CN102101623A - Method for transporting and lifting underground substation large-sized equipment - Google Patents

Method for transporting and lifting underground substation large-sized equipment Download PDF

Info

Publication number
CN102101623A
CN102101623A CN2009102014455A CN200910201445A CN102101623A CN 102101623 A CN102101623 A CN 102101623A CN 2009102014455 A CN2009102014455 A CN 2009102014455A CN 200910201445 A CN200910201445 A CN 200910201445A CN 102101623 A CN102101623 A CN 102101623A
Authority
CN
China
Prior art keywords
voltage transformer
goods
underground substation
vehicle
equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2009102014455A
Other languages
Chinese (zh)
Other versions
CN102101623B (en
Inventor
王怡风
许建华
高小庆
张伟
王固萍
陈平
杨明
陈东浩
金刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Shanghai Municipal Electric Power Co
Original Assignee
GRID CONSTRUCTION Co OF SHANGHAI MUNICIPAL ELECTRIC POWER Co
Shanghai Municipal Electric Power Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GRID CONSTRUCTION Co OF SHANGHAI MUNICIPAL ELECTRIC POWER Co, Shanghai Municipal Electric Power Co filed Critical GRID CONSTRUCTION Co OF SHANGHAI MUNICIPAL ELECTRIC POWER Co
Priority to CN 200910201445 priority Critical patent/CN102101623B/en
Publication of CN102101623A publication Critical patent/CN102101623A/en
Application granted granted Critical
Publication of CN102101623B publication Critical patent/CN102101623B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Load-Engaging Elements For Cranes (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention relates to a method for transporting and lifting underground substation large-sized equipment. The method comprises the following steps of: A, selecting a transport route and a wharf; B, lifting the underground substation large-sized equipment at the selected wharf for lightering and transporting; C, performing highway transport according to the selected transport route; D, loading and unloading the underground substation large-sized equipment at a storage yard; and E, lifting the underground substation large-sized equipment and transporting on a winding road. Compared with the prior art, the invention has the advantages that: the method is safe, reliable, stable and the like.

