CN101811553B - Preparation and on-board installation process of bridge of cutter suction dredger - Google Patents

Preparation and on-board installation process of bridge of cutter suction dredger Download PDF

Info

Publication number
CN101811553B
CN101811553B CN2010101229490A CN201010122949A CN101811553B CN 101811553 B CN101811553 B CN 101811553B CN 2010101229490 A CN2010101229490 A CN 2010101229490A CN 201010122949 A CN201010122949 A CN 201010122949A CN 101811553 B CN101811553 B CN 101811553B
Authority
CN
China
Prior art keywords
welding
crane span
segmentation
line
span structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2010101229490A
Other languages
Chinese (zh)
Other versions
CN101811553A (en
Inventor
刘鹏鑫
刘华
姚祥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nantong Gangzha Shipbuilding Co Ltd
Original Assignee
Nantong Gangzha Shipbuilding Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nantong Gangzha Shipbuilding Co Ltd filed Critical Nantong Gangzha Shipbuilding Co Ltd
Priority to CN2010101229490A priority Critical patent/CN101811553B/en
Publication of CN101811553A publication Critical patent/CN101811553A/en
Application granted granted Critical
Publication of CN101811553B publication Critical patent/CN101811553B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention discloses a preparation and on-board installation process of crane span of cutter suction dredger. The process comprises the following steps: preparing the jig of a crane span, performing sectionalized assembly of the crane span, performing wire-drawing to the trunnion of the crane span, performing wire-drawing to the trunnion of a hull, closing shipways, fixing the crane span, installing bolts, etc. The process of the invention has the advantages of convenient construction and good construction effect; and the installation time of the crane span is fully reduced, and the total cycle time for the preparation of ships is shortened.

Description

Mounting process on the making of cutter suction dredger crane span structure, the ship
Technical field:
The present invention relates to mounting process on a kind of cutter suction dredger crane span structure making, the ship.
Background technology:
4500m 3Cutter suction dredger crane span structure length is long, crane span structure length overall: 45.755m, highly: 9.052m, width: 6.60m, mounting process is long in time limit on its making, the ship, difficulty is big.
Summary of the invention:
The object of the present invention is to provide a kind of easy construction, mounting process on the cutter suction dredger crane span structure making that construction effect is good, the ship.
Technical solution of the present invention is:
Mounting process on a kind of cutter suction dredger crane span structure making, the ship is characterized in that: comprise the following steps:
(1) the crane span structure moulding bed is made: according to crane span structure bottom line style, adopt the manufacturing of identity moulding bed, the moulding bed offset provides accurate table of offsets or rising data value by the numerical control setting-out; The segmentation that molded lines is changed greatly provides loose tool by setting-out, submits construction after the Numerical control cutting to;
Moulding bed adopts the laser transit line, marks crane span structure center line, crane span structure wide line, big jointing line, middle rib bit line and horizontal check line, and makes the embossing seal mark;
Moulding bed completes, and after the acceptance(check) of submission quality testing department, can carry out the line of segmentation bed board and structure, and the precision strictness that moulding bed is made is controlled;
(2) crane span structure sectional making:
Crane span structure is carried out segmentation: crane span structure is divided into 7 three dimensional units, wherein is divided into five segmentations, segmentation about two segmentations of bridge trunnion one side respectively are divided into again along crane span structure length;
During sectional construction, segmentation weight should be controlled at below the 100T; Bed board must with the moulding bed fixation; The welding compensation rate vertically places 1mm as welding shrinkage-compensating value for laterally placing 0.5mm between each spacing of longitudinals between each strong component; All floors, stringers, the weldering of T-shape combination dress finish, and need after the firer proofreaies and correct, to go up segmentation and install; Must open big chamfered transition when the thin butt joint of thickness of slab, thickness difference>=4mm, its inclined-plane length is that 4 times thickness of slab is poor; The big seam two ends of segmentation stays 300mm to postpone welding, by welding in the lump with annulus behind the building berth segment folding; All dull and stereotyped butt joints all adopt arc to weld automatically, and the above butt joint of>=12mm is all opened the single or double groove, and after one side was shaped, another side must weld behind the back chipping; The plate of the big seam of segmentation docks with plate and section bar all opens single face CO 2Bevel for welding; The then two-sided bevel of hand welding butt joint, the whole bag of tricks welding all require the full impregnated weldering of weld seam; After finishing, the segmentation assembling should conscientiously check its integrality according to drawing requirement;
Conscientiously measure major dimension, horizontal error value after the segmentation completion, and perform record, submit data to berth combination; The necessary bevel of section bar butt joint, another side carbon digs the back chipping back welding, guarantees complete penetraction and fusion in welding; The segmentation final lengths should require to mark big seam according to accuracy standard and cut off surplus; Must check its integrality according to drawing after the segmentation completion, all something that gives the game aways are answered repair welding, are polished;
(3) bridge trunnion backguy:
Should check before the gudgeon line that bridge trunnion belongs to the integrality of the assembly project of segmentation, simultaneously to each segmentation except that with the gudgeon connecting portion all welding engineerings should all complete;
Measure the later final deviate of bridge trunnion place segmentation center line welding, obtain final crane span structure center line;
The steel wire of diameter d=0.8mm, the theoretical weight q=3.924g/m of unit of steel wire are adopted in backguy.The weight w=60kg of lift heavy; On the crane span structure in the perforate center weld band steel in advance, as axle center marking;
Find out size positions in the distance of bridge trunnion place segmentation center line and the interior collar extension of gudgeon; Mark upright position, rib position, gudgeon place line simultaneously; The bridge trunnion height has drawn steel wire with the ocean towards making the marking with the above position line respectively apart from underwater dredge pump motor platform 1800mm;
Mark crane span structure outer wall φ 1680mm respectively with the steel wire axle center line, inwall φ 1280mm circular arc line is installed line of cut as gudgeon, all cuts outward by line during cutting, must finally confirm line of cut based on diameter in kind before the cutting;
The bridge trunnion lifting is filled in, and the gudgeon instrument that puts in place adopts cucurbit or jack slowly to fill in and puts in place; After bridge trunnion was filled in, center line was adjusted at each three of the dress weldering of each face and regulates bolt, and as the usefulness of center line adjusting, left and right sides verticality is adjusted at each four of the dress weldering of each face and regulates bolt, as the usefulness of left and right sides verticality adjustment;
Utilize each to regulate bolt and transfer to required precision, carry out the spot welding location, check and accept, must each to be with the fixation of six blocks of horse plates in the interior outside of gudgeon in the time of examination, the stress shrinkage strain after guaranteeing to weld is controlled within the margin of tolerance; CO is adopted in welding 2The symmetry welding up and down of gas shielded arc welding, little electric current; Welding finishes, treat that it cools off fully after, surveying record axle center completion amount;
(4) hull gudgeon backguy:
Should check before the main hull line that the hull gudgeon belongs to the integrality of the assembly project of segmentation, simultaneously in the segmentation except that with the gudgeon connecting portion all welding engineerings should all complete;
Measure the later final deviate of segmentation center line welding, obtain final segmentation center line;
The steel wire of diameter d=0.8mm, the theoretical weight q=3.924g/m of unit of steel wire are adopted in backguy.The weight w=60kg of lift heavy;
Mark hull gudgeon place rib position upright position line in the segmentation and apart from the height and position line of baseline BL4600mm, and respectively the above position line has been drawn steel wire with the ocean towards making the marking;
Mark 3500mm in the distance respectively with the steel wire axle center line; 4200mm longitudinal wall φ 1408mm circular arc line in interior longitudinal wall φ 1678mm and the distance; As gudgeon line of cut is installed, is all cut outward during cutting, must finally confirm line of cut based on diameter in kind before the cutting by line;
The lifting of hull gudgeon is filled in, and the gudgeon instrument that puts in place adopts cucurbit or jack slowly to fill in and puts in place,
After the hull gudgeon was filled in, center line was adjusted at each three of the dress weldering of each face and regulates bolt, and as the usefulness of center line adjusting, left and right sides verticality is adjusted at each four of the dress weldering of each face and regulates bolt, as the usefulness of left and right sides verticality adjustment;
Utilize each to regulate bolt and transfer to required precision respectively, carry out the spot welding location, check and accept, must each to be with the fixation of six blocks of horse plates in the interior outside of gudgeon in the time of examination, the stress shrinkage strain after guaranteeing to weld is controlled within the margin of tolerance;
CO is adopted in welding 2The symmetry welding up and down of gas shielded arc welding, little electric current; Welding finishes, treat that it cools off fully after, surveying record axle center completion amount;
(5) berth combination:
Mark rib bit line before and after hull center line, the big wiring of segmentation, the big seam in building berth fixation position according to boats and ships, the altitude datum line marks respectively on the hull baseline mark post, and the stamp mark of number going abroad;
Be the gap size between control crane span structure and the main hull; Close up the segmentation of crane span structure afterbody earlier; Adopt laser that the crane span structure center line is harmonized and coincide consistently with building berth/hull center line, it is firm to take big horse plate to fix between crane span structure and the hull, then use with quadrat method forward one by one segmentation carry out building berth and locate;
Segmentation building berth when location, should be according to slope of building berth, promptly the hull bottom baseline is consistent therewith, confirm the hull bottom height after, guarantee parallelism between them, cenlerline of berth and hull bottom center line match, four jiaos of horizontal adjusting of segmentation are accurately carried out split fix then;
The big seam rib of segmentation apart from all be controlled at ± 15mm between, must be noted that the length overall that guarantees boats and ships during last segment folding, finally confirm the cutting surplus of segmentation, make it the boats and ships length overall and be controlled among 1/1000 margin of tolerance;
Segments in a circular shape seam assembling and positioning all must be used the welding of Φ 3.2mm low-hydrogen electrode; Big seam adopts CO 2Weldering; All must offer groove by following requirement: deck, outside plate, longitudinal wall and inner bottom plating are opened 30 ° of non-structural planes and are stayed root 0~2mm gap 6~8mm groove; Base plate is opened 30 ° of structural planes and is stayed root 0~2mm gap 6~8mm groove, needs welding after polishing smooth after groove is offered; Necessary fixing apart from long horse plate rigidity reinforcement before the big seam assembling and positioning weldering with surpassing a retaining rib, could transfer electric welding;
(6) the crane span structure Fixed latches is installed:
Before Fixed latches is installed, should crane span structure, main hull structure welding completion be applied for checking and examination; Before Fixed latches is installed, should the location be closed up in the lifting of crane span structure leading portion and finish, close up the seam welding completion greatly and apply for checking and examination; The uniformity of inspection Fixed latches processing dimension and drawing, and whether the bevel for welding that the big chamfered transition groove of periphery is connected with structure is perfect;
On platform, be combined into one crane span structure Fixed latches and portal frame Fixed latches in advance; The assurance upper-lower position in 8mm gap overlaps between two latches; Make liner with the continuous firm position of two pinboards with the 8mm steel plate then, strengthen making it to fuse between the two and with fixed block temporarily; At two liftings of two Fixed latches upper end dress welderings eye plate;
According to crane span structure Fixed latches arrangement requirement to the perforate of ruling of crane span structure and portal frame structure, during line: must be noted that portal frame is different with the shape of two latch appearance and sizes of crane span structure;
After portal frame and the portal structure line, carry out cutting and opening holes again, bore size should add about 1.5mm with the Fixed latches periphery, leaves bevel for welding simultaneously;
The lateral partitions of crane span structure Fixed latches installed position is cut off,, treat again its setting-in to be put in place behind the pinboard location so that lifting puts in place smoothly;
With Fixed latches composite member hoisting and locating, confirming that under the situation that size is coincide, formally weld the side; Require before the weldering to be preheated to 150 ℃~200 ℃, postwelding is taked the insulation measure, and welding rod uses low-hydrogen electrode, and welding wire uses H08mn2siA;
At first guarantee the completion of crane span structure pinboard and portal structure welding, when the pinboard end opening docks horizontal joint with crane span structure and is welded with difficulty, can offer fabrication hole to the end opening of portal frame pinboard, ceramic substrate is posted, this is sewn on crane span structure inside and welds; All welding must be carried out symmetrical welding up and down;
The welding of portal frame Fixed latches: the every position that possibly weld completion that should be all over; To the position that can not weld between crane span structure and the portal frame; After treating that all engineerings of crane span structure all complete; Locating piece between original two Fixed latches is removed, be lowered to crane span structure then and can carry out welding operation construction state, again portal frame outside plate and pinboard butt joint are welded.
Easy construction of the present invention, construction effect is good; Fully compress the building berth set-up time, shortened the overall cycle of shipbuilding.
Below in conjunction with accompanying drawing and embodiment the present invention is described further.
Fig. 1 is crane span structure segmentation division figure.
Fig. 2 is that axle is state diagram.
Fig. 3 is the backguy state diagram.
Fig. 4 is a crane span structure outer wall view.
Fig. 5 is a longitudinal wall view in the crane span structure.
Fig. 6 is that hull gudgeon wire pulling rack making diagrammatic sketch is regulated in the center.
Fig. 7 is a longitudinal wall diagrammatic sketch in the main hull.
Fig. 8 is a main hull outside plate diagrammatic sketch.
Fig. 9 is that Fixed latches is installed diagrammatic sketch.
Bridge trunnion 1, bearing holder (housing, cover) 2, center regulating block 3, motor platform 4, vertical direction regulating block 5, crane span structure upper deck 6, crane span structure main deck 7, portal frame inner platform 8 etc. are arranged among the figure,
The specific embodiment:
Mounting process on a kind of cutter suction dredger crane span structure making, the ship comprises the following steps:
(1) the crane span structure moulding bed is made: according to crane span structure bottom line style, adopt the manufacturing of identity moulding bed, the moulding bed offset provides accurate table of offsets or rising data value by the numerical control setting-out; The segmentation that molded lines is changed greatly provides loose tool by setting-out, submits construction after the Numerical control cutting to;
Moulding bed adopts the laser transit line, marks crane span structure center line, crane span structure wide line, big jointing line, middle rib bit line and horizontal check line, and makes the embossing seal mark;
Moulding bed completes, and after the acceptance(check) of submission quality testing department, can carry out the line of segmentation bed board and structure, and the precision strictness that moulding bed is made is controlled;
(2) crane span structure sectional making:
Crane span structure is carried out segmentation: crane span structure is divided into 7 three dimensional units; Wherein be divided into five segmentations along crane span structure length, two segmentations of bridge trunnion one side respectively be divided into again segmentation up and down (promptly 7 be segmented on 101, on 101 times, 102,102 times, 103,104,105);
During sectional construction, segmentation weight should be controlled at below the 100T; Bed board must with the moulding bed fixation; The welding compensation rate vertically places 1mm as welding shrinkage-compensating value for laterally placing 0.5mm between each spacing of longitudinals between each strong component; All floors, stringers, the weldering of T-shape combination dress finish, and need after the firer proofreaies and correct, to go up segmentation and install; Must open big chamfered transition when the thin butt joint of thickness of slab, thickness difference>=4mm, its inclined-plane length is that 4 times thickness of slab is poor; The big seam two ends of segmentation stays 300mm to postpone welding, by welding in the lump with annulus behind the building berth segment folding; All dull and stereotyped butt joints all adopt arc to weld automatically, and the above butt joint of>=12mm is all opened the single or double groove, and after one side was shaped, another side must weld behind the back chipping; The plate of the big seam of segmentation docks with plate and section bar all opens single face CO 2Bevel for welding; The then two-sided bevel of hand welding butt joint, the whole bag of tricks welding all require the full impregnated weldering of weld seam; After finishing, the segmentation assembling should conscientiously check its integrality according to drawing requirement;
Conscientiously measure major dimension, horizontal error value after the segmentation completion, and perform record, submit data to berth combination; The necessary bevel of section bar butt joint, another side carbon digs the back chipping back welding, guarantees complete penetraction and fusion in welding; The segmentation final lengths should require to mark big seam according to accuracy standard and cut off surplus; Must check its integrality according to drawing after the segmentation completion, all something that gives the game aways are answered repair welding, are polished;
(3) bridge trunnion backguy:
Should check before the gudgeon line that bridge trunnion belongs to the integrality of the assembly project of segmentation, simultaneously to each segmentation except that with the gudgeon connecting portion all welding engineerings should all complete;
Measure the later final deviate of bridge trunnion place segmentation center line welding, obtain final crane span structure center line;
The steel wire of diameter d=0.8mm, the theoretical weight q=3.924g/m of unit of steel wire are adopted in backguy.The weight w=60kg of lift heavy; On the crane span structure in the perforate center weld band steel in advance, as axle center marking;
Find out size positions in the distance of bridge trunnion place segmentation center line and the interior collar extension of gudgeon; Mark upright position, rib position, gudgeon place line simultaneously; The bridge trunnion height has drawn steel wire with the ocean towards making the marking with the above position line respectively apart from underwater dredge pump motor platform 1800mm;
Mark crane span structure outer wall φ 1680mm respectively with the steel wire axle center line, inwall φ 1280mm circular arc line is installed line of cut as gudgeon, all cuts outward by line during cutting, must finally confirm line of cut based on diameter in kind before the cutting;
The bridge trunnion lifting is filled in, and the gudgeon instrument that puts in place adopts cucurbit or jack slowly to fill in and puts in place; After bridge trunnion was filled in, center line was adjusted at each three of the dress weldering of each face and regulates bolt, and as the usefulness of center line adjusting, left and right sides verticality is adjusted at each four of the dress weldering of each face and regulates bolt, as the usefulness of left and right sides verticality adjustment;
Utilize each to regulate bolt and transfer to required precision, carry out the spot welding location, check and accept, must each to be with the fixation of six blocks of horse plates in the interior outside of gudgeon in the time of examination, the stress shrinkage strain after guaranteeing to weld is controlled within the margin of tolerance; CO is adopted in welding 2The symmetry welding up and down of gas shielded arc welding, little electric current; Welding finishes, treat that it cools off fully after, surveying record axle center completion amount;
(4) hull gudgeon backguy:
Should check before the main hull line that the hull gudgeon belongs to the integrality of the assembly project of segmentation, simultaneously in the segmentation except that with the gudgeon connecting portion all welding engineerings should all complete;
Measure the later final deviate of segmentation center line welding, obtain final segmentation center line;
The steel wire of diameter d=0.8mm, the theoretical weight q=3.924g/m of unit of steel wire are adopted in backguy.The weight w=60kg of lift heavy;
Mark hull gudgeon place rib position upright position line in the segmentation and apart from the height and position line of baseline BL4600mm, and respectively the above position line has been drawn steel wire with the ocean towards making the marking;
Mark 3500mm in the distance respectively with the steel wire axle center line; 4200mm longitudinal wall φ 1408mm circular arc line in interior longitudinal wall φ 1678mm and the distance; As gudgeon line of cut is installed, is all cut outward during cutting, must finally confirm line of cut based on diameter in kind before the cutting by line;
The lifting of hull gudgeon is filled in, and the gudgeon instrument that puts in place adopts cucurbit or jack slowly to fill in and puts in place,
After the hull gudgeon was filled in, center line was adjusted at each three of the dress weldering of each face and regulates bolt, and as the usefulness of center line adjusting, left and right sides verticality is adjusted at each four of the dress weldering of each face and regulates bolt, as the usefulness of left and right sides verticality adjustment;
Utilize each to regulate bolt and transfer to required precision respectively, carry out the spot welding location, check and accept, must each to be with the fixation of six blocks of horse plates in the interior outside of gudgeon in the time of examination, the stress shrinkage strain after guaranteeing to weld is controlled within the margin of tolerance;
CO is adopted in welding 2The symmetry welding up and down of gas shielded arc welding, little electric current; Welding finishes, treat that it cools off fully after, surveying record axle center completion amount;
(5) berth combination:
Mark rib bit line before and after hull center line, the big wiring of segmentation, the big seam in building berth fixation position according to boats and ships, the altitude datum line marks respectively on the hull baseline mark post, and the stamp mark of number going abroad;
Be the gap size between control crane span structure and the main hull; Close up the segmentation of crane span structure afterbody earlier; Adopt laser that the crane span structure center line is harmonized and coincide consistently with building berth/hull center line, it is firm to take big horse plate to fix between crane span structure and the hull, then use with quadrat method forward one by one segmentation carry out building berth and locate;
Segmentation building berth when location, should be according to slope of building berth, promptly the hull bottom baseline is consistent therewith, confirm the hull bottom height after, guarantee parallelism between them, cenlerline of berth and hull bottom center line match, four jiaos of horizontal adjusting of segmentation are accurately carried out split fix then;
The big seam rib of segmentation apart from all be controlled at ± 15mm between, must be noted that the length overall that guarantees boats and ships during last segment folding, finally confirm the cutting surplus of segmentation, make it the boats and ships length overall and be controlled among 1/1000 margin of tolerance;
Segments in a circular shape seam assembling and positioning all must be used the welding of Φ 3.2mm low-hydrogen electrode; Big seam adopts CO 2Weldering; All must offer groove by following requirement: deck, outside plate, longitudinal wall and inner bottom plating are opened 30 ° of non-structural planes and are stayed root 0~2mm gap 6~8mm groove; Base plate is opened 30 ° of structural planes and is stayed root 0~2mm gap 6~8mm groove, needs welding after polishing smooth after groove is offered; Necessary fixing apart from long horse plate rigidity reinforcement before the big seam assembling and positioning weldering with surpassing a retaining rib, could transfer electric welding;
(6) the crane span structure Fixed latches is installed:
Before Fixed latches is installed, should crane span structure, main hull structure welding completion be applied for checking and examination; Before Fixed latches is installed, should the location be closed up in the lifting of crane span structure leading portion and finish, close up the seam welding completion greatly and apply for checking and examination; The uniformity of inspection Fixed latches processing dimension and drawing, and whether the bevel for welding that the big chamfered transition groove of periphery is connected with structure is perfect;
On platform, be combined into one crane span structure Fixed latches and portal frame Fixed latches in advance; The assurance upper-lower position in 8mm gap overlaps between two latches; Make liner with the continuous firm position of two pinboards with the 8mm steel plate then, strengthen making it to fuse between the two and with fixed block temporarily; At two liftings of two Fixed latches upper end dress welderings eye plate;
According to crane span structure Fixed latches arrangement requirement to the perforate of ruling of crane span structure and portal frame structure, during line: must be noted that portal frame is different with the shape of two latch appearance and sizes of crane span structure;
After portal frame and the portal structure line, carry out cutting and opening holes again, bore size should add about 1.5mm with the Fixed latches periphery, leaves bevel for welding simultaneously;
The lateral partitions of crane span structure Fixed latches installed position is cut off,, treat again its setting-in to be put in place behind the pinboard location so that lifting puts in place smoothly;
With Fixed latches composite member hoisting and locating, confirming that under the situation that size is coincide, formally weld the side; Require before the weldering to be preheated to 150 ℃~200 ℃, postwelding is taked the insulation measure, and welding rod uses low-hydrogen electrode, and welding wire uses H08mn2siA;
At first guarantee the completion of crane span structure pinboard and portal structure welding, when the pinboard end opening docks horizontal joint with crane span structure and is welded with difficulty, can offer fabrication hole to the end opening of portal frame pinboard, ceramic substrate is posted, this is sewn on crane span structure inside and welds; All welding must be carried out symmetrical welding up and down;
The welding of portal frame Fixed latches: the every position that possibly weld completion that should be all over; To the position that can not weld between crane span structure and the portal frame; After treating that all engineerings of crane span structure all complete; Locating piece between original two Fixed latches is removed, be lowered to crane span structure then and can carry out welding operation construction state, again portal frame outside plate and pinboard butt joint are welded.

Claims (1)

  1. A cutter suction dredger crane span structure make, mounting process on the ship, it is characterized in that: comprise the following steps:
    (1) the crane span structure moulding bed is made: according to crane span structure bottom line style, adopt the manufacturing of identity moulding bed, the moulding bed offset provides accurate table of offsets or rising data value by the numerical control setting-out; The segmentation that molded lines is changed greatly provides loose tool by setting-out, submits construction after the Numerical control cutting to;
    Moulding bed adopts the laser transit line, marks crane span structure center line, crane span structure wide line, big jointing line, middle rib bit line and horizontal check line, and makes the embossing seal mark;
    Moulding bed completes, and after the acceptance(check) of submission quality testing department, can carry out the line of segmentation bed board and structure, and the precision strictness that moulding bed is made is controlled;
    (2) crane span structure sectional making:
    Crane span structure is carried out segmentation: crane span structure is divided into 7 three dimensional units, wherein is divided into five segmentations, segmentation about two segmentations of bridge trunnion one side respectively are divided into again along crane span structure length;
    During sectional construction, segmentation weight should be controlled at below the 100T; Bed board must with the moulding bed fixation; The welding compensation rate vertically places 1mm as welding shrinkage-compensating value for laterally placing 0.5mm between each spacing of longitudinals between each strong component; All floors, stringers, the weldering of T-shape combination dress finish, and need after the firer proofreaies and correct, to go up segmentation and install; Must open big chamfered transition when the thin butt joint of thickness of slab, thickness difference>=4mm, its inclined-plane length is that 4 times thickness of slab is poor; The big seam two ends of segmentation stays 300mm to postpone welding, by welding in the lump with annulus behind the building berth segment folding; All dull and stereotyped butt joints all adopt arc to weld automatically, and the above butt joint of>=12mm is all opened the single or double groove, and after one side was shaped, another side must weld behind the back chipping; The plate of the big seam of segmentation docks with plate and section bar all opens single face CO 2Bevel for welding; The then two-sided bevel of hand welding butt joint, the whole bag of tricks welding all require the full impregnated weldering of weld seam; After finishing, the segmentation assembling should conscientiously check its integrality according to drawing requirement;
