CN101892736B - 高空移动吊篮施工方法 - Google Patents
高空移动吊篮施工方法 Download PDFInfo
- Publication number
- CN101892736B CN101892736B CN2010102499868A CN201010249986A CN101892736B CN 101892736 B CN101892736 B CN 101892736B CN 2010102499868 A CN2010102499868 A CN 2010102499868A CN 201010249986 A CN201010249986 A CN 201010249986A CN 101892736 B CN101892736 B CN 101892736B
- Authority
- CN
- China
- Prior art keywords
- hanging basket
- groups
- chain
- chain blocks
- moving
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
本发明涉及一种高空移动吊篮施工方法,包括以下步骤:吊篮的连接:首先将高强尼龙带绑扎在钢结构下弦杆上,然后在吊篮两端分别用¢16钢丝绳缠绕在吊篮的主龙骨上,最后通过六组环链手拉葫芦分别连接高强尼龙带和钢丝绳以完成吊篮的连接;吊篮的提升:匀速拉动两组与钢丝绳中部连接的手拉葫芦使移动吊篮缓慢上升,直至所需施工高度;吊篮的移动:通过六组环链手拉葫芦的配合使吊篮移动到施工部位为止;吊篮的拆除:解开连接吊篮的主龙骨的四组手拉葫芦,将另两组手拉葫芦缓慢向下拉,至吊篮放至地面为止后,再进行拉绳拆除。本发明的有益效果为:操作人员能够稳定地站在吊篮里面进行施工操作;不占用地面空间;安全性高;节约成本,缩短工期。
Description
技术领域
本发明涉及一种高空移动吊篮施工方法。
背景技术
高空作业中在对天花吊顶施工时,通常采用传统的满堂脚手架,吊顶的高度越高必然要求其底面面积越大,否则会失去稳定,造成安全隐患。所以,当施工环境为例如多跨连续大跨度的空间双向曲面结构,施工总面积较大的桥型建筑时,如果继续采用传统的满堂脚手架,存在下述缺陷:一、搭设满堂脚手的所需要的各类材料数量会相当大,需要数万吨脚手架钢管及扣件,用于脚手架的租赁、运输、搭设、维护等费用将相当高昂;二、脚手架位置移动必然受到所述建筑中两侧支撑和观光层的影响,如果拆卸之后,在下一个位置重新组装,其工作量很大;占用地面空间大,不利于交叉作业,阻碍工期正常进行。
发明内容
本发明的目的是提供一种高空移动吊篮施工方法,以克服现有技术占地面积广,投入成本高,施工周期长,安全隐患大,立体交叉作业难以实现,施工工期难以保证的不足。
实现本发明目的技术方案如下:一种高空移动吊篮施工方法,包括以下步骤:1)吊篮的连接:首先将高强尼龙带绑扎在钢结构下弦杆上,尼龙带与下弦杆之间用3mm厚橡皮胶垫底,尼龙带的下口用U型卸扣固定,然后在吊篮两端分别用¢16钢丝(直径为16毫米的钢丝绳)绳缠绕在吊篮的主龙骨上并用U型卸扣固定钢丝绳,最后通过六组环链手拉葫芦分别连接高强尼龙带和钢丝绳以完成吊篮的连接,所述环链手拉葫芦对称设在移动吊篮两端,三组环链手拉葫芦分别连接钢丝绳的中部和钢丝绳两端的主龙骨;2)吊篮的提升:匀速拉动两组与钢丝绳中部连接的环链手拉葫芦使移动吊篮缓慢上升,直至所需施工高度;3)吊篮的移动:首先在指挥人员的指挥下将连接钢丝绳中部的两组环链手拉葫芦拉紧,使另外四组环链手拉葫芦处于松弛状态,将所述的另外四组环链手拉葫芦连接的高强尼龙带向移动方向小步移动,然后用所述的四组环链手拉葫芦将相应连接的高强尼龙带扣紧,将中部的两组环链手拉葫芦的链条缓慢放下直至链条不受力为止,使吊篮缓慢向移动方向漂移,反复上述步骤至移动吊篮移动到施工部位为止;4)吊篮的拆除:首先在指挥人员的统一指挥下解开连接吊篮的主龙骨的四组环链手拉葫芦,然后将连接钢丝绳中部的两组环链手拉葫芦缓慢向下拉,至吊篮放至地面为止后,再进行拉绳拆除,并抬放到安置仓库。
所述尼龙带缠绕钢结构下弦杆至少两圈。
所述吊篮的主龙骨为C180x50x20x3mm的C型钢,副龙骨为30x50x2.5mm的方钢,安全护栏由30x30x3mm的方钢焊接而成,吊篮内铺满压型钢板作为踏脚板。
所述踏脚板采用台阶状踏脚板。
所述吊篮的安全护栏内侧焊接有钢板网,并14#铁丝绑扎固定,所述钢板网稍微低于安全护栏的高度。
