CN102021916B - A kind of method of iron tower foundation construction - Google Patents

A kind of method of iron tower foundation construction Download PDF

Info

Publication number
CN102021916B
CN102021916B CN201010528160.5A CN201010528160A CN102021916B CN 102021916 B CN102021916 B CN 102021916B CN 201010528160 A CN201010528160 A CN 201010528160A CN 102021916 B CN102021916 B CN 102021916B
Authority
CN
China
Prior art keywords
stake
hole
formwork
foundation
basis
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201010528160.5A
Other languages
Chinese (zh)
Other versions
CN102021916A (en
Inventor
李岩
刘治稳
郭向阳
霍建伟
姚红亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Luoyang Power Supply Co of State Grid Henan Electric Power Co Ltd
Original Assignee
Luoyang Power Supply Co of State Grid Henan Electric Power Co Ltd
Filing date
Publication date
Application filed by Luoyang Power Supply Co of State Grid Henan Electric Power Co Ltd filed Critical Luoyang Power Supply Co of State Grid Henan Electric Power Co Ltd
Priority to CN201010528160.5A priority Critical patent/CN102021916B/en
Publication of CN102021916A publication Critical patent/CN102021916A/en
Application granted granted Critical
Publication of CN102021916B publication Critical patent/CN102021916B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The present invention relates to power transmission sequence foundation construction technical field, a kind of method disclosing iron tower foundation construction, it is to be actually needed according to point hole and formwork precision prescribed and scene, to point vertical grouser of hole nail, carry out basis setting-out, formwork is followed closely the vertical high stake being suitable for basis formwork, correcting, check again, and its step is as follows: 1), iron tower foundation divide hole, 2), iron tower foundation excavates, checks, controls and formwork;The present invention not only reduces piling, school stake, the workload of school nail, also improves a point hole speed, alleviates a point carrying amount for multiple operating points timber, reduce labor intensity, and inspection of construction is convenient and swift.And working procedure, the work efficiency improving power line tower foundation construction and construction quality can be simplified, it is ensured that power transmission sequence safe operation.