Description

The transporting and hoisting method of underground substation main equipment
Technical field
The present invention relates to transporting and hoisting method, particularly relate to the transporting and hoisting method of a kind of underground substation main equipment.
Background technology
Jing'an (Expo) substation project is the core engineering that guarantees the safe and reliable power supply of World Expo, 2,900,000,000 yuan of gross investments, be not only the seat of honour 500 kv substations in the urban district, Shanghai, also will be maximum in the world, state-of-the-art full underground substation, plan to build up and put into operation in 2009, to effectively alleviate after building up and go up the Haicheng District powerup issue, for the 2010 World Fair provides powerful electric power safeguard.This substation is positioned at the zone of BeiJing Xi Road, North Road, Chengdu, Shanhai Pass road, land for growing field crops road surrounding (being located in " eastern eight "), Power Plant Design adopts underground four layers of tubular construction, outside diameter of cylinder reaches 130 meters, the degree of depth reaches 33.5 meters, four layers of layout, main transformer equipment will be placed on-26.5 meters F3/B3.Master control room, import and export and inlet and outlet are only stayed in ground, foundation ditch area sq m more than 1.3 ten thousand, hypogee area 5.3 ten thousand sq ms, superstructure area 1590 sq ms, the floor planning at place is a public lawn, will build " sculpture park ", becomes a new highlight of Shanghai Urban view.
This engineering will be installed 500 kilovolts of 1,500,000 kilovolt-amperes of high capacity main transformers first, and the current period is built 2 covers, and final construction scale is 3 covers, and the current period also will be built 300,000 kilovolt-amperes of main transformers of 220 kilovolts in 2 covers on this basis in addition, and final scale is 3 to overlap.The transformer capacity of 500 kilovolts and 220 kilovolts reaches 4,500,000 kilovolt-amperes and 900,000 kilovolt-amperes the most respectively.
Engineering is held foundation stone laying ceremony on March 23rd, 2006, under the personnel's that all take part in building effort, finishes the construction of 80 width of cloth diaphragm walls July; Finish piling construction December, lay 886 bored concrete piles altogether, structure construction is carried out at the scene just in full preparation, and civil engineering structure is finished substantially to estimate in June, 2008.
After substation's civil engineering proceeds to a certain degree, and then just relate to the transportation of electrical equipment, because this project site is positioned at the business district, large-scale main transformer traffic condition in the equipment is comparatively complicated, how choose reasonable haulway, vehicle configuration, the feasible transporting and hoisting scheme of design safety are to need the problem that solves at present.
Summary of the invention
Technical matters to be solved by this invention is exactly the transporting and hoisting method that a kind of underground substation main equipment is provided for the defective that overcomes above-mentioned prior art existence.
Purpose of the present invention can be achieved through the following technical solutions: the transporting and hoisting method of underground substation main equipment, it is characterized in that, and may further comprise the steps:
A. haulway and harbour chooses;
B. at the harbour of choosing underground substation main equipment is lifted by crane and transfer, and transportation;
C. carry out road transport according to the haulway of choosing;
D. underground substation main equipment is carried out the stockyard loading and unloading;
E. underground substation main equipment is lifted and the Pan Lu transportation.
Described step B further may further comprise the steps:
By crane barge with 4
Figure G2009102014455D00021
-6 * 37 steel ropes are made hoist cable, and pocket is enclosed within voltage transformer lifting mark, and the position that goods contacts with hoist cable is provided with liner, and standby four rated loads are 150 tons No. 4 shackles hook;
Promptly stop to hoist and do following inspection when cargo runner lifts by crane stressed 30%:
Whether the fastening rigging of goods bundling complete removal;
Whether the steel wire loop button bit is put on the suspension centre mark;
The whether slippage of pad such as rubber, angle bar;
Whether goods has damage in the delivery process;
Whether the member stress state of goods is good;
Have or not extruding or the collision may with thing such as goods, hull on every side;
Whether influential operation boats and ships pass through near waters;
Whether whether this crane barge hawser is fastened, stressed even;
After above-mentioned inspection is errorless, send the lifting signal, suspension hook slowly rises with 0.5m/min speed;
Before the goods disembark, the suspension hook perpendicular line must be to the center of gravity of quasi-goods;
Goods is done following the detection: whether suspender is stressed even; Whether goods balance and stability;
Continue with the handling of 2m/min speed above-mentioned definite back; When hoisting handling, initial velocity will delay, and operation then wants steady, makes the goods bottom be higher than running orbit process zone: more than the 0.5m of cabin mouth coaming plate; After treating that goods comes to a complete stop, tighten up hawser, crane barge is moved to harbour, when goods is in the top of vehicle to be installed appropriate location, tighten up hawser and anchor chain location;
Goods draws surely rope when operation downwards, steady rope ties up to goods two ends or four jiaos;
Slowly descend with 0.5m/min speed behind the goods aligned position, about 1 meter away from the sweep that lands stop loose hook, utilize steady rope to adjust the voltage transformer direction,, drop on the sweep at a slow speed after just treating surely by laterally transferring to vertically be;