本发明的有益效果为:吊篮内铺满压型钢板或采用台阶状踏脚板,使操作人员能够稳定地站在吊篮里面进行施工操作;高空移动吊篮的施工高度依据现场具体情况进行相应调整,既可以水平悬挂,也可以倾斜一定角度悬挂;安全性高,占地面积小;节约成本,可以交叉施工从而缩短工期;厚橡皮胶垫底,避免钢丝绳对吊点构件造成磨损和以及拆除架体尾部吊点时对已完成的吊顶板的成品保护。
附图说明
下面根据附图对本发明作进一步详细说明。
图1是应用本发明实施例所述的高空移动吊篮施工方法的吊兰的连接结构示意图。
图中:1、下弦杆;2、尼龙带;3、钢丝绳;4、吊篮;41、主龙骨;42、副龙骨;43、安全护栏;44、踏脚板;45、钢板网;5、环链手拉葫芦。
具体实施方式
现结合吊篮在在武汉火车站项目的应用,阐明其施工方法、涉及的设备的各项要求等,从而将该施工方法推广。
武汉火车站装饰工程吊顶采用铝质管帘天花造型,在钢网架屋顶下弦处,主楼钢网架屋面为多跨连续大跨度的空间双向曲面结构,主核心区单跨宽度达138m,东西屋架长达306.8m;8个扇形区每个宽39m,东西长280 m左右;吊顶标高最高点约59m,最低点约25m。吊篮作业附着结构为钢网架层面下弦杆,杆件直径¢200-¢500不等。主结构网架基本单元为6000×5400方格,每个大小不等,装饰二次钢构及管帘天花完成后,将主方格分割为4个小方格。
本发明实施例所述的一种高空移动吊篮施工方法,包括以下步骤:1)吊篮的连接:首先将高强尼龙带2绑扎在钢结构下弦杆1上,高强度尼龙带2单个可承重3吨以上,下弦杆1的直径200-500毫米尼龙带与下弦杆之间用3mm厚橡皮胶垫底,尼龙带的下口用U型卸扣固定,然后在吊篮两端分别用¢16钢丝绳3缠绕在吊篮4的主龙骨41上并用U型卸扣固定钢丝绳,尼龙带缠绕钢结构下弦杆至少两圈,其可承重3T,最后通过六组环链手拉葫芦5分别连接高强尼龙带和钢丝绳以完成吊篮的连接,并将保险绳按要求扣牢,以便吊装时作临时固定,所述环链手拉葫芦5可承重2吨以上,其对称设在移动吊篮两端,三组环链手拉葫芦5分别连接钢丝绳的中部和钢丝绳两端的主龙骨(如图1所示);2)吊篮的提升:匀速拉动两组与钢丝绳中部连接的环链手拉葫芦5使移动吊篮缓慢上升,直至所需施工高度;3)吊篮的移动:首先在指挥人员的指挥下将连接钢丝绳中部的两组环链手拉葫芦5拉紧,使另外四组环链手拉葫芦5处于松弛状态,将所述的另外四组环链手拉葫芦5连接的高强尼龙带向移动方向小步移动,然后用所述的四组环链手拉葫芦5将相应连接的高强尼龙带扣紧,将中部的两组环链手拉葫芦5的链条缓慢放下直至链条不受力为止,使吊篮缓慢向移动方向漂移,反复上述步骤至移动吊篮移动到施工部位为止;4)吊篮的拆除:首先在指挥人员的统一指挥下解开连接吊篮的主龙骨的四组环链手拉葫芦5,然后将连接钢丝绳中部的两组环链手拉葫芦5缓慢向下拉,至吊篮放至地面为止后,再进行拉绳拆除,并抬放到安置仓库。下拉过程中,速度必须基本一致,以免速度不均匀导致移动吊篮倾斜。
所述吊篮的主龙骨为C180x50x20x3mm的C型钢,使用连接件将主龙骨连接成为主要骨架,副龙骨42焊接在主龙骨之上,各部件焊接焊缝必须达到三级焊缝,连接件与主龙骨连接使用规格为M12x30高强六角螺栓连接,所有螺栓应有防松垫片,丝口突出螺帽4-5扣以上,所有使用的钢材必须为Q345B低碳合金钢,且检验必须全部合格。副龙骨为30x50x2.5mm的方钢,安全护栏53由30x30x3mm的方钢焊接而成,吊篮内铺满压型钢板作为踏脚板44,每两块压型钢板搭接应在副龙骨上,且两块之间应错接至少300mm以上。铺设好之后用自攻自钻螺丝沿副龙骨方向将压型钢板固定,每块钢板固定螺丝不少于4颗。当倾斜使用时,采用异形吊篮的平台为台阶状,基层使用L40x40角钢焊接成直三角,然后焊接在C型钢主梁上,面层铺压型钢板,使用自攻自钻螺丝固定,如此设计目的是解决主拱区钢结构梁斜面过大的问题,使站在异型吊篮两头的工人能根据需要调整施工高度。所述吊篮的安全护栏内侧焊接有钢板网45,并14#铁丝绑扎固定,所述钢板网稍微低于安全护栏43的高度,避免划伤工作人员。
吊篮的受力分析和计算:1、荷载信息(1)恒荷载计算 根据施工单位提供吊篮方案统计,吊篮自重为4.56kN。恒荷载作为均布荷载作用在吊篮结构上。均布荷载标准值为4.56÷(6×0.75)=1.01KN/㎡;(2)活荷载计算,根据施工单位提供吊篮方案统计,吊篮最大施工荷载在铝质管帘天花施工阶段,其施工荷载为1.26kN。考虑如下不利状态:①:活荷载作为均布荷载作用在吊篮结构上(用于一般状态下结构计算)。局部荷载标准值为1.26÷(6×0.75)=0.28KN/㎡;②:活荷载作为集中荷载作用在吊篮结构主梁跨中(用于主梁最不利结构计算)。集中荷载标准值为1.26÷2=0.63 KN/㎡。
