CN102064483A - Safety device for examining and repairing tower - Google Patents

Safety device for examining and repairing tower Download PDF

Info

Publication number
CN102064483A
CN102064483A CN2009102350992A CN200910235099A CN102064483A CN 102064483 A CN102064483 A CN 102064483A CN 2009102350992 A CN2009102350992 A CN 2009102350992A CN 200910235099 A CN200910235099 A CN 200910235099A CN 102064483 A CN102064483 A CN 102064483A
Authority
CN
China
Prior art keywords
bar
straight
cross bar
safety device
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2009102350992A
Other languages
Chinese (zh)
Inventor
高传文
刘志宏
华文健
阮玮
王国安
叶宁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
YANGZHOU JIANGDU POWER SUPPLY COMPANY JIANGSU ELECTRIC POWER Co
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
Yangzhou Power Supply Co of Jiangsu Electric Power Co
Original Assignee
JIANGDU POWER SUPPLY CORP JIANGSU POWER CORP
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGDU POWER SUPPLY CORP JIANGSU POWER CORP filed Critical JIANGDU POWER SUPPLY CORP JIANGSU POWER CORP
Priority to CN2009102350992A priority Critical patent/CN102064483A/en
Publication of CN102064483A publication Critical patent/CN102064483A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Emergency Lowering Means (AREA)

Abstract

The invention discloses a safety device for examining and repairing a tower, and relates to the safety device for aloft work on a power tower. The tower comprises a cross bar with a rectangular section, and consists of a hanging ring, a straight bar, a U-shaped clamping seat and a fastening screw, wherein an opening of the U-shaped clamping seat faces towards a side face; the distance between two side plates of the U-shaped clamping seat is slightly greater than the height of the cross bar; a corresponding wall plate close to the opening is provided with a pair of through holes which are coaxial with each other; the straight bar is inserted into the pair of through holes; axial positioning between the straight bar and the through holes on the clamping seat is realized by a positioning device; the fastening screw is tightly pressed against the cross bar inwards from the exterior of a bottom plate of the U-shaped clamping seat and is tightly pressed against the straight bar through the cross bar, so the cross bar, the straight bar and the clamping seat are fixedly connected with one another; and the hanging ring is fixedly connected to the top end of the straight bar. The safety device is suitable for the examining and repairing on the tower provided with the cross bar with the rectangular section, is convenient to carry, can be quickly and accurately arranged on the cross bar by one person, and then hooks a safety belt on the body of the person into the hanging ring for safety protection.

