CN102001347A - Method for controlling time schedules of urban rail transit electromechanical equipment - Google Patents

Method for controlling time schedules of urban rail transit electromechanical equipment Download PDF

Info

Publication number
CN102001347A
CN102001347A CN2010105493420A CN201010549342A CN102001347A CN 102001347 A CN102001347 A CN 102001347A CN 2010105493420 A CN2010105493420 A CN 2010105493420A CN 201010549342 A CN201010549342 A CN 201010549342A CN 102001347 A CN102001347 A CN 102001347A
Authority
CN
China
Prior art keywords
time schedule
equipment
time
equipment group
mode number
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2010105493420A
Other languages
Chinese (zh)
Other versions
CN102001347B (en
Inventor
许超
张慎明
王军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nari Technology Co Ltd
NARI Nanjing Control System Co Ltd
Original Assignee
Nari Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nari Technology Co Ltd filed Critical Nari Technology Co Ltd
Priority to CN2010105493420A priority Critical patent/CN102001347B/en
Publication of CN102001347A publication Critical patent/CN102001347A/en
Application granted granted Critical
Publication of CN102001347B publication Critical patent/CN102001347B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]

Landscapes

  • Programmable Controllers (AREA)

Abstract

The invention discloses a method for controlling time schedules of urban rail transit electromechanical equipment, which comprises the following steps of: 1. dividing equipment groups; 2. defining operational mode numbers; 3. defining the starting time of the operational mode numbers; and 4. issuing and executing the contents of the time schedules to realize equipment control. By using the method disclosed by the invention, the problem on efficient management and control of complicated electromechanical equipment in the rail transit operation process can be solved, the dispatching management efficiency of the electromechanical equipment is greatly improved, the effect of fast response during normal operation and emergency can be achieved, the functions of full-scale diagnosis and fault positioning and warning for stations and interval equipment can be realized, and the safety and the comfort degree of the urban rail transit operation can be improved.

