CN101922241A - Method for repairing wood beam column of old building by embedded rib reinforcement - Google Patents

Method for repairing wood beam column of old building by embedded rib reinforcement Download PDF

Info

Publication number
CN101922241A
CN101922241A CN 201010252145 CN201010252145A CN101922241A CN 101922241 A CN101922241 A CN 101922241A CN 201010252145 CN201010252145 CN 201010252145 CN 201010252145 A CN201010252145 A CN 201010252145A CN 101922241 A CN101922241 A CN 101922241A
Authority
CN
China
Prior art keywords
stainless steel
beam column
steel strip
wood beam
building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 201010252145
Other languages
Chinese (zh)
Inventor
车汪速
黄维成
黄�良
金永树
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHENGDU CONSTRUCTION ENGINEERING GROUP CORP
Original Assignee
CHENGDU CONSTRUCTION ENGINEERING GROUP CORP
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHENGDU CONSTRUCTION ENGINEERING GROUP CORP filed Critical CHENGDU CONSTRUCTION ENGINEERING GROUP CORP
Priority to CN 201010252145 priority Critical patent/CN101922241A/en
Publication of CN101922241A publication Critical patent/CN101922241A/en
Pending legal-status Critical Current

Links

Images

Abstract

The invention provides a method for repairing a wood beam column of an old building by embedded rib reinforcement, aiming at providing an old building repairing method which only repairs and reinforces the damaged part and ensures the appearance is little difference with the original part with quick construction progress, low construction cost, high safety and no replacement of the whole component. The method is realized by the following technical scheme: firstly, the structure characteristic and the incomplete degree of the building are investigated; a plotting drawing and an investigation report are drawn; a support is arranged on the lower end of the beam and is isolated from soft materials; a groove is reserved on a damaged surface of the wood beam column, a stainless steel strip is embedded in the groove on the surface of the wood beam column to become a whole with the original structure, and glue is applied to the surface of the wood beam column which is embedded with the stainless steel strip to coat and adhere a fiber fabric; and an color paint over with wood oil on the surface course is arranged according to the original appearance decorating pattern of the wood component. The method not only improves the carrying capability of the wood beam column to ensure that the appearance has little difference with the original part, but also prolongs the service life of the wood beam column building because the stainless steel strip cannot be rusted.

Description

The method of repairing wood beam column of old building by embedded rib reinforcement
Technical field
The invention relates to the method for repairing wood beam column of old building by embedded rib reinforcement.
Background technology
The long history of China has been created magnificent ancient civilization, and Chinese ancient architecture has emerged many building masterpiece, has built various palaces handed down from ancient times, mausoleum, temple, gardens, private residence.Chinese ancient architecture becomes cultural heritage highly visible with its graceful soft profile with changing various form.It is a bright jewel in the world architecture art treasure-house.Appreciate Chinese ancient architecture, like opening heavy history records.But these are noticeable, admirable cultural heritage, owing to be subjected to external force effect and self material property degradation such as earthquake, burn into natural environment for a long time, the serious threat that the decline of the bearing capacity of structure and stability, the safety of ancient building have been subjected to being exposed to the sun and rain, wind and frost sleet is damaged, the timber natural defect, damage by worms, the span centre crucial force part of crack initiation, beam-ends splitting, beam column of breaking, knaur, wood are turned round (tiltedly) line or shrinkage crack, and the top layer is rotten serious with aged deterioration.The reparation of ancient architecture has become the important topic that protects cultural heritage.
And at present when ancient building is repaired, people for wooden frame, pin occur rotten, damage by worms, the reparation of cracking, shaft damage, generally all be to take to change whole post, whole beam, or joints cement concrete complementing method solves.The weak point of these methods is, has run counter to the principle of " restoring the old as the old ", makes impaired member lose value as historical relic.Next is before changing beam column, needs the wooden frame post of ancient building is unloaded, and its potential safety hazard is bigger, and construction speed is slow, the cost height, and the difference of outward appearance and original part is big.
Summary of the invention
The objective of the invention is weak point at the prior art existence, principle according to " restoring the old as the old ", it is fast to propose a kind of construction speed, construction cost is low, safe, need not change whole member, only to impaired part repairing and reinforcement, and the method for the little repairing wood beam column of old building by embedded rib reinforcement of the difference of outward appearance and original part.
The object of the invention can reach by following measure.A kind of method of repairing wood beam column of old building by embedded rib reinforcement has following technical characterictic:
1) reconnoitres evaluation: at first be that characteristics of the times, architectural feature, structural feature and incomplete degree to building reconnoitred; Draw the report of reconnoitring of the mapping drawing, photo of damaged situation of this building and size, necessary explanatory note data and prospecting results;
2) inspection and the damaged point of evaluation pin are set up bracing frame in the beam lower end, and bracing frame top and wooden construction contact position isolate with flexible material;
3) Local treatment pin beam damaged part:
When the shrinkage crack degree of depth of pin is no more than 1/3~1/4 of post footpath or draw seam direction sectional dimension, crack width is mended with the batten embedding, and is cemented with sqtructural adhesive during greater than 3mm;
When the pin post heart is intact, only there is the top layer rotten or have when rotten in various degree, earlier rotten part is rejected totally, after preservative treatment, repair neat, and bonding or subsidize tight according to former state and life size with desiccated wood with sqtructural adhesive;
4) tick slot on damaged of wooden frame post is embedded in stainless steel strip in the tick slot of wooden frame post surface, gluing parcel on the wooden frame post surface of the good stainless steel strip of embedding then, and paste cloth and original structure becomes one the preferred basalt fiber cloth of cloth;
5) oil colored paintings: behind parcel good fiber cloth, carry out the oil colored paintings of surface layer according to the original decorative appearance pattern of timber compoment.
The present invention has following beneficial effect than prior art.
The present invention is according to the principle of " restoring the old as the old ", and the historical relic that keeps the ancient building member is worth, and only to impaired part repairing and reinforcement, need not change whole member.The ancient building timber compoment is priceless because of its historical relic is worth; use this worker method can when its supporting capacity of the impaired forfeiture of wood beam column of old building, keep original part; recover its bearing function, meet the principle of " restoring the old as the old ", the protection of national historical relic is significant.
Adopt the wooden frame post repairing and reinforcement of this worker method to ancient building, its damaged part obtains repairing.Wherein adopt the stainless steel strip that higher physical strength and modulus of elasticity are arranged, it is embedded in wooden frame post surface, become one with original structure, and bear more load effect, not only improved the supporting capacity of wooden frame post, make outward appearance and original part keep the little original appearance of difference, and prolonged the life-span of wooden frame post building because of its not corrosion of stainless steel strip.
The present invention can reach following effect at wooden frame post perished surface parcel basalt fiber cloth: the one, improve element bearing capacity by " mould hoop effect "; The 2nd, the globality of raising member makes stainless steel strip combine with original member is better; The 3rd, the protection member is avoided insect pest and environmental attack.
The efficient height has been saved the duration.Handle owing to only the impaired part of wooden frame post is carried out local stiffening, need not change whole member, therefore accelerated construction speed, saved the duration.
Safe.Because when adopting the construction of this worker method, needn't unload wooden frame post building facilities, safety of construction improves widely.Need the wooden frame post of ancient building is unloaded the drawback that potential safety hazard is bigger before having avoided prior art to change beam column.
The construction cost cost is low.The job practices that more renews beam column with prior art is compared, and adopts this worker method can reduce by 70% construction cost, and has saved wood usage amount, is beneficial to environmental protection.
Adopt basalt fiber cloth parcel wooden frame post, than using carbon fiber to be furnished with following advantage:
1, cost performance height, unit price are 20% of carbon cloths.
2, good toughness, fracture elongation almost are 2 times of carbon cloth;
3, flexible winding can be cut out arbitrarily, easily pastes, and construction quality is easy to guarantee.
The present invention is applicable to that wooden frame, the pin to ancient building occurs that the top layer is rotten, damage by worms in the part, the reinforcing reparation when ftractureing.
Description of drawings
Fig. 1 is the construction flow chart of the embedded rib reinforcement construction wood beam column of old building restorative procedure according to the present invention.
The specific embodiment
Consult Fig. 1.According to the technological process that the present invention proposes, need reconnoitre evaluation to the impaired wooden frame of ancient building, pin usually.The reconnoitring of ancient building can be divided into French and reconnoitre with damaged situation and reconnoitre two classes.Wherein to reconnoitre be that characteristics of the times, architectural feature and structural feature to building reconnoitred to French; Damaged situation reconnoitre be to the load-carrying members of building and correlation engineering thereof damage, incomplete degree and reason reconnoitre.
To the reconnoitring of ancient building the time, the instrument of reconnoitring use should be able to satisfy related request.For the object of long-term observation, firm permanent observation reference point should be set still; Ban use of all to impair reconnoitring of ancient building and attached historical relic thereof and observation method simultaneously, as temperature shock, strong illumination, strong vibration etc.Prospecting results still should be with complete set mapping drawing, photo and the necessary explanatory note data of damaged situation of this building and size except that reconnoitring the report.In the process of reconnoitring, if find dangerous situation, or the discovery topic is remembered, historical relic, should keep the scene intact and notify at once authorities immediately, and the explorer must not take the liberty to decide matters by oneself.
In structural reliability is identified, should reach according to the damaged number of spots that occurs in the load-carrying members, issue, deterioration degree structure partial or the whole destruction and the consequence that may cause are assessed.
The inspection of wooden frame, the damaged point of pin and evaluation according to the form below carry out.
1. the inspection and the evaluation form of the damaged point of pin
Figure BSA00000227300400041
2. the inspection and the evaluation form of the damaged point of wooden frame
Figure BSA00000227300400051
When setting up local support frame and handling frame, bracing frame and handling frame can adopt steel pipe scaffold, door-type scaffold or tool type scaffold.The parameter of setting up of the scaffold that adopts should be by load checking computations affirmation.
When pin was repaired, for reducing the load-bearing of pin, bracing frame was set up in the beam lower end that reply links to each other with post.If damaged location in the beam intersection, also should be set up bracing frame to relevant beam.For avoiding damaging the oil colored paintings on the intact part of wooden construction top layer, bracing frame top and wooden construction contact position isolate with flexible material.
To pin, wooden frame damaged part Local treatment the time, to the shrinkage crack of pin, when its degree of depth be no more than post footpath or shrinkage crack direction sectional dimension 1/3 the time, and when crack width during,, and cement with sqtructural adhesive with batten embedding benefit greater than 3mm.When if the horizontal fracture degree of depth of wooden frame is damaged by worms above 1/4 or wooden frame post part of deck-siding or beam diameter, remove rotten mashed position wooden unit, chip earlier, spray antiseptic insect-repelling medicament, then slit embedding benefit bonding is tight with batten and sqtructural adhesive.
When the pin post heart is intact, only there is the top layer rotten, rotten part can be rejected totally, after preservative treatment, repair neatly according to former state and life size with desiccated wood, and bonding with sqtructural adhesive.
When wooden frame has when rotten to some extent, earlier rotten part is rejected totally, after preservative treatment, press required form and size with dry timber, subsidize tight with sqtructural adhesive.
When 1/4 and the supporting capacity checking computation results that surpasses deck-siding or beam diameter when the horizontal fracture degree of depth of wooden frame do not satisfy force request, it was tight then with batten and sqtructural adhesive bonding to be mended in the slit embedding.
For wooden frame, the pin part position of damaging by worms, remove rotten mashed wooden unit, chip earlier, spray antiseptic insect-repelling medicament, it is tight with batten and sqtructural adhesive bonding to be mended in the slit embedding again.
Tick slot on damaged of wooden frame post.After the damaged part to wooden frame, pin carries out the part reparation, the quantity of tick slot and position are consistent with the stainless steel strip that needs to embed on timber compoment, the stainless steel strip cross section that the width of tick slot, the degree of depth embed greater than need, tick slot length is slightly larger than the length of the stainless steel strip that needs embedding.
Paste stainless steel strip, four of embeddings or above stainless steel strip around the impaired cylinder of pin are subjected to curved district to embed two or two above stainless steel strips at wooden frame.When tick slot is embedded in stainless steel strip, should use reperfusion structure glue earlier, embed stainless steel strip again.After embedding stainless steel strip, adopt to be embedded into batten, stainless steel strip is pushed against, again reperfusion structure glue.
After tick slot is embedded into batten and stainless steel strip, gluing parcel cloth.The preferred basalt fiber cloth of cloth also can adopt carbon cloth, glass fabric.
The good stainless steel strip of embedding, and after treating the abundant drying of structure glue, the used structure glue of basalt fiber cloth is pasted in brushing.Evenly, structure glue is not coated in the damaged part surface of wooden frame post with rotary broom or hairbrush with having omission.Structure glue coated face border should be not less than the basalt fiber cloth size of being pasted.Tie mist or moisture is arranged as the wooden construction surface, use hair dryer the surfacing of moist position can be constructed to drying.When basalt fiber cloth is pasted in brushing, with special glue Kun and scraper plate basalt fiber cloth upper edge machine direction exert pressure and to a direction or from the centre to the both direction rolling compaction, make resin adhesive liquid fully flood basalt fiber cloth, form composite material, eliminate bubble and remove unnecessary resin, make basalt fibre and bottom fully bonding.
Structure glue is solidified.After the extremely abundant drying of structure glue gel, as find that there are projection burr or glue knurl in the surface, use emery cloth polishing fairing, answer the above step of repetitive operation if any the part that polishing is worn.
Oil colored paintings.After having wrapped up basalt fiber cloth, after hidden acceptance(check), carry out the oil colored paintings of surface layer according to the original decorative appearance pattern of timber compoment.When the ancient building oil colored paintings, must not change colour painting grade, color original state and decorate subject matter original-pack.
Remove bracing frame and handling frame.After facing decoration is finished, qualified by inspection dismounting bracing frame and handling frame.
Table 1 main material table
Figure BSA00000227300400071

