CN102073931A - Production plan adjustment method and device - Google Patents

Production plan adjustment method and device Download PDF

Info

Publication number
CN102073931A
CN102073931A CN2010106174526A CN201010617452A CN102073931A CN 102073931 A CN102073931 A CN 102073931A CN 2010106174526 A CN2010106174526 A CN 2010106174526A CN 201010617452 A CN201010617452 A CN 201010617452A CN 102073931 A CN102073931 A CN 102073931A
Authority
CN
China
Prior art keywords
supply
demand
data
schedule
user
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2010106174526A
Other languages
Chinese (zh)
Inventor
罗涛
高峰霞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yonyou Software Co Ltd
Original Assignee
Yonyou Software Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yonyou Software Co Ltd filed Critical Yonyou Software Co Ltd
Priority to CN2010106174526A priority Critical patent/CN102073931A/en
Publication of CN102073931A publication Critical patent/CN102073931A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • General Factory Administration (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention provides a production plan adjustment method, which comprises the following steps of: 102, selecting a production plan serving as demand and a production plan serving as supply; 104, selecting data in the demand and data in the supply for matching according to the preset condition; and 106, when the data in the demand and the data in the supply are not matched, adjusting the data in the demand or the data in the supply, so that the data in the demand and the data in the supply are matched. The invention also provides a production plan adjustment device. By the method and the device, a user can conveniently check a contrast relationship between the supply and the demand and adjust the production plan according to the contrast relationship, so that synergism among plans organized by the user according to different latitudes is supported, and the work efficiency of the user is improved.

