CN101949146A - Offshore auxiliary construction platform device and using method thereof - Google Patents
Offshore auxiliary construction platform device and using method thereof Download PDFInfo
- Publication number
- CN101949146A CN101949146A CN 201010280035 CN201010280035A CN101949146A CN 101949146 A CN101949146 A CN 101949146A CN 201010280035 CN201010280035 CN 201010280035 CN 201010280035 A CN201010280035 A CN 201010280035A CN 101949146 A CN101949146 A CN 101949146A
- Authority
- CN
- China
- Prior art keywords
- construction
- operation platform
- box girder
- support
- platform
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
本发明公开了一种海上辅助施工的平台装置及其使用方法,吊机系统设置在可移动的支撑系统上,支撑系统包括两条相互平行的轨道梁,两条轨道梁之间设有与轨道梁长度方向相垂直的横向联系梁,轨道梁和横向联系梁均采用箱梁结构,两箱梁之间用剪刀撑竖向相连,轨道梁下方的承台上放置箱梁支座,支撑系统通过行走机构带动其移动,行走机构是在箱梁支座的上方设有四氟滑板,箱梁下翼缘底铺设方便平台装置整体移动的不锈钢钢板,不锈钢钢板在四氟滑板上移动,并通过位于轨道梁端部的牵引机构进行牵引。该种平台装置能自身从一个作业面移至下一个作业面,避免设备频繁安拆及倒运,既降低海上施工安全风险,又提高了海上墩柱施工的效率。
The invention discloses a platform device for auxiliary construction at sea and a method for using the same. The crane system is arranged on a movable support system, and the support system includes two track beams parallel to each other. The horizontal connecting beam whose length direction is perpendicular to the beam, the track beam and the horizontal connecting beam adopt box girder structure, and the two box girders are vertically connected by scissor braces. The traveling mechanism drives it to move. The traveling mechanism is equipped with a PTFE slide plate above the box girder support. A stainless steel plate is laid on the bottom of the lower flange of the box girder to facilitate the overall movement of the platform device. The stainless steel plate moves on the PTFE slide plate and passes through the The traction mechanism at the end of the track beam performs traction. This kind of platform device can move from one working surface to the next working surface by itself, avoiding frequent installation, dismantling and reverse transportation of equipment, which not only reduces the safety risk of offshore construction, but also improves the efficiency of offshore pier construction.
Description
技术领域technical field
本发明涉及一种建筑机械设备,尤其是涉及一种适用于恶劣海况条件下辅助桥梁现浇墩柱施工的平台装置及其使用方法。The invention relates to a construction machinery equipment, in particular to a platform device suitable for auxiliary bridge cast-in-place pier construction under harsh sea conditions and a method for using the same.
背景技术Background technique
目前,跨海大桥现浇墩柱施工采用两种设备辅助施工,一种是起重船辅助施工,另一种是钢平台辅助施工。At present, the construction of cast-in-situ piers of the cross-sea bridge uses two kinds of equipment to assist construction, one is the auxiliary construction of the crane ship, and the other is the auxiliary construction of the steel platform.
起重船,又称多功能作业船,指的是甲板上设有起重设备的大型平板驳船。起重船抛锚驻位于两个桥墩之间,船舱作为施工人员前场办公生活场所,甲板作为临时材料如钢筋、模板等临时材料堆放场地。船上吊机作为材料、机具垂直运输工具;船上设有水仓、发电机,保证施工现场用水用电。起重船施工完邻近的墩柱即可移锚,拖至另外两个墩柱进行施工。典型起重船平面位置如说明书附图1所示。A crane ship, also known as a multi-purpose operation ship, refers to a large flat barge with lifting equipment on the deck. The crane ship is anchored between the two piers. The cabin is used as the front office and living place for construction workers, and the deck is used as a storage place for temporary materials such as steel bars and formwork. The ship's crane is used as a vertical transportation tool for materials and machinery; the ship is equipped with water tanks and generators to ensure water and electricity for the construction site. After the construction of the adjacent pier column, the crane ship can move the anchor and drag it to the other two pier columns for construction. The plane position of a typical crane ship is shown in Figure 1 of the specification.
用于施工的钢平台是在需要施工的墩位处上用钢管桩做基础、用型钢及钢板焊接而成的临时结构物,在平台上面安装塔吊(或其它起重设备)、发电机、水箱及其它临时生活办公设施。墩柱施工时,利用平台上吊机作为垂直运输工具,平台上可以堆放模板、钢筋等临时材料,也为施工人员提供临时办公生活场地。为了方便设备材料倒运以及施工人员通行,平台尽量利用栈桥与陆地相连,变海上施工为陆地施工。钢平台辅助施工如说明书附图2所示。The steel platform used for construction is a temporary structure made of steel pipe piles as the foundation and welded with section steel and steel plates on the piers that need to be constructed. Tower cranes (or other lifting equipment), generators, etc. are installed on the platform. Water tanks and other temporary living and office facilities. During the construction of pier columns, the platform crane is used as a vertical transportation tool. Temporary materials such as formwork and steel bars can be stacked on the platform, and temporary office and living space are also provided for construction workers. In order to facilitate the transportation of equipment and materials and the passage of construction personnel, the platform is connected to the land by trestle bridges as much as possible, and the offshore construction is transformed into land construction. The auxiliary construction of the steel platform is shown in Figure 2 of the specification.
