CN102166980B CN201110076107A CN201110076107A CN102166980B CN 102166980 B CN102166980 B CN 102166980B CN 201110076107 A CN201110076107 A CN 201110076107A CN 201110076107 A CN201110076107 A CN 201110076107A CN 102166980 B CN102166980 B CN 102166980B
Authority
CN
China
Prior art keywords
vehicle frame
column
feng
place
oil cylinder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201110076107A
Other languages
Chinese (zh)
Other versions
CN102166980A (en
Inventor
任卫国
戴锦明
韦文鑫
马飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jingjiang Jinqiao Pump Industry Co., Ltd
Original Assignee
AVIC HONGBO WINDPOWER EQUIPMENT Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by AVIC HONGBO WINDPOWER EQUIPMENT Co Ltd filed Critical AVIC HONGBO WINDPOWER EQUIPMENT Co Ltd
Priority to CN201110076107A priority Critical patent/CN102166980B/en
Publication of CN102166980A publication Critical patent/CN102166980A/en
Application granted granted Critical
Publication of CN102166980B publication Critical patent/CN102166980B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Jib Cranes (AREA)
  • Body Structure For Vehicles (AREA)

Abstract

The invention discloses a platform vehicle special for transfer in a wind tower field. The platform vehicle comprises a frame, wherein the lower surface of the frame is provided with two travelling systems which are arranged left and right; a power device is arranged between the two travelling systems and connected on the lower surface of the frame; the lower surface of the frame is connected with two upright column groups which are positioned on the outer sides of the two travelling systems respectively; each upright column group comprises two upright columns which are arranged front and back; two rocker seats which are arranged front and back are arranged between the two upright columns in each upright column group, and are connected on the lower surface of the frame; movable roller support mechanisms are arranged between the front upright column and the front rocker seat as well as between the back upright column and the back rocker seat in each upright column group; and a cab is arranged on the lower surface of an optional end of the frame. The platform vehicle special for the transfer in the wind tower field has the advantages that: the cost is saved, the working efficiency is improved, and the resource consumption is reduced.

