CN102021871B - Foundation treatment method for temporary construction subgrade on dredge fill soft foundation site - Google Patents

Foundation treatment method for temporary construction subgrade on dredge fill soft foundation site Download PDF

Info

Publication number
CN102021871B
CN102021871B CN 200910195707 CN200910195707A CN102021871B CN 102021871 B CN102021871 B CN 102021871B CN 200910195707 CN200910195707 CN 200910195707 CN 200910195707 A CN200910195707 A CN 200910195707A CN 102021871 B CN102021871 B CN 102021871B
Authority
CN
China
Prior art keywords
raft
bamboo chip
construction
chip plate
foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN 200910195707
Other languages
Chinese (zh)
Other versions
CN102021871A (en
Inventor
何国富
方强
张玲云
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Petrochemical Corp
Sinopec Shanghai Engineering Co Ltd
Original Assignee
China Petrochemical Corp
Sinopec Shanghai Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Petrochemical Corp, Sinopec Shanghai Engineering Co Ltd filed Critical China Petrochemical Corp
Priority to CN 200910195707 priority Critical patent/CN102021871B/en
Publication of CN102021871A publication Critical patent/CN102021871A/en
Application granted granted Critical
Publication of CN102021871B publication Critical patent/CN102021871B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Foundations (AREA)

Abstract

The invention relates to a foundation treatment method for temporary construction subgrade at the dredge fill soft foundation site, which is realized by the following steps: adopting common standard bamboo boards or rafts; continuously paving the bamboo boards or rafts on the dredge fill according to the planned construction route; and determining the length of the paved standard bamboo boards or rafts according to the walking route and expanding the planned route toward the two sides by 0.8-1.2m based on the width of the planned route to obtain the width of the bamboo boards or rafts, wherein the bamboo boards or rafts are in lap joint with each other and are connected by binding with steel wires to ensure the effectiveness of lap joint and form a whole raft. The method has the beneficial effect of solving the walking problem of the constructors and various construction machines at the dredge fill soft foundation site.