然而,在海上进行现浇墩柱施工时,起重船受到海上潮汐、风浪及台风等影响,尤其是外海受涌浪影响,船舶难以稳定驻位,上面吊机难以正常作业,施工效率较低,安全风险较大;钢平台将海上施工变为陆地施工,但是由于钢平台不能灵活移动,每一个墩位均要进行平台搭设及拆除,平台用钢量大,施工周期较长,施工功效低,成本较高。因此,上述两种辅助施工方式均具有一定的局限性,综合性能不好。However, during the construction of cast-in-place pier columns at sea, the crane ship is affected by sea tides, wind waves and typhoons, especially in the open sea, which makes it difficult for the ship to stand stably, and the crane above it is difficult to operate normally, and the construction efficiency is low , the safety risk is relatively large; the steel platform changes offshore construction into land construction, but because the steel platform cannot be moved flexibly, each pier needs to be erected and dismantled, the platform uses a large amount of steel, the construction period is long, and the construction efficiency is low ,higher cost. Therefore, the above two auxiliary construction methods all have certain limitations, and the comprehensive performance is not good.
发明内容Contents of the invention
本发明所要解决的技术问题是针对现有技术中存在的问题提供一种海上辅助施工平台装置及其使用方法,其目的是不仅能克服外海恶劣的海况,变海上施工为陆地施工,增加起重设备有效作业时间,同时,整套设备能自身从一个作业面移至下一个作业面,避免设备频繁安拆及倒运,提高工作效率。The technical problem to be solved by the present invention is to provide an offshore auxiliary construction platform device and its use method in view of the problems existing in the prior art. The effective working time of the equipment, at the same time, the whole set of equipment can be moved from one working surface to the next working surface by itself, avoiding frequent installation, dismantling and reverse transportation of equipment, and improving work efficiency.
本发明的技术方案是该种海上辅助施工平台装置,包括吊机系统,所述的吊机系统设置在可移动的支撑系统上,支撑系统通过行走机构带动其移动,所述的支撑系统上还安装有抗台及防撞系统。The technical solution of the present invention is that the offshore auxiliary construction platform device includes a crane system, the crane system is arranged on a movable support system, and the support system drives it to move through a walking mechanism, and the support system also has a Anti-Taiwan and anti-collision systems are installed.
所述的支撑系统包括两条相互平行的轨道梁,两条轨道梁之间设有与轨道梁长度方向相垂直的横向联系梁,轨道梁和横向联系梁均采用箱梁结构,两箱梁之间用剪刀撑竖向相连,轨道梁下方的承台上放置箱梁支座。The support system includes two track beams parallel to each other, and a transverse connection beam perpendicular to the length direction of the track beam is arranged between the two track beams. Both the track beam and the transverse connection beam adopt a box girder structure. The spaces are vertically connected with scissor braces, and the box girder support is placed on the platform below the track beam.
所述的行走机构是在箱梁支座的上方设有四氟滑板,箱梁下翼缘底铺设方便平台装置整体移动的不锈钢钢板,不锈钢钢板在四氟滑板上移动,并通过位于轨道梁端部的牵引机构进行牵引。The walking mechanism is provided with a PTFE slide plate above the box girder support, and a stainless steel plate is laid on the bottom of the lower flange of the box girder to facilitate the overall movement of the platform device. The traction mechanism at the bottom is used for traction.
所述的抗台及防撞系统为利用支座抬高轨道梁的标高,在轨道梁上设置减小风荷载的孔,并将轨道梁的锚固定在已施工的承台上。The anti-platform and anti-collision system is to use the support to raise the elevation of the track beam, to set holes on the track beam to reduce the wind load, and to fix the anchor of the track beam on the cap platform that has been constructed.
所述的牵引机构为电动葫芦。The traction mechanism is an electric hoist.
一种利用所述的施工平台装置进行施工的使用方法,具体为:A method of using the construction platform device for construction, specifically:
1)将轨道梁依托于已施工的承台上,将两根轨道梁和横向联系梁进行固定,形成一个稳定的施工平台,在移动平台的轨道梁上安装吊机系统、行走机构;1) Rely on the track beam on the cap platform that has been constructed, fix the two track beams and the horizontal connecting beam to form a stable construction platform, and install the crane system and walking mechanism on the track beam of the mobile platform;
2)待移动施工平台的所有构件全部安装完成,对吊机系统和电动葫芦行走机构进行调试验收后,即可开始现浇墩身施工;2) After all the components of the mobile construction platform are installed, and the crane system and the electric hoist traveling mechanism are debugged and accepted, the construction of the cast-in-place pier can begin;
3)待后端墩身全部施工完成后,将吊机系统的吊臂向前趴在轨道梁上的搁置梁上,移动吊机系统至前一个墩身前侧,就位后将吊机系统以及塔臂前端的搁置梁跟施工平台钢箱梁结构固定在一起;3) After all the construction of the rear pier body is completed, put the boom of the crane system forward on the shelving beam on the track beam, move the crane system to the front side of the previous pier body, and put the crane system in place And the shelving beam at the front end of the tower arm is fixed together with the steel box girder structure of the construction platform;
4)采用电动葫芦作为牵引系统,移动施工平台钢箱梁结构,当后端将要脱离后支座时,停止钢箱梁移动,用螺旋千斤顶缓慢将箱梁顶起,并将支座移开;4) Use the electric hoist as the traction system to move the steel box girder structure of the construction platform. When the rear end is about to break away from the rear support, stop the movement of the steel box girder, slowly lift the box girder with a screw jack, and remove the support;
5)千斤顶缓慢下降,直至施工平台钢箱梁结构移动至脱离支座范围后,抽出千斤顶,箱梁继续前移;5) The jack slowly descends until the steel box girder structure of the construction platform moves out of the range of the support, pull out the jack, and the box girder continues to move forward;
6)施工平台钢箱梁结构移动至前端悬臂一定距离时,将吊机系统的吊臂反转固定在后侧固定,继续移动施工平台钢箱梁结构,当前端到达前一承台时,利用千斤顶调位,使其搁置至前一支座上,直至移动到设计位置;6) When the steel box girder structure of the construction platform moves to a certain distance from the cantilever at the front end, reverse the boom of the crane system and fix it on the rear side, and continue to move the steel box girder structure of the construction platform. When the front end reaches the previous platform, use Adjust the position of the jack so that it rests on the previous support until it moves to the designed position;
7)施工平台钢箱梁结构移动就位后,移动吊机至作业时的设计位置,进行下一个墩身的施工,即完成整个可移动的过程。7) After the steel box girder structure of the construction platform is moved into place, the crane is moved to the design position during operation, and the construction of the next pier is carried out, that is, the entire movable process is completed.
所述的吊机系统在作业时,风力小于或等于8级风,风速小于或等于21m/s。When the crane system is in operation, the wind force is less than or equal to level 8, and the wind speed is less than or equal to 21m/s.
具有上述特殊结构的海上辅助施工平台装置及其使用方法具有以下优点:The offshore auxiliary construction platform device with the above-mentioned special structure and its use method have the following advantages:
1.该种海上辅助施工平台装置同时具备传统设备的优点,具有钢平台的优点,克服了外海恶劣的海况条件,变海上施工为陆地施工,又具有起重船灵活机动性,在施工完一个作业面墩柱,利用自身牵引系统可以滑移至下一个作业面进行施工,设备结合现场实际情况,系统中轨道梁既作为平台支撑,又作为吊机轨道;轨道梁之间采用横向联系梁连成一个整体,有利于行走及抗台的稳定性,整体构想新颖、巧妙、实用。1. This kind of offshore auxiliary construction platform device has the advantages of traditional equipment and steel platforms, overcomes the harsh sea conditions in the open sea, changes offshore construction into land construction, and has the flexibility of lifting ships. The pier column on the working face can be slid to the next working face for construction by using its own traction system. The equipment is combined with the actual situation on site. The track beam in the system is used as both platform support and crane track; the track beams are connected by horizontal connecting beams to form a Overall, it is conducive to walking and stability against typhoons, and the overall concept is novel, ingenious and practical.
2.该种海上辅助施工平台装置利用海上移动式施工平台辅助墩柱施工,既降低海上施工安全风险,又提高了海上墩柱施工的效率。2. This kind of offshore auxiliary construction platform device uses an offshore mobile construction platform to assist pier construction, which not only reduces the safety risk of offshore construction, but also improves the efficiency of offshore pier construction.
3.该种海上辅助施工平台装置整套设备能自身从一个作业面移至下一个作业面,避免设备频繁安拆及倒运。3. The whole set of equipment for this kind of offshore auxiliary construction platform device can be moved from one working surface to the next working surface by itself, avoiding frequent installation and disassembly of equipment and unlucky transportation.
附图说明Description of drawings
下面结合附图对本发明作进一步说明:The present invention will be further described below in conjunction with accompanying drawing:
图1为本发明的总装结构示意图。Fig. 1 is a schematic diagram of the assembly structure of the present invention.