Description

Feng Ta transports in the place special-purpose flat truck
Technical field
The present invention relates to a kind of Feng Ta place and transport special-purpose flat truck.
Background technology
The carrying storage of tube tower is generally lifted outside manufacturing line by the gauntry crane of 50t, 80t or 100t, and horizontal transport vehicle is transported to the designated area, again by gauntry crane or need please be external the vapour company of hanging provide wheel crane to unload to deposit; As use gauntry crane to unload and deposit; There are shortcomings such as cost of investment is high, operation energy consumption is high, the place limitation is big, and gauntry crane operation need laying conduct track, investment is big; Per hour about power consumption 200 degree of gauntry crane operation, power consumption is high; Transhipment in the scope is advanced by the tower section garage of only being expert at, and the place limitation is bigger, and when gauntry crane has the entrucking task gauntry crane the target area in, and the transhipment of tower section need stagnation, directly influences production efficiency; Use wheel crane to unload then to have with high costs and operate shortcoming slowly, wheel crane is unloaded needs the operations simultaneously at tower tube two of two wheel cranes, and the equipment investment volume is higher, and the field will be stayed by the wheel crane operating area on the ground during operation; Reduced the stockyard degree of utilization, the operation overlay area is less, after the several wind Tata of the every operation of the wheel crane section; Will stop operation, pack up arm, the shift position; Reorientate, do operating reserves again, operating efficiency is low; Therefore no matter adopting gauntry crane still is that wheel crane is unloaded, all need be equipped with pluck, the hanging hook personnel, have certain personal security hidden danger during operation.
Summary of the invention
The objective of the invention is provides a kind of saving cost in order to overcome above deficiency, increases work efficiency, and reduces the Feng Ta place of resource consumption and transports special-purpose flat truck.
The object of the invention is realized through following technical scheme: a kind of Feng Ta transports special-purpose flat truck in the place; Comprise vehicle frame, the lower surface of vehicle frame is provided with the running gear of placing about two, is provided with engine installation between two running gears; Engine installation is connected the lower surface of vehicle frame; The lower surface of vehicle frame is connected with two column groups, and two column groups are positioned at the outside of two running gears respectively, the column of placing before and after each column group includes two; Be equipped with the rocker arm bracket of placing before and after two between two columns in each column group; rocker arm bracket all is connected the vehicle frame lower surface, between the column of front portion and the anterior rocker arm bracket, between the rocker arm bracket at the column at rear portion and rear portion, all be connected with the action roller supporting mechanism, the lower surface of the arbitrary end of vehicle frame is provided with operator's compartment in each column group.
Further improvement of the present invention is: the hanging beam of placing before and after each said running gear includes two; One end upper surface of each hanging beam all is connected with the vehicle frame lower surface; The other end of each hanging beam all is connected with driven axle assembly; Each driven axle assembly all is connected with road wheel, and two road wheels in one of them running gear all are connected with Pneumatic brake systems.
Further improvement of the present invention is: the road wheel in each said running gear all is connected with swing bearing, and each swing bearing all is connected with an end of steering hardware.
Further improvement of the present invention is: said engine installation comprises fuel tank and hydraulic reservoir, and the other end of each steering hardware all is connected with engine installation.
Further improvement of the present invention is: each said action roller supporting mechanism includes oil cylinder seat; Oil cylinder seat is fixed on the inboard of column; Oil cylinder seat is connected with oil cylinder and is connected, and oil cylinder is connected with the middle part of rocking arm, and an end of rocking arm is connected with rocker arm bracket; the other end of rocking arm is connected with the support wheel assembly, the groove that said support wheel assembly places vehicle frame to be provided with.
Further improvement of the present invention is: be provided with program control center in the said operator's compartment.
The present invention compared with prior art has the following advantages: cancelled the place restriction that driving and track factor cause through using flat truck, when having practiced thrift track, driving, wheel crane expense, practiced thrift consumption of electric; Practice thrift cost; Used flat truck handle tower section 0.5 hour consuming time approximately, be merely use wheel crane etc. consuming time 1/3rd, make tower section transport speed be greatly improved; Effectively improving production work efficient; When reducing resource consumption, shorten the haul-cycle time again, reduce traffic cost; Thereby the economic benefit of making and energy-saving effect obviously improve, this flat truck can be widely used in the inter process transportation of shipbuilding steel structural hull sections and transfer or steel mill, large-scale steel structure make in especially big, extra heavy workpiece transport field.
Description of drawings:
Fig. 1 is a structural representation of the present invention;
Fig. 2 is the birds-eye view of Fig. 1;
Fig. 3 is the structural representation of action roller supporting mechanism;
Label among the figure: 1-vehicle frame, 2-running gear, 3-engine installation, 4-column, 5-support wheel assembly, 6-rocker arm bracket, 7-operator's compartment, 8-hanging beam, the driven axle assembly of 9-, 10-road wheel, 11-Pneumatic brake systems, 12-swing bearing, 13-steering hardware, 14-oil cylinder seat, 15-oil cylinder, 16-rocking arm.
The specific embodiment:
In order to deepen to understanding of the present invention, will combine embodiment and accompanying drawing that the present invention is made further detailed description below, this embodiment only is used to explain the present invention, does not constitute the qualification to protection domain of the present invention.
Show the specific embodiment that special-purpose flat truck is transported in a kind of Feng Ta of the present invention place like Fig. 1, Fig. 2 and Fig. 3, comprise vehicle frame 1, be provided with the running gear 2 of placement about two at the lower surface of vehicle frame 1; Be provided with engine installation 3 between two running gears 2, engine installation 3 is connected the lower surface of vehicle frame 1, and the lower surface of vehicle frame 1 is connected with two column groups; Two column groups are positioned at the outside of two running gears 2 respectively, and each column group includes the column of placing before and after two 4, the rocker arm bracket of placing before and after being equipped with two between two columns 4 in each column group 6; rocker arm bracket 6 all is connected vehicle frame 1 lower surface; between the column 4 of front portion and the anterior rocker arm bracket 6, between the rocker arm bracket 6 at the column 4 at rear portion and rear portion, all be connected with the action roller supporting mechanism, the lower surface of vehicle frame 1 arbitrary end is provided with operator's compartment 7, the hanging beam of placing before and after each running gear 2 includes two 8; an end upper surface of each hanging beam 8 all is connected with vehicle frame 1 lower surface; the other end of each hanging beam 8 all is connected with driven axle assembly 9, and each driven axle assembly 9 all is connected with road wheel 10, and two road wheels 10 in one of them running gear all are connected with Pneumatic brake systems 11; road wheel 10 in each said running gear 2 all is connected with swing bearing 12; each swing bearing 12 all is connected with an end of steering hardware 13, and engine installation 3 comprises fuel tank and hydraulic reservoir, and the other end of each steering hardware 13 all is connected with engine installation 3; each action roller supporting mechanism includes oil cylinder seat 14; oil cylinder seat 14 is fixed on the inboard of column 4, and oil cylinder seat 14 is connected with oil cylinder 15 and is connected, and oil cylinder 15 is connected with the middle part of rocking arm 16; end of rocking arm 16 is connected with rocker arm bracket 6; other end of rocking arm 18 is connected with support wheel assembly 5, and the groove that support wheel assembly 5 places vehicle frame 1 to be provided with is provided with program control center in the operator's compartment 7 in each column group.
Flat truck in use, through steering hardware 13 can realize keeping straight on, the Eight characters turns to, the oblique angle diagonal, walk crosswise and multiple operation such as original position revolution, makes the car load operation comparatively steadily, flexibly; Can realize that in less occasion zero slip or slippage go, can realize many flat trucks through being flexible coupling and car like the tower tube than length, and the spacing scope be 4~9m; Chaufeur can be outside operator's compartment 7 or car remote driving, no electric quantity consumption has improved transportation function; Send instruction through master controller, oil cylinder 15 promotes rocking arm 16, thereby makes support wheel assembly 5 stretch out the outside of vehicle frame 1; Through crane the tower tube is sling, moved to flat truck top or the traversing entering tower of flat truck tube below, in tower tube dropping process; Because the longitudinal centerline of vehicle and tower tube is difficult to be consistent, then the tower tube needs to contact with the cylinder of the big first side of tower tube earlier, produced horizontal in pass to the gross vehicle controller; Send instruction by master controller according to signal lateral direction of car is moved, until blackout, the tower tube continues to descend; The cylinder of this side of tower tube contacts once more, and the transverse force that is produced passes to the gross vehicle controller again, through the master controller move instruction lateral direction of car is moved like this; Drop on the action roller supporting mechanism until the tower tube, cancelled the place restriction that driving and track factor cause through using flat truck, when having practiced thrift track, driving, wheel crane expense; Practice thrift consumption of electric, practiced thrift cost, used flat truck handle tower section 0.5 hour consuming time approximately; Be merely use wheel crane etc. consuming time 1/3rd, make tower section transport speed be greatly improved, effectively improving production work efficient; When reducing resource consumption, shorten the haul-cycle time again, reduce traffic cost; Thereby the economic benefit of making and energy-saving effect obviously improve, this flat truck can be widely used in the inter process transportation of shipbuilding steel structural hull sections and transfer or steel mill, large-scale steel structure make in especially big, extra heavy workpiece transport field.

