CN102155249A - 一种采空区下方巷道顶板支护方法 - Google Patents

一种采空区下方巷道顶板支护方法 Download PDF

Info

Publication number
CN102155249A
CN102155249A CN2011100580018A CN201110058001A CN102155249A CN 102155249 A CN102155249 A CN 102155249A CN 2011100580018 A CN2011100580018 A CN 2011100580018A CN 201110058001 A CN201110058001 A CN 201110058001A CN 102155249 A CN102155249 A CN 102155249A
Authority
CN
China
Prior art keywords
mined
out area
steel belt
expansion anchor
tunnel roof
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011100580018A
Other languages
English (en)
Inventor
柏建彪
王襄禹
徐营
冯伟
王元明
陈勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology CUMT
Original Assignee
China University of Mining and Technology CUMT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology CUMT filed Critical China University of Mining and Technology CUMT
Priority to CN2011100580018A priority Critical patent/CN102155249A/zh
Publication of CN102155249A publication Critical patent/CN102155249A/zh
Pending legal-status Critical Current

Links

Abstract

一种采空区下方巷道顶板支护方法,采用钢带组合水力膨胀锚杆支护采空区下方巷道顶板。首先对采空区下方掘出的巷道顶板及两帮支设临时支护,在顶板铺设金属网及钢带,使钢带压住金属网,用单体支柱将钢带顶住,从钢带的孔口向巷道顶板打眼钻孔;然后依次将水力膨胀锚杆装入钻孔内,通过托盘使钢带贴紧顶板,逐个向水力膨胀锚杆内注入压力为20~22MPa的高压水,每个水力膨胀锚杆的注液时间不少于2min;重复上述步骤过程,直至完成采空区下方巷道顶板的支护。该方法解决了传统树脂锚固锚杆无法在采空区内锚固,不能有效支护采空区下方极近距离巷道顶板的难题,其工艺简单,操作方便。