图2为图1所示结构的俯视结构示意图。FIG. 2 is a schematic top view of the structure shown in FIG. 1 .
图3为本发明在工作过程中移动的位置一的结构示意图。Fig. 3 is a structural schematic diagram of position 1 where the present invention moves during the working process.
图4为本发明在工作过程中移动的位置二的结构示意图。Fig. 4 is a structural schematic diagram of the second position of the present invention moving during the working process.
图5为本发明在工作过程中移动的位置三的结构示意图。Fig. 5 is a structural schematic diagram of the third position of the present invention moving during the working process.
图6为本发明在工作过程中移动的位置四的结构示意图。Fig. 6 is a schematic structural view of the fourth position of the present invention moving during the working process.
图7为本发明中吊机系统与轨道梁之间的结构示意图。Fig. 7 is a schematic diagram of the structure between the crane system and the track beam in the present invention.
图8为本发明中牵引系统的机构示意图。Fig. 8 is a schematic diagram of the mechanism of the traction system in the present invention.
在图1-8中,1:吊机系统;2:轨道梁;3:横向联系梁;4:箱梁支座。In Fig. 1-8, 1: crane system; 2: track beam; 3: transverse link beam; 4: box girder support.
具体实施方式Detailed ways
由图1-图8所示结构结合可知,该种海上辅助施工平台装置包括吊机系统1,吊机系统1设置在可移动的支撑系统上,支撑系统包括两条相互平行的轨道梁2,两条轨道梁2之间设有与轨道梁2长度方向相垂直的横向联系梁3,轨道梁2和横向联系梁3均采用箱梁结构,两箱梁之间用剪刀撑竖向相连,轨道梁2下方的承台上放置箱梁支座4,支撑系统通过行走机构带动其移动,行走机构是在箱梁支座4的上方设有四氟滑板,箱梁下翼缘底铺设方便平台装置整体移动的不锈钢钢板,不锈钢钢板在四氟滑板上移动,并通过位于轨道梁2端部的牵引机构电动葫芦进行牵引。From the combination of the structures shown in Figures 1 to 8, it can be seen that the offshore auxiliary construction platform device includes a crane system 1, which is arranged on a movable support system, and the support system includes two
支撑系统上还安装有抗台及防撞系统,抗台及防撞系统为利用支座抬高轨道梁2的标高,在轨道梁2上设置减小风荷载的孔,并将轨道梁2的锚固定在易施工的承台上。An anti-table and anti-collision system is also installed on the support system. The anti-table and anti-collision system is to use the support to raise the elevation of the
作为一种具体的实施方式,移动施工平台采用两条长103.4m的轨道梁2,轨道梁2的中心距为6m,两条轨道梁2之间通过11条横向联系梁3连接。轨道梁2采用高2.436m,宽1.0m的箱梁,横向联系梁为两条截面为300×300mm箱型梁,两箱梁间用剪刀撑竖向相连。同时在轨道梁2下方的承台上放置箱梁支座4,箱梁支座4上方设四氟滑板,在箱梁支座4下翼缘底铺设不锈钢钢板,以方便平台系统整体移动。As a specific implementation, the mobile construction platform adopts two
除导梁和轨道梁2之间采用焊接外,轨道梁2和轨道梁连接座通过螺栓连接,轨道梁2与横向联系梁3之间采用螺栓连接。In addition to welding between the guide beam and the
移动式平台系统主梁依托于已施工的承台上,将两根轨道梁2向进行联系固定,形成一个稳定的施工平台。平台可堆放模板、钢筋等材料机具,上面亦可作为临时施工生活区。在移动平台主梁上安装吊机,平台上吊机作为墩身施工垂直运输设备。The main girder of the mobile platform system relies on the cap platform that has been constructed, and connects and fixes the two track beams in two directions to form a stable construction platform. The platform can be stacked with formwork, steel bars and other materials and tools, and it can also be used as a temporary construction living area. The crane is installed on the main girder of the mobile platform, and the crane on the platform is used as the vertical transportation equipment for pier body construction.
利用该种施工平台装置进行施工的使用方法,具体为:The method of using this kind of construction platform device for construction is specifically:
1)将轨道梁2依托于已施工的承台上,将两根轨道梁2和横向联系梁3进行固定,形成一个稳定的施工平台,在移动平台的轨道梁2上安装吊机系统1、行走机构;1) Rely on the
2)待移动施工平台的所有构件全部安装完成,对吊机系统和电动葫芦行走机构进行调试验收后,即可开始现浇墩身施工;2) After all the components of the mobile construction platform are installed, and the crane system and the electric hoist traveling mechanism are debugged and accepted, the construction of the cast-in-place pier can begin;
3)待后端墩身全部施工完成后,将吊机系统的吊臂向前趴在轨道梁2上的搁置梁上,移动吊机系统至前一个墩身前侧,就位后将吊机系统以及塔臂前端的搁置梁跟施工平台钢箱梁结构固定在一起;3) After all the construction of the rear pier body is completed, put the boom of the crane system forward on the shelving beam on the
4)采用电动葫芦作为牵引系统,移动施工平台钢箱梁结构,当后端将要脱离后支座时,停止钢箱梁移动,用螺旋千斤顶缓慢将箱梁顶起,并将支座移开;4) Use the electric hoist as the traction system to move the steel box girder structure of the construction platform. When the rear end is about to break away from the rear support, stop the movement of the steel box girder, slowly lift the box girder with a screw jack, and remove the support;
5)千斤顶缓慢下降,直至施工平台钢箱梁结构移动至脱离支座范围后,抽出千斤顶,箱梁继续前移;5) The jack slowly descends until the steel box girder structure of the construction platform moves out of the range of the support, pull out the jack, and the box girder continues to move forward;
6)施工平台钢箱梁结构移动至前端悬臂一定距离时,将吊机系统的吊臂反转固定在后侧固定,继续移动施工平台钢箱梁结构,当前端到达前一承台时,利用千斤顶调位,使其搁置至前一支座上,直至移动到设计位置;6) When the steel box girder structure of the construction platform moves to a certain distance from the cantilever at the front end, reverse the boom of the crane system and fix it on the rear side, and continue to move the steel box girder structure of the construction platform. When the front end reaches the previous platform, use Adjust the position of the jack so that it rests on the previous support until it moves to the designed position;
7)施工平台钢箱梁结构移动就位后,移动吊机至作业时的设计位置,进行下一个墩身的施工,即完成整个可移动的过程。7) After the steel box girder structure of the construction platform is moved into place, the crane is moved to the design position during operation, and the construction of the next pier is carried out, that is, the entire movable process is completed.
该种设备的工作过程具体为:待移动施工平台的所有构件全部安装完成,并对动臂吊机和电动葫芦行走系统进行调试验收后,即可开始现浇墩身施工。The working process of this kind of equipment is as follows: After all the components of the mobile construction platform are installed, and the boom crane and electric hoist walking system are debugged and accepted, the cast-in-place pier construction can begin.
1)吊机吊装作业,完成后端墩身施工1) Crane hoisting operation, complete the construction of the back-end pier body
全部安装就位后,将吊机固定在指定位置,准备吊装作业。利用船舶将模板、钢筋等运至准备施工墩身的承台另一侧(靠承台),利用吊机吊装,进行该墩身的施工。吊机作业时,风力不得超过8级风,风速不得大于21m/s。After everything is installed in place, fix the crane in the designated position and prepare for hoisting work. Use ships to transport the formwork, steel bars, etc. to the other side of the cap to prepare for the construction of the pier (close to the cap), and use a crane to hoist to carry out the construction of the pier. When the crane is working, the wind force shall not exceed level 8, and the wind speed shall not exceed 21m/s.
2)吊机移动至设计位置2) The crane moves to the design position
待后端墩身全部施工完成后,将吊机的吊臂向前趴在箱梁轨道上的搁置梁上,移动吊机至前一个墩身前侧,就位后将吊机以及塔臂前端的搁置梁跟施工平台钢箱梁结构固定在一起。After all the construction of the rear pier body is completed, put the boom of the crane forward on the shelving beam on the box girder track, move the crane to the front side of the previous pier body, and place the crane and the front end of the tower arm The shelving beam is fixed together with the steel box girder structure of the construction platform.
3)移动箱梁至设计位置3) Move the box girder to the design position
采用电动葫芦作为牵引系统,移动施工平台钢箱梁结构,当后端将要脱离后支座时,停止钢箱梁移动,用螺旋千斤顶缓慢将箱梁顶起,并将支座移开。然后,千斤顶缓慢下降,直至箱梁移动至脱离支座范围后,抽出千斤顶,箱梁继续前移。The electric hoist is used as the traction system to move the steel box girder structure of the construction platform. When the rear end is about to break away from the rear support, stop the movement of the steel box girder, slowly lift the box girder with a screw jack, and remove the support. Then, the jack slowly descends until the box girder moves out of the range of the support, then the jack is pulled out, and the box girder continues to move forward.
施工平台钢箱梁结构移动至前端悬臂超过30m时,将吊机的吊臂反转固定在后侧固定,继续移动施工平台钢箱梁结构,当前端到达前一承台时,利用千斤顶调位,使其搁置至前一支座上,直至移动到设计位置。When the steel box girder structure of the construction platform moves to the front end of the cantilever exceeding 30m, reverse the boom of the crane and fix it on the rear side, and continue to move the steel box girder structure of the construction platform. When the front end reaches the previous cap, use the jack to adjust the position , so that it rests on the previous support until it moves to the design position.