Claims (6)

1. special-purpose flat truck is transported in a Feng Ta place; Comprise vehicle frame (1); It is characterized in that: the lower surface of said vehicle frame (1) is provided with the running gear (2) of placing about two; Be provided with engine installation (3) between two said running gears (2); Said engine installation (3) is connected the lower surface of said vehicle frame (1); The lower surface of said vehicle frame (1) is connected with two column groups, and two said column groups are positioned at the outside of two said running gears (2) respectively, the column of placing before and after each said column group includes two (4); The rocker arm bracket of placing before and after being equipped with two between two said columns (4) in each said column group (6); Said rocker arm bracket (6) all is connected said vehicle frame (1) lower surface, is positioned between the rocker arm bracket (6) of anterior said column (4) and front portion in each said column group, is positioned between the rocker arm bracket (6) at said column (4) and rear portion at rear portion and all is connected with the action roller supporting mechanism, and the lower surface of the arbitrary end of said vehicle frame (1) is provided with operator's compartment (7).
2. transport special-purpose flat truck according to the said Feng Ta of claim 1 place; It is characterized in that: the hanging beam of placing before and after each said running gear (2) includes two (8); One end upper surface of each said hanging beam (8) all is connected with said vehicle frame (1) lower surface; The other end of each said hanging beam (8) all is connected with driven axle assembly (9); Each driven axle assembly (9) all is connected with road wheel (10), and two road wheels (10) in one of them said running gear all are connected with Pneumatic brake systems (11).
3. transport special-purpose flat truck according to the said Feng Ta of claim 2 place; It is characterized in that: the said road wheel (10) in each said running gear (2) all is connected with swing bearing (12), and each said swing bearing (12) all is connected with an end of steering hardware (13).
4. transport special-purpose flat truck according to the said Feng Ta of claim 3 place, it is characterized in that: said engine installation (3) comprises fuel tank and hydraulic reservoir, and the other end of each said steering hardware (13) all is connected with said engine installation (3).
5. transport special-purpose flat truck according to the said Feng Ta of claim 4 place; It is characterized in that: each said action roller supporting mechanism includes oil cylinder seat (14); Oil cylinder seat (14) is fixed on the inboard of said column (4); Said oil cylinder seat (14) is connected with oil cylinder (15) and is connected, and said oil cylinder (15) is connected with the middle part of rocking arm (16), and an end of said rocking arm (16) is connected with said rocker arm bracket (6); The other end of said rocking arm (18) is connected with support wheel assembly (5), the groove that said support wheel assembly (5) places said vehicle frame (1) to be provided with.
6. transport special-purpose flat truck according to the said Feng Ta of claim 5 place, it is characterized in that: said operator's compartment is provided with program control center in (7).
CN201110076107A 2011-03-29 2011-03-29 Platform vehicle special for transfer in wind tower field Active CN102166980B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110076107A CN102166980B (en) 2011-03-29 2011-03-29 Platform vehicle special for transfer in wind tower field