Description

The time schedule control method of urban track traffic electromechanical appliance
Technical field
The present invention relates to a kind of implementation method of electromechanical appliance time schedule controllable function of comprehensive monitoring system, belong to urban track traffic comprehensively monitoring technical field.
Background technology
Be the safety of assurance urban track traffic operation and passenger's traveling comfort, comprehensive monitoring system AT STATION, interval and parking area etc. all installed a large amount of, multi-specialized electromechanical appliance everywhere, as: station Escalator, power and lighting, air-conditioning unit, handpiece Water Chilling Units, interval blower fan, interval water pump, parking area boiler, or the like.
Utilize the mechanism of electromechanical appliance management and running efficiently, comprehensive monitoring system can realize vehicle, signal in normal operation and can rapid reaction when urgent, and station, interval comprehensive diagnostic, fault localization and warning function, can improve the emergency handling ability.
Summary of the invention
In order to overcome the deficiencies in the prior art, the object of the present invention is to provide a kind of monitoring function that how to utilize comprehensive monitoring system to electromechanical appliance, simplify the management process of urban track traffic running scheduling, thereby improve the time schedule control method of the urban track traffic electromechanical appliance of efficiency of operation all kinds of electromechanical appliances.
The present invention is achieved through the following technical solutions:
The time schedule control method of urban track traffic electromechanical appliance is characterized in that, may further comprise the steps:
(1) divide the equipment group: utilize the monitoring function of comprehensive monitoring system to all kinds of electromechanical appliances, and the correlativity of each equipment operation, all electromechanical appliances are divided into a plurality of equipment groups;
(2) definition operational mode number: according to the needs of urban track traffic operation, in comprehensive monitoring system, define a plurality of operational modes number for ready-portioned each equipment group in the step (1), each operational mode number is corresponding with certain running state of equipment in the equipment group, and in the Programmable Logic Controller of comprehensive monitoring system, only distribute a register that is used to deposit operational mode number, guarantee that any time each equipment group only moves a mode number for each equipment group;
(3) run up time of definition operational mode number: based on the different operational modes of each equipment group number, the run up time of definition each operational mode number in comprehensive monitoring system, promptly realize operational mode number and run up time using the analog data of formation time table in pairs;
(4) issuing also, the implementation schedule content realizes device control: the analog data of a plurality of equipment groups that form in the step (3) is the main contents of time schedule, comprehensive monitoring system passage period table function assembly to the content of time schedule edit, check, issue, shared management and executable operations, the analog data of time schedule is handed down to Programmable Logic Controller, the control logic of Programmable Logic Controller is discerned the time schedule content, realizes the control to each equipment.
Above-mentioned equipment group comprises:
Station power and lighting equipment group, it comprises station intraoral illumination equipment (containing escape information sign, emergency lighting etc.), interval light equipment and 0.4KV power plant;
Station air conditioner equipment group, it comprises that the big system in station is that public domain ventilation and air conditioning system and station mini system are on duty and equipment room ventilation and air conditioning system;
Running tunnel draft equipment group;
Station air conditioner water equipment group;
Escalator equipment group;
The plumbing equipment group.
In addition, above-mentioned time schedule also has additional data, it comprises the ID that is used for the definition time table, add automatically when issuing at every turn 1 issue Serial Data and time schedule version number, additional data are issued in the Programmable Logic Controller together.
And above-mentioned time schedule function block comprises:
Time schedule editor and scan tool;
Time schedule issues management tool;
The shared time schedule management tool in all fronts;
Time schedule allows or forbids the operation management instrument.
Wherein:
Time schedule editor and scan tool are at first for the time schedule content is formulated at the station, the definition time table name claims that then, the time schedule of finishing editor is kept in the comprehensive monitoring system, and checks the content of time schedule by comprehensive monitoring system.
Time schedule issues management tool issuing of time schedule is provided with two kinds of executive modes: being ranked issues and issues immediately:
Be ranked and issue: editor's time schedule was issued with predetermined or regular time, set the time schedule that issues from every day on Monday to Sunday;
Issue immediately: come into force behind the edit session table, the times selected table is handed down to Programmable Logic Controller immediately, and start execution.
Shared time schedule management tool is unified operation with the time schedule that a plurality of stations, all fronts have same title completely.
And above-mentioned time schedule allows or forbid that the operation management instrument is provided with time schedule " allow or forbid " zone bit for each equipment group, when being set to " permission ", only the mode number in the implementation schedule is not carried out the control command that other pattern control and equipment point are controlled; When being set to " forbidding ", mode number or device control that comprehensive monitoring system is accepted manually to issue are instructed, and allow to adjust indivedual mode number or equipment running status.
Gordian technique point of the present invention is:
1, utilizes the monitoring function of abundant comprehensive monitoring system, all electromechanical appliances are sorted out, be divided into some equipment groups that in operation, interrelate all kinds of electromechanical appliances;
2, in comprehensive monitoring system, design some operational modes for each equipment group;
3,, in comprehensive monitoring system, define the some assemblies and the realization mechanism thereof of time schedule controllable function based on each operational mode of each equipment group.
The time schedule function of comprehensive monitoring system adopts the mode of layering supervision, control, that is: time schedule is only managed operational mode number, number control each concrete equipment operation by operational mode, operational mode is number towards each equipment group, the equipment that the technology contact is arranged between mutually returned together control, allow the operational mode number operation simultaneously of a plurality of distinct device groups in the time schedule, and do not allow a plurality of operational modes number operation simultaneously of same equipment group.
The main contents of time schedule are by mode number and constitute in pairs its run up time, edit at the comprehensive monitoring system of control center; Resolve, carry out by Programmable Logic Controller after editor finishes, and the feedback execution result; If all mode number successful operations, then this time schedule is in running state, thereby makes the requirement operation of each equipment according to management and running.