Claims (7)

1. the method for a repairing wood beam column of old building by embedded rib reinforcement has following technical characterictic:
1) reconnoitres evaluation: at first be that characteristics of the times, architectural feature, structural feature and incomplete degree to building reconnoitred; Draw the report of reconnoitring of the mapping drawing, photo of damaged situation of this building and size, necessary explanatory note data and prospecting results;
2) inspection and the damaged point of evaluation pin are set up bracing frame in the beam lower end, and bracing frame top and wooden construction contact position isolate with flexible material;
3) Local treatment pin beam damaged part:
When the shrinkage crack degree of depth of pin is no more than 1/3~1/4 of post footpath or draw seam direction sectional dimension, crack width is mended with the batten embedding, and is cemented with sqtructural adhesive during greater than 3mm;
When the pin post heart is intact, only there is the top layer rotten or have when rotten in various degree, earlier rotten part is rejected totally, after preservative treatment, repair neat, and bonding or subsidize tight according to former state and life size with desiccated wood with sqtructural adhesive;
4) tick slot on damaged of wooden frame post is embedded in stainless steel strip in the tick slot of wooden frame post surface, gluing parcel on the wooden frame post surface of the good stainless steel strip of embedding then, and paste cloth and original structure becomes one the preferred basalt fiber cloth of cloth;
5) oil colored paintings: behind parcel good fiber cloth, carry out the oil colored paintings of surface layer according to the original decorative appearance pattern of timber compoment.
2. the method for repairing wood beam column of old building by embedded rib reinforcement as claimed in claim 1, it is characterized in that, in above-mentioned steps 2, after wooden frame, the reparation of pin damaged part Local treatment are finished, then the quantity of tick slot and position are consistent with the stainless steel strip that needs to embed on timber compoment, first reperfusion structure glue in groove, the stainless steel strip cross section that the width of groove, the degree of depth embed greater than need, flute length is greater than the length of the stainless steel strip of need embedding; Around the pin cylinder, embed at least four stainless steel strips, after wooden frame is subjected to curved district to embed at least two stainless steel strips, embeds stainless steel strip, be embedded into batten stainless steel strip is pushed against, again reperfusion structure glue.
3. the method for repairing wood beam column of old building by embedded rib reinforcement as claimed in claim 1, it is characterized in that, when if the horizontal fracture degree of depth of wooden frame post is damaged by worms above 1/4 or wooden frame post part of deck-siding or beam diameter, remove rotten mashed position wooden unit, chip earlier, spray antiseptic insect-repelling medicament, then slit embedding benefit bonding is tight with batten and sqtructural adhesive.
4. the method for repairing wood beam column of old building by embedded rib reinforcement as claimed in claim 1 is characterized in that, described cloth is selected basalt fiber cloth, carbon cloth or glass fabric for use.
5. the method for repairing wood beam column of old building by embedded rib reinforcement as claimed in claim 1 is characterized in that, the good stainless steel strip of embedding, and after treating the abundant drying of structure glue, the used structure glue of basalt fiber cloth is pasted in brushing.
6. the method for repairing wood beam column of old building by embedded rib reinforcement as claimed in claim 5 is characterized in that, described structure glue coated face border is not less than the basalt fiber cloth size of being pasted.
7. the method for repairing wood beam column of old building by embedded rib reinforcement as claimed in claim 1, it is characterized in that, when basalt fiber cloth is pasted in brushing, exert pressure in basalt fiber cloth upper edge machine direction with glue Kun and scraper plate, and to a direction or from the centre to the both direction rolling compaction, make resin adhesive liquid fully flood basalt fiber cloth, form composite material, eliminate bubble and remove unnecessary resin, make basalt fibre and bottom fully bonding.
CN 201010252145 2010-08-13 2010-08-13 Method for repairing wood beam column of old building by embedded rib reinforcement Pending CN101922241A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201010252145 CN101922241A (en) 2010-08-13 2010-08-13 Method for repairing wood beam column of old building by embedded rib reinforcement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201010252145 CN101922241A (en) 2010-08-13 2010-08-13 Method for repairing wood beam column of old building by embedded rib reinforcement

Publications (1)

Publication Number Publication Date
CN101922241A true CN101922241A (en) 2010-12-22

Family

ID=43337425

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201010252145 Pending CN101922241A (en) 2010-08-13 2010-08-13 Method for repairing wood beam column of old building by embedded rib reinforcement

Country Status (1)

Country Link
CN (1) CN101922241A (en)

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102943571A (en) * 2012-12-03 2013-02-27 东南大学 Reinforced structure for lower string beam of wooden structure howe roof truss of historic building
CN105672686A (en) * 2016-01-29 2016-06-15 浙江水利水电学院 Ancient wood building repairing construction method
CN105952182A (en) * 2016-06-21 2016-09-21 南京林业大学 Method for compound reinforcement of wooden beam
CN107083846A (en) * 2017-04-06 2017-08-22 国网山东省电力公司烟台供电公司 A kind of shockproof reinforcement means of log cabin
CN107327154A (en) * 2017-05-19 2017-11-07 中国矿业大学 A kind of method of screw connection aluminium alloy plate reinforcing wood beam
CN108005403A (en) * 2017-12-07 2018-05-08 上海住总集团建设发展有限公司 The restorative procedure and reparation structure of the pin of historical building
CN108060790A (en) * 2017-11-30 2018-05-22 中国矿业大学 A kind of method that screw and glue connect aluminium alloy plate reinforcing wood beam jointly
CN108979187A (en) * 2018-07-23 2018-12-11 南通市紫石古典园林建筑工程有限公司 A kind of ancient building pin anti-crack and anti-seepage reparation integral construction method
CN109057394A (en) * 2018-08-31 2018-12-21 重庆建筑工程职业学院 A kind of excavation-filling method that ancient building pillar slot is rotten
CN110259179A (en) * 2019-07-16 2019-09-20 福建荣冠环境建设集团有限公司 A kind of historic building structure method for repairing and constructing
CN112196583A (en) * 2020-11-26 2021-01-08 广东工业大学 Method for reinforcing cracked tunnel lining by embedding fiber cables on surface layer
CN113482384A (en) * 2021-07-07 2021-10-08 福建省永泰建筑工程公司 Damaged stone material is torn open and is got device for stone material ancient building restoration
CN114658258A (en) * 2022-05-05 2022-06-24 西安建筑科技大学 Reinforcing device and method for cracked wood beam of historic building wood structure
CN114753670A (en) * 2022-05-05 2022-07-15 西安建筑科技大学 Cracked wood beam repairing and FRP reinforcing device and method
CN117432240A (en) * 2023-12-18 2024-01-23 华侨大学 Repairing method of ancient building girder

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2398338A (en) * 2003-02-13 2004-08-18 Pam Ties Ltd Structural reinforcement
CN101054856A (en) * 2007-05-22 2007-10-17 佛山市工程承包总公司 Rehabilitation method for ancient architecture wall
CN101353928A (en) * 2007-07-23 2009-01-28 陈昶良 Concealed type restoring construction method with reinforced parts applied to archaic building components

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2398338A (en) * 2003-02-13 2004-08-18 Pam Ties Ltd Structural reinforcement
CN101054856A (en) * 2007-05-22 2007-10-17 佛山市工程承包总公司 Rehabilitation method for ancient architecture wall
CN101353928A (en) * 2007-07-23 2009-01-28 陈昶良 Concealed type restoring construction method with reinforced parts applied to archaic building components

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
《中华人民共和国国家标准GB50165-92》 19920929 国家技术监督局,中华人民共和国建设部 古建筑木结构维护与加固技术规范 , 1 *
《第五届全国FRP学术交流会论文集》 20071231 麻建锁等 玄武岩纤维修复加固破损木柱的试验方法研究 , 2 *

Cited By (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102943571A (en) * 2012-12-03 2013-02-27 东南大学 Reinforced structure for lower string beam of wooden structure howe roof truss of historic building
CN105672686B (en) * 2016-01-29 2018-06-29 浙江水利水电学院 A kind of historic building structure method for repairing and constructing
CN105672686A (en) * 2016-01-29 2016-06-15 浙江水利水电学院 Ancient wood building repairing construction method
CN105952182A (en) * 2016-06-21 2016-09-21 南京林业大学 Method for compound reinforcement of wooden beam
CN105952182B (en) * 2016-06-21 2018-01-26 南京林业大学 A kind of method of composite consolidation wooden frame
CN107083846A (en) * 2017-04-06 2017-08-22 国网山东省电力公司烟台供电公司 A kind of shockproof reinforcement means of log cabin
CN107327154A (en) * 2017-05-19 2017-11-07 中国矿业大学 A kind of method of screw connection aluminium alloy plate reinforcing wood beam
CN108060790A (en) * 2017-11-30 2018-05-22 中国矿业大学 A kind of method that screw and glue connect aluminium alloy plate reinforcing wood beam jointly
CN108005403A (en) * 2017-12-07 2018-05-08 上海住总集团建设发展有限公司 The restorative procedure and reparation structure of the pin of historical building
CN108979187A (en) * 2018-07-23 2018-12-11 南通市紫石古典园林建筑工程有限公司 A kind of ancient building pin anti-crack and anti-seepage reparation integral construction method
CN109057394A (en) * 2018-08-31 2018-12-21 重庆建筑工程职业学院 A kind of excavation-filling method that ancient building pillar slot is rotten
CN110259179A (en) * 2019-07-16 2019-09-20 福建荣冠环境建设集团有限公司 A kind of historic building structure method for repairing and constructing
CN112196583A (en) * 2020-11-26 2021-01-08 广东工业大学 Method for reinforcing cracked tunnel lining by embedding fiber cables on surface layer
CN113482384A (en) * 2021-07-07 2021-10-08 福建省永泰建筑工程公司 Damaged stone material is torn open and is got device for stone material ancient building restoration
CN114658258A (en) * 2022-05-05 2022-06-24 西安建筑科技大学 Reinforcing device and method for cracked wood beam of historic building wood structure
CN114753670A (en) * 2022-05-05 2022-07-15 西安建筑科技大学 Cracked wood beam repairing and FRP reinforcing device and method
CN114658258B (en) * 2022-05-05 2023-09-26 西安建筑科技大学 Device and method for reinforcing wood beam for cracking of wooden structure of ancient building
CN114753670B (en) * 2022-05-05 2024-04-12 西安建筑科技大学 Device and method for repairing and FRP reinforcing cracking wood beam
CN117432240A (en) * 2023-12-18 2024-01-23 华侨大学 Repairing method of ancient building girder

Similar Documents

Publication Publication Date Title
CN101922241A (en) Method for repairing wood beam column of old building by embedded rib reinforcement
CN202000685U (en) Historic building wooden beams and columns reinforced through embedded ribs
CN103590616B (en) Active powder fiber concrete strengthening concrete column and reinforcement means
CN1834160B (en) Stretchy rubberized asphalt felt for waterproofing and waterproofing material of duplex rubberized asphalt membrane plus felt
WO2020253134A1 (en) Grc plate repairing method
CN109610880A (en) Two layers of pin Dun of ancient building, which connect, raises construction method
JP4127551B2 (en) Method for repairing concrete structure and concrete structure
CN106801517A (en) A kind of schoolhouse surface consolidation of Prefabricated porous plate brick mixed structure strengthens method
Adas Wooden bay window (Rowshan) conservation in Saudi-Hejazi heritage buildings
KR20090033573A (en) Retrofitting and strengthening system of concrete structures using sprayed frp coating
CN105401740B (en) Timber structure and timber structure restorative procedure after reparation
CN104453267A (en) Structure and manufacturing method of CFRP (carbon fiber reinforced plastic) sheet reinforced tenon-and-mortise-structure extension wooden beam
US7168887B1 (en) Method for repairing a crack in a recreational court or surface
KR102177416B1 (en) Repair and protection method of non-slip paint coating on deteriorated roof metal surface
CN205077891U (en) Restore back timber structure
Palanti et al. Wooden doors and windows in the Church of the Nativity: Evaluation of biotic and abiotic decay and proposals of interventions
KR102256371B1 (en) Method For Repairing Cracks In Exterior Concrete Walls
CN209703334U (en) A kind of road and bridge crack reparation fixed structure
CN112593724A (en) Method for repairing traditional building by glass fiber reinforced plastic material
CN208293792U (en) A kind of quick service waterproof construction for toilet warterproof rupture
CN204676830U (en) A kind of weather resistant acrylic acid terrace
CN108252531A (en) It is a kind of to be used for the restorative procedure of historical building metope and reparation structure
Krist et al. The Durbar Square and the Royal Palace of Patan, Nepal–Stone Conservation Before and After the Great Earthquake of April 2015
KR20020076212A (en) A waterproof process method of a concrete structure
Alessandri Roof and windows

Legal Events

Date Code Title Description
DD01 Delivery of document by public notice

Addressee: Che Wangsu

Document name: Notification of Passing Preliminary Examination of the Application for Invention

C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Open date: 20101222