Description

A kind of method of iron tower foundation construction
[technical field]
The present invention relates to power transmission sequence foundation construction technical field, a kind of method especially relating to iron tower foundation construction.
[background technology]
At present, the foundation construction of power transmission sequence, is the important step of power transmission line construction, its work efficiency and construction quality Quality, the safe operation after directly affecting the work efficiency of whole engineering and putting into operation.Real work has found that generally Construction method in work progress, there is also some difficult points.
1, dividing difficult point present in the method work progress of hole such as usual iron tower foundation, iron tower foundation divides hole to determine stake to be not only base Plinth divides the control stake in hole, is also the control stake of foundation construction and inspection, finds, usual ferrum in long-term foundation construction and inspection The construction method in tower foundation point hole there is also defect.
1), general repetition survey of existing rail way divides the timber height in hole to basset on 250mm, the firm spud pile road for guarantee stake position Height typically at 3-5Cm, line steel tower basis end face, design is typically basseted at 200 600mm;Gene basis end face and Fang bolt and the discrepancy in elevation controlling stake existence cause difficulty to basis formwork.
2), general behind point hole the most also to process through channel contact and basic material, behind point hole to foundation construction process this The section time is susceptible to pile displatement and loss, also needs to re-calibrate before formwork.
3), need to coordinate auxiliary pile and 4 bases with theodolite because stake position and foundation forms exist the discrepancy in elevation as shown in figure Plinth tower leg is cross-referenced just can complete basis formwork, and deviation controls difficulty, inefficiency.
4), during formwork, need just can complete under specialty surveys the commander of work the project under construction that foundation forms disposes.
[summary of the invention]
In view of the weak point of above-mentioned existence, a kind of method that it is an object of the invention to provide iron tower foundation construction.Can Simplify working procedure, the work efficiency improving power line tower foundation construction and construction quality, it is ensured that power transmission sequence is transported safely OK;Having simple to operate, work efficiency is high, the feature that deviation is little.
In order to realize foregoing invention purpose, the present invention adopts the following technical scheme that
A kind of method of iron tower foundation construction, is to be actually needed, to a point hole according to point hole and formwork precision prescribed and scene The vertical grouser of nail, carries out basis setting-out, and formwork is followed closely the vertical high stake being suitable for basis formwork, correcting, check again, and its step is such as Under:
1, iron tower foundation divides hole, iron tower foundation to divide hole to require that determining stake is not only the control stake of foundation pits, is also that basis is executed The control stake of work and inspection, but the auxiliary pile that discovery foundation pits nail is vertical in practice is because of above-mentioned reason, must also before formwork Re-calibrate, and in work progress, there is also problems, meeting a point premise for hole required precision based on above reason Lower simplification working procedure nail grouser, with grouser for according to carrying out a point hole;
(1) theodolite is propped up at Center stake O, make four auxiliary piles A, B, C, D according to usual way, auxiliary pile A, It not be used in nail tingle on B, C, D, a point hole required precision can be met;Auxiliary pile A, B, C, D or make of the round steel of diameter 10mm Instrument, replace timber, point hole time ruler end points be placed on round steel root, complete basis being divided hole;
(2) open y according to engine request and near coal-mine length of side a, side root, calculate L1、L2Value, ruler termination is placed on C stake Center, carries out a point hole by usual way;
(3) four near coal-mine position marks of steel tower foundation ditch are understood, then by auxiliary pile by methods such as Calx after dividing hole Pull out, carry out point hole of next base;
2, iron tower foundation excavates, checks, controls and formwork, and described foundation excavation is for avoiding basis ultra-deep, and reserved 200mm is pre- Stay layer;After Yu Liu, following closely stake before can carrying out formwork, determining stake can carry out determining stake according to basis end face and fang bolt height, determines stake After with auxiliary pile for according to complete to basis formwork, control and check;