The invention has the beneficial effects as follows: adopt method of the present invention, solved the difficult problem of the high efficiency management and control of numerous and diverse electromechanical appliance in the track traffic, improved the efficient of electromechanical appliance management and running greatly, in normal operation and can rapid reaction when urgent, realization can improve the safety and the comfort level of urban track traffic operation to comprehensive diagnostic, fault localization and the warning function of station, interval equipment.
Description of drawings
Fig. 1 is the logical organization scheme drawing of time schedule of the present invention.
The specific embodiment
Below in conjunction with accompanying drawing, describe the specific embodiment of the present invention in detail:
Fig. 1 is the logical organization scheme drawing of time schedule of the present invention.
The control method of urban track traffic electromechanical appliance time schedule may further comprise the steps:
(1) divide the equipment group: utilize the monitoring function of comprehensive monitoring system to all kinds of electromechanical appliances, and the correlativity of each equipment operation, all electromechanical appliances are divided into a plurality of equipment groups;
(2) definition operational mode number: according to the needs of urban track traffic operation, in comprehensive monitoring system, define a plurality of operational modes number for ready-portioned each equipment group in the step (1), the running state of certain operational outfit in each operational mode number and the equipment group is corresponding, and in the Programmable Logic Controller of comprehensive monitoring system, only distribute a register (Word) that is used to deposit operational mode number for each equipment group, comprehensive monitoring system only moves the operational mode number in this register (Word), guarantees that any time each equipment group only moves an operational mode number;
(3) run up time of definition operational mode number: based on the different operational modes of each equipment group number, the run up time of definition each operational mode number in comprehensive monitoring system, promptly realize using in pairs operational mode number and run up time, the analog data of formation time table is to realize the time schedule controllable function of comprehensive monitoring system;
(4) issue the time schedule content and realize device control: the analog data that forms in the step (3) is the main contents of time schedule, each to the simulate data amount represent respectively one " mode number " and its activation time (since 0: 0 with hour and minute represent, that is: 0000 to 2359), comprehensive monitoring system passage period table function assembly is edited the content of time schedule, check, issue, shared management and operation, the analog data of time schedule is handed down to Programmable Logic Controller (PLC), the control logic of Programmable Logic Controller is discerned the time schedule content, and circulation in 0: 0, the logical organization of time schedule content as shown in Figure 1, each time schedule all has two extra additional data, the ID that is used for the definition time table, issue Serial Data (adding 1 automatically when at every turn issuing) and time schedule version number, be issued in the lump in the Programmable Logic Controller, realize control each equipment.
Wherein, above-mentioned equipment group comprises:
Station power and lighting equipment group, it comprises station intraoral illumination equipment (containing escape information sign, emergency lighting etc.), interval light equipment and 0.4KV power plant;
Station air conditioner equipment group, it comprises that the big system in station is that public domain ventilation and air conditioning system and station mini system are on duty and equipment room ventilation and air conditioning system;
Running tunnel draft equipment group;
Station air conditioner water equipment group;
Escalator equipment group;
The plumbing equipment group.。
And above-mentioned time schedule function block comprises:
Time schedule editor and scan tool, it is at first for the time schedule content is formulated at the station, the definition time table name claims, as: working day time schedule, major holiday time schedule etc., then, the time schedule of finishing editor is kept in the comprehensive monitoring system, and checks the content of time schedule by comprehensive monitoring system, comprehensive monitoring system generally allows each station to use maximum 10 time schedules that (or more) are different, and the time schedule of finishing editor is kept in the comprehensive monitoring system.In the comprehensive monitoring system at control center and station, can view the content of all 10 (or more) time schedules of being preserved;
Time schedule issues management tool, and it is provided with two kinds of executive modes to issuing of time schedule: being ranked issues and issues immediately:
Be ranked and issue: editor's time schedule was issued with predetermined or regular time, set the time schedule that issues from every day on Monday to Sunday;
Issue immediately: come into force behind the edit session table, the times selected table is handed down to Programmable Logic Controller immediately, and start execution;
The shared time schedule management tool in all fronts, it unifies operation with the time schedule that a plurality of stations, all fronts have same title, simplify the operation course, that is: permission is carried out unified operation such as " be ranked and issue " or " issuing immediately " to the time schedule of the same title at a plurality of stations, when shared time schedule being carried out " issuing immediately " or " be ranked and issue " when operation, the station that has this time schedule title completely will be carried out and be issued operation accordingly;
Shared time schedule is a LnkTools, if comprehensive monitoring system issues for certain shared time schedule (is " time schedule Holiday " such as table name) is provided with to be ranked, this is provided with in the comprehensive monitoring system that can be saved in completely all stations of containing " time schedule Holiday " automatically so, completely all stations with this time schedule will at the appointed time automatically perform the operational mode number in this time schedule, and shared time schedule function also provides the statistics that issues the result to show.
Time schedule allows or forbids the operation management instrument, and it is provided with time schedule " allow or forbid " zone bit for each equipment group, and when being set to " permissions ", the mode number in the implementation schedule is not only carried out the control command that other pattern control and equipment point are controlled; When being set to " forbidding ", mode number that comprehensive monitoring system can be accepted manually to issue or device control instruction allow to adjust indivedual mode number or equipment running status.
The comprehensive monitoring system time schedule adopts the mode of supervising by different level, controlling, that is: time schedule is only managed operational mode number, number control each concrete equipment operation by operational mode, operational mode is number towards each equipment group, the equipment that the technology contact is arranged between mutually returned together control, allow the operational mode number operation simultaneously of a plurality of distinct device groups in the time schedule, and do not allow a plurality of operational modes number operation simultaneously of the different equipment of same equipment group.
The main contents of time schedule are by mode number and constitute its run up time, edit at the comprehensive monitoring system of control center; Resolve, carry out by Programmable Logic Controller (PLC) after editor finishes, and the feedback execution result; If all mode number successful operations, then this time schedule is in running state, thereby makes the requirement operation of each equipment according to management and running.
Below disclose the present invention with preferred embodiment, so it is not in order to restriction the present invention, and all employings are equal to replaces or technical scheme that the equivalent transformation mode is obtained, all drops within protection scope of the present invention.

