cross-linked asphalt colloid mixture and its preparing process
CN1442452A (en) * 2002-09-29 2003-09-17 袁永长 Cold repairing asphalt mixture and its manufacturing method
CN1442449A (en) * 2002-09-29 2003-09-17 袁永长 Cold repairing additive for road and its manufacturing method
US20060130704A1 (en) * 2003-07-14 2006-06-22 Partanen John E Synthetic asphalt recycled tire rubber emulsions and processes for making them
CN100999890A (en) * 2006-12-30 2007-07-18 马银华 Road surface structure of felexiable fibre emulsifying asphalt stable material as base and construction method thereof
CN101008172A (en) * 2006-01-23 2007-08-01 河南省高速公路实业开发公司 Regenerated type road cold-repairing material
CN101475351A (en) * 2009-01-20 2009-07-08 钦兰成 Cold mixing high polymer modified asphalt concrete and preparing method thereof

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4018730A (en) * 1975-06-06 1977-04-19 Mcdonald Charles H Method for emulsifying asphalt-rubber paving material and a stable thixotropic emulsion of said material
CN1396213A (en) * 2002-06-10 2003-02-12 中油销售江苏公司兴能沥青厂 Polymer emulsified and re-cross-linked asphalt colloid mixture and its preparing process
CN1442452A (en) * 2002-09-29 2003-09-17 袁永长 Cold repairing asphalt mixture and its manufacturing method
CN1442449A (en) * 2002-09-29 2003-09-17 袁永长 Cold repairing additive for road and its manufacturing method
US20060130704A1 (en) * 2003-07-14 2006-06-22 Partanen John E Synthetic asphalt recycled tire rubber emulsions and processes for making them
US7547356B2 (en) * 2003-07-14 2009-06-16 John Eric Partanen Synthetic asphalt recycled tire rubber emulsions and processes for making them
CN101008172A (en) * 2006-01-23 2007-08-01 河南省高速公路实业开发公司 Regenerated type road cold-repairing material
CN100999890A (en) * 2006-12-30 2007-07-18 马银华 Road surface structure of felexiable fibre emulsifying asphalt stable material as base and construction method thereof
CN101475351A (en) * 2009-01-20 2009-07-08 钦兰成 Cold mixing high polymer modified asphalt concrete and preparing method thereof

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
《辽宁建材》 20090127 郭浩鹏 等 乳化沥青冷补料在道路养护中的应用 , 第1期 *

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102532658A (en) * 2011-12-16 2012-07-04 陈达溪 Asphalt modifier suitable for rainy region and preparation method and application process thereof
CN102826792A (en) * 2012-09-13 2012-12-19 安徽路达泰克沥青新材料有限公司 Preparation method of LB cold patch material
CN103979896A (en) * 2014-05-15 2014-08-13 中国石油大学(华东) Highly anti-rutting emulsified asphalt mixture for treating rutting on asphalt pavement and preparation method of emulsified asphalt mixture
CN103979896B (en) * 2014-05-15 2016-10-05 中国石油大学(华东) A kind of high Rut resistance Emulsified Asphalt Mixture for asphalt pavement rut punishment and preparation method thereof
CN106477974A (en) * 2016-09-29 2017-03-08 长安大学 A kind of glass fibre and water-base epoxy emulsified asphalt material for road repair
CN106633952A (en) * 2016-10-19 2017-05-10 天津佰思特新材料科技有限公司 Novel asphalt road pavement cracking repair material and preparation method thereof
CN108467700A (en) * 2018-03-29 2018-08-31 宁夏睿泰天成新材料科技有限公司 A kind of SMC pitches cold-patch agent and preparation method thereof
CN110804317A (en) * 2019-12-06 2020-02-18 长安大学 Storable composite modified emulsified asphalt pavement pit cold patching material and preparation method thereof
CN114230236A (en) * 2021-09-23 2022-03-25 临沂市公路事业发展中心费县中心 Cold repairing agent and application thereof in pavement construction

Also Published As

Publication number Publication date
CN102190459B (en) 2013-07-03

Similar Documents

Publication Publication Date Title
CN102190459B (en) Storable emulsified asphalt cold-patch mixture and preparation method and application thereof
CN103866667B (en) Half flexible Supporting Load Pavement paving structure
CN101321814B (en) Water-in-oil bitumen dispersions and methods for producing paving compositions from the same
JP3403415B2 (en) Asphalt emulsion
CN100564684C (en) A kind of resin filling type asphalt concrete steel box-beam bridge deck combined structure paving method
CN101885870B (en) High-viscosity thin-layer bituminous mixture modifier and application thereof
KR100210163B1 (en) A cold-mix, cold-laid asphalt concrete packaging material for using a repair of road and a method for preparing the same
CN103665899B (en) A kind of modifying asphalt base embedding agent and preparation method utilizing waste foam
CN103204644B (en) Warmly bitumen-mixed modifier and preparation method thereof
CN109748528A (en) A kind of regenerated aggregate hardening agent and enhanced processing method
CN106396502A (en) Foamed warm mix recycled asphalt mixture and preparation method thereof
CN104326706B (en) A kind of steel slag asphalt compound and preparation method thereof
CN102492365B (en) Preparation method of liquid rubber asphalt water-proof paint
CN105586819A (en) Asphalt pavement stress reflect crack repairing material and repairing method
CN104371339A (en) Road asphalt plasticity improvement asphalt fat glue and preparation method thereof
CN104496371B (en) A kind of fast dewatering curing agent and its preparation method and application
CN109233309B (en) Environment-friendly modified emulsified asphalt for cold mixing
CN111157461A (en) Test method for measuring mixing and melting degree of new and old asphalt in cold-recycling asphalt mixture
CN106147252B (en) A kind of preparation method of environment-friendly type asphalt mixture additive
CN109133728B (en) A kind of road surface composite seal coat and its preparation method and application
Meng et al. Review of emulsified asphalt modification mechanisms and performance influencing factors
CN105130256B (en) A kind of energy-saving type asphalt concrete modifying agent and preparation method thereof
CN106082792B (en) Composite asphalt cold-patch material and preparation method thereof
CN101735625B (en) Special modified cold-mixing asphalt for cold-region normal-temperature mixing-type asphalt concrete
CN114276049B (en) Environment-friendly asphalt-cement composite material, preparation method and construction process

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant