CN102182286A - 高原干燥气候条件下外墙砖防止空鼓、脱落的施工工艺 - Google Patents

高原干燥气候条件下外墙砖防止空鼓、脱落的施工工艺 Download PDF

Info

Publication number
CN102182286A
CN102182286A CN2011100331157A CN201110033115A CN102182286A CN 102182286 A CN102182286 A CN 102182286A CN 2011100331157 A CN2011100331157 A CN 2011100331157A CN 201110033115 A CN201110033115 A CN 201110033115A CN 102182286 A CN102182286 A CN 102182286A
Authority
CN
China
Prior art keywords
brick
tile
wall
metope
face
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011100331157A
Other languages
English (en)
Inventor
朱治平
曾明江
朱从裕
万里波
李昱东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
YUNNAN JUHE CONSTRUCTION GROUP CO Ltd
Original Assignee
YUNNAN JUHE CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by YUNNAN JUHE CONSTRUCTION GROUP CO Ltd filed Critical YUNNAN JUHE CONSTRUCTION GROUP CO Ltd
Priority to CN2011100331157A priority Critical patent/CN102182286A/zh
Publication of CN102182286A publication Critical patent/CN102182286A/zh
Pending legal-status Critical Current

Links

Abstract

一种高原干燥气候条件下外墙砖防止空鼓、脱落的施工工艺,施工流程为:基层处理→吊垂直、套方、找规矩→贴灰饼→抹底层砂浆→弹线分格→排砖→浸砖→镶贴面砖→面砖勾缝与擦缝,其中通过对施工的温度、湿度、光照、养护等条件的控制,起到了避免墙砖空鼓、脱落的作用,适用于高原干燥气候下各种外墙砖、文化石的粘贴施工。