综上所述,该平台使用阶段受力最为不利。
单根拉索额定载重量(风载)W3=(6×0.75×0.625)÷2=1.41KN 合计:2.28+0.85+1.41=4.54KN 提升阶段采用2T导链葫芦,其破断拉力为20×4=80kN安全系数为n=(80×1)/4.54=17.62满足要求。
(2)使用阶段拉索计算 单根拉索额定载重量(恒载)W1=4.56÷6=0.76KN 单根拉索额定载重量(活载)。W2=(1.26+1.7)÷2=1.48KN 单根拉索额定载重量(风载)W3=(6×0.75×0.625)/6=0.47KN 合计:0.76+1.48+0.47=2.71KN 工作阶段采用2T导链葫芦,其破断拉力为20×4=80kN安全系数为n=(80×1)/2.71=29.52 拉索计算满足要求。
单根拉索额定载重量(风载)W3=(6×0.75×0.625)÷3=0.94KN 合计:1.52+0.85+0.94=3.31KN 提升阶段采用2T导链葫芦,其破断拉力为20×4=80kN安全系数为n=(80×1)/3.31=24.17,满足要求。
Claims (5)
1.一种高空移动吊篮施工方法,其特征在于,包括以下步骤:
1)吊篮的连接:首先将尼龙带绑扎在钢结构下弦杆上,尼龙带与下弦杆之间用3mm厚橡皮胶垫底,尼龙带的下口用U型卸扣固定,然后在吊篮两端分别用¢16钢丝绳缠绕在吊篮的主龙骨上并用U型卸扣固定钢丝绳,最后通过六组环链手拉葫芦分别连接尼龙带和钢丝绳以完成吊篮的连接,所述环链手拉葫芦对称设在移动吊篮两端,三组手拉葫芦分别连接钢丝绳的中部和钢丝绳两端的主龙骨;
2)吊篮的提升:匀速拉动两组与钢丝绳中部连接的手拉葫芦使移动吊篮缓慢上升,直至所需施工高度;
3)吊篮的移动:首先在指挥人员的指挥下将连接钢丝绳中部的两组手拉葫芦拉紧,使另外四组手拉葫芦处于松弛状态,将所述的另外四组手拉葫芦连接的尼龙带向移动方向小步移动,然后用所述的四组手拉葫芦将相应连接的尼龙带扣紧,将中部的两组手拉葫芦的链条缓慢放下直至链条不受力为止,使吊篮缓慢向移动方向漂移,反复上述步骤至移动吊篮移动到施工部位为止;
4)吊篮的拆除:首先在指挥人员的统一指挥下解开连接吊篮的主龙骨的四组手拉葫芦,然后将连接钢丝绳中部的两组手拉葫芦缓慢向下拉,至吊篮放至地面为止后,再进行拉绳拆除,并抬放到安置仓库。
2.根据权利要求1所述的高空移动吊篮施工方法,其特征在于:所述尼龙带缠绕钢结构下弦杆至少两圈。
3.根据权利要求1或2所述的高空移动吊篮施工方法,其特征在于:所述吊篮的主龙骨为C180x50x20x3mm的C型钢,副龙骨为30x50x2.5mm的方钢,安全护栏由30x30x3mm的方钢焊接而成,吊篮内铺满压型钢板作为踏脚板。
4.根据权利要求3所述的高空移动吊篮施工方法,其特征在于:所述踏脚板采用台阶状踏脚板。
5.根据权利要求3所述的高空移动吊篮施工方法,其特征在于:所述吊篮的安全护栏内侧焊接有钢板网,并用14#铁丝绑扎固定,所述钢板网稍微低于安全护栏的高度。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010102499868A CN101892736B (zh) | 2010-08-10 | 2010-08-10 | 高空移动吊篮施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010102499868A CN101892736B (zh) | 2010-08-10 | 2010-08-10 | 高空移动吊篮施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101892736A CN101892736A (zh) | 2010-11-24 |
CN101892736B true CN101892736B (zh) | 2013-12-04 |
Family
ID=43102069
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2010102499868A Expired - Fee Related CN101892736B (zh) | 2010-08-10 | 2010-08-10 | 高空移动吊篮施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101892736B (zh) |
