CN101899816A - Steel structure hangar tunnel and installation method - Google Patents

Steel structure hangar tunnel and installation method Download PDF

Info

Publication number
CN101899816A
CN101899816A CN2009103027448A CN200910302744A CN101899816A CN 101899816 A CN101899816 A CN 101899816A CN 2009103027448 A CN2009103027448 A CN 2009103027448A CN 200910302744 A CN200910302744 A CN 200910302744A CN 101899816 A CN101899816 A CN 101899816A
Authority
CN
China
Prior art keywords
hangar tunnel
steel structure
steel
crossbeam
column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2009103027448A
Other languages
Chinese (zh)
Inventor
杨文俊
梁宗泽
徐全
舒华武
樊向毅
孙显翠
吴芳
赵丽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHENGDU RAILWAY BUREAU CHENGDU TRACK MACHINERY DIVISION GUIYANG LABOUR SERVICE Co Ltd
Original Assignee
CHENGDU RAILWAY BUREAU CHENGDU TRACK MACHINERY DIVISION GUIYANG LABOUR SERVICE Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHENGDU RAILWAY BUREAU CHENGDU TRACK MACHINERY DIVISION GUIYANG LABOUR SERVICE Co Ltd filed Critical CHENGDU RAILWAY BUREAU CHENGDU TRACK MACHINERY DIVISION GUIYANG LABOUR SERVICE Co Ltd
Priority to CN2009103027448A priority Critical patent/CN101899816A/en
Publication of CN101899816A publication Critical patent/CN101899816A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a steel structure hangar tunnel and an installation method. The steel structure hangar tunnel comprises a base (1), wherein an upright post (2) is arranged on the base (1), a longitudinal beam (3) is arranged on the upright post (2), a crossbeam (4) is arranged on the longitudinal beam (3), and a wood board (9) and backfill soil (8) are laid on the crossbeam (4). The invention is designed into a steel structure mode according to the requirements of rigidity, strength and delimitation of a hangar tunnel by the traditional railroad line. The steel structure hangar tunnel is divided into a plurality of parts and assemblies by synthetically considering the characteristics of structural strength and transportation, and all the steel structure assemblies adopt factory production and have interchange ability and universality. The steel structure hangar tunnel is convenient to assemble and disassemble, is light and flexible, has quick construction progress and low interference with running vehicles and can be disassembled for recycling after dangerous cases are eliminated. Due to the adoption of the installation method, the hangar tunnel can be completely installed for 3-5 days in order to greatly reduce construction time.

