CN210104746U - Positioning device for controlling pile body position in soft foundation treatment - Google Patents

Positioning device for controlling pile body position in soft foundation treatment Download PDF

Info

Publication number
CN210104746U
CN210104746U CN201920628564.8U CN201920628564U CN210104746U CN 210104746 U CN210104746 U CN 210104746U CN 201920628564 U CN201920628564 U CN 201920628564U CN 210104746 U CN210104746 U CN 210104746U
Authority
CN
China
Prior art keywords
pendant
long chi
pile body
long
soft foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201920628564.8U
Other languages
Chinese (zh)
Inventor
张恩达
王照辉
岳旭光
郭书林
邢庆龙
雷浩
王勃
马永智
赵磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Construction Bridge Engineering Bureau Group Co Ltd
Original Assignee
China Railway Construction Bridge Engineering Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Construction Bridge Engineering Bureau Group Co Ltd filed Critical China Railway Construction Bridge Engineering Bureau Group Co Ltd
Priority to CN201920628564.8U priority Critical patent/CN210104746U/en
Application granted granted Critical
Publication of CN210104746U publication Critical patent/CN210104746U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The utility model discloses a positioner for controlling pile body position in soft foundation treatment for adopt the steel rule laying-out among the solution prior art, it is hard consuming time, the problem that the error is big. The method comprises the following steps: both ends and middle part all set up the landing leg about the long chi, and the scale has been marked on the long chi to and set up a plurality of marks according to the interval of crowded close stake, sliding connection wiring rope on the long chi, the pendant is connected to the cotton rope below, and the white ash powder of pendant top opening, the inside packing into, pendant bottom opening, the level gauge that can dismantle is set up on the long chi top. The beneficial effects include: the position of crowded close stake can the accurate positioning, effectively solve the error that traditional steel rule lofting brought, the operation only need two people can, effectively practice thrift the manpower, saved a large amount of time.