Claims (8)

1. the time schedule control method of urban track traffic electromechanical appliance is characterized in that, may further comprise the steps:
(1) divide the equipment group: utilize the monitoring function of comprehensive monitoring system to all kinds of electromechanical appliances, and the correlativity of each equipment operation, all electromechanical appliances are divided into a plurality of equipment groups;
(2) definition operational mode number: according to the needs of urban track traffic operation, in comprehensive monitoring system, define a plurality of operational modes number for ready-portioned each equipment group in the step (1), each operational mode number is corresponding with certain running state of equipment in the equipment group, and in the Programmable Logic Controller of comprehensive monitoring system, only distribute a register that is used to deposit operational mode number, guarantee that any time each equipment group only moves a mode number for each equipment group;
(3) run up time of definition operational mode number: based on the different operational modes of each equipment group number, the run up time of definition each operational mode number in comprehensive monitoring system, promptly realize operational mode number and run up time using the analog data of formation time table in pairs;
(4) issuing also, the implementation schedule content realizes device control: the analog data of a plurality of equipment groups that form in the step (3) is the main contents of time schedule, comprehensive monitoring system passage period table function assembly to the content of time schedule edit, check, issue, shared management and executable operations, the analog data of time schedule is handed down to Programmable Logic Controller, the control logic of Programmable Logic Controller is discerned the time schedule content, realizes the control to each equipment.
2. the time schedule control method of urban track traffic electromechanical appliance according to claim 1 is characterized in that, described equipment group comprises:
Station power and lighting equipment group, it comprises station intraoral illumination equipment, interval light equipment and 0.4KV power plant;
Station air conditioner equipment group, it comprises that the big system in station is that public domain ventilation and air conditioning system and station mini system are on duty and equipment room ventilation and air conditioning system;
Running tunnel draft equipment group;
Station air conditioner water equipment group;
Escalator equipment group;
The plumbing equipment group.
3. the time schedule control method of urban track traffic electromechanical appliance according to claim 1, it is characterized in that, described time schedule also has additional data, it comprises the ID that is used for the definition time table, add automatically when issuing at every turn 1 issue Serial Data and time schedule version number, additional data are issued in the Programmable Logic Controller together.
4. the control method of urban track traffic electromechanical appliance time schedule according to claim 1 is characterized in that, described time schedule function block comprises:
Time schedule editor and scan tool;
Time schedule issues management tool;
The shared time schedule management tool in all fronts;
Time schedule allows or forbids the operation management instrument.
5. the time schedule control method of urban track traffic electromechanical appliance according to claim 4, it is characterized in that, described time schedule editor and scan tool are at first for the time schedule content is formulated at the station, the definition time table name claims, then, the time schedule of finishing editor is kept in the comprehensive monitoring system, and checks the content of time schedule by comprehensive monitoring system.
6. the time schedule control method of urban track traffic electromechanical appliance according to claim 4 is characterized in that, described time schedule issues management tool issuing of time schedule is provided with two kinds of executive modes: being ranked issues and issues immediately, wherein:
Be ranked and issue: editor's time schedule was issued with predetermined or regular time, set the time schedule that issues from every day on Monday to Sunday;
Issue immediately: come into force behind the edit session table, the times selected table is handed down to Programmable Logic Controller immediately, and start execution.
7. the time schedule control method of urban track traffic electromechanical appliance according to claim 4 is characterized in that, the shared time schedule management tool in described all fronts is unified operation with the time schedule that a plurality of stations, all fronts have same title.
8. the time schedule control method of urban track traffic electromechanical appliance according to claim 4, it is characterized in that, described time schedule allows or forbids that the operation management instrument is provided with time schedule " allow or forbid " zone bit for each equipment group, when being set to " permission ", only the mode number in the implementation schedule is not carried out the control command that other pattern control and equipment point are controlled; When being set to " forbidding ", mode number or device control that comprehensive monitoring system is accepted manually to issue are instructed, and allow to adjust indivedual mode number or equipment running status.
CN2010105493420A 2010-11-18 2010-11-18 Method for controlling time schedules of urban rail transit electromechanical equipment Active CN102001347B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010105493420A CN102001347B (en) 2010-11-18 2010-11-18 Method for controlling time schedules of urban rail transit electromechanical equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010105493420A CN102001347B (en) 2010-11-18 2010-11-18 Method for controlling time schedules of urban rail transit electromechanical equipment