Families Citing this family (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102358603A (zh) * | 2011-08-29 | 2012-02-22 | 四川国统混凝土制品有限公司 | Pccp成品管安装拉紧工具 |
CN103848321B (zh) * | 2014-03-08 | 2016-03-02 | 柳州欧维姆机械股份有限公司 | 一种能斜向及竖向移动的高空施工吊篮 |
CN104195942A (zh) * | 2014-08-21 | 2014-12-10 | 四川金锋建设有限公司 | 桥梁底面检修结构 |
CN104358393A (zh) * | 2014-10-24 | 2015-02-18 | 中铁航空港建设集团北京有限公司 | 一种高空吊挂水平移动平台 |
CN104963495B (zh) * | 2015-06-05 | 2017-07-14 | 中国十七冶集团有限公司 | 一种安装屋面底层彩板的悬挂吊篮 |
CN110158939A (zh) * | 2019-06-18 | 2019-08-23 | 中建东方装饰有限公司 | 一种空中漂移作业平台及其施工方法 |
CN110409789B (zh) * | 2019-08-02 | 2021-04-02 | 山东金城建设有限公司 | 大斜度屋面造型梁幕墙吊篮安装方法 |
CN110552542A (zh) * | 2019-08-07 | 2019-12-10 | 上海市机械施工集团有限公司 | 一种圆锥建筑结构的施工方法 |
CN110872086A (zh) * | 2019-10-25 | 2020-03-10 | 山西东盛建设工程有限公司 | 球形网架上滑动吊篮装置 |
CN113189111B (zh) * | 2021-04-28 | 2022-11-01 | 西南交通大学 | 一种钢结构网架外观缺陷视觉检测系统及检测方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2758369Y (zh) * | 2004-12-20 | 2006-02-15 | 武汉市金泉绿色科技有限公司 | 机械传动高空作业吊篮 |
CN2821030Y (zh) * | 2005-06-13 | 2006-09-27 | 胡绳 | 脚踏式升降吊篮 |
DE202008016780U1 (de) * | 2008-12-20 | 2009-06-18 | Matthäi Betriebsführungs-GmbH | Montagebühnenkonstruktion zur Arretierung an einem Seecontainer als Lastaufnahmemittel für Personen und Materialien zur Durchführung von Monatgearbeiten an Turmelementen von Windkraft- und ähnlichen baulichen Anlagen |
CN201268937Y (zh) * | 2008-09-05 | 2009-07-08 | 高智鹏 | 高空作业双层吊篮 |
CN201517284U (zh) * | 2009-10-13 | 2010-06-30 | 河南中建七局建筑装饰工程有限公司 | 一种高空半自动悬挂双悬式钢结构滑移操作平台 |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20090183947A1 (en) * | 2008-01-17 | 2009-07-23 | Stacey Leigh Hudgens-Wallace | Portable scaffolding device |
-
2010
- 2010-08-10 CN CN2010102499868A patent/CN101892736B/zh not_active Expired - Fee Related