Loose again hook was removed the hoist cable of crane barge after suitable colligation was reinforced.
Described step C further may further comprise the steps:
The car group of loading facilities is in operation, and the difficulty of transporting according to equipment is provided with some service vehicles, so that safeguard order of traffic;
Single batch of more vehicle is on road during collective's driving, fleet is separated by far away from beginning to end, personnel are numerous, the vehicle crew should utilize advanced communication tool on the way and the watch-dog actv. keeps in touch and the command scheduling vehicle operating, at any time monitoring vehicle, personnel operation and operating condition on the way is to guarantee the safety traffic of vehicle and equipment;
During by the crossing, travel, guarantee safe passing by demand sign.During by four corners or approach crossing, speed ≯ 5km/h, the commander that department is subjected oneself to control in strictness at the uniform velocity travels on specific lane, must not brish acceleration, change gear and emergency braking;
Whole process has the part bend, and at this long transport trolley group, heavy-duty vehicle need keep bend unobstructed when turning;
Vehicle in motion, the entourage should keep a close eye on each key position of observing sweep and the binding situation of equipment, meets fault and should in time handle;
Vehicle start should steady and smooth, must not brish acceleration, and acceleration/accel is not more than 0.5g;
The running method of traction engine: the speed of a motor vehicle is not more than 15km/h in transportation, and the turning speed of a motor vehicle is not more than 3km/h; Enter the complex road surface speed of a motor vehicle and be not more than 5km/h; Meet narrow road section, potted road surface more should travel at a slow speed, forbids sudden stop.Flat truck should be advanced on the main road surface of particular link, avoids in unstable road traveling of roadbed or stop;
The appliance crew notes observing and watches from a height or a distance, and prevents that unforeseen circumstances from causing emergency braking;
Transformer body degree of dip in whole transportation, the handling process: long axis direction is not more than 15 °; Short-axis direction is not more than 10 °.
Forbid rolling to be impacted, acceleration of transportation is limited in: longitudinal acceleration is not more than 0.5g, and transverse acceleration is not more than 0.3g;
Write down impact shock instrument (table) reading in the transportation and confirm signature through the owner;
Described step D further may further comprise the steps:
According to the operation field situation, determine whether ground ballast situation allows door frame directly to use, otherwise application subgrade case or steel plate can use after padding;
Determine that operation ground meets after the door frame operation, carry out the door frame assembly unit, will notice during assembly unit that the bolt that respectively closes link must connect fastening;
The door frame assembly unit finishes, and the door frame hydraulic jacking system is carried out trail run, in that determine safely and effectively under the situation can place in operation;
The staff utilizes suitable hoist cable, shackle to entangle equipment, makes every effort to make the center of crossbeam to occupy on the center of gravity of equipment, produce when preventing to lift by crane significantly get rid of pendulum and weight too amesiality;
During lifting, after voltage transformer hangs loading platform 20cm, suspend and hoist, static 15 minutes and confirm just can continue operation after each stress point in order;
After treating that the voltage transformer lifting is stable, the transport trolley group slowly withdraws from the unloading area;
After car group to be transported withdraws from the unloading area, the hydraulic pressure door frame reduce synchronously the height, until the voltage transformer stable landing on the stockyard;
The entrucking mode of hydraulic pressure door frame is identical with unloading way, and program is opposite;
At first set up the hydraulic pressure door frame, and debugging finishes in the entrucking position of voltage transformer to be installed;
Hanging sleeve hoisting sling on the suspension centre of voltage transformer;
When voltage transformer is promoted by door frame, and after being located in the entrucking position, the carrying voltage transformer is prepared in transport vehicle access arrangement bottom;
Lifting appliance drops to voltage transformer when the flat truck 10cm, and the hydraulic pressure door frame stops to descend.Reaffirm the loading center of the center of gravity aligning transport trolley group of voltage transformer;
After confirming to finish, continue to reduce the height of voltage transformer, all be carried on the transport trolley group until voltage transformer;
Monitor the fulcrum loop of hydraulic pressure car group, guarantee difference of pressure ≯ 10% of each fulcrum.And leveling transport trolley group, height resumes operation;
Shed suspender, finish tying up of voltage transformer and flat truck group;
Described step e underground substation main equipment is lifted further may further comprise the steps:
The hanging device group car of marching into the arena;
Treat the equipment of hanging inspection;
After inspection finishes, on the main equipment of underground substation, Lifting slings is installed;
Examination is hung: end-to-end test ground situation of change and rigging, crane load condition;
Underground substation main equipment is formally lifted:
Recover the lifting back: dismantle Current Collector Sleave, hang lid and attaching parts.
The pushing tow transportation mode is adopted in the Pan Lu transportation of described step e, and it comprises:
Lay the reinforcement subgrade case of 6500 * 2600 * 240mm on passage ground, vertically lay, two of symmetries are laid 31 altogether in 65 meters passage, remain in the voltage transformer shifting process 4 strengthen subgrade cases above.By such handling, make the ground contact area of voltage transformer expand as 13 * 5.2=67.6m2, hydraulic top pushing device is placed subgrade case and above the case of angle, and the space between propelling unit and subgrade case is clogged with the steel plate pad, guarantees that main transformer steadily advances;
The equipment handling to well head, is started hydraulic top pushing device, begin slowly pushing tow voltage transformer,, finish voltage transformer work in place until in place on the basis.
Compared with prior art, the present invention
1) the advanced reasonably device design layout of substation, be convenient to the Pan Lu transportation of transformer equipment:
Expo station transformer equipment is arranged in underground-26.5 meters layers, transportation Rational Parameters Design device layout according to the equipment of voltage transformer is that underground transport channel is designed to wide 6.6 meters square, hang two drift angles that the thing hole is positioned at square passageway, transformer equipment is positioned at the outside of square passageway, no matter which platform voltage transformer can hang down from the thing hole of hanging nearby, and is in place by the straight line transportation, need not turn at underground-26.5 meters layers, save the underground space, convenient transportation.From the actual conditions of engineering, whole lifting, 9 days to 2009 January 22 of lower wall road duration since January in 2009 end of day, only be 14 day duration, the phenomenon of not doing over again in the process.Advance, the reasonableness of design plan have been verified;
2) loop wheel machine selection and loop wheel machine ground are considered permanent scheme, long-range remarkable benefit:
Because the civil Engineering Design at Expo station is not considered the cushion cap basis of large-scale loop wheel machine, so what initial design was considered is to adopt 750 tons of pedrail cranes need not driving piles and handle, not because not allowing of lifting place, this problem through Field Research, economic comparative optimization 500 tons of wheel cranes of TC2600 type, and the permanent cushion cap of the loop wheel machine of having designed and constructed, for the narrow and small city center substation main equipment lifting in place from now on provides experiential basis.
3) ground, underground substation lower wall road technique is preferred:
The Pan Lu that carries out large-scale substation in the 500kV underground substation transports at home still first, and problem has compared four kinds of dish path methods, has finally determined hydraulic top pushing device passing method, for underground substation construction from now on provides experience.
The specific embodiment
Below the invention will be further described.
The transporting and hoisting method of underground substation main equipment may further comprise the steps:
A. haulway and harbour chooses;
B. at the harbour of choosing underground substation main equipment is lifted by crane and transfer, and transportation;
C. carry out road transport according to the haulway of choosing;
D. underground substation main equipment is carried out the stockyard loading and unloading;
E. underground substation main equipment is lifted and the Pan Lu transportation.
Described step B further may further comprise the steps:
By crane barge with 4 -6 * 37 steel ropes are made hoist cable, and pocket is enclosed within voltage transformer lifting mark, and the position that goods contacts with hoist cable is provided with liner, and standby four rated loads are 150 tons No. 4 shackles hook;
Promptly stop to hoist and do following inspection when cargo runner lifts by crane stressed 30%:
Whether the fastening rigging of goods bundling complete removal;
Whether the steel wire loop button bit is put on the suspension centre mark;
The whether slippage of pad such as rubber, angle bar;
Whether goods has damage in the delivery process;
Whether the member stress state of goods is good;
Have or not extruding or the collision may with thing such as goods, hull on every side;
Whether influential operation boats and ships pass through near waters;
Whether whether this crane barge hawser is fastened, stressed even;
After above-mentioned inspection is errorless, send the lifting signal, suspension hook slowly rises with 0.5m/min speed;
Before the goods disembark, the suspension hook perpendicular line must be to the center of gravity of quasi-goods;
Goods is done following the detection: whether suspender is stressed even; Whether goods balance and stability;
Continue with the handling of 2m/min speed above-mentioned definite back; When hoisting handling, initial velocity will delay, and operation then wants steady, makes the goods bottom be higher than running orbit process zone: more than the 0.5m of cabin mouth coaming plate; After treating that goods comes to a complete stop, tighten up hawser, crane barge is moved to harbour, when goods is in the top of vehicle to be installed appropriate location, tighten up hawser and anchor chain location;
Goods draws surely rope when operation downwards, steady rope ties up to goods two ends or four jiaos;
Slowly descend with 0.5m/min speed behind the goods aligned position, about 1 meter away from the sweep that lands stop loose hook, utilize steady rope to adjust the voltage transformer direction,, drop on the sweep at a slow speed after just treating surely by laterally transferring to vertically be;
Loose again hook was removed the hoist cable of crane barge after suitable colligation was reinforced.
Described step C further may further comprise the steps:
The car group of loading facilities is in operation, and the difficulty of transporting according to equipment is provided with some service vehicles, so that safeguard order of traffic;