(1), formwork determine stake, select the height of timber, can firmly hammer into ground;After hammering into ground, ground identity distance fang bolt The height of end face exceeds 3mm, i.e. h2+3mm;
(2), make tetra-auxiliary piles of A, B, C, D according to point method in hole, make face thumb screw 3cm above Ground, and make four Individual auxiliary pile is arranged in a plane;Utilize transit survey, control to nail on little iron nail in stake at A, B, C, D, determine stake complete Afterwards for ensureing that the cement mortar that firmly uses of auxiliary pile is fixed;
(3), on auxiliary pile, cotton rope is hung up, with cotton rope as foundation, according to each spot size in the basis of layout design and work Journey specifies, carries out foundation ditch physical dimension inspection, according to auxiliary pile height with cotton rope for according to cheating deep inspection and repairing hole;
(4), steel ruler zero line is fixed in C pile beacon note, and ruler is tightened in A stake, intercept L respectively from C point4And L7 Size, does mark on cotton rope, is foundation according to cotton rope, completes the formwork of column according to layout design stem height, with The method is respectively completed the arrangement of other fang bolt and other footing step size;Described L1、L2、L3、L4It is C stake respectively to A Stake dipstick metering, footing step, column and foundation bolt diagonal low coverage size;Described L5、L6、L7、L8It is that C stake is to A stake dipstick metering respectively Footing step, column and foundation bolt diagonal long distance size;Described a1、a2、a3, be the length of side of step and column respectively, described a4The fang bolt center length of side to center;Described L1、L2、L3、L4、L5、L6、L7、L8Cut chi length, by geometrical relationship gained:
L1=(y-a1)/L2=(y-a2)/ L3=(y-a3)/ L4=(y-a4)/
L5=(y+a5)/ L6=(y+a6)/ L7=(y+a7)/ L8=(y+a8)/
Owing to have employed technique scheme, the present invention has superiority as follows:
A kind of method of iron tower foundation construction, is by entering traditional method of work difficult point present in the foundation construction Row is analyzed, is found out;Working procedure, the work efficiency improving power line tower foundation construction and construction matter can be simplified Amount, it is ensured that power transmission sequence safe operation;Superiority is as follows:
1) labor intensity is reduced: mainly multiple operating points transfer process that foundation pits relative work intensity is big needs Carry with substantial amounts of timber with for ensureing that the firm of stake position needs to squeeze into timber major part ground, after piling, also need to school Stake, then accurately following closely little iron nail, also needing to accurate school nail under the commander of theodolite subsequently, as long as utilizing interim timber at longitude and latitude Timber can be made in the sight line of instrument to stand in ground play the effect of mark and can complete point hole of iron tower foundation, have ready conditions with homemade Instrument is more convenient.Not only reduce piling, school stake, the workload of school nail, also improve a point hole speed, alleviate point multiple job The carrying amount of some timber.
2) inspection of construction is convenient and swift: iron tower foundation formwork needs to make at specialty survey crew according to common construction method Just can complete the formwork work on basis with theodolite under commanding, workmen needs to wait the measurement knot of each project of survey crew Just complete the adjustment repeatedly of each project of formwork after the most out according to the commander of survey crew, utilize the construction method after improving straight Seeing understandable, general workmen is directly put into position template and fang bolt according to the labelling on cotton rope, during formwork The displacement repeatedly occurred can be adjusted waiting after specialty survey crew repeated measurement the most repeatedly according to the mark on cotton rope Adjust, casting process can also check deviation repeatedly that occur because of construction, be labeled as according to carrying out quality control with cotton rope.
[accompanying drawing explanation]
Template and fang bolt end face and the discrepancy in elevation schematic diagram controlling stake based on Fig. 1;
Fig. 2 is the schematic diagram carrying out iron tower foundation point hole with interim timber;
Fig. 3 is the schematic diagram replacing timber point hole with round steel self-made tool;
Fig. 4 is the schematic diagram that formwork determines piling method;
[detailed description of the invention]
A kind of method of iron tower foundation construction, is according to point hole and formwork precision prescribed and a scene It is actually needed, to point hole vertical grouser of nail, carries out basis setting-out, formwork is followed closely again and vertical is suitable for basis formwork, corrects, check High stake, its step is as follows:
1, iron tower foundation divides hole, iron tower foundation to divide hole to require that determining stake is not only the control stake of foundation pits, is also that basis is executed The control stake of work and inspection, but the auxiliary pile that discovery foundation pits nail is vertical in practice is because of above-mentioned reason, must also before formwork Re-calibrate, and in work progress, there is also problems, meeting a point premise for hole required precision based on above reason Lower simplification working procedure nail grouser, with grouser for according to carrying out a point hole;
(1) theodolite is propped up at Center stake O, make A, B, C, D, four auxiliary piles, auxiliary pile according to usual way A, B, C, D are upper need not follow closely tingle again, can meet a point hole required precision;
(2) open y according to engine request and near coal-mine length of side a, side root, calculate L1、L2Value, ruler termination is placed on C stake Center, carries out a point hole by usual way;
(3) four near coal-mine position marks of steel tower foundation ditch are understood, then by auxiliary pile by methods such as Calx after dividing hole A, B, C, D pull out, and carry out point hole of next base;
(4) instrument or of the round steel of diameter 10mm made, replaces timber, and when dividing hole, ruler end points is placed on round steel root, Complete basis being divided hole.The instrument feature that this round steel makes is in general soil, under the commander surveying work, one inserts i.e. conveniently Can, hard soil is slightly pounded with hammer and just can pound in ground, can use.
2, iron tower foundation excavates, checks, controls and the improvement of formwork
Foundation excavation is for avoiding basis ultra-deep, after reserved 200mm reserves layer, follows closely stake before can carrying out formwork, and determining stake can root Carry out determining stake according to basis end face and fang bolt height, after determine stake with auxiliary pile for according to complete to basic formwork, control and Check.
1) formwork determines stake as shown in Figure 4, after selecting the height of timber firmly can hammer into ground, and ground identity distance fang bolt end face Height exceed about 3mm, i.e. h2+3mm。
2) make four auxiliary piles A, B, C, D according to point method in hole as shown in Figure 2, make a face as shown in Figure 4 above Ground Thumb screw 3cm, and make four auxiliary piles A, B, C, D, in a plane, utilize transit survey four auxiliary pile A, B, C, D controls to nail on little iron nail in stake, is that the firm cement mortar ensureing auxiliary pile A, B, C, D is fixed after determining stake.
3) on auxiliary pile, cotton rope is hung up as shown in Figure 1, with cotton rope as foundation, according to each portion, the basis of layout design chi Very little and engineering discipline carries out foundation ditch physical dimension inspection, according to auxiliary pile height with cotton rope for according to cheating deep inspection and repairing hole.
4) as shown in Figure 1 steel ruler zero line is fixed on as shown in Figure 1 in C pile beacon note, and ruler is tightened in A Stake, intercepts L respectively from C point4And L7Size, does mark on cotton rope, is foundation according to cotton rope, high according to layout design column Spend the formwork of column, be respectively completed the arrangement of other fang bolt and other footing step size in this approach.In figure L1、L2、L3、L4It is C stake respectively to A stake dipstick metering footing step, column and foundation bolt diagonal low coverage size, L in figure5、L6、 L7、L8It is that C stake is to A stake dipstick metering footing step, column and foundation bolt diagonal long distance size respectively;A in figure1、a2、a3, respectively It is the length of side of step and column, a4The fang bolt center length of side to center.L1、L2、L3、L4、L5、L6、L7、L8Cut chi length, There is a geometrical relationship gained in figure:
L1=(y-a1)/L2=(y-a2)/ L3=(y-a3)/ L4=(y-a4)/
L5=(y+a5)/ L6=(y+a6)/ L7=(y+a7)/ L8=(y+a8)/
Described simplification working procedure: point hole determine stake due to point cheat after also need to contact channel, foundation excavation, steel bar meter and Get the raw materials ready, although a point hole is accurately positioned, but foundation pits loses stake and pile displatement phenomenon, also to existing during foundation construction Correction reorientated by needs, and iron tower foundation is different from other concurrent basis, owing to basis end face and basal plane exist design The discrepancy in elevation of 200mm 600mm, although by the control stake of usual method nail under the cooperation of instrument, four basic tower legs are mutually joined According to also can complete to basis formwork and inspection but work efficiency is extremely low.If changing high stake according to the method improved, waste In the past be accurately positioned paid work, less than foundation construction and check control accuracy according to foundation pits precision, with interim Stake can meet requirement.