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2758369Y (zh) * | 2004-12-20 | 2006-02-15 | 武汉市金泉绿色科技有限公司 | 机械传动高空作业吊篮 |
CN2821030Y (zh) * | 2005-06-13 | 2006-09-27 | 胡绳 | 脚踏式升降吊篮 |
CN201268937Y (zh) * | 2008-09-05 | 2009-07-08 | 高智鹏 | 高空作业双层吊篮 |
DE202008016780U1 (de) * | 2008-12-20 | 2009-06-18 | Matthäi Betriebsführungs-GmbH | Montagebühnenkonstruktion zur Arretierung an einem Seecontainer als Lastaufnahmemittel für Personen und Materialien zur Durchführung von Monatgearbeiten an Turmelementen von Windkraft- und ähnlichen baulichen Anlagen |
CN201517284U (zh) * | 2009-10-13 | 2010-06-30 | 河南中建七局建筑装饰工程有限公司 | 一种高空半自动悬挂双悬式钢结构滑移操作平台 |
Also Published As
Publication number | Publication date |
---|---|
CN101892736A (zh) | 2010-11-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101892736B (zh) | 高空移动吊篮施工方法 | |
CN106284668B (zh) | 一种大跨度大空间钢结构屋面桁架安装方法 | |
CN103061506B (zh) | 一种钢结构穹顶的施工方法 | |
CN104929373B (zh) | 大跨度方钢管桁架及其累积滑移施工方法 | |
CN103291076A (zh) | 弧形框架内多层次钢桁架分片逆向吊装施工工法 | |
CN107013038B (zh) | 一种大型建筑物屋顶采光中庭的钢结构滑移换柱施工方法 | |
CN201297036Y (zh) | 一种卸料平台 | |
CN101537976B (zh) | 双塔桅巨型自升降起重设备及其跟携吊装方法 | |
CN101967887A (zh) | 大跨度轻型钢结构屋面梁吊装方法 | |
CN104234200B (zh) | 一种弦支穹顶索杆系逐环提升安装方法 | |
CN101871259B (zh) | 一种钢网架施工用整体滑移式脚手架的搭建方法 | |
CN101761031B (zh) | 大节段桥面梁连续垂直提升装置 | |
CN201376848Y (zh) | 双塔桅巨型自升降起重设备 | |
CN203296361U (zh) | 大跨度钢结构跨外组对吊装平台 | |
CN103899093A (zh) | 巨型框架钢桁架梁分步吊装施工工法 | |
CN111218987A (zh) | 一种承载式网架施工方法 | |
CN205444975U (zh) | 一种带有观景平台的大型屋盖钢结构施工支撑系统 | |
CN104153586A (zh) | 一种用悬索吊来安装檩条的施工方法 | |
CN104533114B (zh) | 一种海岸柔性直流换流站阀厅联合建筑结构体系 | |
CN210713752U (zh) | 一种可三维空间移动的高处作业施工吊篮 | |
CN104495653A (zh) | 一种多功能大吨位架梁起重机及架梁方法 | |
CN103835369A (zh) | 一种可伸缩的高空连体钢结构 | |
CN205276727U (zh) | 金属屋面内板安装施工平台 | |
CN204402001U (zh) | 用于钢结构屋面内板安装的可移动式操作平台系统 | |
CN104912339B (zh) | 长距离多跨段焊接h型钢屋面梁就位方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20131204 Termination date: 20160810 |
|
CF01 | Termination of patent right due to non-payment of annual fee |