Description

高原干燥气候条件下外墙砖防止空鼓、脱落的施工工艺
技术领域
本发明是一种适合高原干燥气候条件下的外墙砖防止空鼓、脱落的粘贴施工工艺。
背景技术
外墙粘贴饰面砖是一种较为耐久,可长期保持色彩的中档饰面材料,具有成本适中,色彩丰富等优点,如处理得当可达到花岗岩的饰面效果,且可减轻建筑物的自重,降低造价。但根据近些年来的工程实践,高原干燥气候地区外墙镶贴饰面砖较普遍存在令人忧虑的质量问题。大多数工程少则一至二年,多则四至五年饰面砖就产生裂纹、脱皮、甚至成片的脱落,使崭新的建筑物斑痕累累。不但达不到预期的艺术效果,相反影响了使用功能,并且维修很困难,造成很大的损失。
发明内容
本发明提出一种高原干燥气候下外墙砖防止空鼓、脱落的施工工艺,它能克服上述存在的问题。本发明通过以下技术方案实现:
一种高原干燥气候下外墙砖防止空鼓、脱落的施工工艺,步骤如下:
(1)、 墙面基层处理
墙面平整达到外墙中级抹灰验收规范:
1)首先将表面尘土清扫干净,用10%火碱水溶液将表面的油污刷掉,随之用净水将碱液冲净,晾干;然后在1:1水泥细砂浆内掺20%的801胶水溶液,将砂浆喷或甩到墙表面上,终凝后浇水养护,直至水泥砂浆疙瘩全部在混凝土光面上达到用手掰不动的强度为止;
2)梁、柱与墙交接处的墙面粉刷前接缝处先钉200mm宽钢丝网,用水泥钢钉固定,间距300mm;
(2)、按常规方式吊垂直、套方、找规矩和贴灰饼;
(3)、采用1:3水泥砂浆进行抹底层砂浆施工,第一层厚度为5mm,抹后划出任意浅痕;待第一层六至七成干时,抹第二层,厚度8~12mm,刮平、搓毛,终凝后浇水养护3-4天;
(4)、待上一步骤的墙面基层灰六至七成干时按图纸要求进行分段弹线分格,同时进行墙表面贴标准点的工作,以控制墙面面层出墙尺寸及垂直、平整;
(5)、根据大样图及墙面尺寸进行横竖排砖,以保证面砖缝隙均匀,符合设计图纸要求;
(6)、釉面砖和外墙面砖镶贴前,先将面砖清扫干净放入净水中浸泡至少2h,取出待表面晾干或擦干净后使用;
(7)、在每一分段或分块内镶贴面砖,均为自下向上镶贴,从最下一层砖下皮的位置线先稳好靠尺,以此托住第一层面砖,在面砖外皮上口拉水平通线,作为镶贴的标准;
(8)、面砖勾缝与擦缝:缝宽一般控制在5~6mm以内,用益胶泥勾缝,先勾水平缝再勾竖缝,勾好后要求凹进面砖外表面1mm,勾缝材料为益胶泥,贴砖前勾缝内要先刮满益胶泥再刮粘贴砂浆,面砖缝子勾完后用布或棉丝蘸稀盐酸擦洗干净;
(9)、使用稀释后草酸进行墙面清洗,清洗之前墙面应大面积先浇水湿润,严禁干砖直接清洗;
(10)、养护:用稻草席子或者塑料薄膜铺贴于粘贴好的外墙砖遮挡阳光,定时浇水保持湿润,向阳面要求保湿养护5-7天,背阴面保湿3-4天。
上述排砖步骤时,非整砖行应排在窗间墙或阴角处等次要部位,要注意一致和对称,遇有突出的卡件,用整砖套割吻合,不得用非整砖拼凑镶贴。
上述镶贴面砖步骤时,女儿墙压顶、窗台、柱角等阳角部位,应采取切30度角后进行碰角粘贴。
本发明提出的施工工艺,操作简便,通过对施工的温度、湿度、光照、养护等条件的控制,起到了避免墙砖空鼓、脱落的作用,适用于高原干燥气候下各种外墙砖、文化石的粘贴施工,可以有效控制粘贴质量,避免了空鼓、脱落、返碱等质量问题。
具体实施方式
一、施工条件
1、施工环境、基面及施用的质料的温度不应低于 5℃。
2、不能在大风环境中或者太阳光直射的墙面上施工,以避免材料在施工过程中失水过快而出现毛细裂痕。
3、不能使用尚未达到硬度的材料,不能在恶劣气候条件下施工,尤其不能受到雨水冲刷。
二、粘贴底层的基本要求
1、墙体的湿润程度不得高于其周围环境的平均湿润程度;
2、墙面应具备足够的强度,粉刷层应具备≥0.3N/mm2的足够抗拔力,不能有开裂、空鼓;
3、墙面应平整,平整度≤0.3cm/2.0m;
4、自来水管、煤气管、空调进出口及各类进户管线等所有进出外墙面的管线均需预埋PVC套管,PVC套管伸出墙面的长度至少30mm;
5、所有固定在外墙上的受力构件,如托架等必需在外墙施工前安装完成,不能等到外墙施工完成后再在墙面上开洞,不然质量及外观成效都难于保证;
6、外墙脚手架钢管距离墙面至少应在15cm以上。
三、施工工艺
施工流程为:墙面基层处理→吊垂直、套方、找规矩→贴灰饼→抹底层砂浆→弹线分格→排砖→浸砖→镶贴面砖→面砖勾缝与擦缝。
1、墙面基层处理
墙面平整度要求到达外墙中级抹灰验收规范;
1)首先将凸出墙面的混凝土剔平,如果基层混凝土表面很光滑可采取如下的“毛化处理”办法:
先将表面尘土清扫干净,用10%火碱水溶液将板面的油污刷掉,随之用净水将碱液冲净,晾干;然后在1:1水泥细砂浆内掺20%的801胶水溶液,喷或用扫帚将砂浆甩到墙上,其甩点要均匀,终凝后浇水养护,直至水泥砂浆疙瘩全部到混凝土光面上,并有较高的强度(用手掰不动)为止。
2)梁、柱与墙交接处处理:墙面粉刷前接缝处先钉200mm宽钢丝网,用水泥钢钉固定,间距300mm。
2、吊垂直、套方、找规矩、贴灰饼。
3、采用质量份比例1:3的水泥砂浆进行抹底层砂浆,第一层厚度宜为5mm,抹后用扫帚扫毛或用灰刀划出任意浅痕;待第一层六至七成干时,即可抹第二层,厚度约8~12mm,随即用木杠刮平、木抹搓毛,终凝后浇水养护3-4天。
4、弹线分格:待墙面基层灰六至七成干时即可按图纸要求进行分段分格弹线,同时进行面层贴标准点的工作,以控制面层出墙尺寸及墙面垂直、平整。
5、排砖:根据大样图及墙面尺寸进行横竖排砖,以保证面砖缝隙均匀,符合设计图纸要求。非整砖行应排在次要部位如窗间墙或阴角处等,但亦要注意一致和对称。如遇有突出的卡件,应用整砖套割吻合,不得用非整砖拼凑镶贴。
6、浸砖:釉面砖和外墙面砖镶贴前,首先要将面砖清扫干净放入净水中浸泡2h以上,取出待表面晾干或擦干净后方可使用。
7、镶贴面砖:在每一分段或分块内的面砖,均为自下向上镶贴。从最下一层砖下皮的位置线先稳好靠尺,以此托住第一皮面砖。在面砖外皮上口拉水平通线,作为镶贴的标准。
女儿墙压顶、窗台、柱角等阳角部位,应采取切30度角后进行碰角粘贴。
8、面砖勾缝与擦缝:缝宽一般控制在5~6mm以内,用益胶泥勾缝,先勾水平缝再勾竖缝,勾好后要求凹进面砖外表面1mm。该项工作与粘贴一起完成,勾缝材料为益胶泥,因此贴砖前缝内要先刮满益胶泥再刮粘贴砂浆。面砖缝子勾完后用布或棉丝蘸稀盐酸擦洗干净。
9、墙面清洗:清洗之前墙面应大面积先浇水湿润,严禁干砖直接清洗。草酸要经过稀释后使用,不得太浓造成勾缝脱皮、起粉,失去强度,或者勾缝发白。
10、养护
养护是避免空鼓、脱落的关键,要求如下:
1)、用稻草席子、或者塑料薄膜铺贴于粘贴好的外墙砖外,遮挡阳光,定时浇水保持湿润。如果是向阳面,每天浇水一次;背阴面可以视干燥情况而定;
2)、雨季可以适当减少浇水次数;
3)、席子或者塑料薄膜应基本同外墙砖贴合;
4)、可以采用其他保湿效果好的材料代替席子;
5)、向阳面要求保湿养护5-7天;背阴面保湿3-4天;雨季可以适当减少天数。

