CN101852312B - Pull tube mounting method of passing pipeline - Google Patents

Pull tube mounting method of passing pipeline Download PDF

Info

Publication number
CN101852312B
CN101852312B CN 200910048811 CN200910048811A CN101852312B CN 101852312 B CN101852312 B CN 101852312B CN 200910048811 CN200910048811 CN 200910048811 CN 200910048811 A CN200910048811 A CN 200910048811A CN 101852312 B CN101852312 B CN 101852312B
Authority
CN
China
Prior art keywords
pipe
guide channel
pipeline
wire rope
dummy pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN 200910048811
Other languages
Chinese (zh)
Other versions
CN101852312A (en
Inventor
赵宪彩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC5 Group Shanghai Corp Ltd
Original Assignee
MCC5 Group Shanghai Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC5 Group Shanghai Corp Ltd filed Critical MCC5 Group Shanghai Corp Ltd
Priority to CN 200910048811 priority Critical patent/CN101852312B/en
Publication of CN101852312A publication Critical patent/CN101852312A/en
Application granted granted Critical
Publication of CN101852312B publication Critical patent/CN101852312B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention relates to the pipeline construction method field of a metallurgy system, in particular to a pull pipe mounting method of a passing pipeline, which comprises the following steps of: unreeling a pipeline; digging pilot trenches; making the pipeline; popping conducts; connecting steel wires; pulling the conducts and the steel wires; pulling sleeves; and penetrating and mounting a construction pipe. The pull pipe mounting method of a passing pipeline is characterized in that when the conducts are popped, the front conduct is popped in by top pressing equipment (4); and then, the rear conduct (12) is popped in; and when the sleeves are pulled, the conducts and the sleeves are connected, the front conduct (11) is pulled, and the rear sleeve (22) is popped in until the front sleeve (21)passes out of a pilot trench (2) at the other side. The invention has low construction cost, short construction period, high mounting quality and high production efficiency.