Single batch of more vehicle is on road during collective's driving, fleet is separated by far away from beginning to end, personnel are numerous, the vehicle crew should utilize advanced communication tool on the way and the watch-dog actv. keeps in touch and the command scheduling vehicle operating, at any time monitoring vehicle, personnel operation and operating condition on the way is to guarantee the safety traffic of vehicle and equipment;
During by the crossing, travel, guarantee safe passing by demand sign.During by four corners or approach crossing, speed ≯ 5km/h, the commander that department is subjected oneself to control in strictness at the uniform velocity travels on specific lane, must not brish acceleration, change gear and emergency braking;
Whole process has the part bend, and at this long transport trolley group, heavy-duty vehicle need keep bend unobstructed when turning;
Vehicle in motion, the entourage should keep a close eye on each key position of observing sweep and the binding situation of equipment, meets fault and should in time handle;
Vehicle start should steady and smooth, must not brish acceleration, and acceleration/accel is not more than 0.5g;
The running method of traction engine: the speed of a motor vehicle is not more than 15km/h in transportation, and the turning speed of a motor vehicle is not more than 3km/h; Enter the complex road surface speed of a motor vehicle and be not more than 5km/h; Meet narrow road section, potted road surface more should travel at a slow speed, forbids sudden stop.Flat truck should be advanced on the main road surface of particular link, avoids in unstable road traveling of roadbed or stop;
The appliance crew notes observing and watches from a height or a distance, and prevents that unforeseen circumstances from causing emergency braking;
Transformer body degree of dip in whole transportation, the handling process: long axis direction is not more than 15 °; Short-axis direction is not more than 10 °.
Forbid rolling to be impacted, acceleration of transportation is limited in: longitudinal acceleration is not more than 0.5g, and transverse acceleration is not more than 0.3g;
Write down impact shock instrument (table) reading in the transportation and confirm signature through the owner;
Described step D further may further comprise the steps:
According to the operation field situation, determine whether ground ballast situation allows door frame directly to use, otherwise application subgrade case or steel plate can use after padding;
Determine that operation ground meets after the door frame operation, carry out the door frame assembly unit, will notice during assembly unit that the bolt that respectively closes link must connect fastening;
The door frame assembly unit finishes, and the door frame hydraulic jacking system is carried out trail run, in that determine safely and effectively under the situation can place in operation;
The staff utilizes suitable hoist cable, shackle to entangle equipment, makes every effort to make the center of crossbeam to occupy on the center of gravity of equipment, produce when preventing to lift by crane significantly get rid of pendulum and weight too amesiality;
During lifting, after voltage transformer hangs loading platform 20cm, suspend and hoist, static 15 minutes and confirm just can continue operation after each stress point in order;
After treating that the voltage transformer lifting is stable, the transport trolley group slowly withdraws from the unloading area;
After car group to be transported withdraws from the unloading area, the hydraulic pressure door frame reduce synchronously the height, until the voltage transformer stable landing on the stockyard;
The entrucking mode of hydraulic pressure door frame is identical with unloading way, and program is opposite;
At first set up the hydraulic pressure door frame, and debugging finishes in the entrucking position of voltage transformer to be installed;
Hanging sleeve hoisting sling on the suspension centre of voltage transformer;
When voltage transformer is promoted by door frame, and after being located in the entrucking position, the carrying voltage transformer is prepared in transport vehicle access arrangement bottom;
Lifting appliance drops to voltage transformer when the flat truck 10cm, and the hydraulic pressure door frame stops to descend.Reaffirm the loading center of the center of gravity aligning transport trolley group of voltage transformer;
After confirming to finish, continue to reduce the height of voltage transformer, all be carried on the transport trolley group until voltage transformer;
Monitor the fulcrum loop of hydraulic pressure car group, guarantee difference of pressure ≯ 10% of each fulcrum.And leveling transport trolley group, height resumes operation;
Shed suspender, finish tying up of voltage transformer and flat truck group;
Described step e underground substation main equipment is lifted further may further comprise the steps:
The hanging device group car of marching into the arena;
Treat the equipment of hanging inspection;
After inspection finishes, on the main equipment of underground substation, Lifting slings is installed;
Examination is hung: end-to-end test ground situation of change and rigging, crane load condition;
Underground substation main equipment is formally lifted:
Recover the lifting back: dismantle Current Collector Sleave, hang lid and attaching parts.
The pushing tow transportation mode is adopted in the Pan Lu transportation of described step e, and it comprises:
Lay the reinforcement subgrade case of 6500 * 2600 * 240mm on passage ground, vertically lay, two of symmetries are laid 31 altogether in 65 meters passage, remain in the voltage transformer shifting process 4 strengthen subgrade cases above.By such handling, make the ground contact area of voltage transformer expand as 13 * 5.2=67.6m2, hydraulic top pushing device is placed subgrade case and above the case of angle, and the space between propelling unit and subgrade case is clogged with the steel plate pad, guarantees that main transformer steadily advances;
The equipment handling to well head, is started hydraulic top pushing device, begin slowly pushing tow voltage transformer,, finish voltage transformer work in place until in place on the basis.

