CN101969183A CN2010102833647A CN201010283364A CN101969183A CN 101969183 A CN101969183 A CN 101969183A CN 2010102833647 A CN2010102833647 A CN 2010102833647A CN 201010283364 A CN201010283364 A CN 201010283364A CN 101969183 A CN101969183 A CN 101969183A
Authority
CN
China
Prior art keywords
opgw
crossbeams
ratchet
wire
hook
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2010102833647A
Other languages
English (en)
Other versions
CN101969183B (zh
Inventor
王光祥
景文川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Electric Power Transmission & Transformation Construction Co Ltd
State Grid Corp of China SGCC
Original Assignee
Sichuan Electric Power Transmission & Transformation Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Electric Power Transmission & Transformation Construction Co Ltd filed Critical Sichuan Electric Power Transmission & Transformation Construction Co Ltd
Priority to CN 201010283364 priority Critical patent/CN101969183B/zh
Publication of CN101969183A publication Critical patent/CN101969183A/zh
Application granted granted Critical
Publication of CN101969183B publication Critical patent/CN101969183B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Electric Cable Installation (AREA)

Abstract

一种鞍式提线器及其施工方法,包括棘轮紧线器,两根平行设置的横梁上安装有四个滑轮,其中,两个端滑轮可转动地安装在两根横梁之间,且分别位于横梁左、右两端;另外两个中滑轮结构相同地安装在两根横梁上方的同一高度位置上:两根支撑角钢分别一一对应的焊接在两根横梁中的一根横梁上,中滑轮可转动地安装在两根支撑角钢之间,且两个中滑轮左、右对称地位于横梁上方;棘轮紧线器设置在上述两个中滑轮之间,两根钢丝绳分别经绳头挂接在棘轮紧线器的左、右挂钩上,两根钢丝绳的外端各自绕过一个中滑轮和一个端滑轮后与一个挂胶提线钩固联;两根横梁上位于两个中滑轮之间设置有两个固定钩。它具有结构简单、方便实用的特点。

Description

鞍式提线器及其施工方法
技术领域
本发明涉及输电线路架设用施工器械,特别是涉及输电线路OPGW直线塔附件安装的鞍式提线器及其施工方法。
背景技术
OPGW(光纤复合架空地线)直线塔附件安装一般是在直线塔两侧OPGW上分别安装一组紧线预绞丝,然后通过两个挂于铁塔上的链条葫芦或其他紧线器牵引紧线预绞丝,使得两组紧线预绞丝间的OPGW松弛后在其上安装预绞丝和线夹,并将线夹连接于金具串上,随后再松出链条葫芦或其他紧线器完成附件安装。这种方法存在作业复杂、效率低、劳动强度大、施工成本高等缺点。
发明内容
本发明的目的是提供一种结构简单、方便实用、用作OPGW直线塔附件安装的鞍式提线器。
本发明的目的是这样实现的:一种鞍式提线器,包括棘轮紧线器,两根平行设置的横梁上安装有四个滑轮,其中,两个端滑轮可转动地安装在两根横梁之间,且分别位于横梁左、右两端;另外两个中滑轮结构相同地安装在两根横梁上方的同一高度位置上:两根支撑角钢分别一一对应的焊接在两根横梁中的一根横梁上,中滑轮可转动地安装在两根支撑角钢之间,且上述两个中滑轮左、右对称地位于横梁上方;所述棘轮紧线器设置在上述两个中滑轮之间,两根钢丝绳分别经绳头挂接在棘轮紧线器的左、右挂钩上,两根钢丝绳的外端各自绕过一个中滑轮和一个端滑轮后与一个挂胶提线钩固联;两根横梁上位于两个中滑轮之间设置有两个固定钩。
上述两个横梁均为角钢;所述两根支撑角钢上均焊接有加强角钢。
上述两根横梁下部焊接有垫块,固定钩从下向上穿过垫块上的孔后经螺帽固定在两根横梁上。
上述滑轮结构为:轮体固定在轴上,轴上设置有铜套。
本发明的另一目的是提供上述鞍式提线器的施工方法。
本发明的另一目的是这样实现的:一种鞍式提线器的施工方法,按以下步骤进行:
1)将OPGW鞍式提线器放置于OPGW横担上,通过固定钩将其安装在OPGW横担角钢上;
2)调整棘轮紧线器其上钢丝绳绳长至合适长度,棘轮紧线器的两个绳钩分别钩住钢丝绳绳头;
3)两个挂胶提线钩钩住OPGW;
4)操作棘轮紧线器收紧钢丝绳,从而提升OPGW,待提升至适当高度时,停止收紧并锁定棘轮紧线器;
5)在两个挂胶提线钩间的OPGW安装预绞丝和线夹,并将线夹连接于金具串上;
6)检查金具串等连接可靠后,操作棘轮紧线器,松出钢丝绳,待其不受力后拆除OPGW鞍式提线器,完成OPGW直线塔附件安装作业;
上述OPGW为光纤复合架空地线。
本发明的有益效果是:结构简单、方便实用、操作简单、作业效率高、劳动强度低、OPGW直线塔附件安装质量更易保证、降低了施工成本,具有很好的应用前景。
附图说明
图1、图2(棘轮紧线器和钢丝绳未示出)分别是本发明的主视图和俯视图;
图3、图4分别是图1沿A-A线和沿B-B线的剖面图。
具体实施方式
附图中,1、横梁;2、支撑角钢;3、加强角钢;4、滑轮;4-1、轮体;4-2、铜套;4-3、轴;4-4、螺帽;5、螺栓;6、棘轮紧线器;7、钢丝绳;7-1、(棘轮紧线器的)挂钩;8、挂胶提线钩;9、固定钩;9-1、垫块;10、(OPGW)横担角钢。
图1、图2示出,本发明包括棘轮紧线器6,两根平行设置的横梁1上安装有四个滑轮4,其中,两个端滑轮可转动地安装在两根横梁之间,且分别位于横梁左、右两端;另外两个中滑轮结构相同地安装在两根横梁上方的同一高度位置上:两根支撑角钢2分别一一对应的焊接在两根横梁中的一根横梁上,中滑轮可转动地安装在两根支撑角钢之间,且上述两个中滑轮左、右对称地位于横梁上方;所述棘轮紧线器6设置在上述两个中滑轮之间,两根钢丝绳7分别经绳头挂接在棘轮紧线器的左、右挂钩7-1上,两根钢丝绳的外端各自绕过一个中滑轮和一个端滑轮后与一个挂胶提线钩8相固联;两根横梁上位于两个中滑轮之间设置有两个固定钩9。两个横梁1均为角钢;所述两根支撑角钢2上均焊接有加强角钢3(参见图4)。两根横梁1下部焊接有垫块9-1,固定钩9从下向上穿过垫块上的孔后经螺帽固定在两根横梁上。滑轮4结构为:轮体4-1固定在轴4-3上,轴4-3上设置有铜套4-2(参见图3)。
一种鞍式提线器的施工方法,按以下步骤进行:
1)将OPGW鞍式提线器放置于OPGW横担上,通过固定钩将其安装在OPGW横担角钢上;
2)调整棘轮紧线器其上钢丝绳绳长至合适长度,棘轮紧线器的两个绳钩分别钩住钢丝绳绳头;
3)两个挂胶提线钩钩住OPGW;
4)操作棘轮紧线器收紧钢丝绳,从而提升OPGW,待提升至适当高度时,停止收紧并锁定棘轮紧线器;
5)在两个挂胶提线钩间的OPGW安装预绞丝和线夹,并将线夹连接于金具串上;
6)检查金具串等连接可靠后,操作棘轮紧线器,松出钢丝绳,待其不受力后拆除OPGW鞍式提线器,完成OPGW直线塔附件安装作业;
上述OPGW为光纤复合架空地线。

Claims (5)

1.一种鞍式提线器,包括,棘轮紧线器(6),其特征是:两根平行设置的横梁(1)上安装有四个滑轮(4),其中,两个端滑轮可转动地安装在两根横梁之间,且分别位于横梁左、右两端;另外两个中滑轮结构相同地安装在两根横梁上方的同一高度位置上:两根支撑角钢(2)分别一一对应的焊接在两根横梁中的一根横梁上,中滑轮可转动地安装在两根支撑角钢之间,且上述两个中滑轮左、右对称地位于横梁上方;所述棘轮紧线器(6)设置在上述两个中滑轮之间,两根钢丝绳(7)分别经绳头挂接在棘轮紧线器的左、右挂钩(7-1)上,两根钢丝绳的外端各自绕过一个中滑轮和一个端滑轮后与一个挂胶提线钩(8)相固联;两根横梁上位于两个中滑轮之间设置有两个固定钩(9)。
2.根据权利要求1所述鞍式提线器,其特征是:所述两个横梁(1)均为角钢;所述两根支撑角钢(2)上均焊接有加强角钢(3)。
3.根据权利要求2所述鞍式提线器,其特征是:所述两根横梁(1)下部焊接有垫块(9-1),固定钩(9)从下向上穿过垫块上的孔后经螺帽固定在两根横梁上。
4.根据权利要求3所述鞍式提线器,其特征是:所述滑轮(4)结构为:轮体(4-1)固定在轴(4-3)上,该轴(4-3)上设置有铜套(4-2)。
5.一种如权利要求1所述鞍式提线器的施工方法,其特征是:按以下步骤进行:
1)将OPGW鞍式提线器放置于OPGW横担上,通过固定钩将其安装在OPGW横担角钢上;
2)调整棘轮紧线器其上钢丝绳绳长至合适长度,棘轮紧线器的两个绳钩分别钩住钢丝绳绳头;
3)两个挂胶提线钩钩住OPGW;
4)操作棘轮紧线器收紧钢丝绳,从而提升OPGW,待提升至适当高度时,停止收紧并锁定棘轮紧线器;
5)在两个挂胶提线钩间的OPGW安装预绞丝和线夹,并将线夹连接于金具串上;
6)检查金具串等连接可靠后,操作棘轮紧线器,松出钢丝绳,待其不受力后拆除OPGW鞍式提线器,完成OPGW直线塔附件安装作业;
上述OPGW为光纤复合架空地线。
CN 201010283364 2010-09-16 2010-09-16 鞍式提线器及其施工方法 Active CN101969183B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201010283364 CN101969183B (zh) 2010-09-16 2010-09-16 鞍式提线器及其施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201010283364 CN101969183B (zh) 2010-09-16 2010-09-16 鞍式提线器及其施工方法

Publications (2)

Publication Number Publication Date
CN101969183A true CN101969183A (zh) 2011-02-09
CN101969183B CN101969183B (zh) 2013-04-03

Family

ID=43548298

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201010283364 Active CN101969183B (zh) 2010-09-16 2010-09-16 鞍式提线器及其施工方法

Country Status (1)

Country Link
CN (1) CN101969183B (zh)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103545751A (zh) * 2013-10-16 2014-01-29 国家电网公司 架空输电线路地线光缆金具更换支架
CN103795003A (zh) * 2014-02-27 2014-05-14 江苏省电力公司常州供电公司 35kV供电线路带电作业用的绝缘提线装置
CN104113014A (zh) * 2014-07-31 2014-10-22 国家电网公司 上扛提线滑车
CN104134948A (zh) * 2014-08-05 2014-11-05 国家电网公司 500kV架空线路直线塔避雷线起吊作业装置
CN104538887A (zh) * 2014-12-01 2015-04-22 国家电网公司 一种避雷线提升转换器
CN104779555A (zh) * 2015-04-22 2015-07-15 国家电网公司 可拆卸式10千伏砼杆架线用省力支架
CN104810773A (zh) * 2015-04-03 2015-07-29 国家电网公司 一种无头绝缘绳装置
CN105262005A (zh) * 2015-11-05 2016-01-20 国家电网公司 用于电杆架空地线及opgw光缆的辅助支撑装置
CN107069562A (zh) * 2017-06-28 2017-08-18 云南电网有限责任公司曲靖供电局 带电更换绝缘子方法及载荷转移装置
CN107086499A (zh) * 2017-06-28 2017-08-22 云南电网有限责任公司曲靖供电局 导线荷载转移工具及绝缘子串更换装置
CN107086495A (zh) * 2017-06-28 2017-08-22 云南电网有限责任公司曲靖供电局 载荷转移工具及电力维护设备

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201332246Y (zh) * 2008-12-31 2009-10-21 河南送变电建设公司 大吨位导线提线器
CN201426030Y (zh) * 2009-04-17 2010-03-17 江苏省送变电公司 提线器
CN201829862U (zh) * 2010-09-16 2011-05-11 四川电力送变电建设公司 鞍式提线器

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201332246Y (zh) * 2008-12-31 2009-10-21 河南送变电建设公司 大吨位导线提线器
CN201426030Y (zh) * 2009-04-17 2010-03-17 江苏省送变电公司 提线器
CN201829862U (zh) * 2010-09-16 2011-05-11 四川电力送变电建设公司 鞍式提线器