Description

The safety device of pylon maintenance
Technical field
The present invention relates to a kind of safety device of work high above the ground, relate in particular to the safety device that carries out work high above the ground on the electric tower.
Background technology
The isolating switch maintenance is that we are engaged in an important content of working in the substation equipment maintenance and repair, belong to the work high above the ground category, for effectively preventing the generation of personal injury and equipment breakdown, we adopt safety belt is directly tied up on the isolating switch support insulator in maintenance such as high voltage isolator in the past, but with in " the electric power safety working regulation " newly issued in June, 2005 about " use of safety belt is stipulated again in the high-rise working; " safety belt must not hang down and hang high using, forbid being to hang on the isolating switch supporter, should hang on the firm member or aim on the steelframe that hanging safety belt uses " the isotactic phasing conflicts; and we in time improve the method to set up of above-mentioned safety measure, and adopting the herringbone insulating ladder is to tie up safety belt.The method has met the rules requirement by the application of one-year age nearly though find the use of safety belt, and consuming time, effort has increased the workload that isolating switch overhauls greatly.
Though the method has met the requirement of rules defineds, in isolating switch maintenance, used a period of time after, we have still found many problems.With a GW4-110 type isolating switch maintenance is example, and we maintainer overhauled this type isolating switch in the past, needs 4 maintainers earlier double ladder to be carried to the working site, when carrying out service work, need 1 maintainer, 2 people help, and 1 people transmits the Work tool that inspection and repair shop needs.In addition, because of being subjected to the restriction of space for maintenance, an isolating switch has 3 phases, 6 contacts, needs mobile double ladder 6 times at least, just can finish the service work of an isolating switch.Need 4 maintainers to cooperate around here altogether, the time of wherein installing safety measure and being spent accounts for about 1/3 of the major overhaul time, expends more human and material resources.
The flow process of safety devices device is as follows during the isolating switch maintenance: 4 people are carried to the working site with double ladder and set up; 2 people help, and 1 people climbs up and fastens seat belts and work, and 1 people transmits object; An isolation switch contact maintenance is finished, and behind the Awaiting Overhaul personnel descending stair, 4 people adjust the ladder position; 4 people move away from the working site with double ladder behind the end-of-job; Finish.Find out thus, adopt double ladder to fasten the safety belt and carry out the method for isolating switch maintenance that can not improve the operating efficiency of maintenance really, the human and material resources that spent have accounted for very big ratio in the cost of overhaul.
Summary of the invention
The present invention is directed to above problem, provide a kind of easy for installation, the safety device of the pylon maintenance that reliability is high.
Technical scheme of the present invention is: described pylon comprises that a cross section is the cross bar of rectangle, and it is made of suspension ring, straight-bar, U-shaped deck and trip bolt; Described U-shaped deck opening is towards the side, and distance is slightly larger than the height of described cross bar between U-shaped deck biside plate; Offer the through hole of a pair of coaxial line on the approaching corresponding wallboard of described opening, described straight-bar inserts in this a pair of through hole, and realizes the axial location between through hole on straight-bar and the deck by positioner; Described trip bolt inwardly holds out against described cross bar by the outside of U-shaped deck base plate, holds out against described straight-bar by cross bar again, makes between cross bar, straight-bar and deck and fixedlys connected; Described suspension ring are fixedly connected on the top of straight-bar.
Described straight-bar bottom is provided with the step that is used for locating with the last through hole of described wallboard justifies, and the distance of described step distance of round straight-bar bottom is slightly larger than the width of described U-shaped deck.
Described straight-bar bottom is provided with the radial direction through hole that is used to be provided with split pin.
The present invention is applicable to when overhauling and uses that horizontal U-shaped deck, straight-bar can carry tower by personnel easily on the pylon with square-section cross bar, a people can attach it on the cross bar quickly and accurately; Be suspended in the suspension ring with being about to personnel's safety strap hook on one's body, play the effect of security protection.
Description of drawings
Fig. 1 is a structural representation of the present invention
1 is safety belt among the figure, the 2nd, and straight-bar, the 3rd, step circle, the 4th, through hole, the 5th, radial direction through hole, the 6th, soldered, the 7th, trip bolt, the 8th, nut, the 9th, stiffener, the 10th, U-shaped deck, the 11st, cross bar, the 12nd, suspension ring.
Embodiment
The present invention as shown in Figure 1, described pylon comprises that a cross section is the cross bar 11 of rectangle, it is made of safety device of the present invention suspension ring 12, straight-bar 2, U-shaped deck 10 and trip bolt 7; Described U-shaped deck 10 openings are (" Contraband " shape) towards the side, and distance is slightly larger than the height of described cross bar 11 between U-shaped deck 10 biside plates; Offering a pair of through hole 4 near on the corresponding wallboard of described opening, described straight-bar 2 stretches in the hole 4 from the top, and spacing is slightly larger than the width of described cross bar 11 between straight-bar 2 and U-shaped deck 10 base plates; Described trip bolt 7 inwardly holds out against described cross bar 11 by the outside of U-shaped deck 10 base plates; Described suspension ring 10 are fixedly connected on the top of straight-bar 2.
Described straight-bar 2 bottoms are provided with the step circle 3 that is used for described through hole 4 (through hole on the deck wainscot) location, and described step circle 3 distances apart from straight-bar 2 bottoms are slightly larger than the width of described U-shaped deck 10.
Described straight-bar 2 bottoms are provided with the radial direction through hole 5 that is used to be provided with split pin.
When making device of the present invention, for improving the intensity of structure, can weld a stiffener 9 again in the base plate bottom of U-shaped deck 10, for strengthening the reliability of the trip bolt connecting hole on stiffener 9, U-shaped deck 10 base plates, outside the connecting hole of stiffener 9 outsides, can set up nut 8 again.After completing, many soldereds 6 are handled, to guarantee good looking appearance.
During operation: hand-held safety devices instrument of 1 people and cooperation 1 people are in addition carried single ladder to the scene; Pylon is installed behind the safety devices device and is fastened seat belts 1 on maintainer's ascending stair, and 1 people carries out cooperating and can begin service work in addition; Behind the end-of-job, detaching device, hand-held device, the scene is singly left in 2 people carrying.