Description

一种采空区下方巷道顶板支护方法
技术领域
本发明涉及一种采空区下方巷道顶板支护方法,尤其适用极近距离煤层群开采时,采空区下方巷道的顶板支护,也可应用于厚煤层分层开采下分层巷道顶板的支护。
背景技术
我国近距离煤层赋存和开采所占比重很大,大多矿区都存在近距离煤层群开采的问题。随着煤矿开采强度的不断增大,特别是近年来快速发展的高产高效技术,己经使大部分矿区开采条件好的煤层在较短的服务年限内接近枯竭,促使近距离煤层的开采问题迅速进入人们的视野,并引起高度重视。对于煤层群开采,当煤层层间距离较大时,上部煤层开采后对下部煤层的开采影响程度很小。但是,随着煤层间距离减小,上下煤层间开采的相互影响会逐渐增大,特别是当煤层间距很近时(小于1.5m),下部煤层开采前顶板的完整程度已受上部煤层开采损伤影响,其上又为上部煤层开采垮落的矸石,采用传统的数值锚固锚杆无法在采空区内锚固,因而不能有效支护采空区下方的巷道顶板,从而使下部煤层巷道的顶板支护变的困难。以前对于这种条件通常的做法是采用架棚支护。厚煤层分层开采时下分层巷道通常也是采用架棚支护。采用架棚支护工人劳动强度大,且属于被动支护,巷道顶板依靠棚梁来支撑,只有顶板发生变形,支架的棚梁才起到支撑顶板的作用。但巷道顶板通常情况下很难与棚梁发生直接接触,只有顶板发生较大的离层松动,产生较大变形后,棚梁才能够支撑顶板。而一旦巷道顶板发生离层松动,由于金属棚梁能承受的压力是有限制的,因而根本无法抵抗巷道围岩发生较大离层产生的变形破坏所释放出来的能量,最终导致顶板进一步的离层、松动,引发冒顶事故。
发明内容
技术问题:本发明的目的是克服已有技术中的不足,提供一种方法简单、操作方便的用于采空区下方巷道顶板的支护方法。
技术方案:本发明的采空区下方巷道顶板支护方法,包括以下步骤:
a.首先将采空区下方掘出的巷道顶板及两帮的危石处理掉,支设临时支护;
b.对掘进出的巷道顶板铺设金属网,用布有孔径与水力膨胀锚杆直径相匹配的钢带托住金属网,然后用单体液压支柱将钢带顶住,贴紧顶板;
c.用与水力膨胀锚杆直径相匹配的钻头配合钻机依次从该排钢带的孔口向巷道顶板打眼钻孔,孔深与水力膨胀锚杆长度相匹配;
d.依次将水力膨胀锚杆装入钻孔内,并通过水力膨胀锚杆尾部的托盘使钢带贴紧顶板;
e.通过注液连接器逐个向水力膨胀锚杆内注入压力为20~22MPa的高压水,每个水力膨胀锚杆的注液时间不少于2min;
f.重复上述步骤b、c、d、e,直至完成采空区下方巷道顶板的支护
有益效果:本发明采用钢带组合水力膨胀锚杆支护采空区下方巷道的顶板,钢带护顶面积大,护表作用强,适用于极近距离煤层群开采采空区下方巷道的顶板支护,也适用于厚煤层分层开采下分层巷道顶板的支护,以及其他松散破碎围岩巷道的支护。水力膨胀锚杆能够立即承载,锚固性能随围岩性质变化不大,能够实现全长锚固,锚固力大,且随着杆体收缩能够产生一定的预紧力,在杆体膨胀后对围岩产生挤压作用,改善围岩应力状态。解决了采用传统树脂锚固锚杆不能有效支护采空区下方极近距离巷道顶板的难题。与现有的架棚支护技术相比,首先是变被动支护为主动支护;2是减少了架棚时的各种工序,降低了劳动强度;3是注水过程中能够大大降低粉尘污染,改善劳动环境;4是操作简单,支护效果好,在本技术领域内具有广泛的实用性。
具体实施方式
下面对本发明的一个实施例作进一步的描述:
本发明的采空区下方巷道顶板支护方法,首先将采空区下方掘出的巷道顶板及两帮的危石处理掉,支设临时支护;对掘进出的巷道顶板铺设双层菱形金属网,用孔径为40mm×60mm的W钢带托住金属网,按照作业规程中要求的排距定位顶板钢带的位置,然后用单体液压支柱将钢带顶住,使其贴紧顶板;用直径40mm的钻头配合钻机依次从钢带的孔口向巷道顶板打眼钻孔,孔深与水力膨胀锚杆长度相匹配,孔深2500mm;依次将直径30mm长2500mm的水力膨胀锚杆装入钻孔内,使用液压千斤顶通过水力膨胀锚杆尾部的托盘使钢带贴紧顶板;通过注液连接器逐个向水力膨胀锚杆内注入压力为20~22MPa的高压水,每个水力膨胀锚杆的注液时间不少于2min;完成一排水力膨胀锚杆安装之后,重复上述过程,进行下一排水力膨胀锚杆的安装,周而复始,直至完成采空区下方巷道顶板的支护。

Claims (1)

1.一种用于采空区下方巷道顶板支护方法,其特征在于包括以下步骤:
a.首先将采空区下方掘出的巷道顶板及两帮的危石处理掉,支设临时支护;
b.对掘进出的巷道顶板铺设金属网,用布有孔径与水力膨胀锚杆直径相匹配的钢带托住金属网,然后用单体液压支柱将钢带顶住,贴紧顶板;
c.用与水力膨胀锚杆直径相匹配的钻头配合钻机依次从该排钢带的孔口向巷道顶板打眼钻孔,孔深与水力膨胀锚杆长度相匹配;
d.依次将水力膨胀锚杆装入钻孔内,并通过水力膨胀锚杆尾部的托盘使钢带贴紧顶板;
e.通过注液连接器逐个向水力膨胀锚杆内注入压力为20~22MPa的高压水,每个水力膨胀锚杆的注液时间不少于2min;
f.重复上述步骤b、c、d、e,直至完成采空区下方巷道顶板的支护。
CN2011100580018A 2011-03-11 2011-03-11 一种采空区下方巷道顶板支护方法 Pending CN102155249A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011100580018A CN102155249A (zh) 2011-03-11 2011-03-11 一种采空区下方巷道顶板支护方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011100580018A CN102155249A (zh) 2011-03-11 2011-03-11 一种采空区下方巷道顶板支护方法