Description

The trombone slide installation method of bypass pipeline
Technical field
The present invention relates to the pipeline construction method field of metallurgical system, be specially a kind of trombone slide installation method of bypass pipeline.
Background technique
In the pipeline construction engineering, if there is not obstacle can adopt slot grooving, but usually need pass highway, railway, building, river etc. during pipelining, in this case, usually do not allow slot grooving or slot grooving difficulty and drop into all larger, can't or be difficult in the situation of fluting, usually adopting at present construction by pipeline jacking method.A kind of tunneling formula method of construction that pipe jacking method adopts when being the various obstacles such as under ground piping railroad crossing, road, river or building, during construction, press the work mine pit as starting point take ready top first, after pipe is discharged into working pit, by power transmission top iron and guide track, with the hydraulic jack that is supported on the foundation ditch back seat pipe is pressed in the soil layer, excavates simultaneously and transport the earth in pipe front.After the first pipe joint all heads into soil layer, then the second pipe joint is connected on the back and continues jacking, as long as the resistance that produces when the top power of jack is enough to overcome push pipe, whole jack-in process repeats with regard to capable of circulation.But construction by pipeline jacking method needs expensive professional equipment, and is subjected to the restriction ratio in place larger during construction, and construction cost is high.
Summary of the invention
In order to overcome the defective of prior art, a kind of, operation simple pipeline construction method few to equipment and place restrictive condition is provided, the invention discloses a kind of trombone slide installation method of bypass pipeline.
The present invention reaches goal of the invention by following technical solution:
A kind of trombone slide installation method of bypass pipeline, carry out successively as follows: pipe alignment → excavation guide channel → making pipeline → top conduit → connect wire rope → pull catheter and wire rope → help pull a cart are managed → are worn the engineering pipe and install, during the excavation guide channel, respectively at the required obstacle both sides excavation guide channel that passes through, and in guide channel fixing position limiting pile, wear engineering pipeline and when installing, engineering pipeline passed by guide channel threading on one side and from the another side guide channel, it is characterized in that:
When making pipeline, conduit diameter is 1/5~1/3 of the required engineering pipeline diameter that penetrates, conduit divides dummy pipe and rear tube two-part, the front portion of dummy pipe and the rear portion of rear tube all have the hole of reeving, there is the flange-like interface rear portion of dummy pipe and the front portion of rear tube, casing inner diameter is than the required diameter large 1/5~1/3 that penetrates engineering pipeline, sleeve pipe divides anterior cannula and rear sleeve two-part, between anterior cannula and the rear sleeve by being welded and fixed, the front portion of anterior cannula also is welded and fixed taper sheath, and the taper sheath top has the hole of reeving.
During the top conduit, with pressing device first with under the position limiting pile of dummy pipe in the guide channel to the guide channel jacking of obstacle another side, when just also heading into the stratum, do not end the flange-like interface for the treatment of the dummy pipe rear portion, the flange-like interface of again rear tube being connected with dummy pipe connects with bolt, then jacking rear tube is until dummy pipe ends when passing in the another side guide channel.
When connecing wire rope, after dummy pipe passes in the another side guide channel, penetrate wire rope in the hole of reeving of dummy pipe front portion, the wire rope the other end connects winch.
When pull catheter and wire rope, after connecting dummy pipe and winch with wire rope, start winch pulling dummy pipe, continue the jacking rear tube with pressing device simultaneously, until end when just also not heading into the stratum in the hole of reeving at rear tube rear portion.
When helping pull a cart pipe, wire rope is penetrated respectively the hole of reeving at reeve hole and the taper sheath top at rear tube rear portion, with this conduit is connected with sleeve pipe, start winch pulling dummy pipe, use simultaneously pressing device jacking rear sleeve, until anterior cannula is ended when passing in the another side guide channel.
The trombone slide installation method of described bypass pipeline is characterized in that: during the conduit of top, pressing device is selected backacter, break point the dead ahead of engineering pipeline to be installed or directly over.
It is that common standard equipment has solved the technical barrier in pipelining highway crossing, railway, building, river and reached the purpose of protection Adjacent Buildings safety that the present invention uses.Adopt method of the present invention can finish the installation of one section pipe of passing by on one's way in 6 hours, and do not affect surrounding building, save a large amount of shoveling expenses with routine fluting pipe laying method phase specific energy, compare with the pipe jacking method of routine, save the expense of using expensive professional equipment.The invention has the beneficial effects as follows: select common standard equipment operation, construction cost is low, short construction period, and installation quality is high, and manufacturing efficiency is high.
Description of drawings
Fig. 1 is the structural representation of conduit among the present invention;
Fig. 2 is the structural representation of middle sleeve of the present invention;
Fig. 3 is the schematic representation of conduit operation in top among the present invention;
Fig. 4 is that the sound of A-A is looked enlarged view among Fig. 3;
Fig. 5 is the cutaway view Amplified image of B-B among Fig. 3;
Fig. 6 helps pull a cart among the present invention to manage the schematic representation of operation;
Fig. 7 is the cutaway view Amplified image of A-A among Fig. 6;
Fig. 8 is the cutaway view Amplified image of B-B among Fig. 6.
Embodiment
Below further specify the present invention by specific embodiment.
Embodiment 1
A kind of trombone slide installation method of bypass pipeline, engineering pipeline diameter to be installed is 300mm, carries out successively as follows:
Pipe alignment → excavation guide channel → making pipeline → top conduit → connect wire rope → pull catheter and wire rope → help pull a cart are managed → are worn the engineering pipe and install, and concrete steps are:
During excavation guide channel 2, respectively at the required obstacle that passes through 1 both sides excavation guide channel 2, and at guide channel 2 interior fixedly position limiting piles 3.
When making pipeline, conduit as shown in Figure 1, diameter is 1/5~1/3 of the required engineering pipeline diameter that penetrates, diameter is got 100mm, conduit divides dummy pipe 11 and rear tube 12 two-part, the rear portion of the front portion of dummy pipe 11 and rear tube 12 all has the hole 101 of reeving, and there is flange-like interface 13 front portion of the rear portion of dummy pipe 11 and rear tube 12.The jacking of conduit and pulling direction are as shown by the arrows in Figure 1.Sleeve pipe as shown in Figure 2, internal diameter is than the required diameter large 1/5~1/3 that penetrates engineering pipeline, get 400mm, sleeve pipe divides anterior cannula 21 and rear sleeve 22 two-part, between anterior cannula 21 and the rear sleeve 22 by being welded and fixed, the front portion of anterior cannula 21 also is welded and fixed taper sheath 23, and taper sheath 23 tops have the hole 201 of reeving.The jacking of sleeve pipe and pulling direction are as shown by the arrows in Figure 2.
During the top conduit, such as Fig. 3~shown in Figure 5, first with position limiting pile 3 time guide channel 2 jackings to obstacle 1 another side of dummy pipe 11 in the guide channel 2, the jacking direction of conduit as shown by the arrows in Figure 3 with pressing device 4.Pressing device 4 is selected backacter, break point the dead ahead of engineering pipeline to be installed or directly over.Scraper bowl top with backacter presses dummy pipe 11 to advance in the stratum, when just also heading into the stratum, do not end the flange-like interface 13 for the treatment of dummy pipe 11 rear portions, the flange-like interface 13 usefulness bolts of again rear tube 12 being connected with dummy pipe connect, then the jacking rear tube 12, until dummy pipe 11 ends when passing in the another side guide channel 2.
When connecing wire rope, after dummy pipe 11 passes in the another side guide channel 2, penetrate wire rope 5 in the hole 101 of reeving of dummy pipe 11 front portions, wire rope 5 the other ends connect winch 6.
When pull catheter and wire rope 5, after connecting dummy pipes 11 and winch 6 with wire rope 5, start winch 6 pulling dummy pipes 11, continue jacking rear tubes 12 with pressing device 4 simultaneously, until end when just also not heading into the stratum in the hole 101 of reeving at rear tube 12 rear portions.
When helping pull a cart pipe, such as Fig. 6~shown in Figure 8, wire rope 5 is penetrated respectively the hole 201 of reeving at reeve hole 101 and taper sheath 23 tops at rear tube 12 rear portions, with this conduit is connected with sleeve pipe, start winch 6 pulling dummy pipes 11, use simultaneously pressing device 4 jacking rear sleeves 22, the jacking of sleeve pipe and pulling direction are as shown by the arrows in Figure 6.Until anterior cannula 21 is ended when passing in the another side guide channel 2.
Wear engineering pipeline and when installing, engineering pipeline 7 is passed by guide channel 2 threadings on one side and from another side guide channel 2, thereby finish trombone slide the bypass pipeline construction is installed.