Description

The method for processing foundation of the interim construction roadbed on the barged-in fill soft foundation field
Technical field
The present invention relates to a kind of method for processing foundation, relate in particular to the method for processing foundation of interim construction roadbed on a kind of barged-in fill.
Background technology
China's Coastal Areas adopts the growth momentum of carrying out engineering construction of reclaiming fields from the sea very swift and violent.The mode of reclaiming fields from the sea mainly is to banket with what the hydraulic fill silt particle formed, is commonly called as barged-in fill.It is the very poor weak soil of a kind of engineering property, its particular structural property and full water-based, and general free-hand pedestrian almost also can't get on, and must just can be applicable to the foundation condition of construction of structures through artificial treatment.Extensive whole audience ground is carried out the ground processing or needs regional area to carry out the concrete pipe base construction; Method is varied; But no matter adopt any processing method; At first must solve the construction walking problem of constructor and all kinds of large-scale construction equipments, this just need carry out planning and designing to construction access road zone (being the big machinery track route sometimes).
Because the provisional and simplification of construction access road, so the design that its ground is handled is not often paid attention to by people.Mainly contain two kinds of ways at present:
The first, with the permanent road of site planning a part as interim construction access road.Accomplish roadbase earlier by the pavement design requirement of permanent road and handle, road surfacing is construction again before whole engineering construction is near completion.
The second, handle and the pile foundation construction flow process by the place ground, plan various construction access roads.The construction roadbed adopts lays bamboo chip plate (raft) or simple and easy wooden splint earlier; After adopt or fall (row) water or shake and various measures such as dash and carry out preliminary treatment, treat that foundation soil has certain intensity after, lay bedding and padding such as ballast aggregate, rubble; If intensity improves enough big, then do not re-lay bedding and padding.
Two kinds of ways of existing engineering all exist certain defective.
First method has in fact just been utilized the basic unit of permanent road; It is used as temporary road; Equal during whole construction, to have done the preliminary treatment that rolls repeatedly, can reduce roadbed subsidence in the future, but problem is before doing basic unit, to construct to road; Need do preliminary treatment to foundation soil equally, otherwise be difficult to the assurance personnel and machinery is walked in the above.In addition, interim builder's road not necessarily covers the track route of big machinery.
Second method is actually the conventional method of comparison of present employing.Though satisfied the construction walking problem of personnel with general small-sized machine turnover place; But it still can not satisfy the walking problem of big machinery; Simultaneously, the various ground preliminary treatment of carrying out improve limited often to intensity, and the time that need expend than length just can reach required intensity; Sometimes a large amount of bedding and padding of also having to lay, time-consuming expense material is required great effort again.
Summary of the invention
The technical issues that need to address of the present invention have provided the method for processing foundation of the interim construction roadbed on a kind of barged-in fill soft foundation field, are intended to solve the above problems.
In order to solve the problems of the technologies described above, the present invention realizes through following steps:
Adopt common standard bamboo chip plate or raft;
By the construction access road of planning, continuous laying bamboo chip plate or raft on barged-in fill should overlap each other between bamboo chip plate or the raft, and connect with steel wire lashing, guarantee the validity of overlap joint, form the integrated piece raft;
The standard bamboo chip plate of continuous laying or the length of raft confirms according to the track route needs, and width is the programme path width and extends out out 0.8-1.2 rice to both sides.
Compared with prior art, the invention has the beneficial effects as follows: solved walking problem at weak ground constructor of barged-in fill and all kinds of construction machineries.
Description of drawings
Fig. 1 adopts structural representation of the present invention.
The specific embodiment
Below in conjunction with the accompanying drawing and the specific embodiment the present invention is described in further detail:
Visible by Fig. 1: the present invention realizes through following steps:
1, adopts common standard bamboo chip plate or raft;
2, by the construction access road of planning, continuous laying bamboo chip plate or raft 2 should overlap each other between bamboo chip plate or the raft, and connect with steel wire lashing on barged-in fill 1, guarantee the validity of overlap joint, form the integrated piece raft;
3, the length of the standard bamboo chip plate of continuous laying or raft is confirmed according to the track route needs, and width is the programme path width and extends out out 0.8-1.2 rice to both sides;
In step 2: for the large-scale construction equipment track route; Lay bamboo chip plate or raft earlier; Lay thick ballast aggregate of 280-320mm or piece stone 3 then in the above, on ballast aggregate or piece stone, lay the thick rubble 4 of 70-100mm, on rubble, lay the thick plain soil 5 of 300-500mm.
Key of the present invention is that the bamboo chip plate (raft) of continuous laying has played the effect of reinforcement body in soft foundation; Can improve the mechanical characteristic of soil greatly; The level that has improved globality native in the reinforcement body region scope and soil is to continuity; The soil body after making the point load on the face of land through reinforcement is converted into evenly distributed load and reaches lower floor, has reduced the subsidiary stress of foundation soil.
The present invention adopts a kind of very simple and easy and effective continuous laying bamboo chip plate (raft) and optionally overlays the method for bedding and padding such as ballast aggregate, piece stone and rubble, has solved in weak of the barged-in fill walking problem of constructor and all kinds of large-scale construction equipments on the ground.The key of its know-why is that the bamboo chip plate (raft) of continuous and lapped layup has played the effect of reinforcement body in soft foundation; Can improve the mechanical characteristic of soil greatly; The level that has improved globality native in the reinforcement body region scope and soil is to continuity; The soil body after making the point load on the face of land through reinforcement is converted into evenly distributed load and reaches lower floor, has reduced the subsidiary stress of foundation soil.Its principle is similar to the effect of geotextiles; But it is high to have overcome the geotextiles cost; The construction trouble; Do not have rigidity and a shortcoming of meeting the easy broken invalids of sharp comer such as ballast aggregate, piece stone; Made full use of the firm and high characteristics of tensile strength of the gentle middle band of bamboo chip plate (raft), very suitable as interim construction construction timber for earth-work.

Claims (1)

1. the method for processing foundation of the interim construction roadbed on the barged-in fill soft foundation field, realize through following steps:
(1), adopts common standard bamboo chip plate or raft;
(2), by the construction access road of planning, continuous laying bamboo chip plate or raft on barged-in fill should overlap each other between bamboo chip plate or the raft, and connect with steel wire lashing, guarantee the validity of overlap joint, form the integrated piece raft;
(3), the length of the standard bamboo chip plate of continuous laying or raft confirms according to the track route needs, width is the programme path width and extends out out 0.8-1.2 rice to both sides; Wherein in step (2): for the large-scale construction equipment track route; Lay bamboo chip plate or raft earlier; Lay thick ballast aggregate of 280-320mm or piece stone then in the above, on ballast aggregate or piece stone, lay the thick rubble of 70-100mm, on rubble, lay the thick plain soil of 300-500mm.
CN 200910195707 2009-09-15 2009-09-15 Foundation treatment method for temporary construction subgrade on dredge fill soft foundation site Active CN102021871B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200910195707 CN102021871B (en) 2009-09-15 2009-09-15 Foundation treatment method for temporary construction subgrade on dredge fill soft foundation site

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200910195707 CN102021871B (en) 2009-09-15 2009-09-15 Foundation treatment method for temporary construction subgrade on dredge fill soft foundation site

Publications (2)

Publication Number Publication Date
CN102021871A CN102021871A (en) 2011-04-20
CN102021871B true CN102021871B (en) 2012-05-23

Family

ID=43863613

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200910195707 Active CN102021871B (en) 2009-09-15 2009-09-15 Foundation treatment method for temporary construction subgrade on dredge fill soft foundation site

Country Status (1)