Publications (1)

Publication Number Publication Date
CN102155249A true CN102155249A (zh) 2011-08-17

Family

ID=44436893

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011100580018A Pending CN102155249A (zh) 2011-03-11 2011-03-11 一种采空区下方巷道顶板支护方法

Country Status (1)

Country Link
CN (1) CN102155249A (zh)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102505949A (zh) * 2011-11-12 2012-06-20 山西煤炭运销集团科学技术研究有限公司 一种煤层巷道过采空区的支护方法
CN102900449A (zh) * 2012-10-11 2013-01-30 北京圆之翰煤炭工程设计有限公司 一种煤矿井下采空区顶板的支护方法
CN103470289A (zh) * 2013-09-25 2013-12-25 大同煤矿集团有限责任公司 极近距离煤层开采支护方法
CN105715273A (zh) * 2016-04-06 2016-06-29 中国神华能源股份有限公司 特厚硬煤下分层的巷道布置方式
CN105863639A (zh) * 2016-05-27 2016-08-17 安徽理工大学 松散煤层的采煤方法
CN106884670A (zh) * 2017-03-06 2017-06-23 西安科技大学 一种煤矿井下采空区顶板的支护方法
CN112459813A (zh) * 2020-10-30 2021-03-09 山东东山新驿煤矿有限公司 一种综采工作面超前支护的锚索设置计算方法

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2367771Y (zh) * 1999-04-15 2000-03-08 周正濂 楔式二翼管状锚杆
US20020028113A1 (en) * 2000-09-01 2002-03-07 Robertson Roy Lee Method and apparatus for secondary roof support in an underground mine
CN1966937A (zh) * 2006-11-24 2007-05-23 天地科技股份有限公司 深部巷道强力锚杆一次支护方法
CN201170106Y (zh) * 2008-03-28 2008-12-24 尚海峰 巷道锚杆支护系统
CN201187308Y (zh) * 2008-05-06 2009-01-28 中国科学院武汉岩土力学研究所 大倾角厚煤层留小煤柱沿空掘巷支架
CN201232558Y (zh) * 2008-06-24 2009-05-06 义马煤业(集团)有限责任公司 综采切眼全断面锚网支护
CN101457651A (zh) * 2008-11-19 2009-06-17 淮南矿业(集团)有限责任公司 煤气共采y型通风系统中沿空留巷的充填垛超前支护方法

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2367771Y (zh) * 1999-04-15 2000-03-08 周正濂 楔式二翼管状锚杆
US20020028113A1 (en) * 2000-09-01 2002-03-07 Robertson Roy Lee Method and apparatus for secondary roof support in an underground mine
CN1966937A (zh) * 2006-11-24 2007-05-23 天地科技股份有限公司 深部巷道强力锚杆一次支护方法
CN201170106Y (zh) * 2008-03-28 2008-12-24 尚海峰 巷道锚杆支护系统
CN201187308Y (zh) * 2008-05-06 2009-01-28 中国科学院武汉岩土力学研究所 大倾角厚煤层留小煤柱沿空掘巷支架
CN201232558Y (zh) * 2008-06-24 2009-05-06 义马煤业(集团)有限责任公司 综采切眼全断面锚网支护
CN101457651A (zh) * 2008-11-19 2009-06-17 淮南矿业(集团)有限责任公司 煤气共采y型通风系统中沿空留巷的充填垛超前支护方法