Claims (1)

1. the method for an iron tower foundation construction, it is characterised in that: it is according to point hole and the actual need of formwork precision prescribed and scene Want, to point vertical grouser of hole nail, carry out basis setting-out, formwork is followed closely again the vertical high stake being suitable for basis formwork, correcting, check, Its step is as follows:
1), iron tower foundation divide hole, iron tower foundation to divide hole to require determine stake and be not only the control stake of foundation pits, be also foundation construction with The control stake checked, but the auxiliary pile that discovery foundation pits nail is vertical in practice is because of above-mentioned reason, must also be again before formwork Correction, and in work progress, there is also problems, based on above reason, letter on the premise of meeting point hole required precision Change working procedure nail grouser, with grouser for according to carrying out a point hole;
(1) theodolite is propped up at Center stake O, makes four auxiliary piles A, B, C, D according to usual way, auxiliary pile A, B, C, D is upper need not follow closely tingle again, can meet a point hole required precision;When dividing hole, ruler end points is placed on auxiliary pile A, B, C, D root, completes Basis is divided hole;
(2) open y according to engine request and near coal-mine length of side a, side root, calculate L1、L2Value, ruler termination is placed in C stake The heart, carries out a point hole by usual way;Wherein L1Value is C stake to A stake dipstick metering basis first step diagonal low coverage size, L2Value It is that C stake is to A stake dipstick metering basis second step diagonal low coverage size;
(3) by Calx method, four near coal-mine position marks of steel tower foundation ditch are understood, then by auxiliary pile A, B, C, D after dividing hole Pull out, carry out point hole on next basis;
2), iron tower foundation excavate, check, control and formwork, described foundation excavation is for avoiding basis ultra-deep, and reserved 200mm reserves Layer;After Yu Liu, i.e. carry out following closely before formwork stake, determine stake and carry out determining stake according to basic end face and fang bolt height, determine after stake with auxiliary Helping stake is according to completing the formwork to basis, controlling and check;
(1), formwork determine stake, select the height of timber, can firmly hammer into ground;After timber hammers into ground, ground identity distance fang bolt The height of end face exceeds 3mm, i.e. h2+3mm;h2It is that ground is to fang bolt apical side height;
(2), make four auxiliary piles A, B, C, D according to point method in hole, make face thumb screw 3cm above Ground, and make four auxiliary A, B, C, a D is helped to be arranged in a plane;Utilize transit survey, four auxiliary pile A, B, C, D control stakes nail on little Iron nail, uses cement mortar to fix for the firm of guarantee auxiliary pile A, B, C, D after determining stake;
(3), on auxiliary pile A, B, C, D, hang up cotton rope, with cotton rope as foundation, according to each spot size in the basis of layout design and Engineering discipline, carries out foundation ditch physical dimension inspection, according to auxiliary pile height with cotton rope for according to cheating deep inspection and repairing hole;
(4), steel ruler zero line is fixed in C pile beacon note, and ruler is tightened in A stake, intercept L respectively from C stake point4And L7Chi Very little, cotton rope does mark, is foundation according to cotton rope, completes the formwork of column according to layout design stem height, with this Method is respectively completed the arrangement of other fang bolt and other footing step size;Wherein L4It is that C stake is to A stake dipstick metering column diagonal angle Line low coverage size, L7Size is that C stake is to A stake dipstick metering column diagonal long distance size.
CN201010528160.5A 2010-11-02 A kind of method of iron tower foundation construction Expired - Fee Related CN102021916B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201010528160.5A CN102021916B (en) 2010-11-02 A kind of method of iron tower foundation construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201010528160.5A CN102021916B (en) 2010-11-02 A kind of method of iron tower foundation construction

Publications (2)

Publication Number Publication Date
CN102021916A CN102021916A (en) 2011-04-20
CN102021916B true CN102021916B (en) 2016-12-14

Family

ID=

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS59233019A (en) * 1983-05-30 1984-12-27 Kyoei Densetsu Kk Method and part for forming earth anchor and automatic penetrator therefor
SU1534143A1 (en) * 1987-07-13 1990-01-07 Ленинградский инженерно-строительный институт Method of determining soil resistance at lateral surface and point of a pile
CN2056680U (en) * 1988-10-24 1990-05-02 能源部西南电力设计院 Light optimization iron tower foundation
CN101349063A (en) * 2008-08-21 2009-01-21 孟庆波 Iron tower foundation of overhead power transmission line severely-weathered rock formation winding anchor rod
CN201495555U (en) * 2009-08-18 2010-06-02 天津二建建筑工程有限公司 Cap tower-crane foundation of concrete cast-in-place high pile for tower erection at the house center

