CN101879751A - Production method of concrete pipe pile - Google Patents

Production method of concrete pipe pile Download PDF

Info

Publication number
CN101879751A
CN101879751A CN 201010206339 CN201010206339A CN101879751A CN 101879751 A CN101879751 A CN 101879751A CN 201010206339 CN201010206339 CN 201010206339 CN 201010206339 A CN201010206339 A CN 201010206339A CN 101879751 A CN101879751 A CN 101879751A
Authority
CN
China
Prior art keywords
mould
stretch
draw
concrete
production method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 201010206339
Other languages
Chinese (zh)
Inventor
陈芳斌
陈巧
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Builds China Pipe Pile Co Ltd
Original Assignee
Jiangsu Builds China Pipe Pile Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Builds China Pipe Pile Co Ltd filed Critical Jiangsu Builds China Pipe Pile Co Ltd
Priority to CN 201010206339 priority Critical patent/CN101879751A/en
Publication of CN101879751A publication Critical patent/CN101879751A/en
Pending legal-status Critical Current

Links

Abstract

The invention discloses a production method of a concrete pipe pile. The method sequentially comprises the following steps of: (A) loading cage ribs required for producing a pipe pile into a mould, then closing an upper mould and a lower mould and tightening screws; (B) conveying a prepared concrete material into the cavity of the mould; (C) stretching the cage ribs in the mould and applying prestress; and (D) hanging the mould onto a centrifugal machine for centrifuging and molding. The method aims to overcome the defects in the prior art and provide a production method of a concrete pipe pile having simple process, convenient processing, relatively lower cost, stable product quality and higher production efficiency.