Claims (2)

1. the trombone slide installation method of a bypass pipeline, carry out successively as follows: pipe alignment → excavation guide channel → making pipeline → top conduit → connect wire rope → pull catheter and wire rope → help pull a cart are managed → are worn the engineering pipe and install, during excavation guide channel (2), respectively at the required obstacle that passes through (1) both sides excavation guide channel (2), and in guide channel (2) fixing position limiting pile (3), wear engineering pipeline and when installing, engineering pipeline is passed by guide channel (2) threading on one side and from another side guide channel (2), it is characterized in that:
When making pipeline, conduit diameter is 1/5~1/3 of the required engineering pipeline diameter that penetrates, conduit divides dummy pipe (11) and rear tube (12) two-part, the rear portion of the front portion of dummy pipe (11) and rear tube (12) all has the hole of reeving (101), there is flange-like interface (13) front portion of the rear portion of dummy pipe (11) and rear tube (12), casing inner diameter is than the required diameter large 1/5~1/3 that penetrates engineering pipeline, sleeve pipe divides anterior cannula (21) and rear sleeve (22) two-part, between anterior cannula (21) and the rear sleeve (22) by being welded and fixed, the front portion of anterior cannula (21) also is welded and fixed taper sheath (23), and taper sheath (23) top has the hole of reeving (201);
During the top conduit, with pressing device (4) first with under the position limiting pile (3) of dummy pipe (11) in the guide channel (2) to guide channel (2) jacking of obstacle (1) another side, the flange-like interface (13) for the treatment of dummy pipe (11) rear portion does not end when just also heading into the stratum, again rear tube (12) is connected 11 with dummy pipe) flange-like interface (13) connect with bolt, then jacking rear tube (12) is until dummy pipe (11) ends when passing in the another side guide channel (2);
When connecing wire rope, after dummy pipe (11) passes in the another side guide channel (2), penetrate wire rope (5) in the anterior hole of reeving (101) of dummy pipe (11), wire rope (5) the other end connects winch (6);
When pull catheter and wire rope (5), after connecting dummy pipe (11) and winch (6) with wire rope (5), start winch (6) pulling dummy pipe (11), use simultaneously pressing device (4) to continue jacking rear tube (12), until does not end when just also heading into the stratum in the hole of reeving (101) at rear tube (12) rear portion;
When helping pull a cart pipe, wire rope (5) is penetrated respectively the hole of reeving (101) at rear tube (12) rear portion and the hole of reeving (201) at taper sheath (23) top, with this conduit is connected with sleeve pipe, start winch (6) pulling dummy pipe (11), use simultaneously pressing device (4) jacking rear sleeve (22), until anterior cannula (21) is ended when passing in the another side guide channel (2).
2. the trombone slide installation method of bypass pipeline as claimed in claim 1, it is characterized in that: during the conduit of top, pressing device (4) is selected backacter, break point the dead ahead of engineering pipeline to be installed or directly over.
CN 200910048811 2009-04-03 2009-04-03 Pull tube mounting method of passing pipeline Active CN101852312B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200910048811 CN101852312B (en) 2009-04-03 2009-04-03 Pull tube mounting method of passing pipeline

