CN101973649B - Continuous sewage treatment device for petroleum gas well - Google Patents

Continuous sewage treatment device for petroleum gas well Download PDF

Info

Publication number
CN101973649B
CN101973649B CN 201010296124 CN201010296124A CN101973649B CN 101973649 B CN101973649 B CN 101973649B CN 201010296124 CN201010296124 CN 201010296124 CN 201010296124 A CN201010296124 A CN 201010296124A CN 101973649 B CN101973649 B CN 101973649B
Authority
CN
China
Prior art keywords
pipe
angle steel
pond
wall
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN 201010296124
Other languages
Chinese (zh)
Other versions
CN101973649A (en
Inventor
杨学锋
李辉
陈文斌
蒋学彬
李萍
陈立荣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China National Petroleum Corp
CNPC Chuanqing Drilling Engineering Co Ltd
Original Assignee
CNPC Chuanqing Drilling Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CNPC Chuanqing Drilling Engineering Co Ltd filed Critical CNPC Chuanqing Drilling Engineering Co Ltd
Priority to CN 201010296124 priority Critical patent/CN101973649B/en
Publication of CN101973649A publication Critical patent/CN101973649A/en
Application granted granted Critical
Publication of CN101973649B publication Critical patent/CN101973649B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Sewage (AREA)

Abstract

The invention discloses a continuous sewage treatment device for a petroleum gas well, which relates to the technical field of the environmental pollution control of petroleum gas wells. The device comprises a control room, a treating pond and a reverse osmosis device, wherein a pipe rack structure is arranged among the control room, the treating pond and the reverse osmosis device. In the device, the pipe rack structure is arranged among the control room, the treating pond and the reverse osmosis device, and polyvinyl chloride (PVC) pipes can be put into order by using grooves formed among clapboards due to the specific structure of a pipe rack, so that pipes in a mess can be put into order and the appearance of the continuous treatment device is improved. Due to the specific structure of a pipe rack passageway, operating personnel only needs to pass through a passageway plate easily and conveniently without treading the PVC pipes when the operating personnel needs to pass though the region, so that the operating personnel is prevented from being stumbled and hurt by the pipes.