Description

Positioning device for controlling pile body position in soft foundation treatment
Technical Field
The utility model relates to a ground treatment technical field especially relates to a positioner that is arranged in control soft ground to handle pile body position.
Background
The bearing capacity of the foundation can be enhanced by measures such as compaction piles, cement mixing piles, gravel piles, high-pressure jet grouting piles and the like in the design of the general soft foundation, the existing pile body positioning generally adopts steel rulers to discharge samples one by one, a large amount of time and labor are consumed, and meanwhile, the error is large.
Disclosure of Invention
An embodiment of the utility model provides a positioner for controlling pile body position in soft foundation treatment for adopt the steel rule laying-out among the solution prior art, it is hard consuming time, problem that the error is big.
The embodiment of the utility model provides a positioner for controlling pile body position in soft foundation treatment, include: a long ruler, a support leg, a mark, a thread rope and a pendant; both ends and middle part all set up the landing leg about the long chi, and the scale has been marked on the long chi to and set up a plurality of marks according to the interval of crowded close stake, sliding connection wiring rope on the long chi, the pendant is connected to the cotton rope below, and the white ash powder of pendant top opening, the inside packing into, pendant bottom opening, the level gauge that can dismantle is set up on the long chi top.
Preferably, the upper part of the long ruler is a dovetail guide rail, a dovetail groove is arranged below the marking block, and the marking blocks are arranged on the dovetail guide rail in a matched mode and can be adjusted to proper positions according to the interval of the compaction piles.
Preferably, the bottom end of the long ruler is provided with a T-shaped slide rail, a C-shaped slide block is installed in cooperation with the T-shaped slide rail, and a rope and a pendant are connected below the C-shaped slide block.
The utility model discloses beneficial effect includes: the position of crowded close stake can the accurate positioning, effectively solve the error that traditional steel rule lofting brought, the operation only need two people can, effectively practice thrift the manpower, saved a large amount of time.
Drawings
Fig. 1 is a schematic front view of a positioning device for controlling the position of a pile body in soft foundation treatment in an embodiment of the present invention;
fig. 2 is a schematic side view of a positioning device for controlling the position of a pile body in soft foundation treatment according to an embodiment of the present invention;
fig. 3 is a schematic view of a partially enlarged structure of a positioning device for controlling the position of a pile body in soft foundation treatment according to an embodiment of the present invention;
in the drawings: the long ruler comprises a long ruler 1, a marking block 2, a supporting leg 3, a thread rope 4, a pendant 5, a C-shaped sliding block 6, a T-shaped sliding rail 7 and a level meter 8.
Detailed Description
In order to provide a preferred embodiment, the following description is made of the preferred embodiments of the present invention with reference to the accompanying drawings.
Referring to fig. 1-3, an embodiment of the present invention provides a positioning device for controlling a position of a pile in soft foundation treatment, including: a long ruler 1, a support leg 3, a mark, a thread rope 4 and a pendant 5; both ends and middle part all set up landing leg 3 about long chi 1, and the scale has been marked on long chi 1 to and set up a plurality of marks according to the interval of crowded close stake, slide linkage wire rope 4 on long chi 1, pendant 5 is connected to 4 belows on the cotton rope, the 5 top openings of pendant, the white lime that packs into in inside, the 5 bottom openings of pendant, long chi 1 top sets up the spirit level 8 that can dismantle.
The upper part of the long ruler 1 is a dovetail guide rail, a dovetail groove is arranged below the marking blocks 2, and the marking blocks 2 are installed on the dovetail guide rail in a matched mode and can be adjusted to proper positions according to the interval of the compaction piles. The bottom of the long ruler 1 is provided with a T-shaped slide rail 7, a C-shaped slide block 6 is installed in cooperation with the T-shaped slide rail 7, and a rope 4 and a pendant 5 are connected below the C-shaped slide block 6.
Specifically, the distance of adjacent compaction stake position is X, and two adjacent rows of compaction stake distances are Y, can be directly with obvious mark with X, 2X, 3X … … NX's position mark, and the preferred through removing mark block 2, moves mark block 2 to X, 2X, on 3X … … NX's the position, behind the survey crew lofting compaction stake position with GPS, uses the utility model provides a positioner accuracy encryption location. At first on fixing the position of GPS laying-out with landing leg 3 at 1 both ends of long ruler, again according to the levelness of 1 spirit level 8 adjustment long ruler 1 of long ruler, then according to the scale of long ruler 1, adjust mark piece 2 to suitable position according to the lateral distance of two compaction stake positions, remove C word slider, make it drive cotton rope 4 and 5 perpendicular laying-out of pendant, position the stake position under pendant 5, open the opening of 5 below pendants, make the direct whereabouts of lime powder on the point position of location, carry out the mark of compaction stake position. The same is carried out in the Y direction, the pile positions of the compaction piles are distributed in a quincunx pile type, two points in the X direction are found, the middle point of the two points is calculated, the pile position in the Y direction is positioned on the extension line of the middle point, the two ends of the long ruler 1 are fixed on the extension line of the middle point of the two points in the X direction in a mode of being perpendicular to the X direction, the levelness is adjusted through the level gauge 8, marking is carried out on the point positions of Y, 3Y and 5Y … …, then the first row of first points in the X direction is found, marking is carried out on the point positions of 2Y, 4Y and 6Y … … in the Y direction perpendicular to the X direction, after the two rows of point positions in the Y direction are marked, the point positions of the first row in the X direction are continuously carried out according to the method of positioning the first row in the X direction, the distance of Y is also adjusted through the marking block 2, and the value.
It will be apparent to those skilled in the art that various changes and modifications may be made without departing from the spirit and scope of the invention. Thus, if such modifications and variations of the present invention fall within the scope of the claims and their equivalents, the present invention is also intended to include such modifications and variations.