Description

The production method of concrete tubular pile
Technical field
The present invention relates to the production method of concrete tubular pile.
Background technology
In the prior art, producing the concrete tubular pile order generally is to adopt dress steel reinforcement cage, cloth concrete material, matched moulds, post-stretching, centrifugal forming more earlier.The concrete tubular pile that the method is produced mainly contains following defective:
1, quality aspect: the concrete tubular pile of producing commissure spillage, joint close occur than phenomenons such as broads, causes pile tube the time to batter down easily and influence its useful life in construction simultaneously;
2, equipment aspect: when punching block carries out matched moulds, be difficult to close tight, cause between the upper and lower mould running wheel gap bigger, thereby cause punching block when centrifugal, to beat, damage punching block and centrifuge because of concrete particle drops;
3, secure context: drop because of concrete particle is arranged, the wind gunner hinders hand when the matched moulds of punching block is cleared up easily, has great potential safety hazard;
4, required labour aspect: because of when the concrete distributing, have a large amount of particles to drop, need personnel in time clear up and insert and smash, per tour needs 4~6 people to clear up the concrete particle that these drop, waste of manpower at least;
5, auxiliary material aspect:, need a large amount of spades and besom because concrete particle is scattered on flatcar and the ground easily when concrete carries out cloth;
Summary of the invention
The objective of the invention is provides a kind of technology simple, easy to process in order to overcome weak point of the prior art, relatively low, the constant product quality of cost, the production method of the concrete tubular pile that production efficiency is higher.
In order to achieve the above object, the present invention adopts following scheme:
The production method of concrete tubular pile may further comprise the steps successively:
A, will produce the needed cage muscle of pile tube and pack into behind the mould, the upper and lower mould that closes tightens the screw;
B, pre-assigned concrete material is transported to dies cavity;
C, the cage muscle in the above-mentioned mould is carried out stretch-draw, apply prestressing force;
D, mould is hung centrifugal forming on centrifuge.
The production method of aforesaid concrete tubular pile, it is characterized in that adopting among the step C stretch-draw machine that the cage muscle in the mould is carried out stretch-draw, concrete operation is that the cage muscle with the pipe die head end is fixed on the stretch-draw machine with ground tackle, open the stretch-draw machine, the 0.5-0.8 that regulates stretch-draw intensity and be cage muscle overall strength doubly, stretch-draw 10-60 second;
The production method of aforesaid concrete tubular pile is characterized in that stretch-draw intensity among the step C is 0.7 times of cage muscle overall strength
In sum, beneficial effect of the present invention:
One, quality assurance
Because the concrete tubular pile that the method is produced is to adopt first matched moulds, tightens the screw earlier, closes tightlyer between the upper and lower mould, has solved the problem of concrete tubular pile joint close spillage, thereby has ensured the pile tube quality.
Two, equipment fault reduces
Because of what adopt is first matched moulds, and the gap is less between the upper and lower mould, and beating when centrifugal has not had, and the wearing and tearing of punching block and centrifuge running wheel reduce, impaired the reducing of bearing of centrifuge.Thereby reduced equipment failure rate, improved production efficiency and reduced the maintenance of equipment expense.
Three, reduced the labour
Because what adopt is first matched moulds, the direct cloth of concrete is to the inner chamber of punching block, and the existing picture that does not exist concrete particle to drop has reduced cleaning mould limit and smash personnel with slotting, thereby reduced recruitment, saves the work people.
Four, reduce production costs
Because of what adopt is first matched moulds, need not spades and instrument such as besom, reduced production cost.
The specific embodiment
Below in conjunction with the specific embodiment the present invention is described further:
Embodiment 1
The production method of concrete tubular pile of the present invention may further comprise the steps:
A, will produce the needed cage muscle of pile tube and pack into behind the mould, the upper and lower mould that closes tightens the screw;
B, pre-assigned concrete material is transported to dies cavity;
C, employing stretch-draw machine carry out stretch-draw to the cage muscle in the above-mentioned mould, apply prestressing force in mould; Concrete operation is that the cage muscle with the pipe die head end is fixed on the stretch-draw machine with ground tackle, open the stretch-draw machine, according to specification and the arrangement of reinforcement number of producing stake, regulate stretch-draw intensity, general stretch-draw intensity be cage muscle overall strength 0.5-0.8 doubly, adopt in the present embodiment 0.7 times cage muscle overall strength as stretch-draw intensity to cage muscle stretch-draw 10-60 second;
D, mould is hung centrifugal forming on centrifuge.
Embodiment 2
The production method of concrete tubular pile of the present invention may further comprise the steps:
A, will produce the needed cage muscle of pile tube and pack into behind the mould, the upper and lower mould that closes tightens the screw;
B, pre-assigned concrete material is transported to dies cavity;
C, employing stretch-draw machine carry out stretch-draw to the cage muscle in the above-mentioned mould, apply prestressing force in mould; Concrete operation is that the cage muscle with the pipe die head end is fixed on the stretch-draw machine with ground tackle, open the stretch-draw machine, according to specification and the arrangement of reinforcement number of producing stake, regulate stretch-draw intensity, general stretch-draw intensity be cage muscle overall strength 0.5-0.8 doubly, adopt in the present embodiment 0.5 times cage muscle overall strength as stretch-draw intensity to cage muscle stretch-draw 60 seconds;
D, mould is hung centrifugal forming on centrifuge.
Embodiment 3
The production method of concrete tubular pile of the present invention may further comprise the steps:
A, will produce the needed cage muscle of pile tube and pack into behind the mould, the upper and lower mould that closes tightens the screw;
B, pre-assigned concrete material is transported to dies cavity;
C, employing stretch-draw machine carry out stretch-draw to the cage muscle in the above-mentioned mould, apply prestressing force in mould; Concrete operation is that the cage muscle with the pipe die head end is fixed on the stretch-draw machine with ground tackle, open the stretch-draw machine, according to specification and the arrangement of reinforcement number of producing stake, regulate stretch-draw intensity, general stretch-draw intensity be cage muscle overall strength 0.5-0.8 doubly, adopt in the present embodiment 0.8 times cage muscle overall strength as stretch-draw intensity to cage muscle stretch-draw 10 seconds;
D, mould is hung centrifugal forming on centrifuge.