Description

Oil and gas well drilling sewage apparatus for continous treatment
Technical field
The present invention relates to oil and gas well drilling environmental pollution treatment technology field, exactly relate to a kind of oil and gas well drilling sewage apparatus for continous treatment, be used for the continuous processing of oil and gas well drilling sewage.
Background technique
In the oil and gas well drilling, need handle continuously, occur on the market thus carrying out processed continuously device to sewage to sewage.
In the existing technology; Publication number is CN101139147; The Chinese patent file that open day is on March 12nd, 2008 discloses a kind of oil drilling continuous processing technique; Comprise the steps: stone oil well drilling sullage continuous processing technique, comprise the steps: that coagulation-help coagulates-deposition-filtration-oxidation absorption-qualified discharge.The present invention efficiently solves and combines difficult, not good, the discontinuous problem of disposing of sewage of treatment effect between the cell processing of stone oil well drilling sullage; Not only reduce sewage colourity and other pollutants; Especially can effectively remove being dissolved in pollutants in sewage matter; And chemical coagulation sedimentation, catalytic oxidation and physical absorption are applied in the cover flow process, realize that sewage continuously, after the depth treatment, meet the qualified discharge standard.
Simultaneously, publication number is CN201074193, and the Chinese patent file that open day is June 18 in 2008 discloses a kind of oil drilling apparatus for continous treatment.Comprise the coagulating basin that is communicated with through pipeline successively, help pond, deposition tank with fixed attention, also comprise the filter basin that are communicated with the deposition tank pipeline, the oxidation adsorption tank that is communicated with the filter basin pipeline.The utility model efficiently solves and combines difficult, not good, the discontinuous problem of disposing of sewage of treatment effect between each cell processing pond of stone oil well drilling sullage; Not only reduce sewage colourity and other pollutants; Especially can effectively remove being dissolved in pollutants in sewage matter; And each single treatment device is integrated, realizes that sewage continuously, after the depth treatment, meet the qualified discharge standard.
At present; Usually use the CN101139147 treatment process; With the CN201074193 treatment device sewage is handled continuously; Above-mentioned apparatus for continous treatment is divided by function and is comprised control room, treatment pond, reverse osmosis unit three parts basically, but there is following shortcoming in above-mentioned oil and gas well drilling sewage apparatus for continous treatment:
1, the Chi Kou of each treatment pond of drilling waste water apparatus for continous treatment end face is the open type state.In the treatment pond top-side one narrower passageway is installed, in the design and installation of both sides, passageway railing is arranged, operator operate very inconvenient in the above, when needs clear a fence when operating, the risk that crashes into treatment pond are just arranged.
2, in each processing unit of drilling waste water apparatus for continous treatment, each unit cells notch portion does not have the design of reinforcing, and is carrying out drilling waste water when handling continuously; Because each unit water level is not at sustained height; Along with the passing of service time, each unit cells oralia distortion is comparatively serious, and each handles the unit cells oralia can become waveform; Had a strong impact on working life, thereby influenced the trouble-free operation of whole apparatus for continous treatment.
3, the turnover water pipe of each processing unit of drilling waste water apparatus for continous treatment and drain pipe layout is comparatively messy, at first, seems not attractive in appearance; Secondly; When carrying, be easy to the import and export joint that stretches out is broken, simultaneously, the structural type of drain pipe exists such problem too.
4, in the drilling waste water apparatus for continous treatment precipitation unit; Collector pipe is to be placed on the angle steel shelf that is welded on the pool wall; Such structural type makes the space below the shelf just can not place the bigger parts of volume; And because the precipitation unit swash plate is contained in the tilting box, place collector pipe as still adopting aforesaid way, tilting box just can not be in place on request.
5, in the existing technology, it is the glass wood tile that precipitation unit is used more corrugated sheet, and the form of plastic honeycomb board as swash plate that adopt also arranged, and general the employing approaches corrosion resistant plate.But the said structure form because fixing not firm, causes corrugated sheet along with being flowing in the deposition tank of sewage swung, and after sewage was static, swash plate was in original position, thereby influenced sedimentation effect.
6, drilling waste water apparatus for continous treatment control room did not have the design of wall coil, and all pipelines all stretch out through the rectangular opening that the body of wall in the control room is left, and outside body of wall, connected the PVC armoured hose again.Cross the fixing of wall coil for each, on ground, control room, be welded with the piping support frame.But because each pipeline stretches out side by side; Distance is very little between the tube and tube, does not just have the position that nameplate is installed, and makes that each pipeline sign is unclear; And because drillng operation in the open air; Toy such as mouse, snake will creep into from the rectangular opening that the control room body of wall is left in the control room, can cause mouse to bite the equipment electric wire broken, and snake is taken place the accident that personnel damage.
7, existing drilling waste water apparatus for continous treatment is provided with various PVC steel wires and reinforces flexible pipe, is used for each pump in each pond of treatment pond and control room is coupled together.Various pvc pipe bulk storages on the ground, and are very messy, on the one hand influenced the apparatus for continous treatment overall appearance and not attractive in appearance, very inconvenient when the people need be from the zone passage of these bulk storage pipes on the other hand, even possibly tripped and tumble injury.
Summary of the invention
For solving the problems of the technologies described above; The present invention proposes a kind of processed continuously device that is used for oil and gas well drilling sewage; The invention solves when needs and clear a fence when operating, the technical problem of the risk that crashes into treatment pond is just arranged, realized operator's safety operation; Simultaneously, along with the passing of service time, the pond oralia also can be prolonged indeformable; Long service life is for the trouble-free operation of whole apparatus for continous treatment provides good assurance, when carrying; The joint of turnover water pipe and drain pipe can not broken, and having solved tilting box can not technical problem in place on request, after sewage is static; The corrugated sheet original position of still can returning, sedimentation effect is very good, does not need that the mounting pipe bearing support fixed wall coil in the control room; Practice thrift cost, and also avoided causing in the toy inlet chambers such as mouse, snake the accident of device damage and casualties to take place, eliminated potential safety hazard; Do not need that the mounting pipe bearing support fixed wall coil in the control room; Practice thrift cost, and also avoided causing in the toy inlet chambers such as mouse, snake the accident of device damage and casualties to take place, eliminated potential safety hazard.
The present invention realizes through adopting following technical proposals:
A kind of oil and gas well drilling sewage apparatus for continous treatment comprises control room, treatment pond and reverse osmosis unit, it is characterized in that: be provided with the pipe bent structure between control room, treatment pond and the reverse osmosis unit; The pipe bent structure comprises pipe row support; Said pipe row support comprises two sole bar angles, and upper fixed connects at least two located lateral angle steel between two sole bar angles, on the sole bar angle between the two located lateral angle steel; Be set with equally distributed a plurality of dividing plate; It is identical with the located lateral angle steel that dividing plate is provided with direction, and the respective diaphragms position consistency on two sole bar angles forms the groove that can place pvc pipe between any two dividing plates on each sole bar angle.
The pipe bent structure also comprises pipe row passageway, and said pipe row passageway comprises at least two horizontal angle steel, and two horizontal angle steel and said two located lateral angle steel are complementary; And laterally angle steel is provided with locating stud, has U-groove bevel on the said located lateral angle steel, and locating stud matches with U-groove bevel; Be set with guidance tape between the two horizontal angle steel; A plurality of pvc pipes are crossed in the space that forms between guidance tape and the said sole bar angle said, and the outside of two horizontal angle steel respectively is provided with two inclination sole bar angles, and an end of two inclination sole bar angles contacts with ground; The other end is fixed on the horizontal angle steel, also is fixed with guidance tape between the two inclination sole bar angles.
The treatment pond top structure comprises pond, end mouth body of wall and pond, side mouth body of wall; Between the mouth body of wall of pond, bi-side, the support square steel is installed; With supporting on the square steel passageway bracket is installed at pond, said end mouth body of wall; Embedded passageway between pond, end mouth body of wall and support square steel is fixedly connected with said passageway bracket; Be provided with the sole bar angle that is fixed between support square steel and pond, the end mouth body of wall along pond, side mouth wall direction, the plane that the special-shaped angle steel at sole bar angle and edge, embedded passageway forms is provided with the loose-leaf type cover net cover that covers treatment pond, and closed guard rail is installed around treatment pond.
Treatment pond comprises pond oralia structure, and the side of the pond oralia of each unit is provided with angle steel, and the cross section of angle steel is isosceles triangle, and the base of isosceles triangle is welded on the side of said pond oralia.
Treatment pond comprises turnover water pipe structure and drain pipe structure; Said turnover water pipe structure comprises rapid pipe joint, piping support folder, two union formula ball valve, CPVC pipe, crossover sub, 90 ° of elbows, union loose joint and Stainless Steel Elbows; Have water inlet and weep hole on the treatment pond body of wall; Stainless Steel Elbow is welded in said water inlet and the weep hole; Crossover sub, CPVC pipe, two union formula ball valve, piping support folder are connected with rapid pipe joint successively, and loose joint is connected 90 ° of elbows successively with union; Said drain pipe structure comprises blowdown valve outlet connection, CPVC adpting flange, threeway, big union loose joint, big CPVC pipe, bassoon holding clamp and blowdown valve; Wherein, Blowdown valve is installed on the flange of deposition tank lower box; Threeway, big union loose joint, big CPVC pipe, CPVC adpting flange connect successively, and the bassoon holding clamp is welded on the skid base flat board, and the blowdown valve outlet connection is installed on the CPVC adpting flange.
The treatment pond precipitation unit comprises that collector pipe is with folding bearing support; Folding bearing support comprises the hinge base that is welded on the precipitation unit pool wall; Be fixed on the joint pin on the hinge base, with the support plate that is connected with joint pin, said support plate is around the reciprocal 180 degree rotations of said joint pin.
The treatment pond precipitation unit comprises corrugated board box; Corrugated board box comprises the corrugated board box main body that is formed by the angle steel rectangular frame; Be welded with two root bottom part angle steel in said angle steel rectangular frame bottom, be welded with four both sides angle steel respectively, on the angle steel of said both sides, be welded with the stainless steel round steel in angle steel rectangular frame both sides; A plurality of stainless steel round steel dislocation welding are fixing and in the angle steel rectangular frame, form inclined spaces; Angle steel rectangular frame top is provided with spacing angle steel, and corrugated sheet is spacing in said inclined spaces through bottom angle steel, both sides angle steel, stainless steel round steel and spacing angle steel.
The control room was provided with the wall coil structure, was included in the porthole of offering on the interior wall of control room of crossing, and passed the wall coil of crossing of porthole; With the wall coil connecting plate excessively that is threaded with the indoor end of mistake wall coil; Saidly cross wall coil and cross the porthole drive fit, the sectional area of crossing the wall coil connecting plate is greater than the said sectional area of crossing porthole, and the control room is outside equipped with the lengthening joint pipe; The lengthening joint pipe runs through said to be crossed in the wall coil, and the pipe that inputs or outputs in the control room is connected with said lengthening joint pipe thread through crossover sub.
Compared with prior art, the technique effect that the present invention reached is following:
1, among the present invention; Be provided with the pipe bent structure between control room, treatment pond and the reverse osmosis unit; Each groove that the concrete structure of pipe row support makes each pvc pipe all can be formed between the dividing plate is put in order; Each pipe that can be very messy is put in order very regularly, has improved the aesthetic property of apparatus for continous treatment.The concrete structure in pipe row passageway makes that operator need be from this zone through out-of-date, only need from cross guidance tape through and the pvc pipe of can not stepping on, very convenient easily, stopped to occur to be tripped and the situation of tumble injury takes place by pipe.Pipe row passageway is provided with the inclination sole bar angle, is provided with guidance tape between the inclination sole bar angle, and with regard to the up and down whole pipe row of ability easy-to-operat personnel passageway, whole pipe bent structure also seems very attractive in appearance like this.
2, among the present invention; The treatment pond top structure, owing to the Chi Kou top of the structure that adopts embedded passageway and loose-leaf type cover net cover with treatment pond covers in fully, and the guard rail of design and installation sealing around treatment pond; Make the treatment pond top form a platform; Solved when needs and cleared a fence when operating, the technical problem of the risk that crashes into treatment pond has just been arranged, realized operator's safety operation.
3, among the present invention, pond oralia structure adopts cross section to be the angle steel of isosceles triangle and such consolidation process is fixed in the side welding of pond oralia; After permanent the use, the pond oralia can not be out of shape yet, and is able to working life prolong; Each Chi Kou carries out drilling waste water under different water levels handles continuously; Each unit cells oralia produces distortion all the time, has satisfied designing requirement, for the trouble-free operation of whole apparatus for continous treatment provides good assurance.
4, among the present invention, turnover water pipe structure and drain pipe structure, very both artistic and practical; Simple in structure, when carrying, owing to have water inlet and weep hole on the bay wall body; Stainless Steel Elbow is welded in water inlet and the weep hole, so the joint of turnover water pipe and drain pipe can not broken.
5, among the present invention, precipitation unit comprises that collector pipe with folding bearing support, adopts hinge base and precipitation unit pool wall are fixed; Support plate can around reciprocal 180 degree of joint pin promptly about the mode of each 90 degree rotation, when needs prevent tilting box, can support plate is folding to the pool wall face; After placing tilting box, again support plate is turned back original position and be used to place header tank, tilting box can be in place as requested; The present invention is simple in structure, and is convenient and practical.
6, among the present invention, precipitation unit comprises corrugated board box, is welded with two root bottom part angle steel owing to be employed in base of frame; Corrugated sheet is not fallen down at the bottom of the precipitation unit,, in framework, just formed the space of an inclination because the dislocation of stainless steel round steel is welded; The stupefied plate of henry chloranthus herb is put into these spaces respectively, the more spacing angle steel of frame roof is fixed with the bolt two ends, corrugated sheet just is limited in the inclined spaces that the spacing angle steel by bottom angle steel, both sides angle steel, front and back stainless steel round steel, top forms; When sewage transport to precipitation unit, along with the flowing and roll of sewage, corrugated sheet is all the time in inclined spaces; Can not drift with the tide; After sewage was static, corrugated sheet was got back to original position under the effect of gravity, and sedimentation effect is very good.
7, among the present invention, the control room was provided with the wall coil structure, owing in control, offered porthole; With mistake porthole drive fit wall coil was arranged, and outdoor equipment was connected such mode with indoor CPVC pipe after passing wall coil through the lengthening joint pipe through crossover sub; Separately each pipe all has one and crosses porthole and cross wall coil with one of configuration; Cross wall coil and cross porthole, the gap of crossing between wall coil and the lengthening joint pipe is all very little, so in the control room, just do not need the piping support frame of design special to fix the CPVC pipe; Various toys can not get into the control room from crossing wall coil, have eliminated potential safety hazard; Each pump inputs or outputs pipe and on the body of wall of control room, arranges comparatively dispersion, and body of wall has each pump of enough space mounting to input or output the signboard of pipe outside the control room.