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200910048811 CN101852312B (en) 2009-04-03 2009-04-03 Pull tube mounting method of passing pipeline

Publications (2)

Publication Number Publication Date
CN101852312A CN101852312A (en) 2010-10-06
CN101852312B true CN101852312B (en) 2013-03-13

Family

ID=42803940

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200910048811 Active CN101852312B (en) 2009-04-03 2009-04-03 Pull tube mounting method of passing pipeline

Country Status (1)

Country Link
CN (1) CN101852312B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102767643B (en) * 2012-07-27 2014-01-15 河北二十冶工程技术有限公司 Sectional laying and mounting method for long-distance pipeline in culvert
CN105673935B (en) * 2016-03-24 2017-12-29 北京木石金河环保科技有限公司 Split slotting method underground utilities replacing options
CN106481881B (en) * 2016-12-22 2018-12-07 上海煤气第二管线工程有限公司 A kind of original pipe position no-dig technique splits the construction method that pipe repairs underground piping
CN113443569A (en) * 2021-05-27 2021-09-28 中国华冶科工集团有限公司 Method for installing pipeline in workshop

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1106512A (en) * 1994-10-10 1995-08-09 戴君 Digging-free underground pipeline layer
CN1197175A (en) * 1997-04-16 1998-10-28 东邦瓦斯株式会社 Replacing construction method and appts. for pipe
CN1280263A (en) * 1999-07-12 2001-01-17 四川石油管理局川东钻探公司 Construction method of drawing casing through drilled hole
CN1331395A (en) * 2000-06-29 2002-01-16 泰安市自来水公司 Technology for installing great-diameter prestressed reinforced concrete pipe

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1106512A (en) * 1994-10-10 1995-08-09 戴君 Digging-free underground pipeline layer
CN1197175A (en) * 1997-04-16 1998-10-28 东邦瓦斯株式会社 Replacing construction method and appts. for pipe
CN1280263A (en) * 1999-07-12 2001-01-17 四川石油管理局川东钻探公司 Construction method of drawing casing through drilled hole
CN1331395A (en) * 2000-06-29 2002-01-16 泰安市自来水公司 Technology for installing great-diameter prestressed reinforced concrete pipe

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
JP特开平11-323887A 1999.11.26

Also Published As

Publication number Publication date
CN101852312A (en) 2010-10-06

Similar Documents

Publication Publication Date Title
CN101852311B (en) Pipe-jacking installation method of bypass pipeline
RU2392390C2 (en) Trenchless pipe driving method
KR101069705B1 (en) Method for installing waterproofing steel plate in construction of undergound tunnel
RU2573086C2 (en) Device to install pipelines in soil
CN102518873B (en) Method for paving large-diameter pipeline in soft soil in jacking and pulling combined manner
CN101852312B (en) Pull tube mounting method of passing pipeline
JP4317843B2 (en) Construction method for underground structures
CN105673934A (en) Non-excavation cable laying and pipe arranging method
CN210263066U (en) But quick installation recovery type stake anchor combines excavation supporting construction
KR101925828B1 (en) Underground structure pressing system for reducing friction and construction method using the same
CN111911712A (en) Push pipe type trenchless pipeline construction method
KR20030045695A (en) Method for Digging a Tunnel
CN115573771A (en) Tunnel drainage method for laying drainage pipe based on ultra-long distance horizontal directional drilling
JP7357517B2 (en) Pipe construction method using propulsion method
RU2428544C2 (en) Built-up structure for pulling through pipelines in wells made by method of horizontal drilling in unstable earth
CN107060776A (en) The unit development machine combination of underground interface channel draws in construction method
CN102677724B (en) Mechanical steel sleeve installation device and mechanical steel sleeve installation method
CN202381844U (en) Tool pipe applicable to laying large-diameter pipelines in soft soil in jacking and pulling combination mode
EA017789B1 (en) Tool for drilling through loosely-packed materials
KR20060101734A (en) Method for constructing non-excavation directivity pipe
KR101067218B1 (en) The Construction Method of laying Pipe Underground for Ultra soft Ground
KR101440987B1 (en) System constructing underground structure by the pulling force of tension member and method constructing underground structure thereby
KR20100135525A (en) Gradual progress drive tunnel digging method and that component
RU2338111C1 (en) Method of trenchless pipe laying
CN214889296U (en) Damaged pipe jacking pullback device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant