CN102097828A - 一种基于功率预测的风电优化调度方法 - Google Patents
一种基于功率预测的风电优化调度方法 Download PDFInfo
- Publication number
- CN102097828A CN102097828A CN2010106143104A CN201010614310A CN102097828A CN 102097828 A CN102097828 A CN 102097828A CN 2010106143104 A CN2010106143104 A CN 2010106143104A CN 201010614310 A CN201010614310 A CN 201010614310A CN 102097828 A CN102097828 A CN 102097828A
- Authority
- CN
- China
- Prior art keywords
- wind
- power
- electricity generation
- powered electricity
- prediction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims abstract description 28
- 238000010248 power generation Methods 0.000 claims abstract description 17
- 230000005611 electricity Effects 0.000 claims description 135
- 238000005457 optimization Methods 0.000 claims description 10
- 230000010354 integration Effects 0.000 claims description 5
- 150000001875 compounds Chemical class 0.000 claims description 3
- 238000005315 distribution function Methods 0.000 claims description 3
- 238000009472 formulation Methods 0.000 claims description 3
- 239000000203 mixture Substances 0.000 claims description 3
- 238000012544 monitoring process Methods 0.000 claims description 2
- 230000029087 digestion Effects 0.000 abstract 1
- 238000007726 management method Methods 0.000 description 4
- 230000007812 deficiency Effects 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 238000009434 installation Methods 0.000 description 2
- 230000003319 supportive effect Effects 0.000 description 2
- TVZRAEYQIKYCPH-UHFFFAOYSA-N 3-(trimethylsilyl)propane-1-sulfonic acid Chemical compound C[Si](C)(C)CCCS(O)(=O)=O TVZRAEYQIKYCPH-UHFFFAOYSA-N 0.000 description 1
- 238000004458 analytical method Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000004891 communication Methods 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 230000005684 electric field Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000007613 environmental effect Effects 0.000 description 1
- 238000010438 heat treatment Methods 0.000 description 1
- 230000001105 regulatory effect Effects 0.000 description 1
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/70—Wind energy
- Y02E10/76—Power conversion electric or electronic aspects
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E40/00—Technologies for an efficient electrical power generation, transmission or distribution
- Y02E40/70—Smart grids as climate change mitigation technology in the energy generation sector
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S10/00—Systems supporting electrical power generation, transmission or distribution
- Y04S10/12—Monitoring or controlling equipment for energy generation units, e.g. distributed energy generation [DER] or load-side generation
- Y04S10/123—Monitoring or controlling equipment for energy generation units, e.g. distributed energy generation [DER] or load-side generation the energy generation units being or involving renewable energy sources
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S10/00—Systems supporting electrical power generation, transmission or distribution
- Y04S10/50—Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications
Abstract
Description
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201010614310.4A CN102097828B (zh) | 2010-12-30 | 2010-12-30 | 一种基于功率预测的风电优化调度方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201010614310.4A CN102097828B (zh) | 2010-12-30 | 2010-12-30 | 一种基于功率预测的风电优化调度方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102097828A true CN102097828A (zh) | 2011-06-15 |
CN102097828B CN102097828B (zh) | 2014-03-12 |
Family
ID=44130745
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201010614310.4A Active CN102097828B (zh) | 2010-12-30 | 2010-12-30 | 一种基于功率预测的风电优化调度方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102097828B (zh) |
Cited By (37)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102496962A (zh) * | 2011-12-31 | 2012-06-13 | 清华大学 | 调峰调频约束下电力系统可消纳风电的辨识与控制方法 |
CN102510063A (zh) * | 2011-11-07 | 2012-06-20 | 国电南瑞科技股份有限公司 | 互联电网分级调频控制方法 |
CN102510093A (zh) * | 2011-12-19 | 2012-06-20 | 国网电力科学研究院 | 基于功率预测信息的风电场有功功率控制方法 |
CN102545707A (zh) * | 2012-01-11 | 2012-07-04 | 云南电力试验研究院(集团)有限公司电力研究院 | 以发电单元为基本预测单元的发电功率预测方法及系统 |
CN102738835A (zh) * | 2012-07-17 | 2012-10-17 | 太原电力高等专科学校 | 基于多智能体的“风-火-水”协同调度方法 |
CN103138294A (zh) * | 2013-03-25 | 2013-06-05 | 国电联合动力技术有限公司 | 一种大型风电机组在微电网系统中的运行控制方法 |
CN103151804A (zh) * | 2013-03-18 | 2013-06-12 | 甘肃省电力公司 | 一种计及风电主动控制能力的风电备用量确定方法 |
CN103208813A (zh) * | 2013-01-21 | 2013-07-17 | 云南电网公司电网规划研究中心 | 一种准确计及风电影响的电力系统日调峰能力评估方法 |
CN103219751A (zh) * | 2013-05-08 | 2013-07-24 | 东南大学 | 一种集群风电场有功功率控制方法 |
CN103295077A (zh) * | 2013-05-17 | 2013-09-11 | 高文忠 | 一种考虑预测误差分布特性的风电场集群调度方法 |
WO2013174146A1 (zh) * | 2012-05-23 | 2013-11-28 | 国家电网公司 | 以降低网损为目标的多约束条件下风电送出功率优化评估方法 |
CN103544534A (zh) * | 2013-09-23 | 2014-01-29 | 侯丰花 | 一种基于2g网络风电预测方法 |
CN103762620A (zh) * | 2013-05-10 | 2014-04-30 | 南京南瑞集团公司 | 基于预测调节性能和安全约束的新能源并网功率控制方法 |
CN104036337A (zh) * | 2013-03-04 | 2014-09-10 | 中国电力科学研究院 | 基于预测不确定度和净空出力的光伏发电优化调度方法 |
CN104143839A (zh) * | 2013-11-06 | 2014-11-12 | 国家电网公司 | 基于功率预测的风电场集群限出力有功功率分配方法 |
CN104283236A (zh) * | 2014-10-25 | 2015-01-14 | 国网重庆武隆县供电有限责任公司 | 一种风光储能并网发电智能优化调度方法 |
CN104573858A (zh) * | 2014-12-26 | 2015-04-29 | 国家电网公司 | 一种电网负荷的预测和调控方法 |
CN104821600A (zh) * | 2015-05-14 | 2015-08-05 | 南通大学 | 分布式风光互补发电系统灵活并网调度算法 |
CN104934996A (zh) * | 2015-07-12 | 2015-09-23 | 国家电网公司 | 一种匹配风电接纳可行域储能系统的控制方法 |
CN105164886A (zh) * | 2013-06-19 | 2015-12-16 | 艾思玛太阳能技术股份公司 | 光伏安装装置中的动态功率分配 |
CN105576825A (zh) * | 2015-11-30 | 2016-05-11 | 深圳合纵能源技术有限公司 | 一种含多种可再生能源的智能微电网能量管理系统及方法 |
CN105656078A (zh) * | 2016-01-25 | 2016-06-08 | 华北电力科学研究院有限责任公司 | 风电场发电裕度的分配方法及系统 |
CN106532693A (zh) * | 2016-12-12 | 2017-03-22 | 西安交通大学 | 考虑直流功率控制的电力系统备用紧急调用优化方法 |
CN107420261A (zh) * | 2017-09-19 | 2017-12-01 | 江苏安纳泰克能源服务有限公司 | 风力发电机的控制方法 |
CN107563564A (zh) * | 2017-09-14 | 2018-01-09 | 重庆大学 | 一种风电场调度过程的效能评估方法 |
CN108155666A (zh) * | 2017-12-29 | 2018-06-12 | 湖南优利泰克自动化系统有限公司 | 一种风电场有功调控方法 |
CN108155675A (zh) * | 2017-12-19 | 2018-06-12 | 国电南瑞南京控制系统有限公司 | 基于预测信息与运行状态的风电场群功率优化调度方法 |
CN108695845A (zh) * | 2018-05-28 | 2018-10-23 | 华润电力风能(汕头潮南)有限公司 | 一种风电机组可利用率的计算方法及系统 |
CN109193791A (zh) * | 2018-11-10 | 2019-01-11 | 东北电力大学 | 一种基于改进shapley值的风电汇聚趋势性分状态量化方法 |
CN109474003A (zh) * | 2018-09-12 | 2019-03-15 | 国网浙江省电力有限公司嘉兴供电公司 | 一种接入风电场的区域电网优化调度方法 |
CN110197321A (zh) * | 2019-04-17 | 2019-09-03 | 无锡利信能源科技有限公司 | 一种基于多机组供热单元协同供热安全经济调度的方法 |
CN111216586A (zh) * | 2020-03-28 | 2020-06-02 | 东南大学 | 考虑风电消纳的居民小区电动汽车有序充电控制方法 |
CN111797496A (zh) * | 2020-05-21 | 2020-10-20 | 中国电力科学研究院有限公司 | 一种新能源场站发电出力时间序列构建方法和装置 |
CN112350371A (zh) * | 2020-10-26 | 2021-02-09 | 国网天津市电力公司电力科学研究院 | 一种基于公平原则的风电场分阶段有功调度方法及系统 |
CN112467801A (zh) * | 2020-10-21 | 2021-03-09 | 中国电力科学研究院有限公司 | 一种新能源场站日内发电计划优化方法和系统 |
CN113626767A (zh) * | 2021-08-02 | 2021-11-09 | 中节能风力发电股份有限公司 | 一种风机限电识别方法、系统、设备和存储介质 |
CN114172157A (zh) * | 2021-07-28 | 2022-03-11 | 国网冀北电力有限公司电力科学研究院 | 一种新能源和数据中心增量负荷调度方法及装置 |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104037814B (zh) * | 2014-06-27 | 2015-10-28 | 大连理工大学 | 一种分段平滑法与邻域搜索算法相结合的多电网调峰负荷分配方法 |
CN107276221B (zh) * | 2017-05-23 | 2019-12-03 | 中国农业大学 | 一种优化风电消纳的电力系统调度方法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20020103745A1 (en) * | 2000-12-29 | 2002-08-01 | Abb Ab | System, method and computer program product for enhancing commercial value of electrical power produced from a renewable energy power production facility |
JP2003083229A (ja) * | 2001-09-06 | 2003-03-19 | Mitsubishi Heavy Ind Ltd | 風力発電制御装置およびその制御方法 |
CN101706335A (zh) * | 2009-11-11 | 2010-05-12 | 华南理工大学 | 一种基于遗传算法优化bp神经网络的风电功率预测方法 |
CN101931241A (zh) * | 2010-09-21 | 2010-12-29 | 许继集团有限公司 | 风电场并网协调控制方法 |
-
2010
- 2010-12-30 CN CN201010614310.4A patent/CN102097828B/zh active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20020103745A1 (en) * | 2000-12-29 | 2002-08-01 | Abb Ab | System, method and computer program product for enhancing commercial value of electrical power produced from a renewable energy power production facility |
JP2003083229A (ja) * | 2001-09-06 | 2003-03-19 | Mitsubishi Heavy Ind Ltd | 風力発電制御装置およびその制御方法 |
CN101706335A (zh) * | 2009-11-11 | 2010-05-12 | 华南理工大学 | 一种基于遗传算法优化bp神经网络的风电功率预测方法 |
CN101931241A (zh) * | 2010-09-21 | 2010-12-29 | 许继集团有限公司 | 风电场并网协调控制方法 |
Cited By (61)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102510063B (zh) * | 2011-11-07 | 2013-11-20 | 国电南瑞科技股份有限公司 | 互联电网分级调频控制方法 |
CN102510063A (zh) * | 2011-11-07 | 2012-06-20 | 国电南瑞科技股份有限公司 | 互联电网分级调频控制方法 |
CN102510093A (zh) * | 2011-12-19 | 2012-06-20 | 国网电力科学研究院 | 基于功率预测信息的风电场有功功率控制方法 |
CN102510093B (zh) * | 2011-12-19 | 2014-04-30 | 国网电力科学研究院 | 基于功率预测信息的风电场有功功率控制方法 |
CN102496962B (zh) * | 2011-12-31 | 2013-02-13 | 清华大学 | 调峰调频约束下电力系统可消纳风电的辨识与控制方法 |
CN102496962A (zh) * | 2011-12-31 | 2012-06-13 | 清华大学 | 调峰调频约束下电力系统可消纳风电的辨识与控制方法 |
CN102545707A (zh) * | 2012-01-11 | 2012-07-04 | 云南电力试验研究院(集团)有限公司电力研究院 | 以发电单元为基本预测单元的发电功率预测方法及系统 |
CN102545707B (zh) * | 2012-01-11 | 2016-04-20 | 云南电力试验研究院(集团)有限公司电力研究院 | 以发电单元为基本预测单元的发电功率预测方法及系统 |
WO2013174146A1 (zh) * | 2012-05-23 | 2013-11-28 | 国家电网公司 | 以降低网损为目标的多约束条件下风电送出功率优化评估方法 |
CN102738835A (zh) * | 2012-07-17 | 2012-10-17 | 太原电力高等专科学校 | 基于多智能体的“风-火-水”协同调度方法 |
CN102738835B (zh) * | 2012-07-17 | 2014-08-20 | 山西大学 | 基于多智能体的“风-火-水”协同调度方法 |
CN103208813A (zh) * | 2013-01-21 | 2013-07-17 | 云南电网公司电网规划研究中心 | 一种准确计及风电影响的电力系统日调峰能力评估方法 |
CN103208813B (zh) * | 2013-01-21 | 2015-03-25 | 云南电网公司电网规划研究中心 | 一种准确计及风电影响的电力系统日调峰能力评估方法 |
CN104036337A (zh) * | 2013-03-04 | 2014-09-10 | 中国电力科学研究院 | 基于预测不确定度和净空出力的光伏发电优化调度方法 |
CN103151804B (zh) * | 2013-03-18 | 2018-08-21 | 国家电网公司 | 一种计及风电主动控制能力的风电备用量确定方法 |
CN103151804A (zh) * | 2013-03-18 | 2013-06-12 | 甘肃省电力公司 | 一种计及风电主动控制能力的风电备用量确定方法 |
CN103138294A (zh) * | 2013-03-25 | 2013-06-05 | 国电联合动力技术有限公司 | 一种大型风电机组在微电网系统中的运行控制方法 |
CN103138294B (zh) * | 2013-03-25 | 2015-07-15 | 国电联合动力技术有限公司 | 一种大型风电机组在微电网系统中的运行控制方法 |
CN103219751A (zh) * | 2013-05-08 | 2013-07-24 | 东南大学 | 一种集群风电场有功功率控制方法 |
CN103219751B (zh) * | 2013-05-08 | 2015-04-29 | 东南大学 | 一种集群风电场有功功率控制方法 |
CN103762620B (zh) * | 2013-05-10 | 2015-12-02 | 南京南瑞集团公司 | 基于预测调节性能和安全约束的新能源并网功率控制方法 |
CN103762620A (zh) * | 2013-05-10 | 2014-04-30 | 南京南瑞集团公司 | 基于预测调节性能和安全约束的新能源并网功率控制方法 |
CN103295077B (zh) * | 2013-05-17 | 2016-08-03 | 高文忠 | 一种考虑预测误差分布特性的风电场集群调度方法 |
CN103295077A (zh) * | 2013-05-17 | 2013-09-11 | 高文忠 | 一种考虑预测误差分布特性的风电场集群调度方法 |
CN105164886A (zh) * | 2013-06-19 | 2015-12-16 | 艾思玛太阳能技术股份公司 | 光伏安装装置中的动态功率分配 |