Description of drawings
To combine Figure of description and embodiment that the present invention is done further detailed description below, wherein:
Fig. 1 is a treatment pond structural representation of the present invention
Fig. 2 is a plan view among Fig. 1
Fig. 3 is a left view among Fig. 1
Fig. 4 is pipe bent structure schematic representation
Fig. 5 is a plan view among Fig. 4
Fig. 6 is a left view among Fig. 4
Fig. 7 is pipe row supporting structure schematic representation
Fig. 8 is a plan view among Fig. 7
Fig. 9 is a left view among Fig. 7
Figure 10 is pipe row passageway structural representation
Figure 11 is a plan view among Figure 10
Figure 12 is a left view among Figure 10
Reference character among Fig. 4-12: 1, pipe row's support, 2, pvc pipe, 3, pipe row passageway, 4, the located lateral angle steel, 5, sole bar angle, 6, dividing plate, 7, the inclination sole bar angle, 8, horizontal angle steel, 9, cross guidance tape, 10, locating stud.
Figure 13 is placed on the local schematic top plan view in the bracket of passageway for embedded passageway
Figure 14 is the local schematic top plan view that installs embedded passageway and loose-leaf type cover net cover
Local schematic side view when Figure 15 raises for loose-leaf type cover net cover
Reference character among Figure 13 to 15: 1, passageway bracket, 2, sole bar angle, 3, embedded passageway, 4, support square steel; 5, handle, 6, hinge assemblies, 7, loose-leaf type cover net cover, 8, hook; 9, connecting bolt, 10, treatment pond, 11, pond, end mouth body of wall, 12, pond, side mouth body of wall.
Figure 16 is a pond oralia structural representation
Figure 16 a is a k-k sectional view among Figure 16
Reference character among Figure 16-16a: 1, pond oralia, 2, angle steel.
Figure 17 arranges schematic representation for treatment pond right side pipe
Figure 17 a is a plan structure schematic representation among Figure 17
Figure 18 is that treatment pond left side pipe is arranged schematic representation
Figure 18 a is a plan structure schematic representation among Figure 18
Figure 19 arranges schematic representation for the precipitation unit drain pipe
Figure 19 a is a plan structure schematic representation among Figure 19
Reference character among Figure 17-19a: 1, rapid pipe joint, 2, piping support folder, 3, two union formula ball valve, 4, the CPVC pipe; 5, crossover sub, 6,90 ° of elbows, 7, the union loose joint, 8, Stainless Steel Elbow; 9, blowdown valve outlet connection, 10, the CPVC adpting flange, 11, threeway, 12, big union loose joint; 13, big CPVC pipe, 14, the bassoon holding clamp, 15, blowdown valve, 16, the treatment pond body of wall.
Figure 20 is folding branching bolster structure schematic representation
Figure 21 is a schematic top plan view among Figure 20
Reference character among Figure 20-21: 1, hinge base, 2, joint pin, 3, support plate.
Figure 22 is the structural representation of corrugated sheet
Figure 23 is a schematic top plan view among Figure 22
Figure 24 is the corrugated board box structural representation
Figure 25 is Figure 24 schematic top plan view
Figure 26 is Figure 24 schematic side view
Reference character among Figure 22-26: 1, corrugated sheet, 2, the angle steel rectangular frame, 3, the bottom angle steel, 4, the both sides angle steel, 5, the stainless steel round steel, 6, spacing angle steel, 7, bolt.
Figure 27 was the structural representation of wall coil
Figure 28 is a left view among Figure 27
Figure 29 was a wall coil connecting plate schematic representation
Figure 30 is a left view among Figure 29
Figure 31 was a wall coil structural entity structural representation
Figure 32 is that each crosses wall coil distribution and home position schematic representation outside the control room
Reference character among Figure 27-32: 1, cross wall coil, 2, cross the wall coil connecting plate, 3, the lengthening joint pipe, 4, crossover sub, 5, the CPVC pipe, 6, pump, 7, the output tube sign, 8, the supplying tube sign, 9, limited step.
Embodiment
Embodiment 1
Shown in Fig. 1-3, the invention discloses a kind of oil and gas well drilling sewage apparatus for continous treatment, comprise control room, treatment pond and reverse osmosis unit.
Shown in Fig. 4-12; Be provided with the pipe bent structure between control room, treatment pond and the reverse osmosis unit, comprise pipe row support 1, said pipe row support 1 comprises two sole bar angles 5; Upper fixed connects at least two located lateral angle steel 4 between two sole bar angles 5; On the sole bar angle 5 between the two located lateral angle steel 4, be set with equally distributed a plurality of dividing plate 6, it is identical with located lateral angle steel 4 that dividing plate 6 is provided with direction; Respective diaphragms 6 position consistency on two sole bar angles 5 form the groove that can place pvc pipe 2 between any two dividing plates 6 on each sole bar angle 5.Also comprise pipe row passageway 3; Said pipe row passageway 3 comprises that at least two horizontal angle steel 8, two horizontal angle steel 8 are complementary with said two located lateral angle steel 4, and laterally angle steel 8 is provided with locating stud 10; Have U-groove bevel on the said located lateral angle steel 4; Locating stud 10 matches with U-groove bevel, is set with guidance tape 9 between the two horizontal angle steel 8, and a plurality of pvc pipes 2 are crossed in the space that forms between guidance tape 9 and the said sole bar angle 5 said.The end that the outside that also comprises two horizontal angle steel 8 respectively is provided with two inclination sole bar angles, 7, two inclination sole bar angles 7 contacts with ground, and the other end is fixed on the horizontal angle steel 8, also is fixed with guidance tape 9 between the two inclination sole bar angles 7.
Embodiment 2