Claims (3)

1. the production method of concrete tubular pile is characterized in that may further comprise the steps successively:
A, will produce the needed cage muscle of pile tube and pack into behind the mould, the upper and lower mould that closes tightens the screw;
B, pre-assigned concrete material is transported to dies cavity;
C, the cage muscle in the above-mentioned mould is carried out stretch-draw, apply prestressing force;
D, mould is hung centrifugal forming on centrifuge.
2. the production method of concrete tubular pile according to claim 1, it is characterized in that adopting among the step C stretch-draw machine that the cage muscle in the mould is carried out stretch-draw, concrete operation is that the cage muscle with the pipe die head end is fixed on the stretch-draw machine with ground tackle, open the stretch-draw machine, the 0.5-0.8 that regulates stretch-draw intensity and be cage muscle overall strength doubly, stretch-draw 10-60 second.
3. the production method of concrete tubular pile according to claim 2 is characterized in that stretch-draw intensity among the step C is 0.7 times of cage muscle overall strength.
CN 201010206339 2010-06-23 2010-06-23 Production method of concrete pipe pile Pending CN101879751A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201010206339 CN101879751A (en) 2010-06-23 2010-06-23 Production method of concrete pipe pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201010206339 CN101879751A (en) 2010-06-23 2010-06-23 Production method of concrete pipe pile

Publications (1)

Publication Number Publication Date
CN101879751A true CN101879751A (en) 2010-11-10

Family

ID=43051952

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201010206339 Pending CN101879751A (en) 2010-06-23 2010-06-23 Production method of concrete pipe pile

Country Status (1)

Country Link
CN (1) CN101879751A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102229484A (en) * 2011-06-10 2011-11-02 江苏建华管桩有限公司 Method for manufacturing tubular pile by adopting pump concrete
CN103481363A (en) * 2013-09-07 2014-01-01 安徽富强混凝土有限公司管桩分公司 Production process of concrete pipe pile

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101863078A (en) * 2010-06-12 2010-10-20 江苏建华管桩有限公司 Production method of concrete tube pile

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101863078A (en) * 2010-06-12 2010-10-20 江苏建华管桩有限公司 Production method of concrete tube pile

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102229484A (en) * 2011-06-10 2011-11-02 江苏建华管桩有限公司 Method for manufacturing tubular pile by adopting pump concrete
CN103481363A (en) * 2013-09-07 2014-01-01 安徽富强混凝土有限公司管桩分公司 Production process of concrete pipe pile

Similar Documents

Publication Publication Date Title
CN101863078A (en) Production method of concrete tube pile
CN101863080B (en) Equipment and method for producing concrete tubular pile
CN206027887U (en) Take battery anode material crushing apparatus of precomminution device
CN206731210U (en) A kind of quartzy disintegrating machine
CN200980319Y (en) Beans and corn cooling skin-removing device
CN101879751A (en) Production method of concrete pipe pile
CN207138082U (en) Dry method building waste process for producing line
CN107695117A (en) A kind of saponification process technique for bolt class product
CN201693668U (en) Equipment for producing concrete tubular piles
CN211463448U (en) Concrete waste recovery device for civil engineering
CN205124891U (en) Shrimp shell crab shell reducing mechanism
CN205009645U (en) Crop straw briquetting device
CN204224911U (en) A kind of paper grade (stock) bamboo chip pulverizer
CN207138808U (en) A kind of pickup system
CN108605520A (en) Castor-oil plant shelling separating one-piece
CN205935681U (en) Inflatable plastics mould shell removal tool
CN212040625U (en) Novel primary crushing equipment for recycled concrete raw materials
CN205291522U (en) Edge -trim reclamation device
CN205008042U (en) Hammer crusher hammer sieve clearance adjustment device
CN205291344U (en) Prolong a class membrane system of processing with edge -trim reclamation device
CN112388932A (en) Production equipment and production method of efficient water-retaining material for crops
CN207630319U (en) A kind of powder pretreatment unit
CN207478945U (en) A kind of building demolition rubbish pre-sorting device based on style characteristic
CN206170608U (en) Double screw extruder who possesses wear compensation
CN205413237U (en) Dead weight formula biax shredder

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20101110