Claims (3)

1.一种高原干燥气候条件下外墙砖防止空鼓、脱落的施工工艺,其特征在于步骤如下:
一、 墙面基层处理
  1)首先将表面尘土清扫干净,用10%火碱水溶液将表面的油污刷掉,随之用净水将碱液冲净,晾干;然后在质量比1:1的水泥砂浆内掺20%的801胶水溶液,将砂浆喷或甩到墙表面上,终凝后浇水养护,直至砂浆疙瘩在混凝土光面上达到用手掰不动的强度为止; 
2)梁、柱与墙交接处的墙面粉刷前接缝处先钉200mm宽钢丝网,用水泥钢钉固定,间距300mm;
二、按常规方式吊垂直、套方、找规矩和贴灰饼;
三、采用质量比1:3配成的水泥砂浆进行抹底层砂浆施工,第一层厚度为5mm,抹后划出任意浅痕;待第一层六至七成干时,抹第二层,厚度8~12mm,刮平、搓毛,终凝后浇水养护3-4天; 
四、待上一步骤的墙面基层灰六至七成干时按图纸要求进行分段弹线分格,同时进行墙表面贴标准点的工作,以控制墙面面层出墙尺寸及垂直、平整; 
五、根据大样图及墙面尺寸进行横竖排砖,以保证面砖缝隙均匀,符合设计图纸要求; 
六、釉面砖和外墙面砖镶贴前,先将面砖清扫干净放入净水中浸泡至少2h,取出待表面晾干或擦干净后使用;
七、在每一分段或分块内镶贴面砖,均为自下向上镶贴,从最下一层砖下皮的位置线先稳好靠尺,以此托住第一层面砖,在面砖外皮上口拉水平通线,作为镶贴的标准; 
八、面砖勾缝与擦缝:缝宽一般控制在5~6mm以内,用益胶泥勾缝,先勾水平缝再勾竖缝,勾好后要求凹进面砖外表面1mm,勾缝材料为益胶泥,贴砖前勾缝内要先刮满益胶泥再刮粘贴砂浆,面砖缝子勾完后用布或棉丝蘸稀盐酸擦洗干净;
九、使用稀释后草酸进行墙面清洗,清洗之前墙面应大面积先浇水湿润,严禁干砖直接清洗; 
十、养护:用稻草席子或者塑料薄膜铺贴于粘贴好的外墙砖遮挡阳光,定时浇水保持湿润,向阳面要求保湿养护5-7天,背阴面保湿3-4天。
2.根据权利要求1所述的高原干燥气候下外墙砖防止空鼓、脱落的施工工艺,其特征在于:上述排砖步骤时,非整砖行应排在窗间墙或阴角处等次要部位,要注意一致和对称,遇有突出的卡件,用整砖套割吻合,不得用非整砖拼凑镶贴。
3.根据权利要求1所述的高原干燥气候下外墙砖防止空鼓、脱落的施工工艺,其特征在于:上述镶贴面砖步骤时,女儿墙压顶、窗台和柱角等阳角部位,应采取切30度角后进行碰角粘贴。
CN2011100331157A 2011-01-31 2011-01-31 高原干燥气候条件下外墙砖防止空鼓、脱落的施工工艺 Pending CN102182286A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011100331157A CN102182286A (zh) 2011-01-31 2011-01-31 高原干燥气候条件下外墙砖防止空鼓、脱落的施工工艺