As the present invention's one preferred embodiments; Shown in Figure 13-15; The treatment pond top structure; Comprise pond, end mouth body of wall 11 and pond, side mouth body of wall 12, between pond, bi-side mouth body of wall 12, be equipped with and support square steel 4, with supporting on the square steel 4 passageway bracket 1 is installed at pond, said end mouth body of wall 11; Embedded passageway 3 between pond, end mouth body of wall 11 and support square steel 4 is fixedly connected with said passageway bracket 1; Be provided with the sole bar angle 2 that is fixed between support square steel 4 and pond, the end mouth body of wall 11 along pond, side mouth body of wall 12 directions, the plane that the special-shaped angle steel at sole bar angle 2 and 3 edges, embedded passageway forms is provided with the loose-leaf type cover net cover 7 that covers treatment pond 10, and closed guard rail is installed around treatment pond 10.All the other are with embodiment 1.
Embodiment 3
As the present invention's one preferred embodiments; Shown in figure 16, pond oralia structure comprises pond oralia 1, and the side of oralia 1 is provided with angle steel 2 in the pond of each unit; The cross section of angle steel 2 is isosceles triangle, and the base of isosceles triangle is welded on the side of said pond oralia 1.All the other are with embodiment 2.
Embodiment 4
As the present invention's one preferred embodiments; Shown in Figure 17-19a; Turnover water pipe comprises compositions (the right side pipe arranges and see Fig. 1 that the left side pipe is arranged and seen Fig. 2) such as rapid pipe joint 1, piping support folder 2, two union formula ball valve 3, CPVC pipe 4,5,90 ° of elbows 6 of crossover sub, union loose joint 7, Stainless Steel Elbow 8.Drain pipe comprises compositions (Fig. 3) such as blowdown valve outlet connection 9, CPVC adpting flange 10, threeway 11, big union loose joint 12, big CPVC pipe 13, bassoon holding clamp 14, blowdown valve 15.It is characterized in that: on the treatment pond body of wall, drive water hole and weep hole into respectively by design; Soldering stainless steel elbow 8; Crossover sub 5, CPVC pipe 4,7,90 ° of elbows 6 of union loose joint, two union formula ball valve 3, rapid pipe joint 1 are installed respectively from top to bottom, from right to left, at last piping support folder 2 are welded on the treatment pond body of wall, load onto pipe clamp; Load onto bolt and the nut of screwing, make the pipe location.During on-the-spot the use, in rapid pipe joint 1, connect the PVC armoured hose and just can use.
The installation of drain pipe is to use bolt to be installed on the flange of deposition tank lower box blowdown valve 15; Threeway 11, big union loose joint 12, big CPVC pipe 13, CPVC adpting flange 10 are installed respectively again; Bassoon holding clamp 14 is welded on the skid base flat board; Load onto pipe clamp, load onto bolt and the nut of screwing, pipe is fixed.Use bolt that blowdown valve outlet connection 9 is installed on the CPVC adpting flange 10 at last.During on-the-spot the use, on blowdown valve outlet connection 9, connect the PVC armoured hose and just can use.All the other are with embodiment 3.
Embodiment 5
As the present invention's one preferred embodiments, shown in Figure 20-21, folding bearing support comprises hinge base 1, hinge base 2, support plate 3.It is characterized in that: become a folding bearing support by hinge base 1, joint pin 2, support plate 3 group welding pieces, support plate 3 can be around 90 ° of joint pin 2 left rotation and right rotation.During installation, measure good each size, the hinge base 1 of the folding bearing support that assembles is welded on the precipitation unit pool wall; In the time will placing tilting box, can be folding to the pool wall face with folding bearing support, place tilting box after; Again bearing support is turned back original position and place collector pipe, all the other are with embodiment 4.
Embodiment 6
As the present invention's one preferred embodiments, shown in Figure 22-26, the corrugated board box main body is made up of angle steel rectangular frame 2, is welded with 2 root bottom part angle steel 3 in base of frame, and corrugated sheet is not fallen down at the bottom of the precipitation unit.Be welded with 4 both sides angle steel 4 respectively in the framework both sides; On angle steel 4, be welded with stainless steel round steel 5; Because the dislocation of stainless steel round steel is welded, and in framework, has just formed the space of an inclination, and 4 corrugated sheets 1 are put into these spaces respectively; Spacing angle steel 6 usefulness bolts 7 two ends of frame roof are fixed, corrugated sheet 1 just is limited in the space that the spacing angle steel 6 by bottom angle steel 3, both sides angle steel 4, front and back stainless steel round steel 5, top forms again.When sewage transport to precipitation unit, along with the flowing and roll of sewage, corrugated sheet 1 in the space, can not drift with the tide all the time.After sewage was static, corrugated sheet was got back to original position under the effect of gravity, and all the other are with embodiment 5.
Embodiment 7
As best mode for carrying out the invention, shown in Figure 27-32, cross the wall coil structure; Be included in the porthole of offering on the interior wall of control room of crossing; Passed porthole cross wall coil 1 and with cross that wall coil 1 indoor end is threaded cross wall coil connecting plate 2, saidly cross wall coil 1 and cross the porthole drive fit; The sectional area of crossing wall coil connecting plate 2 is greater than the said sectional area of crossing porthole; The control room is outside equipped with the lengthening joint pipe, and lengthening joint pipe 3 runs through said to be crossed in the wall coil 1, and the pipe that inputs or outputs in the control room is threaded with said lengthening joint pipe 3 through crossover sub 4.Because the gap of crossing between wall coil 1 and the lengthening joint pipe 3 is very little, so in the control room, just do not need the piping support frame of design special to fix CPVC pipe 5, various toys can not eliminated potential safety hazard from crossing wall coil 1 entering control room yet; Each pump 6 inputs (or output) pipe arranges comparatively on the body of wall of control room and disperses that body of wall has the signboard of each pump 6 inputs (or output) pipe of enough space mounting outside the control room.All the other are with embodiment 6.