Description

Steel structure hangar tunnel and mounting method
Technical field
The present invention relates to a kind of steel structure hangar tunnel and mounting method, belong to the hangar tunnel technical field.
Background technology
In the tunnel and the special cutting place of existing rail track, because the variation of landform, landforms, there are disasters such as landslide, landslide, falling rocks to take place during massif and seriously jeopardize traffic safety.Traditional approach is to build permanent hangar tunnel (reinforced concrete structure), and shortcoming is a cost height, long in time limit, needs 120 days usually, and construction is disturbed big to transportation, more can not adapt to sudden specific demand of speedily carrying out rescue work.And, the problem that line standard is low, disease is many is arranged for the railway in mountain area, along with transportation development all will progressively be transformed, building hangar tunnel is interim measure, therefore builds permanent hangar tunnel and more there is no need.
Summary of the invention
The objective of the invention is to: provide a kind of suitable road to speedily carry out rescue work and transform the steel structure hangar tunnel and the mounting method of preceding interim measure with existing line, to overcome the deficiencies in the prior art.
The present invention constitutes like this: steel structure hangar tunnel, structure comprises base, is provided with column on base, is provided with longeron on column, is provided with crossbeam on longeron, lays plank and backfill on crossbeam.
Above-mentioned steel structure hangar tunnel is provided with pull bar between column.
Above-mentioned steel structure hangar tunnel, column is formed by connecting by bolt by the steel buttress.
Above-mentioned steel structure hangar tunnel, the structure of steel buttress comprise iron plate and following iron plate, 4 angle steel of welding between last iron plate and following iron plate, and the band steel of usefulness is strengthened in welding between 4 angle steel.
Above-mentioned steel structure hangar tunnel is provided with insulating slab below crossbeam.
The steel structure hangar tunnel mounting method, in factory, make each parts of steel structure hangar tunnel earlier, build the floor manufacture base of position at hangar tunnel, the steel buttress of making is installed on the base,, the steel buttress is connected by bolt according to design height, be assembled into column, fixing longeron on column is installed crossbeam again on longeron, lay plank and backfill at last on crossbeam.
Above-mentioned steel structure hangar tunnel mounting method, each parts of described steel structure hangar tunnel comprise steel buttress, pull bar, longeron and crossbeam.
Above-mentioned steel structure hangar tunnel mounting method, backfill adopt the earth bag husky and soil of packing into to fold sign indicating number.
The present invention is designed to the steel work pattern according to the requirement of existing railway line to hangar tunnel rigidity, intensity, gauge.Take all factors into consideration structural strength, the transportation characteristics are divided into several portions, parts, and all these steelwork components adopt batch production production, have interchangeability, versatility.On-the-spot need or in case dangerous situation takes place, be transported to the scene after, can carry out composite assembly (building block system), be characterized in that handling demolition is convenient, light and handy flexibly, construction speed is fast, interference on the road is little, after dangerous situation was eliminated, dismountable turnover was used.Adopt method of the present invention, only needed just hangar tunnel can be installed in 3~5 days, shortened the engineering time greatly, especially be fit to the interim measure before railway emergency rescue and existing line are transformed.
Description of drawings
Accompanying drawing 1 is a structural representation of the present invention;
Accompanying drawing 2 is that the A of accompanying drawing 1 is to view;
Accompanying drawing 3 is the structural representation of steel buttress of the present invention.
The specific embodiment
Embodiments of the invention: in factory, make parts such as steel buttress 6, pull bar 5, longeron 3 and crossbeam 4 earlier, build the floor manufacture base 1 of position at hangar tunnel, steel buttress 6 is installed on the base 1, according to design height, steel buttress 6 is connected by bolt, be assembled into column 2, fixing longeron 3 on column 2 tops, crossbeam 4 is installed on longeron 3 again, on crossbeam 4, is laid plank 9 and backfill 8 at last, can obtain hangar tunnel.Cylinder lever connecting rod 5 between column 2, guarantee the Stability Analysis of Structures of hangar tunnel.Fitting insulating panels 7 can also be installed bearing diagonal 14 to guarantee safety between column 2 and crossbeam 4 below crossbeam 4, improves stability.
The structure of steel buttress 6 comprises iron plate 12 and following iron plate 13,4 angle steel 10 of welding between last iron plate 12 and following iron plate 13, and the band steel 11 of usefulness is strengthened in welding between 4 angle steel 10, produces screw on last iron plate 12 and the following iron plate 13.
Longeron 3 and crossbeam 4 adopt alloy-steel plate weldering system, and longeron 3 is fixed on the column 2 by high-strength bolt, and crossbeam 4 is tiled on the longeron 3 with constant spacing.Plank 9 is made into same specification in factory, then at plank 9 bottom surface installing and locating angle steel, on-the-spot plank 9 is fixed gets final product on crossbeam 4.Backfill 8 adopts the earth bag husky and soil of packing into to fold sign indicating number, and easy to operate, speed is fast.
The senior rustproof paint of all steel part sparies two roads, the special-purpose finish paint of steel bridge two roads are with anti-corrosion.

Claims (8)

1. steel structure hangar tunnel, structure comprises base (1), it is characterized in that: be provided with column (2) on base (1), be provided with longeron (3) on column (2), be provided with crossbeam (4) on longeron (3), go up at crossbeam (4) and lay plank (9) and backfill (8).
2. steel structure hangar tunnel according to claim 1 is characterized in that: be provided with pull bar (5) between column (2).
3. steel structure hangar tunnel according to claim 1 is characterized in that: column (2) is formed by connecting by bolt by steel buttress (6).
4. steel structure hangar tunnel according to claim 3, it is characterized in that: the structure of steel buttress (6) comprises iron plate (12) and following iron plate (13), welding 4 angle steel (10) between last iron plate (12) and following iron plate (13), the band steel (11) of usefulness is strengthened in welding between 4 angle steel (10).
5. steel structure hangar tunnel according to claim 1 is characterized in that: be provided with insulating slab (7) in crossbeam (4) below.
6. steel structure hangar tunnel mounting method, it is characterized in that: each parts of in factory, making steel structure hangar tunnel earlier, build the floor manufacture base of position at hangar tunnel, the steel buttress of making is installed on the base,, the steel buttress is connected by bolt according to design height, be assembled into column, fixing longeron on column is installed crossbeam again on longeron, lay plank and backfill at last on crossbeam.
7. steel structure hangar tunnel mounting method according to claim 5 is characterized in that: each parts of described steel structure hangar tunnel comprise steel buttress, pull bar, longeron and crossbeam.
8. steel structure hangar tunnel mounting method according to claim 5 is characterized in that: backfill adopts the earth bag husky and soil of packing into to fold sign indicating number.
CN2009103027448A 2009-05-27 2009-05-27 Steel structure hangar tunnel and installation method Pending CN101899816A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009103027448A CN101899816A (en) 2009-05-27 2009-05-27 Steel structure hangar tunnel and installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009103027448A CN101899816A (en) 2009-05-27 2009-05-27 Steel structure hangar tunnel and installation method