Claims (6)

1. the transporting and hoisting method of underground substation main equipment is characterized in that, may further comprise the steps:
A. haulway and harbour chooses;
B. at the harbour of choosing underground substation main equipment is lifted by crane and transfer, and transportation;
C. carry out road transport according to the haulway of choosing;
D. underground substation main equipment is carried out the stockyard loading and unloading;
E. underground substation main equipment is lifted and the Pan Lu transportation.
2. according to the transporting and hoisting method of right 1 described underground substation main equipment, it is characterized in that described step B further may further comprise the steps:
By crane barge with 4
Figure F2009102014455C00011
Steel rope is made hoist cable, and pocket is enclosed within voltage transformer lifting mark, and the position that goods contacts with hoist cable is provided with liner, and standby four rated loads are 150 tons No. 4 shackles hook;
Promptly stop to hoist and do following inspection when cargo runner lifts by crane stressed 30%:
Whether the fastening rigging of goods bundling complete removal;
Whether the steel wire loop button bit is put on the suspension centre mark;
The whether slippage of pad such as rubber, angle bar;
Whether goods has damage in the delivery process;
Whether the member stress state of goods is good;
Have or not extruding or the collision may with thing such as goods, hull on every side;
Whether influential operation boats and ships pass through near waters;
Whether whether this crane barge hawser is fastened, stressed even;
After above-mentioned inspection is errorless, send the lifting signal, suspension hook slowly rises with 0.5m/min speed;
Before the goods disembark, the suspension hook perpendicular line must be to the center of gravity of quasi-goods;
Goods is done following the detection: whether suspender is stressed even; Whether goods balance and stability;
Continue with the handling of 2m/min speed above-mentioned definite back; When hoisting handling, initial velocity will delay, and operation then wants steady, makes the goods bottom be higher than running orbit process zone: more than the 0.5m of cabin mouth coaming plate; After treating that goods comes to a complete stop, tighten up hawser, crane barge is moved to harbour, when goods is in the top of vehicle to be installed appropriate location, tighten up hawser and anchor chain location;
Goods draws surely rope when operation downwards, steady rope ties up to goods two ends or four jiaos;
Slowly descend with 0.5m/min speed behind the goods aligned position, about 1 meter away from the sweep that lands stop loose hook, utilize steady rope to adjust the voltage transformer direction,, drop on the sweep at a slow speed after just treating surely by laterally transferring to vertically be;
Loose again hook was removed the hoist cable of crane barge after suitable colligation was reinforced.
3. according to the transporting and hoisting method of right 1 or 2 described underground substation main equipments, it is characterized in that described step C further may further comprise the steps:
The car group of loading facilities is in operation, and the difficulty of transporting according to equipment is provided with some service vehicles, so that safeguard order of traffic;
Single batch of more vehicle is on road during collective's driving, fleet is separated by far away from beginning to end, personnel are numerous, the vehicle crew should utilize advanced communication tool on the way and the watch-dog actv. keeps in touch and the command scheduling vehicle operating, at any time monitoring vehicle, personnel operation and operating condition on the way is to guarantee the safety traffic of vehicle and equipment;
During by the crossing, travel, guarantee safe passing by demand sign.During by four corners or approach crossing, speed ≯ 5km/h, the commander that department is subjected oneself to control in strictness at the uniform velocity travels on specific lane, must not brish acceleration, change gear and emergency braking;
Whole process has the part bend, and at this long transport trolley group, heavy-duty vehicle need keep bend unobstructed when turning;
Vehicle in motion, the entourage should keep a close eye on each key position of observing sweep and the binding situation of equipment, meets fault and should in time handle;
Vehicle start should steady and smooth, must not brish acceleration, and acceleration/accel is not more than 0.5g;
The running method of traction engine: the speed of a motor vehicle is not more than 15km/h in transportation, and the turning speed of a motor vehicle is not more than 3km/h; Enter the complex road surface speed of a motor vehicle and be not more than 5km/h; Meet narrow road section, potted road surface more should travel at a slow speed, forbids sudden stop.Flat truck should be advanced on the main road surface of particular link, avoids in unstable road traveling of roadbed or stop;
The appliance crew notes observing and watches from a height or a distance, and prevents that unforeseen circumstances from causing emergency braking;
Transformer body degree of dip in whole transportation, the handling process: long axis direction is not more than 15 °; Short-axis direction is not more than 10 °.