Claims (3)

1. the safety device of pylon maintenance, described pylon comprises that a cross section is the cross bar of rectangle, it is characterized in that, it is made of suspension ring, straight-bar, U-shaped deck and trip bolt; Described U-shaped deck opening is towards the side, and distance is slightly larger than the height of described cross bar between U-shaped deck biside plate; Offer the through hole of a pair of coaxial line on the approaching corresponding wallboard of described opening, described straight-bar inserts in this a pair of through hole, and realizes the axial location between through hole on straight-bar and the deck by positioner; Described trip bolt inwardly holds out against described cross bar by the outside of U-shaped deck base plate, holds out against described straight-bar by cross bar again, makes between cross bar, straight-bar and deck and fixedlys connected; Described suspension ring are fixedly connected on the top of straight-bar.
2. the safety device of pylon maintenance according to claim 1 is characterized in that, described straight-bar bottom is provided with the step that is used for locating with the last through hole of described wallboard justifies, and the distance of described step distance of round straight-bar bottom is slightly larger than the width of described U-shaped deck.
3. the safety device of pylon maintenance according to claim 2 is characterized in that described straight-bar bottom is provided with the radial direction through hole that is used to be provided with split pin.
CN2009102350992A 2009-11-17 2009-11-17 Safety device for examining and repairing tower Pending CN102064483A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009102350992A CN102064483A (en) 2009-11-17 2009-11-17 Safety device for examining and repairing tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009102350992A CN102064483A (en) 2009-11-17 2009-11-17 Safety device for examining and repairing tower

Publications (1)

Publication Number Publication Date
CN102064483A true CN102064483A (en) 2011-05-18

Family

ID=43999651

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009102350992A Pending CN102064483A (en) 2009-11-17 2009-11-17 Safety device for examining and repairing tower

Country Status (1)

Country Link
CN (1) CN102064483A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102364779A (en) * 2011-11-18 2012-02-29 安徽省电力公司蚌埠供电公司 Three-phase tubular bus synchronization hoisting auxiliary apparatus
CN111509603A (en) * 2020-04-30 2020-08-07 贵州电网有限责任公司 Protection screen cabinet safety measure protective belt

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102364779A (en) * 2011-11-18 2012-02-29 安徽省电力公司蚌埠供电公司 Three-phase tubular bus synchronization hoisting auxiliary apparatus
CN111509603A (en) * 2020-04-30 2020-08-07 贵州电网有限责任公司 Protection screen cabinet safety measure protective belt

Similar Documents

Publication Publication Date Title
CN103175998B (en) A kind of portable test shaft tower detected for transmission circuit insulator string high-voltage performance
CN102691474A (en) Maintenance platform
CN110219581B (en) Quick lapped maintenance ladder
CN107317258A (en) One kind is ascended a height operation simple platform
CN203039270U (en) Isolating switch repair protective frame
CN201562887U (en) Overhauling bracket of disconnector
CN102064483A (en) Safety device for examining and repairing tower
CN107147065B (en) A kind of tool-free sliding dismounting sealing plate package assembly of bus bridge
CN201918653U (en) Protective bracket for overhaul of high-voltage disconnectors
CN205791238U (en) A kind of 10kV distribution line charged lifter of straightway three-phase conducting wire
CN201883932U (en) Hoop-type vertical insulating single ladder
CN200992805Y (en) Knife inspection scaffold
CN215443391U (en) Transmission line and 5G communication sharing steel pipe pole
CN201263047Y (en) Safety holder pile for maintaining isolation knife brake
CN214286363U (en) Special stores pylon based on 35kV framework formula equipment safety belt
CN204760830U (en) Isolator maintenance work frame
CN205882560U (en) Special circulation cord rack device of distribution live working earth potential
CN203361596U (en) Auxiliary support of integrated lifting operation platform
CN210326671U (en) Isolating switch overhauling platform
CN209823252U (en) Transformer overhauls protection frame
CN203345999U (en) Special multifunctional lifting frame for busbar bridge
CN112439139A (en) Special stores pylon based on 35kV framework formula equipment safety belt
CN201453878U (en) Power distribution switch overhaul anti-dropping device
CN206934480U (en) A kind of 110kv disconnecting switch maintenance safety band suspension arrangement
CN201549792U (en) 220KV mutual inductor overhauling workbench

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
ASS Succession or assignment of patent right

Owner name: JIANGSU ELECTRIC POWER COMPANY, YANGZHOU JIANGDU P

Free format text: FORMER OWNER: JIANGDU POWER SUPPLY CORP. JIANGSU POWER CORP.

Effective date: 20121121

Owner name: YANGZHOU POWER SUPPLY CO., JIANGSU PROV ELECTRIC P

Effective date: 20121121

C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20121121

Address after: 225200 No. 38 East worker peasant Road, Jiangdu District, Jiangsu, Yangzhou

Applicant after: Yangzhou Jiangdu Power Supply Company, Jiangsu Electric Power Company

Applicant after: Yangzhou Power Supply Company of Jiangsu Electric Power Company

Applicant after: Jiangsu Electric Power Company

Applicant after: State Grid Corporation of China

Address before: 225200 No. 38 East worker peasant Road, Jiangdu City, Jiangsu Province

Applicant before: Jiangdu Power Supply Corp. Jiangsu Power Corp.

C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20110518