Country Link
CN (1) CN102021871B (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102498772A (en) * 2011-11-07 2012-06-20 天津市北方园林生态科学技术研究所 Method for in-situ improvement of dredger fill into soil for planting
CN103132416A (en) * 2011-11-28 2013-06-05 四川蜀渝石油建筑安装工程有限责任公司 Method of bamboo wood handling mollisol filling highway subgrade
CN102953308B (en) * 2012-05-17 2014-11-26 湖南大学 Construction method of bamboo wood reinforcement bidirectional enhanced part-cut and part-fill weak roadbed
CN102888794B (en) * 2012-10-22 2015-09-09 安蓉建设总公司 A kind of construction method of place mat road on debris flow soft base
CN103614955B (en) * 2013-11-25 2016-03-16 中国电力工程顾问集团西南电力设计院有限公司 A kind of processing method of soft soil foundation construction road
CN107419628A (en) * 2017-04-14 2017-12-01 中交天津港湾工程研究院有限公司 A kind of construction method of the rapid build road on reclaimed ground
CN110747839A (en) * 2019-09-19 2020-02-04 国网浙江省电力有限公司建设分公司 Construction method for backfilling on soft mud flat foundation

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1035860A (en) * 1988-03-18 1989-09-27 天津石油化工公司炼油厂 Enclosing treatment of soft-earth fundation for buildings and structures
CN2519819Y (en) * 2001-11-22 2002-11-06 水利部交通部电力工业部南京水利科学研究院 Solidified foundation with horizontal water drainage board
CN1560378A (en) * 2004-03-09 2005-01-05 徐土龙 Method of processing soft foundation by quick low position high vacuum layering pre-compacting consolidation
CN2895529Y (en) * 2006-04-06 2007-05-02 沈阳建筑大学 Composite foundation of combining raft and column and external wall type foundation

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1035860A (en) * 1988-03-18 1989-09-27 天津石油化工公司炼油厂 Enclosing treatment of soft-earth fundation for buildings and structures
CN2519819Y (en) * 2001-11-22 2002-11-06 水利部交通部电力工业部南京水利科学研究院 Solidified foundation with horizontal water drainage board
CN1560378A (en) * 2004-03-09 2005-01-05 徐土龙 Method of processing soft foundation by quick low position high vacuum layering pre-compacting consolidation
CN2895529Y (en) * 2006-04-06 2007-05-02 沈阳建筑大学 Composite foundation of combining raft and column and external wall type foundation

Also Published As

Publication number Publication date
CN102021871A (en) 2011-04-20

Similar Documents

Publication Publication Date Title
CN102021871B (en) Foundation treatment method for temporary construction subgrade on dredge fill soft foundation site
CN101368383B (en) Method for treating soft soil roadbed by artificial composite crust layer
CN102296507B (en) Treatment method of subgrade cracks
CN204059124U (en) A kind of sand drain strong rammer grouting behind shaft or drift lining foundation reinforcing structure
CN204608536U (en) A kind of high-fill roadbed structure
CN204940030U (en) Reconstruction and extension project new-old concrete bond Pavement mosaic structure
CN206052680U (en) A kind of gradual change type treatment of soft foundation transition section structure
CN101634143A (en) Method for treating spiral oil-extruding filling pile composite foundation in stratum containing soft clay
CN105803922B (en) A kind of high embankment filled soil end of the bridge anti-settling structure
CN105200881B (en) The construction method of High-cold regions roadbed freeze-harm Comprehensive Treatment structure
CN104358196B (en) Highway open to traffic Embankment Subsidence disposes the construction method of structure
CN104452510B (en) Immediate construction method of rural road
CN103046446A (en) Highway reconstruction and extension project joint portion treatment structure
CN105672077A (en) Bituminous pavement geopolymer grouting construction method
CN103790151B (en) Plugging structure and construction method after a kind of soft soil roadbed draining precompressed
CN101424063A (en) Interim and permanent roads single time construction method
CN104863031A (en) Karst region ductile anti-collapse roadbed structure and construction method of Karst region ductile anti-sag roadbed structure
CN103758109B (en) For setting and the processing method of the draining rotary churning pile ground of underconsolidated soil
CN109113045A (en) A kind of soft-soil foundation treatment method
CN105220620A (en) The bumping at bridge-head processing method of darker mud soft soil foundation after platform
CN208884292U (en) Soft soil roadbed and normal roadbed intersection anti-settling structure
CN111287040A (en) Method for constructing liquid soil road
CN207452609U (en) A kind of hassock layer Foam lightweight soil road structure in deep soft foundation section
CN203096758U (en) Hard concrete smooth foundation pit for installing drainage pipeline
AU2021102288A4 (en) Composite Replacement Structure and Treatment for Soft Base of Coastal Mudflat

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee
CP01 Change in the name or title of a patent holder

Address after: 100029 Beijing, Chaoyangmen, North Street, No. 22, No.

Patentee after: China Petrochemical Group Corp.

Patentee after: SINOPEC Shanghai Engineering Company Limited

Address before: 100029 Beijing, Chaoyangmen, North Street, No. 22, No.

Patentee before: China Petrochemical Group Corp.

Patentee before: Sinopec Shanghai Engineering Co., Ltd.