CN101837609A - 高速铁路轨道板、预制构件的预埋套管精确定位装置 - Google Patents
高速铁路轨道板、预制构件的预埋套管精确定位装置 Download PDFInfo
- Publication number
- CN101837609A CN101837609A CN 201010160026 CN201010160026A CN101837609A CN 101837609 A CN101837609 A CN 101837609A CN 201010160026 CN201010160026 CN 201010160026 CN 201010160026 A CN201010160026 A CN 201010160026A CN 101837609 A CN101837609 A CN 101837609A
- Authority
- CN
- China
- Prior art keywords
- movable sleeve
- buried conduit
- steel ball
- spring
- fixed cover
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Manufacturing Of Tubular Articles Or Embedded Moulded Articles (AREA)
Abstract
本发明涉及一种高速铁路轨道板、预制构件的预埋导管精确定位,快速自动分离装置。该装置包括活动套(3),固定套(5),弹簧张紧(6)和呈螺旋状的钢珠(4)四种部件。其特征是:钢珠按预埋导管的内螺纹尺寸呈活动状态镶在活动套的侧孔内,活动套与弹簧用一构件联接,弹簧置于固定套内孔中,活动套套在固定套上部短圆柱外而成的一种精确定位装置;该装置的固定套下部用螺母紧固在钢模的预制孔内,以保证各预埋导管之间的尺寸偏差。在混凝土轨道板脱模时直接利用起吊外力克服弹簧张力而达到快速自动分离。本发明可适用于各种型号、各种规格的高速铁路混凝土轨道板、预制构件的预埋导管的精确定位和快速自动分离。
Description
一.所属技术领域
本发明涉及一种高速铁路混凝土轨道板、预制构件预制时预埋套管能精确定位,脱模时预埋套管与定位器能快速自动分离的装置。
二.背景技术
预埋在混凝土轨道板中用于紧固钢轨的预埋导管,每块混凝土轨道板上布有4排,每排6~10件(数量由板型确定)。
预埋导管在混凝土轨道板预制时其安装定位精度要求高,且在轨道板预制达到一定强度后需要脱模时又必须使定位装置和预埋导管可以分离,以方便脱模。
此种装置目前有二类。第一类是按定位方法分,有二种:一种用预埋套管内螺纹定位;另一种用弹力夹持预埋导管下部内孔定位。第二类是按分离方法分,也有二种:一种是单个装置同轨道板脱模时一起拔出,逐个从预埋导管中拧出,再重新安装到钢模上;另一种是轨道板脱模前使用一种机构把该装置与预埋导管先分离,以便轨道板脱模。
上述装置存在结构复杂,安装不便,操作麻烦,维修困难,特别是第一类第二种定位方法存在难以保证预埋导管定位准确的不足。
三.发明内容
为了克服现有定位装置的上述不足,本发明提供一种精确定位,快速自动分离的装置。
本发明解决其技术问题所采用的技术方案是:在活动套周向按预埋导管内螺纹螺距均布三颗定位用钢珠,在下部固定套内设置一压缩(或拉伸)弹簧,用一构件连接活动套、弹簧和固定套,固定套下部固定在钢模的预制孔内。预埋导管安装定位时,活动套在弹簧的拉(或压)力作用下紧贴固定套上部短圆柱,三颗钢珠在固定套上部短圆柱挤动下成螺旋线状高出活动套表面,起到固定预埋导管的作用,确保在轨道板预制时浇捣和振实混凝土过程中预埋导管定位精确。当需要把已制好的轨道板从钢模中脱离时,只需往上平移轨道板,利用钢珠与预埋导管内壁的接触力压缩(或拉伸)弹簧,此时活动套上移,当活动套上的钢珠均超出固定套上部短圆柱顶部时,钢珠被预埋导管的内壁迫使内缩,当钢珠齐平活动套外圆时,预埋导管与定位装置自动分离,使轨道板方便脱模。
本发明的有益效果是:不需要其它附加装置,即可达到精确定位和自动分离的效果,特别是分离时与脱模起吊同步完成,结构简单,操作方便。
四.附图说明
下面结合附图对本发明进一步说明:
附图1是预埋导管精确定位装置定位时工作示意图;
附图2是预埋导管精确定位装置脱模时工作示意图;
图中:(1).混凝土轨道板;(2).预埋导管;(3).活动套;(4).钢珠;(5).固定套;(6).弹簧;(7).钢模;(8).螺母。
在钢模(7)上预制混凝土轨道板(1)时,预埋导管(2)需按技术要求定位在钢模(7)上,预埋导管(2)内孔制有内螺纹。在图中,钢珠(4)的三粒钢珠按预埋导管(2)的内螺纹尺寸呈活动状态镶在活动套(3)的三个周向孔内,活动套(3)和弹簧(6)用一构件联接,弹簧(6)放置在固定套(5)的内孔中,在弹簧(6)的作用下,使活动套(3)始终套在固定套(5)的上部短圆柱上。由于固定套(5)的上部短圆柱对钢珠(4)的挤动作用,便3个呈螺旋状的钢珠高出活动套(3)表面约1.5mm,起到牢固固定预埋导管的作用。固定套(5)下部用螺母(8)紧固在钢模的预制孔内,以保证附图中的L尺寸偏差。当需要把已制好的轨道板从钢模中脱离时,只需往上平移轨道板,利用预埋导管内螺纹与三颗钢珠(4)的接触力压缩弹簧,活动套(3)上移,当三颗钢珠均超出固定套(5)上部短圆柱顶端,钢珠(4)被预埋导管的内壁迫使内缩,此时钢珠齐平活动套(3)外圆,预埋导管与定位装置自动分离,使轨道板方便脱模。当预埋导管脱离该装置后,活动套(3)在弹簧拉力作用下重新回到原位,恢复到定位的工作位置。
Claims (3)
1.一种高速铁路轨道板、预制构件的预埋导管精确定位装置,在固定套内孔中,用一构件把弹簧与套在固定套上部短圆柱外的活动套连接,活动套周向呈螺旋状孔内均布钢珠,其特征是:在弹簧的拉(或压)力作用下,利用活动套上凸起的钢珠固定预埋导管,当需要脱离时,起吊混凝土轨道板时预埋导管带动活动套上移一定高度,活动套上的钢珠内缩而平齐活动套外圆。
2.根椐权利要求1所述的高速铁路轨道板、预制构件的预埋导管精确定位装置,其特征是:预埋导管(2)安装定位时,活动套(3)在弹簧(6)的拉(或压)力作用下紧贴固定套(5)上部短圆柱,钢珠(4)在固定套上部短圆柱挤动下成螺旋线状高出活动套表面,预埋导管顺钢珠螺旋线往下拧紧,以固定预埋导管,固定套下部用螺母(8)紧固在钢模(7)的预制孔内。
3.根椐权利要求1所述的高速铁路轨道板、预制构件的预埋导管精确定位装置,其特征是:当需要把已制好的轨道板(1)从钢模(7)中脱离时,只需往上吊起轨道板,利用钢珠(4)与预埋导管(2)内壁的接触力压缩(或拉伸)弹簧(6),使活动套(3)上移,当活动套上的钢珠均超出固定套上部短圆柱顶部时,钢珠被预埋导管的内壁迫使内缩,此时预埋导管与定位装置自动快速分离。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201010160026 CN101837609A (zh) | 2010-04-29 | 2010-04-29 | 高速铁路轨道板、预制构件的预埋套管精确定位装置 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201010160026 CN101837609A (zh) | 2010-04-29 | 2010-04-29 | 高速铁路轨道板、预制构件的预埋套管精确定位装置 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN101837609A true CN101837609A (zh) | 2010-09-22 |
Family
ID=42741393
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201010160026 Pending CN101837609A (zh) | 2010-04-29 | 2010-04-29 | 高速铁路轨道板、预制构件的预埋套管精确定位装置 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101837609A (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105880529A (zh) * | 2016-06-18 | 2016-08-24 | 无锡市翱宇特新科技发展有限公司 | 一种模具预埋套管的固定装置 |
CN112025934A (zh) * | 2020-08-28 | 2020-12-04 | 上海城建预制构件有限公司 | 一种用于预制构件中扣件埋件的固定装置及其应用方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP1380687A1 (de) * | 2002-07-09 | 2004-01-14 | Pfleiderer Infrastrukturtechnik GmbH & Co. KG | Schwelle mit Dübelstein und Herstellungsverfahren einer festen Fahrbahn |
CN2908107Y (zh) * | 2005-05-17 | 2007-06-06 | 杨丽华 | 预埋套管定位装置 |
CN100421895C (zh) * | 2007-07-17 | 2008-10-01 | 中铁一局集团有限公司 | 轨枕预埋套管定位装置及定位与脱模方法 |
CN201140446Y (zh) * | 2007-12-13 | 2008-10-29 | 中铁二十三局集团有限公司 | 易脱模式套管定位装置 |
CN201346800Y (zh) * | 2008-12-24 | 2009-11-18 | 葫芦岛首钢东华机械有限公司 | 无砟轨道轨道板膜具套管固定体 |
-
2010
- 2010-04-29 CN CN 201010160026 patent/CN101837609A/zh active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP1380687A1 (de) * | 2002-07-09 | 2004-01-14 | Pfleiderer Infrastrukturtechnik GmbH & Co. KG | Schwelle mit Dübelstein und Herstellungsverfahren einer festen Fahrbahn |
CN2908107Y (zh) * | 2005-05-17 | 2007-06-06 | 杨丽华 | 预埋套管定位装置 |
CN100421895C (zh) * | 2007-07-17 | 2008-10-01 | 中铁一局集团有限公司 | 轨枕预埋套管定位装置及定位与脱模方法 |
CN201140446Y (zh) * | 2007-12-13 | 2008-10-29 | 中铁二十三局集团有限公司 | 易脱模式套管定位装置 |
CN201346800Y (zh) * | 2008-12-24 | 2009-11-18 | 葫芦岛首钢东华机械有限公司 | 无砟轨道轨道板膜具套管固定体 |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105880529A (zh) * | 2016-06-18 | 2016-08-24 | 无锡市翱宇特新科技发展有限公司 | 一种模具预埋套管的固定装置 |
CN112025934A (zh) * | 2020-08-28 | 2020-12-04 | 上海城建预制构件有限公司 | 一种用于预制构件中扣件埋件的固定装置及其应用方法 |
CN112025934B (zh) * | 2020-08-28 | 2021-07-13 | 上海城建预制构件有限公司 | 一种用于预制构件中扣件埋件的固定装置及其应用方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201865054U (zh) | 高桥墩用液压爬模装置 | |
CN104552576B (zh) | 卧式侧翻可调预制楼梯模具 | |
CN101837609A (zh) | 高速铁路轨道板、预制构件的预埋套管精确定位装置 | |
CN112659345A (zh) | 一种混凝土空心预制构件自动脱模装置 | |
CN2863311Y (zh) | 铝活塞单模铸造机 | |
CN201268953Y (zh) | 单面支模装置 | |
CN201881475U (zh) | 无砟轨道板螺纹套管预埋件定位轴 | |
CN211806899U (zh) | 一种建筑混凝土预制模具用脱模装置 | |
CN114871796A (zh) | 智能化模具加工设备 | |
CN202039257U (zh) | 预应力轨道板强制脱模装置 | |
CN201357482Y (zh) | 无砟轨道板模具端侧板脱模结构 | |
CN201140429Y (zh) | 一种阳极炭块成型机的模套装置 | |
CN207250316U (zh) | 变压器浇注线圈脱模装置 | |
CN202292996U (zh) | 一种机器制作组合空腔构件用模具 | |
CN201511127U (zh) | 一种双工位式浇注结构 | |
CN201236486Y (zh) | 杠杆式脱模机构 | |
CN205343714U (zh) | 减震链过线圈成形模板固定结构 | |
CN203658118U (zh) | 混凝土试件现场养护装置 | |
CN220517101U (zh) | 一种拼装式隧道模型试验衬砌制作装置 | |
CN221271512U (zh) | 一种预制箱梁的支撑结构 | |
CN209156954U (zh) | 用于模具的托起装置和模具 | |
CN108385550A (zh) | 一种涵洞墙体建筑用装置 | |
CN215038690U (zh) | 一种低噪音的小预制构件震动脱模机构 | |
CN221626839U (zh) | 一种自动化辅助箱梁侧模安拆设备 | |
CN201816134U (zh) | 一种道岔板模具围板固定装置 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20100922 |