Claims (7)

1. an oil and gas well drilling sewage apparatus for continous treatment comprises control room, treatment pond and reverse osmosis unit, it is characterized in that: be provided with the pipe bent structure between control room, treatment pond and the reverse osmosis unit; The pipe bent structure comprises pipe row support, and said pipe row support comprises two sole bar angles, and upper fixed connects at least two located lateral angle steel between two sole bar angles; On the sole bar angle between the two located lateral angle steel, be set with equally distributed a plurality of dividing plate, it is identical with the located lateral angle steel that dividing plate is provided with direction; Respective diaphragms position consistency on two sole bar angles forms the groove that can place pvc pipe between any two dividing plates on each sole bar angle, the pipe bent structure also comprises pipe row passageway; Said pipe row passageway comprises at least two horizontal angle steel, and two horizontal angle steel and said two located lateral angle steel are complementary, and laterally angle steel is provided with locating stud; Have U-groove bevel on the said located lateral angle steel; Locating stud matches with U-groove bevel, is set with guidance tape between the two horizontal angle steel, and a plurality of pvc pipes are crossed in the space that forms between guidance tape and the said sole bar angle said; The outside of two horizontal angle steel respectively is provided with two inclination sole bar angles; One end of two inclination sole bar angles contacts with ground, and the other end is fixed on the horizontal angle steel, also is fixed with guidance tape between the two inclination sole bar angles.
2. oil and gas well drilling sewage apparatus for continous treatment according to claim 1; It is characterized in that: the treatment pond top structure comprises pond, end mouth body of wall and pond, side mouth body of wall; Between the mouth body of wall of pond, bi-side, the support square steel is installed; With supporting pipe row passageway bracket is installed on the square steel at pond, said end mouth body of wall; Embedded pipe row passageway between pond, end mouth body of wall and support square steel is fixedly connected with said pipe row passageway bracket; Be provided with the sole bar angle that is fixed between support square steel and pond, the end mouth body of wall along pond, side mouth wall direction, the plane that the special-shaped angle steel at sole bar angle and embedded pipe row edge, passageway forms is provided with the loose-leaf type cover net cover that covers treatment pond, and closed guard rail is installed around treatment pond.
3. oil and gas well drilling sewage apparatus for continous treatment according to claim 2; It is characterized in that: treatment pond comprises pond oralia structure; The side of the pond oralia of each unit is provided with angle steel; The cross section of angle steel is isosceles triangle, and the base of isosceles triangle is welded on the side of said pond oralia.
4. oil and gas well drilling sewage apparatus for continous treatment according to claim 3 is characterized in that: treatment pond comprises turnover water pipe structure and drain pipe structure; Said turnover water pipe structure comprises rapid pipe joint, piping support folder, two union formula ball valve, CPVC pipe, crossover sub, 90 ° of elbows, union loose joint and Stainless Steel Elbows; Have water inlet and weep hole on the treatment pond body of wall; Stainless Steel Elbow is welded in said water inlet and the weep hole; Crossover sub, CPVC pipe, two union formula ball valve, piping support folder are connected with rapid pipe joint successively, and loose joint is connected 90 ° of elbows successively with union; Said drain pipe structure comprises blowdown valve outlet connection, CPVC adpting flange, threeway, big union loose joint, big CPVC pipe, bassoon holding clamp and blowdown valve; Wherein, Blowdown valve is installed on the flange of deposition tank lower box; Threeway, big union loose joint, big CPVC pipe, CPVC adpting flange connect successively, and the bassoon holding clamp is welded on the skid base flat board, and the blowdown valve outlet connection is installed on the CPVC adpting flange.
5. oil and gas well drilling sewage apparatus for continous treatment according to claim 4; It is characterized in that: the treatment pond precipitation unit comprises that collector pipe is with folding bearing support; Folding bearing support comprises the hinge base that is welded on the precipitation unit pool wall; Be fixed on the joint pin on the hinge base, with the support plate that is connected with joint pin, said support plate is around the reciprocal 180 degree rotations of said joint pin.
6. oil and gas well drilling sewage apparatus for continous treatment according to claim 5; It is characterized in that: the treatment pond precipitation unit comprises corrugated board box; Corrugated board box comprises the corrugated board box main body that is formed by the angle steel rectangular frame; Be welded with two root bottom part angle steel in said angle steel rectangular frame bottom, be welded with four both sides angle steel respectively, on the angle steel of said both sides, be welded with the stainless steel round steel in angle steel rectangular frame both sides; A plurality of stainless steel round steel dislocation welding are fixing and in the angle steel rectangular frame, form inclined spaces; Angle steel rectangular frame top is provided with spacing angle steel, and corrugated sheet is spacing in said inclined spaces through bottom angle steel, both sides angle steel, stainless steel round steel and spacing angle steel.
7. oil and gas well drilling sewage apparatus for continous treatment according to claim 6; It is characterized in that: the control room was provided with the wall coil structure, was included in the porthole of offering on the interior wall of control room of crossing, and passed the wall coil of crossing of porthole; With the wall coil connecting plate excessively that is threaded with the indoor end of mistake wall coil; Saidly cross wall coil and cross the porthole drive fit, the sectional area of crossing the wall coil connecting plate is greater than the said sectional area of crossing porthole, and the control room is outside equipped with the lengthening joint pipe; The lengthening joint pipe runs through said to be crossed in the wall coil, and the pipe that inputs or outputs in the control room is connected with said lengthening joint pipe thread through crossover sub.
CN 201010296124 2010-09-28 2010-09-28 Continuous sewage treatment device for petroleum gas well Active CN101973649B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201010296124 CN101973649B (en) 2010-09-28 2010-09-28 Continuous sewage treatment device for petroleum gas well