Publications (1)

Publication Number Publication Date
CN101899816A true CN101899816A (en) 2010-12-01

Family

ID=43225703

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009103027448A Pending CN101899816A (en) 2009-05-27 2009-05-27 Steel structure hangar tunnel and installation method

Country Status (1)

Country Link
CN (1) CN101899816A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103244183A (en) * 2013-05-28 2013-08-14 中铁上海设计院集团有限公司 Construction method for additionally constructing shed tunnel contact network in water disaster area
CN106638340A (en) * 2016-12-02 2017-05-10 大连理工大学 Combined energy dissipation shed frame structure for preventing rockfall of high and steep slope in earthquake region
CN110919085A (en) * 2019-12-12 2020-03-27 广东中烨建筑钢构有限公司 Steel cutting device and ground steel structure construction method
CN116537442A (en) * 2023-05-18 2023-08-04 中建铁路投资建设集团有限公司 Cross-height cutting road building bottom plate and construction method thereof

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103244183A (en) * 2013-05-28 2013-08-14 中铁上海设计院集团有限公司 Construction method for additionally constructing shed tunnel contact network in water disaster area
CN103244183B (en) * 2013-05-28 2015-09-16 中铁上海设计院集团有限公司 A kind of water damage location increases builds hangar tunnel contact network construction method
CN106638340A (en) * 2016-12-02 2017-05-10 大连理工大学 Combined energy dissipation shed frame structure for preventing rockfall of high and steep slope in earthquake region
CN110919085A (en) * 2019-12-12 2020-03-27 广东中烨建筑钢构有限公司 Steel cutting device and ground steel structure construction method
CN116537442A (en) * 2023-05-18 2023-08-04 中建铁路投资建设集团有限公司 Cross-height cutting road building bottom plate and construction method thereof

Similar Documents

Publication Publication Date Title
CN104141383B (en) A kind of Bailey beam pendent form support system and construction thereof
CN101550769B (en) Movable trestle
CN101985826B (en) Construction method for high-altitude section prefabricating, beam moving, beam storing and assembling of large concrete box beam
CN103924525B (en) Urban interchange industrialization short-term precast assembly construction method
CN107558378B (en) Bridge girder erection machine for erecting full precast girder and bridge girder erection method thereof
CN101781878B (en) Integral lifting template of main pylon of single-pylon cable-stayed bridge without dorsal cables and lifting construction method thereof
CN103758024B (en) The steel structure footbridge of quickly dismantled
CN102364012A (en) Method for expanding existing large-span truss
CN103334379A (en) Construction method for hanging part of anti-collision guardrail on expressway
CN101899816A (en) Steel structure hangar tunnel and installation method
CN102220741A (en) Steel-concrete composite girder construction technology striding current lines and being parallel to existing lines
CN203474271U (en) Special assembly type rail base for portal crane
CN103669218B (en) Novel toughened internal stress steel box-girder module and spelling method thereof
CN103711082A (en) Construction method for elevated section used for straddle type single-track transportation
CN203248170U (en) Lining trolley for secondary lining construction of pedestrian crosswalk
CN203684061U (en) Steel pedestrian overcrossing fast to disassemble or assemble
CN102733406A (en) Railway construction method of solid concrete roadbed in large-size industrial plant
CN201412162Y (en) Steel structure shed tunnel
CN107313628A (en) A kind of basic digging-free assembled tower-type space garage and its construction method
CN103590839B (en) Subway station cast-in-place structural portal support construction technology
CN103711071A (en) Elevated section structure used for straddle type single-track transportation
CN208203298U (en) A kind of big punching block of rail type side wall
CN102454298B (en) Large-sized reinforced concrete construction of frame beam method
CN202718126U (en) Deep foundation pit earthwork excavation conversion platform
CN202622992U (en) Universal-type post-tensioned T-beam precast pedestal with detachable modules and adjustable steel members

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20101201