Forbid rolling to be impacted, acceleration of transportation is limited in: longitudinal acceleration is not more than 0.5g, and transverse acceleration is not more than 0.3g;
Write down impact shock instrument (table) reading in the transportation and confirm signature through the owner;
4. according to the transporting and hoisting method of right 3 described underground substation main equipments, it is characterized in that described step D further may further comprise the steps:
According to the operation field situation, determine whether ground ballast situation allows door frame directly to use, otherwise application subgrade case or steel plate can use after padding;
Determine that operation ground meets after the door frame operation, carry out the door frame assembly unit, will notice during assembly unit that the bolt that respectively closes link must connect fastening;
The door frame assembly unit finishes, and the door frame hydraulic jacking system is carried out trail run, in that determine safely and effectively under the situation can place in operation;
The staff utilizes suitable hoist cable, shackle to entangle equipment, makes every effort to make the center of crossbeam to occupy on the center of gravity of equipment, produce when preventing to lift by crane significantly get rid of pendulum and weight too amesiality;
During lifting, after voltage transformer hangs loading platform 20cm, suspend and hoist, static 15 minutes and confirm just can continue operation after each stress point in order;
After treating that the voltage transformer lifting is stable, the transport trolley group slowly withdraws from the unloading area;
After car group to be transported withdraws from the unloading area, the hydraulic pressure door frame reduce synchronously the height, until the voltage transformer stable landing on the stockyard;
The entrucking mode of hydraulic pressure door frame is identical with unloading way, and program is opposite;
At first set up the hydraulic pressure door frame, and debugging finishes in the entrucking position of voltage transformer to be installed;
Hanging sleeve hoisting sling on the suspension centre of voltage transformer;
When voltage transformer is promoted by door frame, and after being located in the entrucking position, the carrying voltage transformer is prepared in transport vehicle access arrangement bottom;
Lifting appliance drops to voltage transformer when the flat truck 10cm, and the hydraulic pressure door frame stops to descend.Reaffirm the loading center of the center of gravity aligning transport trolley group of voltage transformer;
After confirming to finish, continue to reduce the height of voltage transformer, all be carried on the transport trolley group until voltage transformer;
Monitor the fulcrum loop of hydraulic pressure car group, guarantee difference of pressure ≯ 10% of each fulcrum.And leveling transport trolley group, height resumes operation;
Shed suspender, finish tying up of voltage transformer and flat truck group;
5. according to the transporting and hoisting method of right 4 described underground substation main equipments, it is characterized in that described step e underground substation main equipment is lifted further may further comprise the steps:
The hanging device group car of marching into the arena;
Treat the equipment of hanging inspection;
After inspection finishes, on the main equipment of underground substation, Lifting slings is installed;
Examination is hung: end-to-end test ground situation of change and rigging, crane load condition;
Underground substation main equipment is formally lifted:
Recover the lifting back: dismantle Current Collector Sleave, hang lid and attaching parts.
6. according to the transporting and hoisting method of right 5 described underground substation main equipments, it is characterized in that the pushing tow transportation mode is adopted in the Pan Lu transportation of described step e, it comprises:
Lay the reinforcement subgrade case of 6500 * 2600 * 240mm on passage ground, vertically lay, two of symmetries are laid 31 altogether in 65 meters passage, remain in the voltage transformer shifting process 4 strengthen subgrade cases above.By such handling, make the ground contact area of voltage transformer expand as 13 * 5.2=67.6m2, hydraulic top pushing device is placed subgrade case and above the case of angle, and the space between propelling unit and subgrade case is clogged with the steel plate pad, guarantees that main transformer steadily advances;
The equipment handling to well head, is started hydraulic top pushing device, begin slowly pushing tow voltage transformer,, finish voltage transformer work in place until in place on the basis.
CN 200910201445 2009-12-18 2009-12-18 Method for transporting and lifting underground substation large-sized equipment Active CN102101623B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200910201445 CN102101623B (en) 2009-12-18 2009-12-18 Method for transporting and lifting underground substation large-sized equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200910201445 CN102101623B (en) 2009-12-18 2009-12-18 Method for transporting and lifting underground substation large-sized equipment