CN103544534A (zh) * | 2013-09-23 | 2014-01-29 | 侯丰花 | 一种基于2g网络风电预测方法 |
CN104143839B (zh) * | 2013-11-06 | 2016-03-09 | 国家电网公司 | 基于功率预测的风电场集群限出力有功功率分配方法 |
CN104143839A (zh) * | 2013-11-06 | 2014-11-12 | 国家电网公司 | 基于功率预测的风电场集群限出力有功功率分配方法 |
CN104283236A (zh) * | 2014-10-25 | 2015-01-14 | 国网重庆武隆县供电有限责任公司 | 一种风光储能并网发电智能优化调度方法 |
CN104573858A (zh) * | 2014-12-26 | 2015-04-29 | 国家电网公司 | 一种电网负荷的预测和调控方法 |
CN104573858B (zh) * | 2014-12-26 | 2018-04-17 | 国家电网公司 | 一种电网负荷的预测和调控方法 |
CN104821600A (zh) * | 2015-05-14 | 2015-08-05 | 南通大学 | 分布式风光互补发电系统灵活并网调度算法 |
CN104934996A (zh) * | 2015-07-12 | 2015-09-23 | 国家电网公司 | 一种匹配风电接纳可行域储能系统的控制方法 |
CN105576825A (zh) * | 2015-11-30 | 2016-05-11 | 深圳合纵能源技术有限公司 | 一种含多种可再生能源的智能微电网能量管理系统及方法 |
CN105656078A (zh) * | 2016-01-25 | 2016-06-08 | 华北电力科学研究院有限责任公司 | 风电场发电裕度的分配方法及系统 |
CN106532693A (zh) * | 2016-12-12 | 2017-03-22 | 西安交通大学 | 考虑直流功率控制的电力系统备用紧急调用优化方法 |
CN106532693B (zh) * | 2016-12-12 | 2019-04-12 | 西安交通大学 | 考虑直流功率控制的电力系统备用紧急调用优化方法 |
CN107563564A (zh) * | 2017-09-14 | 2018-01-09 | 重庆大学 | 一种风电场调度过程的效能评估方法 |
CN107420261B (zh) * | 2017-09-19 | 2019-04-12 | 江苏安纳泰克能源服务有限公司 | 风力发电机的控制方法 |
CN107420261A (zh) * | 2017-09-19 | 2017-12-01 | 江苏安纳泰克能源服务有限公司 | 风力发电机的控制方法 |
CN108155675A (zh) * | 2017-12-19 | 2018-06-12 | 国电南瑞南京控制系统有限公司 | 基于预测信息与运行状态的风电场群功率优化调度方法 |
CN108155675B (zh) * | 2017-12-19 | 2019-12-31 | 国电南瑞南京控制系统有限公司 | 基于预测信息与运行状态的风电场群功率优化调度方法 |
CN108155666A (zh) * | 2017-12-29 | 2018-06-12 | 湖南优利泰克自动化系统有限公司 | 一种风电场有功调控方法 |
CN108155666B (zh) * | 2017-12-29 | 2020-12-29 | 湖南优利泰克自动化系统有限公司 | 一种风电场有功调控方法 |
CN108695845A (zh) * | 2018-05-28 | 2018-10-23 | 华润电力风能(汕头潮南)有限公司 | 一种风电机组可利用率的计算方法及系统 |
CN109474003A (zh) * | 2018-09-12 | 2019-03-15 | 国网浙江省电力有限公司嘉兴供电公司 | 一种接入风电场的区域电网优化调度方法 |
CN109474003B (zh) * | 2018-09-12 | 2022-02-15 | 国网浙江省电力有限公司嘉兴供电公司 | 一种接入风电场的区域电网优化调度方法 |
CN109193791A (zh) * | 2018-11-10 | 2019-01-11 | 东北电力大学 | 一种基于改进shapley值的风电汇聚趋势性分状态量化方法 |
CN109193791B (zh) * | 2018-11-10 | 2021-05-25 | 东北电力大学 | 一种基于改进shapley值的风电汇聚趋势性分状态量化方法 |
CN110197321B (zh) * | 2019-04-17 | 2021-06-22 | 无锡利信能源科技有限公司 | 一种基于多机组供热单元协同供热安全经济调度的方法 |
CN110197321A (zh) * | 2019-04-17 | 2019-09-03 | 无锡利信能源科技有限公司 | 一种基于多机组供热单元协同供热安全经济调度的方法 |
CN111216586A (zh) * | 2020-03-28 | 2020-06-02 | 东南大学 | 考虑风电消纳的居民小区电动汽车有序充电控制方法 |
CN111216586B (zh) * | 2020-03-28 | 2022-07-08 | 东南大学 | 考虑风电消纳的居民小区电动汽车有序充电控制方法 |
CN111797496A (zh) * | 2020-05-21 | 2020-10-20 | 中国电力科学研究院有限公司 | 一种新能源场站发电出力时间序列构建方法和装置 |
CN111797496B (zh) * | 2020-05-21 | 2023-05-23 | 中国电力科学研究院有限公司 | 一种新能源场站发电出力时间序列构建方法和装置 |
CN112467801A (zh) * | 2020-10-21 | 2021-03-09 | 中国电力科学研究院有限公司 | 一种新能源场站日内发电计划优化方法和系统 |