Publications (2)

Publication Number Publication Date
CN102001347A true CN102001347A (en) 2011-04-06
CN102001347B CN102001347B (en) 2012-08-15

Family

ID=43809132

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010105493420A Active CN102001347B (en) 2010-11-18 2010-11-18 Method for controlling time schedules of urban rail transit electromechanical equipment

Country Status (1)

Country Link
CN (1) CN102001347B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108170110A (en) * 2017-12-26 2018-06-15 中交机电工程局有限公司 Urban track traffic electronic & mechanic machine control system
CN113777959A (en) * 2020-06-10 2021-12-10 南京南瑞继保工程技术有限公司 Mode sequential control method and device based on comprehensive monitoring system

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3347286B2 (en) * 1998-04-15 2002-11-20 三菱電機株式会社 Train operation control device
JP2005319927A (en) * 2004-05-11 2005-11-17 Hitachi Ltd Train diagram display device
CN101492062A (en) * 2009-03-11 2009-07-29 卓越信通电子(北京)有限公司 Deep integration and interconnection method for track traffic system

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3347286B2 (en) * 1998-04-15 2002-11-20 三菱電機株式会社 Train operation control device
JP2005319927A (en) * 2004-05-11 2005-11-17 Hitachi Ltd Train diagram display device
CN101492062A (en) * 2009-03-11 2009-07-29 卓越信通电子(北京)有限公司 Deep integration and interconnection method for track traffic system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108170110A (en) * 2017-12-26 2018-06-15 中交机电工程局有限公司 Urban track traffic electronic & mechanic machine control system
CN113777959A (en) * 2020-06-10 2021-12-10 南京南瑞继保工程技术有限公司 Mode sequential control method and device based on comprehensive monitoring system

Also Published As

Publication number Publication date
CN102001347B (en) 2012-08-15

Similar Documents

Publication Publication Date Title
CN202703637U (en) Rail transit integrated automation system based on traffic command
CN103631234B (en) A kind of intelligent optimization dispatching method of cascade hydropower Masterstation Automation System
CN104299475A (en) Simulator used for automatic monitoring system of train
CN102001347B (en) Method for controlling time schedules of urban rail transit electromechanical equipment
CN102556125A (en) Maintenance support system of automatic train control system
CN110705808A (en) Power transmission network planning scheme generation system and method considering maintenance under new energy access
CN103738369A (en) ATS device and system based on OPC UA technology
CN109308586A (en) Planning method of rail transit emergency response program based on progress control management
WO2018007345A1 (en) Method and device for monitoring a power supply device of a traffic system
CN117495034A (en) Subway carbon management system and method based on ISCS
CN109249961A (en) One kind being suitable for the unpiloted comprehensive monitoring system of rail traffic
CN104217620A (en) Nuclear power plant full-scope simulator auxiliary operation panel lamp test system and method
CN201842547U (en) SOC field programmable elevator system
Leso The Railway 4.0 Concept–the vision of a digital railway in the Czech Republic (CR)
CN102050139B (en) Method for comprehensively monitoring BAS (Building Automation System) schedule functions
Ferreira et al. The contribution of automation to resilience in rail traffic control
CN102681456B (en) Device and method capable of self-combining network and programming and used for collecting, processing and outputting signals
CN106059075B (en) Extra-high voltage direct-current is latched by the accurate lot control system of end load
CN113071539A (en) Magnetic suspension traffic comprehensive monitoring system
Van Dijk et al. Small-scale hydropower development for rural electrification in South Africa
Dong et al. Parallel transportation management and control system for subway systems based on ACP approach
CN103365221B (en) The control method of wind-driven generator
Khujaev et al. Features of improving the operation of the ventilation system in underground communication structures
CN113212500B (en) Rail transit signal and vehicle professional interface linkage verification method and device
KR101221842B1 (en) Train group management system for energy saving

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: NARI NANJING CONTROL SYSTEM LTD.

Effective date: 20141202

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20141202

Address after: High road Pukou high tech Development Zone in Nanjing city of Jiangsu Province, No. 4 Building 210061 19-1

Patentee after: NARI Technology Development Co., Ltd.

Patentee after: SGCC NARI Nanjing Control System Co., Ltd.

Address before: High road high tech Zone of Nanjing City, Jiangsu Province, No. 20 210061

Patentee before: NARI Technology Development Co., Ltd.