Cited By (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103545751A (zh) * 2013-10-16 2014-01-29 国家电网公司 架空输电线路地线光缆金具更换支架
CN103545751B (zh) * 2013-10-16 2015-11-04 国家电网公司 架空输电线路地线光缆金具更换支架
CN103795003B (zh) * 2014-02-27 2016-04-13 江苏省电力公司常州供电公司 35kV供电线路带电作业用的绝缘提线装置
CN103795003A (zh) * 2014-02-27 2014-05-14 江苏省电力公司常州供电公司 35kV供电线路带电作业用的绝缘提线装置
CN105811301B (zh) * 2014-02-27 2017-10-17 国网江苏省电力公司常州供电公司 低成本的35kV供电线路带电作业用的绝缘提线装置
CN105811301A (zh) * 2014-02-27 2016-07-27 江苏省电力公司常州供电公司 低成本的35kV供电线路带电作业用的绝缘提线装置
CN105811302A (zh) * 2014-02-27 2016-07-27 江苏省电力公司常州供电公司 35kV直线绝缘子更换作业方法
CN104113014A (zh) * 2014-07-31 2014-10-22 国家电网公司 上扛提线滑车
CN104134948A (zh) * 2014-08-05 2014-11-05 国家电网公司 500kV架空线路直线塔避雷线起吊作业装置
CN104538887B (zh) * 2014-12-01 2017-10-03 国家电网公司 一种避雷线提升转换器
CN104538887A (zh) * 2014-12-01 2015-04-22 国家电网公司 一种避雷线提升转换器
CN104810773A (zh) * 2015-04-03 2015-07-29 国家电网公司 一种无头绝缘绳装置
CN104779555A (zh) * 2015-04-22 2015-07-15 国家电网公司 可拆卸式10千伏砼杆架线用省力支架
CN105262005A (zh) * 2015-11-05 2016-01-20 国家电网公司 用于电杆架空地线及opgw光缆的辅助支撑装置
CN105262005B (zh) * 2015-11-05 2018-01-02 国家电网公司 用于电杆架空地线及opgw光缆的辅助支撑装置
CN107069562A (zh) * 2017-06-28 2017-08-18 云南电网有限责任公司曲靖供电局 带电更换绝缘子方法及载荷转移装置
CN107086499A (zh) * 2017-06-28 2017-08-22 云南电网有限责任公司曲靖供电局 导线荷载转移工具及绝缘子串更换装置
CN107086495A (zh) * 2017-06-28 2017-08-22 云南电网有限责任公司曲靖供电局 载荷转移工具及电力维护设备
CN107086499B (zh) * 2017-06-28 2019-03-08 云南电网有限责任公司曲靖供电局 导线荷载转移工具及绝缘子串更换装置
CN107086495B (zh) * 2017-06-28 2019-05-31 云南电网有限责任公司曲靖供电局 载荷转移工具及电力维护设备

Also Published As

Publication number Publication date
CN101969183B (zh) 2013-04-03

Similar Documents

Publication Publication Date Title
CN101969183B (zh) 鞍式提线器及其施工方法
CN202090286U (zh) 一种适用于自锚式双索面悬索桥的牵引系统
CN102290742B (zh) 张力架线施工工艺
JP5812325B2 (ja) 電線張力低減装置及び電線張力低減工法
CN104143782B (zh) 一种±800kV线路耐张绝缘子串的带电更换工具及方法
CN103758042B (zh) 一种紧缆机
CN105621280B (zh) 安装和拆卸起重臂的装置和方法
CN103618258B (zh) 一种输电线路架设紧线器
CN105672138A (zh) 一种贯通式斜拉索安装循环系统及其穿索施工方法
CN106505482B (zh) 大规格电缆地下埋管长距离敷设方法
CN103594976B (zh) 用于线路导线紧线的组合紧线工具
CN201829862U (zh) 鞍式提线器
CN110172919A (zh) 一种矮塔斜拉桥穿索方法及系统
CN101173501A (zh) 缆索挤紧机及其挤紧方法
CN202543802U (zh) 一种复合预应力筋成品拉索
CN102709855A (zh) 用于配电线路中边相导线的张紧方法
CN203859438U (zh) 多用途脚踏式飞车
CN203536865U (zh) 用于线路导线紧线的组合紧线工具
CN201191731Y (zh) 电动绞磨
CN206265180U (zh) 一种履带连接装置
CN101767753B (zh) 一种垂直提升皮带吊装方法
CN202626985U (zh) 葫芦牵引锚索穿索装置
CN102849622A (zh) 塔架的桅杆逐节垂直吊装方法
CN209779465U (zh) 一种主塔竖转斜拉桥的挂索施工系统
CN107650979B (zh) 一种电缆辅助搬运装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: STATE GRID CORPORATION OF CHINA

Effective date: 20121226

C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20121226

Address after: 610051 Chenghua District, Chengdu, Cui Cui shop north road, No. 1, No. 6, Sichuan

Applicant after: Sichuan Electric Power Transmission & Transformation Construction Co., Ltd.

Applicant after: State Grid Corporation of China

Address before: 610051 Chenghua District, Chengdu, Cui Cui shop north road, No. 1, No. 6, Sichuan

Applicant before: Sichuan Electric Power Transmission & Transformation Construction Co., Ltd.

C14 Grant of patent or utility model
GR01 Patent grant