4)移动吊机就位进行下一墩身施工4) The mobile crane is in place for the next pier construction
施工平台钢箱梁结构移动就位后,移动吊机至作业时的设计位置,进行下一个墩身的施工。After the steel box girder structure of the construction platform is moved into place, the crane is moved to the design position during operation, and the construction of the next pier is carried out.
该种设备采用的关键技术、工艺和方案如下:The key technologies, processes and schemes adopted by this equipment are as follows:
1)整体构想新颖、巧妙、实用。1) The overall concept is novel, ingenious and practical.
该套设备既整合了传统设备的优点,又克服了传统设备的缺点;设备结合现场实际情况,系统中主梁既作为平台支撑,又作为吊机轨道;主梁之间采用横梁连成一个整体,有利于行走及抗台的稳定性。整体构想新颖、巧妙、实用。This set of equipment not only integrates the advantages of traditional equipment, but also overcomes the shortcomings of traditional equipment; the equipment is combined with the actual situation on site, the main beam in the system is not only used as a platform support, but also as a crane track; the main beams are connected to form a whole , is conducive to walking and anti-table stability. The overall concept is novel, ingenious and practical.
2)构建间采用独特的连接方式,便于安拆2) The construction room adopts a unique connection method, which is convenient for installation and disassembly
轨道梁2之间采用连接座连接,轨道梁2与横向联系梁3之间采用螺栓连接,便于制作和现场尤其是海上安拆。The track beams 2 are connected by connecting seats, and the track beams 2 and the transverse connecting beams 3 are connected by bolts, which is convenient for manufacture and on-site installation and disassembly especially at sea.
3)采用简单可靠的行走系统3) Adopt simple and reliable walking system
行走系统采用不锈钢板在四氟滑板上移动,利用电动葫芦作为牵引,该套行走系统较其它行走系统,简单可靠、成本低,便于操作。The walking system adopts stainless steel plate to move on the PTFE slide plate, and the electric hoist is used as traction. Compared with other walking systems, this walking system is simple, reliable, low in cost and easy to operate.
4)简易牢靠的防台系统4) Simple and reliable anti-typhoon system
防台系统采用如下简易措施:a、利用支座抬高主梁标高,减小风暴潮的影响;b、另一方面在主梁上开孔,既减小风荷载又节省钢材用量;c、充分利用现场已有预埋件,将主梁锚固在易施工的承台上。The anti-typhoon system adopts the following simple measures: a. Use the support to raise the elevation of the main girder to reduce the impact of storm surge; b. On the other hand, open holes on the main girder to reduce the wind load and save steel consumption; c. Make full use of the existing embedded parts on site, and anchor the main beam on the cap platform that is easy to construct.
5)曲线桥过孔技术5) Curved bridge via technology
该套系统不仅能施工直线桥,也能施工曲线桥,能实现曲线桥自行过孔,扩大该套设备的适用条件。This system can not only construct straight bridges, but also construct curved bridges, and realize the self-passing of curved bridges, expanding the applicable conditions of this set of equipment.
采用该种海上移动式施工平台辅助墩柱施工,具有钢平台的优点,克服了外海恶劣的海况条件,变海上施工为陆地施工;又具有起重船灵活机动性,在施工完一个作业面墩柱,利用自身牵引系统可以滑移至下一个作业面进行施工。利用海上移动式施工平台辅助墩柱施工,既降低海上施工安全风险,又提高了海上墩柱施工的效率。The use of this kind of offshore mobile construction platform to assist the construction of pier columns has the advantages of steel platforms, overcomes the harsh sea conditions in the open sea, and transforms offshore construction into land construction; it also has the flexibility of crane ships, and can be completed after the construction of a working face pier The column can be slid to the next working surface for construction by using its own traction system. Using the offshore mobile construction platform to assist the construction of pier columns not only reduces the safety risk of offshore construction, but also improves the efficiency of offshore pier column construction.