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011100331157A CN102182286A (zh) 2011-01-31 2011-01-31 高原干燥气候条件下外墙砖防止空鼓、脱落的施工工艺

Publications (1)

Publication Number Publication Date
CN102182286A true CN102182286A (zh) 2011-09-14

Family

ID=44568563

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011100331157A Pending CN102182286A (zh) 2011-01-31 2011-01-31 高原干燥气候条件下外墙砖防止空鼓、脱落的施工工艺

Country Status (1)

Country Link
CN (1) CN102182286A (zh)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103758312A (zh) * 2011-12-31 2014-04-30 常熟古建园林建设集团有限公司 面砖贴面施工方法
CN104405102A (zh) * 2014-11-25 2015-03-11 浙江深美装饰工程有限公司 抛光砖防空鼓施工工艺
CN106760291A (zh) * 2017-03-08 2017-05-31 江苏嘉洋华联建筑装饰股份有限公司 地砖粘贴于墙面的方法
CN107461034A (zh) * 2017-07-21 2017-12-12 马明才 一种老栏杆内墙面重粉方法
CN108265946A (zh) * 2017-12-15 2018-07-10 夹江县盛世东方陶瓷有限公司 一种陶瓷书画砖贴砖方法
CN110541534A (zh) * 2019-09-07 2019-12-06 深圳洲际建筑装饰集团有限公司 一种防脱落饰面砖及其施工工艺
CN112282267A (zh) * 2020-06-19 2021-01-29 青岛中建联合集团有限公司 一种建筑外墙饰面材料
CN113323314A (zh) * 2021-06-10 2021-08-31 中国建筑第八工程局有限公司 一种冻融环境下烧结陶瓷砖外墙铺贴施工方法
CN113530124A (zh) * 2021-07-27 2021-10-22 中建一局华江建设有限公司 一种墙面火山石内防外阻水湿贴施工方法
CN113653208A (zh) * 2021-06-28 2021-11-16 上海天能保温防水工程有限公司 一种墙体保温结构及施工方法

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1436908A (zh) * 2003-01-26 2003-08-20 卢桂才 防治外墙饰面砖渗漏和脱落的补强方法
CN1786363A (zh) * 2005-12-12 2006-06-14 张建荣 外墙外保温系统粘贴面砖、石材的施工方法
CN101008192A (zh) * 2006-01-24 2007-08-01 宁波荣山新型材料有限公司 一种采用复合型保温面砖的外墙外保温系统施工方法

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1436908A (zh) * 2003-01-26 2003-08-20 卢桂才 防治外墙饰面砖渗漏和脱落的补强方法
CN1786363A (zh) * 2005-12-12 2006-06-14 张建荣 外墙外保温系统粘贴面砖、石材的施工方法
CN101008192A (zh) * 2006-01-24 2007-08-01 宁波荣山新型材料有限公司 一种采用复合型保温面砖的外墙外保温系统施工方法