Description

Production schedule method of adjustment and device
Technical field
The present invention relates to the Enterprise Resources Optimization system, more specifically, relate to production schedule method of adjustment and device in the enterprise production management.
Background technology
In the manufacturing production of assembling, assembly technology is often inconsistent with manufacturing BOM (Bill Of Materials, Bill of Material (BOM) are called for short BOM).May also not come out during such as the machine work technology of general assembly, the parts plan of going into operation need launch according to the BOM structure, and the assembling plan will rely on assembly production orders to launch, and adjusts parts on-stream times with this, quickens or postpones the parts manufacturing.And assembling itself also can reasonably be adjusted assemble sequence according to neat cover situation.Assemble and make relatively independently and carry out, coordinate mutually again.Existing software systems can not form the production schedule of oneself substantially according to a plurality of different latitude by department's pushing-type, specify the demand that is intended to be of certain latitude then, another latitude be intended to be supply, the production schedule of department is made pull-type coupling according to demand, form collaborative operation deck watch, according to the supply and demand ratio his-and-hers watches, the function of that side's the production schedule is changed in decision then.
So-called department pushing-type is meant by MRP (Material Requirement Planning, MRP are called for short MRP) and forms the production schedule or form the assembling plan with reference to operation.
Therefore, need a kind of production schedule method of adjustment, can make the user according to the operation deck watch who inquires, the supply and demand ratio of adjusting both sides is to relation, support the user according to working in coordination with between the plan of different latitude establishment, improve user's work efficiency, reach inner the reaching of unified department and organize multidisciplinary collaborative purpose of working out a production plan more.
Summary of the invention
In view of this, technical matters to be solved by this invention is, a kind of production schedule method of adjustment is provided, can make the user according to the operation deck watch who inquires, the supply and demand ratio of adjusting both sides is to relation, support the user according to working in coordination with between the plan of different latitude establishment, improve user's work efficiency, reach unified department inside and organize multidisciplinary collaborative purpose of working out a production plan more.
The invention provides a kind of production schedule method of adjustment, comprising: step 102, select the production schedule as demand, and as the production schedule of supplying; Step 104 according to preset condition, selects data, the data in the described supply in the described demand to mate; Step 106 when the data in data in described demand and the described supply do not match, is adjusted data in the described demand or the data in the described supply, so that the data in data in the described demand and the described supply match each other.By this technical scheme, the relativity that can make the user check supply and demand easily, and according to the relativity adjustment production schedule, working in coordination with between the plan of support user different latitude establishment improves user's work efficiency.
In technique scheme, preferably, in described step 104, the data of described demand are write the demand schedule that presets, the data of described supply are write supply schedule, by described demand schedule, described supply schedule to carry out the data in the described demand, the coupling of data in the described supply.Like this, the user can inquire about the information of supply and demand easily, and realizes the adjustment of the production schedule by the supply and demand contrast.
In technique scheme, preferably, in described step 104, can also be according to the default described condition of the field in described demand schedule, the described supply schedule.Like this, the user can be provided with the matching condition of supply and demand according to the demand of actual production.
In technique scheme, preferably, in described step 106, when adjusting the data in the described demand, with the maximum date of supply of described supply or user's named date Date Required as described demand, and with the quantity of all supply quantity sums of described supply or the user's appointment quantity required as described demand.Like this, can reach the production schedule, by the pull-type function that forms the production schedule of supplier or party in request according to pushing-type formation self.
In technique scheme, preferably, in described step 106, when adjusting the data in the described supply, with the Date Required of described demand or user's named date date of supply as described supply, and with the quantity of the quantity required of described demand or the user's appointment supply quantity as described supply.Like this, can reach the production schedule, by the pull-type function that forms the production schedule of supplier or party in request according to pushing-type formation self.
By production schedule method of adjustment provided by the invention, can make the user according to the operation deck watch who inquires, the supply and demand ratio of adjusting both sides is to relation, support the user according to working in coordination with between the plan of different latitude establishment, reach the production schedule according to pushing-type formation self, by the pull-type function that forms the production schedule of supplier or party in request, improve user's work efficiency, reach inner the reaching of unified department and organize multidisciplinary collaborative purpose of working out a production plan more.
The present invention also provides a kind of production schedule adjusting gear, comprising: select module, select the production schedule as demand, and as the production schedule of supplying; Matching module according to preset condition, selects data, the data in the described supply in the described demand to mate; Adjusting module when the data in data in described demand and the described supply do not match, is adjusted data in the described demand or the data in the described supply, so that the data in data in the described demand and the described supply match each other.By this technical scheme, the relativity that can make the user check supply and demand easily, and according to the relativity adjustment production schedule, working in coordination with between the plan of support user different latitude establishment improves user's work efficiency.
In technique scheme, preferably, described matching module writes the demand schedule that presets with the data of described demand, and the data of described supply are write supply schedule, by described demand schedule, described supply schedule to carry out the data in the described demand, the coupling of data in the described supply.Like this, the user can inquire about the information of supply and demand easily, and realizes the adjustment of the production schedule by the supply and demand contrast.
In technique scheme, preferably, can also comprise: the condition setting module, according to the default described condition of the field in described demand schedule, the described supply schedule.Like this, the user can be provided with the matching condition of supply and demand according to the demand of actual production.
In technique scheme, preferably, when described adjusting module is adjusted data in the described demand, with the maximum date of supply of described supply or user's named date Date Required as described demand, and with the quantity of all supply quantity sums of described supply or the user's appointment quantity required as described demand.Like this, can reach the production schedule, by the pull-type function that forms the production schedule of supplier or party in request according to pushing-type formation self.
In technique scheme, preferably, when described adjusting module is adjusted data in the described supply, with the Date Required of described demand or user's named date date of supply as described supply, and with the quantity of the quantity required of described demand or the user's appointment supply quantity as described supply.Like this, can reach the production schedule, by the pull-type function that forms the production schedule of supplier or party in request according to pushing-type formation self.
By production schedule adjusting gear provided by the invention, can make the user according to the operation deck watch who inquires, the supply and demand ratio of adjusting both sides is to relation, support the user according to working in coordination with between the plan of different latitude establishment, reach the production schedule according to pushing-type formation self, by the pull-type function that forms the production schedule of supplier or party in request, improve user's work efficiency, reach inner the reaching of unified department and organize multidisciplinary collaborative purpose of working out a production plan more.
Description of drawings
Fig. 1 shows the process flow diagram of production schedule method of adjustment according to an embodiment of the invention;
Fig. 2 shows the block diagram of production schedule adjusting gear according to an embodiment of the invention;
Fig. 3 shows the operational flowchart of production schedule adjusting gear according to an embodiment of the invention;
Fig. 4 shows the work synoptic diagram of production schedule adjusting gear according to an embodiment of the invention.
Embodiment
In order more to be expressly understood above-mentioned purpose of the present invention, feature and advantage, the present invention is further described in detail below in conjunction with the drawings and specific embodiments.
Set forth a lot of details in the following description so that fully understand the present invention, still, the present invention can also adopt other to be different from other modes described here and implement, and therefore, the present invention is not limited to the restriction of following public specific embodiment.
Fig. 1 shows the process flow diagram of production schedule method of adjustment according to an embodiment of the invention.
As shown in Figure 1, the invention provides and the invention provides a kind of production schedule method of adjustment, comprising: step 102, select the production schedule as demand, and as the production schedule of supplying; Step 104 according to preset condition, selects data, the data in the described supply in the described demand to mate; Step 106 when the data in data in described demand and the described supply do not match, is adjusted data in the described demand or the data in the described supply, so that the data in data in the described demand and the described supply match each other.By this technical scheme, the relativity that can make the user check supply and demand easily, and according to the relativity adjustment production schedule, working in coordination with between the plan of support user different latitude establishment improves user's work efficiency.
In technique scheme, in described step 104, the data of described demand are write the demand schedule that presets, the data of described supply are write supply schedule, by described demand schedule, described supply schedule to carry out the data in the described demand, the coupling of data in the described supply.Like this, the user can inquire about the information of supply and demand easily, and realizes the adjustment of the production schedule by the supply and demand contrast.
In technique scheme, in described step 104, can also be according to the default described condition of the field in described demand schedule, the described supply schedule.Like this, the user can be provided with the matching condition of supply and demand according to the demand of actual production.
In technique scheme, in described step 106, when adjusting the data in the described demand, with the maximum date of supply of described supply or user's named date Date Required as described demand, and with the quantity of all supply quantity sums of described supply or the user's appointment quantity required as described demand.Like this, can reach the production schedule, by the pull-type function that forms the production schedule of supplier or party in request according to pushing-type formation self.
In technique scheme, in described step 106, when adjusting the data in the described supply, with the Date Required of described demand or user's named date date of supply as described supply, and with the quantity of the quantity required of described demand or the user's appointment supply quantity as described supply.Like this, can reach the production schedule, by the pull-type function that forms the production schedule of supplier or party in request according to pushing-type formation self.
By production schedule method of adjustment provided by the invention, can make the user according to the operation deck watch who inquires, the supply and demand ratio of adjusting both sides is to relation, support the user according to working in coordination with between the plan of different latitude establishment, reach the production schedule according to pushing-type formation self, by the pull-type function that forms the production schedule of supplier or party in request, improve user's work efficiency, reach inner the reaching of unified department and organize multidisciplinary collaborative purpose of working out a production plan more.
Fig. 2 shows the block diagram of production schedule adjusting gear according to an embodiment of the invention.
As shown in Figure 2, the present invention also provides a kind of production schedule adjusting gear 200, comprising: select module 202, select the production schedule as demand, and as the production schedule of supplying; Matching module 204 according to preset condition, selects data, the data in the described supply in the described demand to mate; Adjusting module 206 when the data in data in described demand and the described supply do not match, is adjusted data in the described demand or the data in the described supply, so that the data in data in the described demand and the described supply match each other.By this technical scheme, the relativity that can make the user check supply and demand easily, and according to the relativity adjustment production schedule, working in coordination with between the plan of support user different latitude establishment improves user's work efficiency.
In technique scheme, described matching module 204 writes the demand schedule that presets with the data of described demand, the data of described supply are write supply schedule, by described demand schedule, described supply schedule to carry out the data in the described demand, the coupling of data in the described supply.Like this, the user can inquire about the information of supply and demand easily, and realizes the adjustment of the production schedule by the supply and demand contrast.
In technique scheme, can also comprise: condition setting module 208, according to the default described condition of the field in described demand schedule, the described supply schedule.Like this, the user can be provided with the matching condition of supply and demand according to the demand of actual production.
In technique scheme, during data that described adjusting module 206 is adjusted in the described demand, with the maximum date of supply of described supply or user's named date Date Required as described demand, and with the quantity of all supply quantity sums of described supply or the user's appointment quantity required as described demand.Like this, can reach the production schedule, by the pull-type function that forms the production schedule of supplier or party in request according to pushing-type formation self.
In technique scheme, during data that described adjusting module 206 is adjusted in the described supply, with the Date Required of described demand or user's named date date of supply as described supply, and with the quantity of the quantity required of described demand or the user's appointment supply quantity as described supply.Like this, can reach the production schedule, by the pull-type function that forms the production schedule of supplier or party in request according to pushing-type formation self.
By production schedule adjusting gear provided by the invention, can make the user according to the operation deck watch who inquires, the supply and demand ratio of adjusting both sides is to relation, support the user according to working in coordination with between the plan of different latitude establishment, reach the production schedule according to pushing-type formation self, by the pull-type function that forms the production schedule of supplier or party in request, improve user's work efficiency, reach inner the reaching of unified department and organize multidisciplinary collaborative purpose of working out a production plan more.
Fig. 3 shows the operational flowchart of production schedule adjusting gear according to an embodiment of the invention.
As shown in Figure 3, step 302, the user selects to participate in the demand and the supply production schedule of operation comparison;
Step 304, the user determines the selection of carrying out;
Step 306, the production schedule adjusting gear in the present embodiment are called the method for supply and demand contrast;
Step 308 is at first created supply and demand correlation data table;
Particularly, the structure of data table of using in the present embodiment can be as follows:
The demand gauge outfit
The supply gauge outfit
Title Data type Describe
Affiliated gauge outfit Gauge outfit Must typing
Capable number int Must typing
The supply tissue Tissue Can be empty
The supply production schedule The production schedule
Demand schedule is capable
Figure BDA0000042231920000072
Supply schedule is capable
Figure BDA0000042231920000081
Step 310, the production schedule adjusting gear of present embodiment are carried out the demonstration of supply and demand data after carrying out the supply and demand contrast;
Wherein, in the present embodiment device carry out supply and demand contrast concrete mode can for:
Wherein method comprises:
1) according to the user method that forms the operation deck watch is set, this method is according to material, quantity contrast demand and supply, mate according to order from front to back with reference to date of supply, it is capable that demand writes demand schedule, there have the supply of demand to write supply schedule to be capable, and it is capable to write down demand schedule therein, and it is capable that the supply of no demand only writes supply schedule, specific as follows:
Read plan of needs one by one and do following processing:
10, it is capable to create demand schedule;
20, in demand schedule is capable, write down quantity required;
30, according to the supply data of not supplying of material inquiry supply plan as other demands;
40, read the supply data that inquires from front to back one by one according to date of supply;
40.10 it is capable to create supply schedule according to supply data, it is capable to write down demand schedule therein;
40.20, supply is denoted as supply requirement;
40.30, rebuild quantity required;
40.40, if next bar supply is then read in quantity required>0;
50, read next bar demand;
60, the supply data of not supplying of inquiry supply plan as other demands;
70, read the supply data that inquires from front to back one by one according to date of supply;
70.10 it is capable to create supply schedule according to supply data, wherein, the table that does not write down demand is capable;
70.20, read next bar supply data;
All read and finish, preserve all data;
2) select the method for the change request production schedule according to the user, this method receives the demand data that user selects, and reads one by one, and uses the Date Required of the maximum date of supply of supply as demand;
3) select to change the method for supplying the production schedule according to the user, this method receives the supply data that user selects, and read one by one, and the Date Required of user demand is as the date of supply of supply;
Step 312, the user loads the supply and demand correlation data of reservation;
Step 314, the device of present embodiment are put down in writing the data that are retained in the tables of data for the user;
Step 316, the user edits the supply and demand correlation data:
Step 318, the user preserves after editing and finishing;
Step 320, the device of present embodiment is changed the data in the tables of data according to user's editor;
Step 322, the user need to select the correlation data of change;
Step 324, the user need to select change request still to need supply;
Step 326, the user determines, submits the selection of oneself to;
Step 328, the device of present embodiment calls variation according to user's selection;
Step 330 is according to different variations, to supply or demand change.
According to the technical scheme of present embodiment, the example of planning to adjust as shown in Figure 4.
As shown in Figure 4, the left side is the plan of going into operation, and the right side is corresponding schedule.Production schedule adjusting gear by present embodiment is intended to be supply with operation, with corresponding schedule as demand, carry out supply and demand contrast after, comparison result is recorded in the tables of data.
If select to become according to demand supply, just the plan of then going into operation is with as follows:
Material Date
B 1.1-2.28
C 1.1-2.28
D 2.16-3.15
E 2.16-3.15
If select according to supply change demand, just then corresponding schedule is followed as follows:
Material Date
B 1.1-2.28
C 1.1-2.28
D 2.1-2.28
E 2.1-2.28
At this moment, do not need to rerun MRP and regroup the adjustment production schedule.
By above technical scheme, can realize a kind of production schedule method of adjustment and device, support that the user changes the existing production schedule according to the adjusted production schedule, and preserve the user and adjust the result, reach the production schedule according to pushing-type formation self, by the pull-type function that forms the production schedule of supplier or party in request, support is according to working in coordination with between the different latitude establishment ground plan, improved user's work efficiency, reached inner the reaching of unified department and organized multidisciplinary collaborative purpose of working out a production plan more.
The above is the preferred embodiments of the present invention only, is not limited to the present invention, and for a person skilled in the art, the present invention can have various changes and variation.Within the spirit and principles in the present invention all, any modification of being done, be equal to replacement, improvement etc., all should be included within protection scope of the present invention.

Claims (10)

1. a production schedule method of adjustment is characterized in that, comprising:
Step 102 is selected the production schedule as demand, and as the production schedule of supplying;
Step 104 according to preset condition, selects data, the data in the described supply in the described demand to mate;
Step 106 when the data in data in described demand and the described supply do not match, is adjusted data in the described demand or the data in the described supply, so that the data in data in the described demand and the described supply match each other.
2. production schedule method of adjustment according to claim 1, it is characterized in that, in described step 104, the data of described demand are write the demand schedule that presets, the data of described supply are write supply schedule, by described demand schedule, described supply schedule to carry out the data in the described demand, the coupling of data in the described supply.
3. production schedule method of adjustment according to claim 1 is characterized in that, in described step 104, also according to the default described condition of the field in described demand schedule, the described supply schedule.
4. production schedule method of adjustment according to claim 1, it is characterized in that, in described step 106, when adjusting the data in the described demand, with the maximum date of supply of described supply or user's named date Date Required as described demand, and with the quantity of all supply quantity sums of described supply or the user's appointment quantity required as described demand.
5. according to each described production schedule method of adjustment in the claim 1 to 4, it is characterized in that, in described step 106, when adjusting the data in the described supply, with the Date Required of described demand or user's named date date of supply as described supply, and with the quantity of the quantity required of described demand or the user's appointment supply quantity as described supply.
6. a production schedule adjusting gear is characterized in that, comprising:
Select module, select the production schedule as demand, and as the production schedule of supplying;
Matching module according to preset condition, selects data, the data in the described supply in the described demand to mate;
Adjusting module when the data in data in described demand and the described supply do not match, is adjusted data in the described demand or the data in the described supply, so that the data in data in the described demand and the described supply match each other.
7. production schedule adjusting gear according to claim 6, it is characterized in that, described matching module writes the demand schedule that presets with the data of described demand, the data of described supply are write supply schedule, by described demand schedule, described supply schedule to carry out the data in the described demand, the coupling of data in the described supply.
8. production schedule adjusting gear according to claim 6 is characterized in that, also comprises:
The condition setting module is according to the default described condition of the field in described demand schedule, the described supply schedule.
9. production schedule adjusting gear according to claim 6, it is characterized in that, described adjusting module is adjusted the data in the described demand, with the maximum date of supply of described supply or user's named date Date Required as described demand, and with the quantity of all supply quantity sums of described supply or the user's appointment quantity required as described demand.
10. according to each described production schedule adjusting gear in the claim 6 to 9, it is characterized in that, when described adjusting module is adjusted data in the described supply, with the Date Required of described demand or user's named date date of supply as described supply, and with the quantity of the quantity required of described demand or the user's appointment supply quantity as described supply.
CN2010106174526A 2010-12-31 2010-12-31 Production plan adjustment method and device Pending CN102073931A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010106174526A CN102073931A (en) 2010-12-31 2010-12-31 Production plan adjustment method and device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010106174526A CN102073931A (en) 2010-12-31 2010-12-31 Production plan adjustment method and device

Publications (1)

Publication Number Publication Date
CN102073931A true CN102073931A (en) 2011-05-25

Family

ID=44032464

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010106174526A Pending CN102073931A (en) 2010-12-31 2010-12-31 Production plan adjustment method and device

Country Status (1)

Country Link
CN (1) CN102073931A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105279633A (en) * 2015-11-30 2016-01-27 用友网络科技股份有限公司 Automatic material supply-demand matching device and method
CN107977818A (en) * 2017-12-05 2018-05-01 北京小米移动软件有限公司 Supply data processing method, device, computing device and storage medium
JP2018128919A (en) * 2017-02-09 2018-08-16 三菱重工業株式会社 Work plan creation system, work plan creation method and work plan creation program
CN116125935A (en) * 2023-04-14 2023-05-16 成都飞机工业(集团)有限责任公司 Method, device, equipment and medium for constructing assembly process flow

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1584895A (en) * 2003-08-22 2005-02-23 台湾积体电路制造股份有限公司 Method and system of matching customer demand with production capacity, recording medium and management system
CN101894322A (en) * 2010-06-29 2010-11-24 用友软件股份有限公司 Product stock distribution method and device

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1584895A (en) * 2003-08-22 2005-02-23 台湾积体电路制造股份有限公司 Method and system of matching customer demand with production capacity, recording medium and management system
CN101894322A (en) * 2010-06-29 2010-11-24 用友软件股份有限公司 Product stock distribution method and device

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105279633A (en) * 2015-11-30 2016-01-27 用友网络科技股份有限公司 Automatic material supply-demand matching device and method
JP2018128919A (en) * 2017-02-09 2018-08-16 三菱重工業株式会社 Work plan creation system, work plan creation method and work plan creation program
CN107977818A (en) * 2017-12-05 2018-05-01 北京小米移动软件有限公司 Supply data processing method, device, computing device and storage medium
CN116125935A (en) * 2023-04-14 2023-05-16 成都飞机工业(集团)有限责任公司 Method, device, equipment and medium for constructing assembly process flow
CN116125935B (en) * 2023-04-14 2023-07-21 成都飞机工业(集团)有限责任公司 Method, device, equipment and medium for constructing assembly process flow

Similar Documents

Publication Publication Date Title
CN105389653A (en) Adaptive material requirement plan (MRP) calculation method
CN101329746A (en) System and method for automatically arranging production plan
US20130066677A1 (en) System and method for media and commerce management
US20090299811A1 (en) System and method for task management
US20020032492A1 (en) Data model for supply chain planning
Miller et al. A global supply chain profit maximization and transfer pricing model
CN102073931A (en) Production plan adjustment method and device
US20140257935A1 (en) System and method for media and commerce management
US20090150208A1 (en) Method and apparatus for integrated inventory and planning
US11790421B2 (en) Systems for generating, customizing, and automatedly e-mailing a request for quotation for fabricating a computer-modeled structure from within a CAD program
EP2610696A1 (en) Process design/production planning device
CN103095848A (en) Method of cloud folder arrangement and information interaction for enterprise client terminal
CN105512826A (en) Color matrix configuration method based on PLM platform
CN106325232A (en) Mold manufacture automatic production control system and method
CN101719243A (en) Method for processing production order, application server and group enterprise network system
EP2413272A1 (en) Capturing and processing data generatid in an erp interim phase
CN102982414A (en) Data generating device and method
CN105912343A (en) Desktop plug-in splitting method and mobile terminal
Kovács Novel supply chain concepts and optimization of virtual enterprises to reduce cost, increase productivity and boost competitiveness
CN102004972A (en) Method and device for altering work breakdown structure (WBS)
Gautam et al. Comparison of JIT with other industrial production approaches: a review
Nopparat et al. Resource consumption in additive manufacturing with a PSS approach
CN105975271A (en) Desktop plug-in merging method and mobile terminal
JP2004192169A (en) Business support system
US20230098485A1 (en) Systems and methods for efficiently generating reliable client billing quotes

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20110525