Claims (7)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2010102800357A CN101949146B (en) | 2010-09-08 | 2010-09-08 | Offshore auxiliary construction platform device and using method thereof |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2010102800357A CN101949146B (en) | 2010-09-08 | 2010-09-08 | Offshore auxiliary construction platform device and using method thereof |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN101949146A true CN101949146A (en) | 2011-01-19 |
| CN101949146B CN101949146B (en) | 2012-05-30 |
Family
ID=43452763
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN2010102800357A Expired - Fee Related CN101949146B (en) | 2010-09-08 | 2010-09-08 | Offshore auxiliary construction platform device and using method thereof |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN101949146B (en) |
Cited By (12)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102071647A (en) * | 2010-12-30 | 2011-05-25 | 中铁大桥局集团第二工程有限公司 | Method for mounting dismountable steel trestle |
| CN102852095A (en) * | 2012-09-07 | 2013-01-02 | 中交第二航务工程局有限公司 | Prefabricated bridge abutment multifunctional lifting system and construction procedure thereof |
| CN102926397A (en) * | 2012-09-07 | 2013-02-13 | 中交第二航务工程局有限公司 | Multifunctional hydraulic hanger for bridge prefabricated foundation construction and construction steps thereof |
| CN103184722A (en) * | 2013-03-18 | 2013-07-03 | 广州市市政工程机械施工有限公司 | Large-span double-layer Bailey truss structure and construction method thereof |
| CN105421453A (en) * | 2015-11-27 | 2016-03-23 | 中交第二航务工程局有限公司 | Pile block movable platform steel pipe pile driving construction method |
| CN105507160A (en) * | 2015-11-25 | 2016-04-20 | 杭州江润科技有限公司 | Method of operation platform for movable-type bailey beams for construction of cast-in-place box beams |
| CN105696538A (en) * | 2016-04-06 | 2016-06-22 | 中交航局第二工程有限公司 | Mobile offshore unit piling construction process and equipment |
| CN106088141A (en) * | 2014-08-14 | 2016-11-09 | 中国建筑第八工程局有限公司 | For reinforcing the construction method of the base structure of lowering or hoisting gear |
| CN106704705A (en) * | 2017-01-12 | 2017-05-24 | 中交天航南方交通建设有限公司 | Water pipeline assembly operation method and system |
| CN110172922A (en) * | 2019-06-17 | 2019-08-27 | 中国建筑第六工程局有限公司 | A kind of environmentally friendly downlink Self-propelled steel trestle work structure construction method |
| CN110468721A (en) * | 2019-08-29 | 2019-11-19 | 中铁大桥局集团有限公司 | A kind of large span trestle Cantilever Construction Method |
| CN116289565A (en) * | 2022-12-30 | 2023-06-23 | 保利长大工程有限公司 | Construction method of walk-on-detachable trestle bridge |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR20080093263A (en) * | 2007-04-16 | 2008-10-21 | (주)석탑엔지니어링 | Continuous construction method of steel composite steel bridge |
| CN201209237Y (en) * | 2008-05-22 | 2009-03-18 | 中铁大桥局股份有限公司 | Multi-beam-section bracket of movable formwork |
| CN101581073A (en) * | 2008-07-10 | 2009-11-18 | 中铁大桥局股份有限公司 | Downlink movable mould frame and walking method thereof |
| CN101792015A (en) * | 2010-03-08 | 2010-08-04 | 中铁大桥局股份有限公司 | Multi-functional assembling type waterborne movable device |
| CN201762699U (en) * | 2010-09-08 | 2011-03-16 | 中交二航局第四工程有限公司 | Offshore auxiliary construction platform device |
-
2010
- 2010-09-08 CN CN2010102800357A patent/CN101949146B/en not_active Expired - Fee Related
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR20080093263A (en) * | 2007-04-16 | 2008-10-21 | (주)석탑엔지니어링 | Continuous construction method of steel composite steel bridge |
| CN201209237Y (en) * | 2008-05-22 | 2009-03-18 | 中铁大桥局股份有限公司 | Multi-beam-section bracket of movable formwork |
| CN101581073A (en) * | 2008-07-10 | 2009-11-18 | 中铁大桥局股份有限公司 | Downlink movable mould frame and walking method thereof |
| CN101792015A (en) * | 2010-03-08 | 2010-08-04 | 中铁大桥局股份有限公司 | Multi-functional assembling type waterborne movable device |
| CN201762699U (en) * | 2010-09-08 | 2011-03-16 | 中交二航局第四工程有限公司 | Offshore auxiliary construction platform device |
Cited By (19)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102071647A (en) * | 2010-12-30 | 2011-05-25 | 中铁大桥局集团第二工程有限公司 | Method for mounting dismountable steel trestle |
| CN102852095A (en) * | 2012-09-07 | 2013-01-02 | 中交第二航务工程局有限公司 | Prefabricated bridge abutment multifunctional lifting system and construction procedure thereof |
| CN102926397A (en) * | 2012-09-07 | 2013-02-13 | 中交第二航务工程局有限公司 | Multifunctional hydraulic hanger for bridge prefabricated foundation construction and construction steps thereof |
| CN102852095B (en) * | 2012-09-07 | 2014-10-22 | 中交第二航务工程局有限公司 | Prefabricated bridge abutment multifunctional lifting system and construction procedure thereof |
| CN103184722A (en) * | 2013-03-18 | 2013-07-03 | 广州市市政工程机械施工有限公司 | Large-span double-layer Bailey truss structure and construction method thereof |