Publications (2)

Publication Number Publication Date
CN102101623A true CN102101623A (en) 2011-06-22
CN102101623B CN102101623B (en) 2012-12-05

Family

ID=44154719

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200910201445 Active CN102101623B (en) 2009-12-18 2009-12-18 Method for transporting and lifting underground substation large-sized equipment

Country Status (1)

Country Link
CN (1) CN102101623B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102926799A (en) * 2012-10-24 2013-02-13 广东省工业设备安装公司重庆分公司 Large-scale equipment hoisting and transporting method for underground construction
CN103482038A (en) * 2013-09-24 2014-01-01 国网上海市电力公司 Water transportation method for large component
CN108119702A (en) * 2016-11-29 2018-06-05 中冶天工集团天津有限公司 A kind of auxiliary system and construction method of underground pipe gallery Pipe installing
CN109553008A (en) * 2018-12-07 2019-04-02 中联重科股份有限公司 Lifting equipment and lifting assembly

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1186751C (en) * 2003-02-11 2005-01-26 上海奥达光电子科技有限公司 Self-adapting system for managing traffic stream on roads and bridges
AT501062B1 (en) * 2004-06-04 2007-06-15 Katt Transp Gmbh METHOD FOR PROMOTING GOODS AND PLANT FOR IMPLEMENTING THE PROCESS
CN1741052A (en) * 2005-09-22 2006-03-01 上海交通大学 Vehicle stowage and path optimizing system

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102926799A (en) * 2012-10-24 2013-02-13 广东省工业设备安装公司重庆分公司 Large-scale equipment hoisting and transporting method for underground construction
CN102926799B (en) * 2012-10-24 2016-01-27 广东省工业设备安装公司重庆分公司 Underground construction main equipment hoisting transportation method
CN103482038A (en) * 2013-09-24 2014-01-01 国网上海市电力公司 Water transportation method for large component
CN103482038B (en) * 2013-09-24 2016-08-10 国网上海市电力公司 A kind of Water transportation method of big component
CN108119702A (en) * 2016-11-29 2018-06-05 中冶天工集团天津有限公司 A kind of auxiliary system and construction method of underground pipe gallery Pipe installing
CN109553008A (en) * 2018-12-07 2019-04-02 中联重科股份有限公司 Lifting equipment and lifting assembly

Also Published As

Publication number Publication date
CN102101623B (en) 2012-12-05

Similar Documents

Publication Publication Date Title
CN101429752B (en) Pier column prefabrication splicing building technology
CN201494438U (en) Simple and fast installation cableway for maintenance and rush repair of mountain pipeline
CN101831888B (en) 1200 tonner water conservancy aqueduct transportation and erection equipment
CN202899044U (en) Vierendeel box-shaped double-girder bridge crane
CN102101623B (en) Method for transporting and lifting underground substation large-sized equipment
CN107905116A (en) Construction method of large-span through type rigid tied steel arch bridge
CN106284083A (en) Pushing tow climbs shifting formula cable crane arch bridge hanging method
CN105484162B (en) Suspension bridge construction stiff girder secondary on the bank swings moving device and method
CN201280818Y (en) Traveler gantry nacelle
CN102808380B (en) Cable saddle transverse moving system and cable saddle transverse moving construction method
CN101476287A (en) Construction method for carrying large box girder by tire type portal jib crane
CN105673070A (en) Transport system for inclined shaft in tunnel construction and installation method of system
CN102587284B (en) Independent derrick mast and beam plate mounting method
CN110230261A (en) A kind of construction method of installation set a roof beam in place on the double-deck synchronous beam
CN205500610U (en) Handling system of low latitude group
CN104060592B (en) Method for 1/4 land territory preassembling and overwater dispersion of large cylinder main grids of cellular steel sheet piles
CN201325826Y (en) Rock anchor beam hoisting device for underground power house
CN102926388A (en) Earth moving device and method for deep foundation pit excavation
CN110616638A (en) Bracket-free hoisting method for steel box girder in shallow beach area of suspension bridge
CN209290620U (en) Large-scale component lifting transport installation integrated ship
CN116142832A (en) Roll-on method for loading SPMT for portal crane
CN106320181A (en) Construction method for installing precast beam slabs by adopting bridge girder erection machine
CN115744675A (en) Large member hoisting equipment for offshore shallow water area and hoisting method thereof
CN202148145U (en) Floor-rail-type gantry crane
CN108018778A (en) The cat road rope in navigable waters does not set up trailer system and cat road rope fast erecting method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: STATE GRID CORPORATION OF CHINA

Free format text: FORMER OWNER: SHANGHAI ELECTRIC POWER COMPANY GRID CONSTRUCTION COMPANY

Effective date: 20121212

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20121212

Address after: 200122 Shanghai City, Pudong New Area source deep road, No. 1122

Patentee after: Shanghai Electric Power Corporation

Patentee after: State Grid Corporation of China

Address before: 200122 Shanghai City, Pudong New Area source deep road, No. 1122

Patentee before: Shanghai Electric Power Corporation

Patentee before: Grid Construction Company of Shanghai Municipal Electric Power Company