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
刘建国: "水胀式锚杆在隧道施工中的应用", 《现代隧道技术》 *
夏云峰: "复合再生顶板条件下锚杆支护技术研究", 《能源技术与管理》 *
李海燕: "新汶矿区煤巷锚杆支护技术应用与发展", 《煤矿开采》 *

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102505949A (zh) * 2011-11-12 2012-06-20 山西煤炭运销集团科学技术研究有限公司 一种煤层巷道过采空区的支护方法
CN102505949B (zh) * 2011-11-12 2013-10-30 山西煤炭运销集团科学技术研究有限公司 一种煤层巷道过采空区的支护方法
CN102900449A (zh) * 2012-10-11 2013-01-30 北京圆之翰煤炭工程设计有限公司 一种煤矿井下采空区顶板的支护方法
CN102900449B (zh) * 2012-10-11 2014-07-23 北京圆之翰煤炭工程设计有限公司 一种煤矿井下采空区顶板的支护方法
CN103470289A (zh) * 2013-09-25 2013-12-25 大同煤矿集团有限责任公司 极近距离煤层开采支护方法
CN105715273A (zh) * 2016-04-06 2016-06-29 中国神华能源股份有限公司 特厚硬煤下分层的巷道布置方式
CN105863639A (zh) * 2016-05-27 2016-08-17 安徽理工大学 松散煤层的采煤方法
CN106884670A (zh) * 2017-03-06 2017-06-23 西安科技大学 一种煤矿井下采空区顶板的支护方法
CN112459813A (zh) * 2020-10-30 2021-03-09 山东东山新驿煤矿有限公司 一种综采工作面超前支护的锚索设置计算方法

Similar Documents

Publication Publication Date Title
CN100577986C (zh) 三软地质条件下采空区留巷围岩支护方法
CN102155249A (zh) 一种采空区下方巷道顶板支护方法
CN100554642C (zh) 一种长壁综采回收房式开采煤柱的方法
CN104074529B (zh) 一种深部巷硐连续双壳加固方法
CN104863629A (zh) 一种利用复合钻孔抽覆岩下离层瓦斯及排水注浆的方法
CN103306714B (zh) 近距离煤层群底抽巷钻孔一孔三用的瓦斯治理方法
CN111878080B (zh) 煤矿综采工作面的设备回撤及回撤通道自成巷的方法
CN102135005B (zh) 一种煤柱与采空区过渡段下方巷道顶板支护方法
WO2013102309A1 (zh) 一种长壁工作面无煤柱开采方法
CN102900449B (zh) 一种煤矿井下采空区顶板的支护方法
CN108087008B (zh) 一种三软煤层沿空巷道支护方法
CN110409461A (zh) 一种基于装配式大直径管桩的基坑支护施工方法
CN103758529A (zh) 一种煤矿沿空留巷巷旁支护方法
CN109209490B (zh) 一种矸石充填辅助末采阶段工作面回撤方法
CN102587962A (zh) 一种扩帮瓦斯抽采钻场的布置及支护方法
CN103485808A (zh) 井下膨胀软岩的电渗法原位改性巷道锚固方法
CN104047629A (zh) 薄煤层综采沿空留巷定向钻进抽采临近下煤层瓦斯的方法
CN104895072A (zh) 一种预应力锚索以及预应力锚索一次成型施工方法
CN104074534B (zh) 一种综采/综放工作面的沿空留巷方法
CN105909284B (zh) 一种大采高煤壁片帮防治控制方法
CN102155248B (zh) 一种煤柱下方巷道支护方法
CN102425428A (zh) 巷道迎头极破碎顶板控制方法
CN1948714A (zh) 矿山井下巷道围岩破碎带施工支护的方法
CN210919066U (zh) 综放工作面煤顶下一体化掘进装置
CN102425417A (zh) 易冒顶板锚索毛石墙联合沿空留巷方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20110817