| CN103184722B (en) * | 2013-03-18 | 2015-01-28 | 广州市市政工程机械施工有限公司 | Large-span double-layer Bailey truss structure and construction method thereof |
| CN106088141B (en) * | 2014-08-14 | 2018-02-06 | 中国建筑第八工程局有限公司 | For the construction method for the foundation structure for reinforcing lowering or hoisting gear |
| CN106088141A (en) * | 2014-08-14 | 2016-11-09 | 中国建筑第八工程局有限公司 | For reinforcing the construction method of the base structure of lowering or hoisting gear |
| CN105507160A (en) * | 2015-11-25 | 2016-04-20 | 杭州江润科技有限公司 | Method of operation platform for movable-type bailey beams for construction of cast-in-place box beams |
| CN105507160B (en) * | 2015-11-25 | 2017-04-26 | 杭州江润科技有限公司 | Method of operation platform for movable-type bailey beams for construction of cast-in-place box beams |
| CN105421453A (en) * | 2015-11-27 | 2016-03-23 | 中交第二航务工程局有限公司 | Pile block movable platform steel pipe pile driving construction method |
| CN105696538A (en) * | 2016-04-06 | 2016-06-22 | 中交航局第二工程有限公司 | Mobile offshore unit piling construction process and equipment |
| CN105696538B (en) * | 2016-04-06 | 2018-07-06 | 中交第一航务工程局有限公司 | Marine mobile platform piling construction technique and equipment |
| CN106704705A (en) * | 2017-01-12 | 2017-05-24 | 中交天航南方交通建设有限公司 | Water pipeline assembly operation method and system |
| CN106704705B (en) * | 2017-01-12 | 2019-12-17 | 中交天航南方交通建设有限公司 | Method and system for assembling a water pipeline |
| CN110172922A (en) * | 2019-06-17 | 2019-08-27 | 中国建筑第六工程局有限公司 | A kind of environmentally friendly downlink Self-propelled steel trestle work structure construction method |
| CN110468721A (en) * | 2019-08-29 | 2019-11-19 | 中铁大桥局集团有限公司 | A kind of large span trestle Cantilever Construction Method |
| CN110468721B (en) * | 2019-08-29 | 2021-04-20 | 中铁大桥局集团有限公司 | A kind of cantilever construction method of large-span trestle bridge |
| CN116289565A (en) * | 2022-12-30 | 2023-06-23 | 保利长大工程有限公司 | Construction method of walk-on-detachable trestle bridge |
Also Published As
| Publication number | Publication date |
|---|---|
| CN101949146B (en) | 2012-05-30 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN101949146B (en) | Offshore auxiliary construction platform device and using method thereof | |
| CN115652859B (en) | An integral installation method for the superstructure of offshore pile-based marine structures | |
| CN110468816A (en) | A sliding installation method and system for an offshore electrical platform | |
| CN113026563B (en) | Suspension bridge high-low displacement girder trestle girder hoisting facility and construction method thereof | |
| CN203049466U (en) | Downward bracket self-moving formwork bridge fabrication machine | |
| CN102127899A (en) | System for lifting and sliding large-tonnage steel box girder in land area and shoal area and construction method thereof | |
| CN101792015B (en) | Multi-functional assembling type waterborne movable device | |
| CN102953343A (en) | Descending bracket self-mobile model framework bridge fabrication machine | |
| CN105926457A (en) | Method for mounting steel box girders in main tower area of cable-stayed bridge and auxiliary girder erection crane base | |
| CN201762699U (en) | Offshore auxiliary construction platform device | |
| CN105544409B (en) | Double guide beam bridge erecting machine sets up combination beam and now spells a section girder steel construction technology | |
| CN206986743U (en) | A kind of fixed trestle navigable vertical lift device | |
| CN115387228A (en) | High-stability steel truss beam pushing and floating towing bracket construction method | |
| CN115874594A (en) | Translation load receiving system and translation load receiving method for ocean booster station | |
| CN101806053A (en) | Integral installation method of cantilever beams of self lifting type well drilling platform | |
| CN208009277U (en) | A kind of short sliding installation system of land-based area large-tonnage steel box beam | |
| CN202481956U (en) | Attached climbing type conventionalized dual-purpose platform | |
| CN102041781B (en) | Enclosed lake beam type steel bridge installation method based on portal crane | |
| CN202416191U (en) | Lifting device of main girder for offshore demolition of downward mobile formwork | |
| CN104386586B (en) | The land installation method of water conservancy project prefabricated components | |
| CN203782670U (en) | Floating box platform for over-water construction | |
| CN216238670U (en) | Bailey beam steel trestle steel pipe pile position and verticality measuring device | |
| CN209989858U (en) | A kind of auxiliary tool for river dredging | |
| CN218619992U (en) | Jacking device is changed in maintenance of bank bridge gate leg | |
| CN204151665U (en) | A kind of cable-stayed type opens trestle |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20120530 Termination date: 20160908 |