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201010296124 CN101973649B (en) 2010-09-28 2010-09-28 Continuous sewage treatment device for petroleum gas well

Publications (2)

Publication Number Publication Date
CN101973649A CN101973649A (en) 2011-02-16
CN101973649B true CN101973649B (en) 2012-10-10

Family

ID=43573566

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201010296124 Active CN101973649B (en) 2010-09-28 2010-09-28 Continuous sewage treatment device for petroleum gas well

Country Status (1)

Country Link
CN (1) CN101973649B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
BR112017024025A2 (en) * 2015-05-12 2018-07-17 Tempero 2000 S L procedure and means for diluting or concentrating solutions applied to water desalination processes

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0407239A1 (en) * 1989-07-06 1991-01-09 Automobiles Peugeot Device for fastening an assembly of tubes or similar on a wall
CN2390078Y (en) * 1998-05-29 2000-08-02 上海新奇五金有限公司 Angle steel device with improved shape for swing pipe
JP2001032963A (en) * 1999-07-22 2001-02-06 Sekisui Chem Co Ltd Holder of piping or the like
US7457506B1 (en) * 2005-12-30 2008-11-25 Osborne Orthopedic Group, Inc. Line organizer

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0407239A1 (en) * 1989-07-06 1991-01-09 Automobiles Peugeot Device for fastening an assembly of tubes or similar on a wall
CN2390078Y (en) * 1998-05-29 2000-08-02 上海新奇五金有限公司 Angle steel device with improved shape for swing pipe
JP2001032963A (en) * 1999-07-22 2001-02-06 Sekisui Chem Co Ltd Holder of piping or the like
US7457506B1 (en) * 2005-12-30 2008-11-25 Osborne Orthopedic Group, Inc. Line organizer

Also Published As

Publication number Publication date
CN101973649A (en) 2011-02-16

Similar Documents

Publication Publication Date Title
CN205688563U (en) A kind of integrated sewage disposal pumping plant import waste lifting device
CN209323663U (en) A kind of cable ditch water discharge structure
CN101973649B (en) Continuous sewage treatment device for petroleum gas well
CN206664655U (en) A kind of civil construction pipeline rack
CN209768328U (en) Greening isolation device for environmental protection
CN201942584U (en) Continuous sewage treatment device for petroleum and gas drilling well
CN215060078U (en) Safety device is used in installation of building water and electricity
CN213831703U (en) Overhauling platform
CN211069140U (en) Sedimentation tank sedimentation unit and folded plate horizontal flow sedimentation tank
CN213115094U (en) Green building wall
CN214365181U (en) Steel roof structure cistern
CN210421679U (en) Building water supply and drainage pipeline
CN206071107U (en) Between a kind of environmentally-friendly sanitary
CN207847166U (en) Container column and container roof tissue discharge structure
CN207267823U (en) A kind of underwater aeration device for rainwater-collecting processing and reuse
CN207314953U (en) A kind of drainage mechanism in outdoor verticallifting stereo garage
CN210133935U (en) High-efficient ecological bed that floats suitable for still water view
CN215417413U (en) Bulletin board for building engineering management
CN208471746U (en) A kind of intensive arragement construction of power plant water cleaning shop
CN220247561U (en) Outer frame wall connecting piece connecting device
CN2664543Y (en) Filtering apparatus of reverse osmosis drinking machine
CN221001284U (en) Zero-blockage drainage system for planting top plate
US20230151627A1 (en) Swimming pool structure with an edge gutter
CN215211274U (en) Building rainwater collecting system based on BIM
CN218407348U (en) Can have enough to meet need pressure-bearing well casing operation platform

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20200922

Address after: 100007 Beijing, Dongzhimen, North Street, No. 9, No.

Patentee after: CHINA NATIONAL PETROLEUM Corp.

Patentee after: CNPC Chuanqing Drilling Engineering Co.,Ltd.

Address before: The 1 section of No. 3 company Chuanqing Drilling Technology Information Office Chenghua District Green Road 610051 Chengdu City, Sichuan Province

Patentee before: CNPC Chuanqing Drilling Engineering Co.,Ltd.

TR01 Transfer of patent right