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
张晔: "谈寒冷地区外墙饰面砖的施工质量", 《中小企业管理与科技》 *
邓建华: "高分子益胶泥在外墙防水工程的应用", 《施工技术》 *
邓高飞: "外墙面砖镶贴施工技术分析", 《中国高新技术企业》 *
隋德福,等: "浅析建筑房屋外墙饰面砖的施工技巧", 《民营科技》 *

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103758312A (zh) * 2011-12-31 2014-04-30 常熟古建园林建设集团有限公司 面砖贴面施工方法
CN104405102A (zh) * 2014-11-25 2015-03-11 浙江深美装饰工程有限公司 抛光砖防空鼓施工工艺
CN106760291A (zh) * 2017-03-08 2017-05-31 江苏嘉洋华联建筑装饰股份有限公司 地砖粘贴于墙面的方法
CN107461034A (zh) * 2017-07-21 2017-12-12 马明才 一种老栏杆内墙面重粉方法
CN108265946A (zh) * 2017-12-15 2018-07-10 夹江县盛世东方陶瓷有限公司 一种陶瓷书画砖贴砖方法
CN110541534A (zh) * 2019-09-07 2019-12-06 深圳洲际建筑装饰集团有限公司 一种防脱落饰面砖及其施工工艺
CN112282267A (zh) * 2020-06-19 2021-01-29 青岛中建联合集团有限公司 一种建筑外墙饰面材料
CN113323314A (zh) * 2021-06-10 2021-08-31 中国建筑第八工程局有限公司 一种冻融环境下烧结陶瓷砖外墙铺贴施工方法
CN113653208A (zh) * 2021-06-28 2021-11-16 上海天能保温防水工程有限公司 一种墙体保温结构及施工方法
CN113530124A (zh) * 2021-07-27 2021-10-22 中建一局华江建设有限公司 一种墙面火山石内防外阻水湿贴施工方法
CN113530124B (zh) * 2021-07-27 2023-02-21 中建一局华江建设有限公司 一种墙面火山石内防外阻水湿贴施工方法

Similar Documents

Publication Publication Date Title
CN102182286A (zh) 高原干燥气候条件下外墙砖防止空鼓、脱落的施工工艺
CN103470067B (zh) 一种用于既有建筑外墙的清水混凝土饰面改造施工方法
CN101565997A (zh) 大面积不规则地面砖施工方法
CN106284929B (zh) 一种墙面瓷砖防空鼓镶贴施工方法
CN204826464U (zh) 女儿墙的防水结构
CN103952052A (zh) 仿洞石弹性质感涂料及其制备方法
CN112681643A (zh) 外墙面水洗石施工工法
CN106284998A (zh) 内墙抹灰满铺玻璃纤维网格布施工方法
CN101713250A (zh) 一种地面砖粘贴施工工艺
CN104405102A (zh) 抛光砖防空鼓施工工艺
CN104120860A (zh) 一种水泥砂浆地面找平的施工方法
CN104120848A (zh) 一种内墙贴面砖施工方法
CN106049780A (zh) 一种高精砌体的免抹灰施工工艺
CN107829536A (zh) 石材铺贴泛碱防治方法
CN207194343U (zh) 蒸压加气混凝土砌块外墙的饰面砖铺贴结构
CN104712114A (zh) 一种外墙泥塑施工方法及其使用的灰浆
CN107119807B (zh) 一种清水混凝土表面保护的施工方法
CN105625650A (zh) 一种屋面女儿墙泛水保护层施工方法
CN205777261U (zh) 一种柔性基层半胶壁纸粘贴工艺结构
CN102094494A (zh) 在坡度大于60度的屋面上铺设s形瓦的施工工艺
CN103184784A (zh) 屋面油毡瓦铺装方法
CN102383562A (zh) 文化石外墙镶贴工艺及防渗漏处理方法
CN103758312A (zh) 面砖贴面施工方法
CN205907857U (zh) 一种双面硬装隔墙结构
CN106193462A (zh) 仿古屋面劈开砖施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20110914