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110076107A CN102166980B (en) 2011-03-29 2011-03-29 Platform vehicle special for transfer in wind tower field

Publications (2)

Publication Number Publication Date
CN102166980A CN102166980A (en) 2011-08-31
CN102166980B true CN102166980B (en) 2012-09-05

Family

ID=44488365

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110076107A Active CN102166980B (en) 2011-03-29 2011-03-29 Platform vehicle special for transfer in wind tower field

Country Status (1)

Country Link
CN (1) CN102166980B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104670362B (en) * 2015-02-14 2017-03-22 中铁十七局集团电气化工程有限公司 Self-controlled pulling V-shaped tower hoisting and transporting platform lorry
CN104816768B (en) * 2015-04-20 2017-06-13 上海交通大学 Travelling bogie

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201031768Y (en) * 2007-04-24 2008-03-05 刘景斌 Bionics type wind motor
CN101196177A (en) * 2006-12-08 2008-06-11 天津市海恩海洋工程技术服务有限公司 Installation construction method for wind generator set on the sea
CN202011354U (en) * 2011-03-29 2011-10-19 中航虹波风电设备有限公司 Special transport flat car for wind tower field

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101196177A (en) * 2006-12-08 2008-06-11 天津市海恩海洋工程技术服务有限公司 Installation construction method for wind generator set on the sea
CN201031768Y (en) * 2007-04-24 2008-03-05 刘景斌 Bionics type wind motor
CN202011354U (en) * 2011-03-29 2011-10-19 中航虹波风电设备有限公司 Special transport flat car for wind tower field

Also Published As

Publication number Publication date
CN102166980A (en) 2011-08-31

Similar Documents

Publication Publication Date Title
CN201261705Y (en) Platform capable of lifting and moving vehicle
CN103866060A (en) Hinged connection type U-shaped slag tank vehicle
CN201943008U (en) Polycarbonate (PC) rail track beam erecting equipment
CN201841892U (en) Compact type independent turning self-supplied power type module transportation vehicle
CN102166980B (en) Platform vehicle special for transfer in wind tower field
CN102815643B (en) Vehicle mounted type handling goods implement
CN202011354U (en) Special transport flat car for wind tower field
CN205601678U (en) A on -vehicle handling device for container loading and unloading
CN202764962U (en) Kiloton self-traction air cushion car
CN204250196U (en) low loading platform truck
CN206938575U (en) The beam car of two-way fortune beam on a kind of asymmetric whole opening box girder beam of achievable large-tonnage
CN201516877U (en) Continuous miner handling platform trailer
CN104527670A (en) Railway freight car and cargo loading and unloading system
CN102249096B (en) Carrying and storing method of wind tower
CN102371931A (en) Carrier of slag pot of hot steel-making slag
CN102351001A (en) Unpowered material storage and conveyance vehicle
CN202671135U (en) Freight forklift
CN204341039U (en) Railway truck and shipping loading and unloading system
CN201941844U (en) Concave tyre type beam-transporting vehicle
CN2126838Y (en) Container transport vehicle cabable of automatic dismounting
CN202272089U (en) Carrying cart for thermal-state slag tank
CN203063917U (en) Mechanism achieving four-way driving of forklift and forklift
CN203112854U (en) Hinged U-shaped slag pot carrier
CN201817210U (en) Rubber-tyred gantry crane capable of overturning ship section in air for shipbuilding
CN220518106U (en) Electric self-lifting transfer trolley

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20200113

Address after: 313000 No.5-8, Changhe Road, Huaxi street, Changxing County, Huzhou City, Zhejiang Province

Patentee after: Zhejiang Changxing green battery technology Co., Ltd

Address before: The three group of Tongzhou District Xingren Zhen Sun Jia Qiao Cun, Jiangsu city of Nantong province 226000

Patentee before: AVIC Hongbo Windpower Equipment Co., Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20200914

Address after: Room 501, Office Building of Market Supervision Bureau of Langchuan Avenue, Jianping Town, Langxi County, Xuancheng City, Anhui Province

Patentee after: Langxi pinxu Technology Development Co., Ltd

Address before: 313000 No.5-8, Changhe Road, Huaxi street, Changxing County, Huzhou City, Zhejiang Province

Patentee before: Zhejiang Changxing green battery technology Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20201123

Address after: No.98 Jiangping Road, Hongguang industrial concentration zone, Shengci Town, Jingjiang City, Taizhou City, Jiangsu Province

Patentee after: Jingjiang Jinqiao Pump Industry Co., Ltd

Address before: Room 501, Office Building of Market Supervision Bureau of Langchuan Avenue, Jianping Town, Langxi County, Xuancheng City, Anhui Province

Patentee before: Langxi pinxu Technology Development Co., Ltd