Claims (3)

1. A positioning device for controlling the position of a pile body in soft foundation treatment, comprising: a long ruler, a support leg, a mark, a thread rope and a pendant; both ends and middle part all set up the landing leg about the long chi, and the scale has been marked on the long chi to and set up a plurality of marks according to the interval of crowded close stake, sliding connection wiring rope on the long chi, the pendant is connected to the cotton rope below, and the white ash powder of pendant top opening, the inside packing into, pendant bottom opening, the level gauge that can dismantle is set up on the long chi top.
2. The positioning device for controlling the position of the pile body in soft foundation treatment as claimed in claim 1, wherein the upper part of the long ruler is a dovetail guide rail, a dovetail groove is arranged below the marking block, and a plurality of marking blocks are fittingly installed on the dovetail guide rail and can be adjusted to proper positions according to the interval of the compacted piles.
3. The positioning device for controlling the position of the pile body in soft foundation treatment as claimed in claim 1, wherein the bottom end of the long ruler is provided with a T-shaped slide rail, a C-shaped slide block is arranged in cooperation with the T-shaped slide rail, and a wire rope and a pendant are connected below the C-shaped slide block.
CN201920628564.8U 2019-05-05 2019-05-05 Positioning device for controlling pile body position in soft foundation treatment Expired - Fee Related CN210104746U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920628564.8U CN210104746U (en) 2019-05-05 2019-05-05 Positioning device for controlling pile body position in soft foundation treatment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920628564.8U CN210104746U (en) 2019-05-05 2019-05-05 Positioning device for controlling pile body position in soft foundation treatment

Publications (1)

Publication Number Publication Date
CN210104746U true CN210104746U (en) 2020-02-21

Family

ID=69539936

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920628564.8U Expired - Fee Related CN210104746U (en) 2019-05-05 2019-05-05 Positioning device for controlling pile body position in soft foundation treatment

Country Status (1)

Country Link
CN (1) CN210104746U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112012213A (en) * 2020-09-07 2020-12-01 北京市政建设集团有限责任公司 Method for improving positioning accuracy of cast-in-situ bored pile

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112012213A (en) * 2020-09-07 2020-12-01 北京市政建设集团有限责任公司 Method for improving positioning accuracy of cast-in-situ bored pile

Similar Documents

Publication Publication Date Title
CN110375711B (en) Subway tunnel inner ring network trackless measurement construction method
CN204479060U (en) A kind of subgrade stability recording geometry
CN210104746U (en) Positioning device for controlling pile body position in soft foundation treatment
CN212227899U (en) Building engineering surveying and mapping device
CN109373988A (en) Contact network in tunnel trackless construction survey instrument and method
CN103486954B (en) Coal mine roadway deformation measuring device and method
CN207727631U (en) Earthwork construction slope detection device
CN207091890U (en) A kind of steady elevation control device of new type water
CN102877447B (en) Shallow stratum multi-point settlement real-time monitoring device and method
CN208042973U (en) Accurately crack vertical strain monitoring device
CN208059782U (en) Accurately crack tension and changing of the relative positions deformation monitoring device
CN105973201A (en) Device and method for measuring gradient of edge slope by fishing rod type gradient ruler from opening line position of edge slope
CN201138200Y (en) Stereoscopic rapid measurement tool for roads
CN105887941A (en) Pile foundation pile length measuring and calculating method
CN101603946B (en) Tillage erosion measurement magnetism tracer method
CN205580449U (en) Side slope detection ruler of highway subgrade construction
CN103344214B (en) 1.6-degree parabolic extralarge pier measuring and pier body linear control method
CN102538648A (en) Accurate laneway surface convergence measuring method
CN104006798B (en) Pier stud verticality measuring instrument
CN102031757A (en) Method for constructing bottom plate guide layer of jacked-in frame bridge
CN202850007U (en) Shallow stratum multipoint settlement real-time monitoring device
CN106123873B (en) Upright projection positioning measuring device positions cultellation construction method
CN201924288U (en) Guide device for bottom plate of jacked frame bridge
CN207163464U (en) Portable integrated adjustable water level compass device
CN102564391A (en) Regional distributed sedimentation monitoring system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200221