CN112350371A (zh) * | 2020-10-26 | 2021-02-09 | 国网天津市电力公司电力科学研究院 | 一种基于公平原则的风电场分阶段有功调度方法及系统 |
CN112350371B (zh) * | 2020-10-26 | 2023-07-28 | 国网天津市电力公司电力科学研究院 | 一种基于公平原则的风电场分阶段有功调度方法及系统 |
CN114172157A (zh) * | 2021-07-28 | 2022-03-11 | 国网冀北电力有限公司电力科学研究院 | 一种新能源和数据中心增量负荷调度方法及装置 |
CN114172157B (zh) * | 2021-07-28 | 2024-02-13 | 国网冀北电力有限公司电力科学研究院 | 一种新能源和数据中心增量负荷调度方法及装置 |
CN113626767A (zh) * | 2021-08-02 | 2021-11-09 | 中节能风力发电股份有限公司 | 一种风机限电识别方法、系统、设备和存储介质 |
Also Published As
Publication number | Publication date |
---|---|
CN102097828B (zh) | 2014-03-12 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102097828B (zh) | 一种基于功率预测的风电优化调度方法 | |
CN108092324B (zh) | 一种风电参与调峰调频的agc控制系统和控制方法 | |
CN101752903B (zh) | 一种时序递进式电力调度方法 | |
CN106505635B (zh) | 弃风最小的有功调度模型及调度系统 | |
CN103050989B (zh) | 一种集群风电场有功功率智能控制系统和方法 | |
CN106384168A (zh) | 针对特性各异电源的多目标协调优化调度模型 | |
CN104933516A (zh) | 一种多时间尺度的电力系统鲁棒调度系统设计方法 | |
CN103997039B (zh) | 基于概率区间预测的计及风电接纳的旋转备用区间预测方法 | |
CN105046395A (zh) | 一种含多类型新能源的电力系统日内滚动计划编制方法 | |
CN106160000B (zh) | 一种分调-省调两级协调的风电增发控制方法 | |
CN106682808A (zh) | 在线滚动优化调度模型 | |
US20230268742A1 (en) | A method for quantification of flexibility requirements and coordinated optimization of a hydro-wind-solar multi-energy complementary systems | |
CN106602613B (zh) | 一种省地两级调度断面协调控制方法 | |
CN102593874A (zh) | 一种用于微电网的能量调度方法 | |
CN110443401A (zh) | 一种智能电网的优化调度方法 | |
CN102003349A (zh) | 风电受限状态下的大规模风电有功优化方法 | |
CN102184468A (zh) | 间歇性能源发电有功调度方法 | |
CN105305485A (zh) | 一种消纳大规模间歇性能源的安全约束经济调度方法 | |
CN117077974A (zh) | 虚拟电厂资源优化调度方法、装置、设备及存储介质 | |
CN102904248A (zh) | 基于风电出力不确定性集合的电力系统调度方法 | |
CN104036337A (zh) | 基于预测不确定度和净空出力的光伏发电优化调度方法 | |
CN107947246A (zh) | 一种考虑调频增发的风电发电指标分配及增发评估方法 | |
Tian et al. | Coordinated RES and ESS Planning Framework Considering Financial Incentives Within Centralized Electricity Market | |
CN116014797A (zh) | 一种配网新能源接纳能力提升的评估方法 | |
CN110929968A (zh) | 一种智慧城市多能源联合供给综合调控方法及系统 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
ASS | Succession or assignment of patent right |
Owner name: STATE ELECTRIC NET CROP. Effective date: 20130809 |
|
C41 | Transfer of patent application or patent right or utility model | ||
TA01 | Transfer of patent application right |
Effective date of registration: 20130809 Address after: 100192 Beijing city Haidian District Qinghe small Camp Road No. 15 Applicant after: China Electric Power Research Institute Applicant after: State Grid Corporation of China Address before: 100192 Beijing city Haidian District Qinghe small Camp Road No. 15 Applicant before: China Electric Power Research Institute |
|
GR01 | Patent grant | ||
GR01 | Patent grant |