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS59233019A (en) * 1983-05-30 1984-12-27 Kyoei Densetsu Kk Method and part for forming earth anchor and automatic penetrator therefor
SU1534143A1 (en) * 1987-07-13 1990-01-07 Ленинградский инженерно-строительный институт Method of determining soil resistance at lateral surface and point of a pile
CN2056680U (en) * 1988-10-24 1990-05-02 能源部西南电力设计院 Light optimization iron tower foundation
CN101349063A (en) * 2008-08-21 2009-01-21 孟庆波 Iron tower foundation of overhead power transmission line severely-weathered rock formation winding anchor rod
CN201495555U (en) * 2009-08-18 2010-06-02 天津二建建筑工程有限公司 Cap tower-crane foundation of concrete cast-in-place high pile for tower erection at the house center

Similar Documents

Publication Publication Date Title
CN109653755B (en) Construction method for large-diameter slurry shield to pass through ballastless track roadbed without settlement
CN206191060U (en) Gas pipeline push pipe construction structures
CN106894422B (en) Complex environment deep foundation pit supporting construction method
CN105971611A (en) Roadbed settlement control method for subway tunnel passing under existing trunk railway closely
CN109281328A (en) The accurate construction method of steel cofferdam guide pile
CN109596112B (en) Measuring method for controlling long-distance construction of large-diameter shield tunneling machine to smoothly go out of tunnel
CN107859034B (en) Large diameter pile foundation spillage immediate processing method
CN102021916B (en) A kind of method of iron tower foundation construction
CN207351729U (en) A kind of square soil sample sampler of paleomagnetism test
CN103344214B (en) 1.6-degree parabolic extralarge pier measuring and pier body linear control method
CN102031757B (en) Method for constructing bottom plate guide layer of jacked-in frame bridge
CN104088292A (en) Axis single-pile multi-tripod foundation and construction method thereof
CN106403996A (en) Production method of forced centering observation mark stake for precision engineering measurement
CN110258556A (en) A kind of pile extension method of engineering tubular pile construction
CN206477240U (en) A kind of trestle pile foundation for deep water drift net riverbed
CN112922623B (en) Pipe jacking construction process for mountain tunnel
CN107419726B (en) A kind of vibration pressure prefabricated tubular pile accurate positioning plant pile construction method
CN108571008A (en) Lid digs station steel pipe column positioning construction method
CN105714686B (en) Double L-shaped pipe curtain structure controls frame core-tube system jacking method
CN201666794U (en) Special line laying tool for lateral central lines on working layer of molten iron mixer body
CN210164421U (en) Visual accurate positioning device for construction of three-axis stirring pile
CN102021916A (en) Foundation construction method of iron tower
CN210104746U (en) Positioning device for controlling pile body position in soft foundation treatment
CN108978647A (en) Road cement mixing pile measurement and positioning tool and localization method
CN104266638A (en) Pit-in-pit fixed-point line laying method

Legal Events

Date Code Title Description
PB01 Publication
SE01 Entry into force of request for substantive examination
GR01 Patent grant
CP03 Change of name, title or address

Address after: Xigong District 471000 Henan province Luoyang Kaixuan Road No. 12

Patentee after: LUOYANG POWER SUPPLY COMPANY OF STATE GRID HENAN ELECTRIC POWER Co.

Address before: 471000 No. 259 Kaiyuan Road, New District, Henan, Luoyang

Patentee before: Luoyang Power Supply Company of Henan Electric Power Co.

TR01 Transfer of patent right

Effective date of registration: 20191127

Address after: Xigong District 471000 Henan province Luoyang Kaixuan Road No. 12

Co-patentee after: LUOYANG LONGYU GROUP Co.,Ltd.

Patentee after: LUOYANG POWER SUPPLY COMPANY OF STATE GRID HENAN ELECTRIC POWER Co.

Address before: Xigong District 471000 Henan province Luoyang Kaixuan Road No. 12

Patentee before: LUOYANG POWER SUPPLY COMPANY OF STATE GRID HENAN ELECTRIC POWER Co.

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20161214