    Conscientiously measure major dimension, horizontal error value after the segmentation completion, and perform record, submit data to berth combination; The necessary bevel of section bar butt joint, another side carbon digs the back chipping back welding, guarantees complete penetraction and fusion in welding; The segmentation final lengths should require to mark big seam according to accuracy standard and cut off surplus; Must check its integrality according to drawing after the segmentation completion, all something that gives the game aways are answered repair welding, are polished;
    (3) bridge trunnion backguy:
    Should check before the gudgeon line that bridge trunnion belongs to the integrality of the assembly project of segmentation, simultaneously to each segmentation except that with the gudgeon connecting portion all welding engineerings should all complete;
    Measure the later final deviate of bridge trunnion place segmentation center line welding, obtain final crane span structure center line;
    The steel wire of diameter d=0.8mm, the theoretical weight q=3.924g/m of unit of steel wire are adopted in backguy.The weight w=60kg of lift heavy; On the crane span structure in the perforate center weld band steel in advance, as axle center marking;
    Find out size positions in the distance of bridge trunnion place segmentation center line and the interior collar extension of gudgeon; Mark upright position, rib position, gudgeon place line simultaneously; The bridge trunnion height has drawn steel wire with the ocean towards making the marking with the above position line respectively apart from underwater dredge pump motor platform 1800mm;
    Mark crane span structure outer wall φ 1680mm respectively with the steel wire axle center line, inwall φ 1280mm circular arc line is installed line of cut as gudgeon, all cuts outward by line during cutting, must finally confirm line of cut based on diameter in kind before the cutting;
    The bridge trunnion lifting is filled in, and the gudgeon instrument that puts in place adopts cucurbit or jack slowly to fill in and puts in place; After bridge trunnion was filled in, center line was adjusted at each three of the dress weldering of each face and regulates bolt, and as the usefulness of center line adjusting, left and right sides verticality is adjusted at each four of the dress weldering of each face and regulates bolt, as the usefulness of left and right sides verticality adjustment;
    Utilize each to regulate bolt and transfer to required precision, carry out the spot welding location, check and accept, must each to be with the fixation of six blocks of horse plates in the interior outside of gudgeon in the time of examination, the stress shrinkage strain after guaranteeing to weld is controlled within the margin of tolerance; CO is adopted in welding 2The symmetry welding up and down of gas shielded arc welding, little electric current; Welding finishes, treat that it cools off fully after, surveying record axle center completion amount;
    (4) hull gudgeon backguy:
    Should check before the main hull line that the hull gudgeon belongs to the integrality of the assembly project of segmentation, simultaneously in the segmentation except that with the gudgeon connecting portion all welding engineerings should all complete;
    Measure the later final deviate of segmentation center line welding, obtain final segmentation center line;
    The steel wire of diameter d=0.8mm, the theoretical weight q=3.924g/m of unit of steel wire are adopted in backguy.The weight w=60kg of lift heavy;
    Mark hull gudgeon place rib position upright position line in the segmentation and apart from the height and position line of baseline 4600mm, and respectively the above position line has been drawn steel wire with the ocean towards making the marking;
    Mark 3500mm in the distance respectively with the steel wire axle center line; 4200mm longitudinal wall φ 1408mm circular arc line in interior longitudinal wall φ 1678mm and the distance; As gudgeon line of cut is installed, is all cut outward during cutting, must finally confirm line of cut based on diameter in kind before the cutting by line;
    The lifting of hull gudgeon is filled in, and the gudgeon instrument that puts in place adopts cucurbit or jack slowly to fill in and puts in place,
    After the hull gudgeon was filled in, center line was adjusted at each three of the dress weldering of each face and regulates bolt, and as the usefulness of center line adjusting, left and right sides verticality is adjusted at each four of the dress weldering of each face and regulates bolt, as the usefulness of left and right sides verticality adjustment;
    Utilize each to regulate bolt and transfer to required precision respectively, carry out the spot welding location, check and accept, must each to be with the fixation of six blocks of horse plates in the interior outside of gudgeon in the time of examination, the stress shrinkage strain after guaranteeing to weld is controlled within the margin of tolerance;
    CO is adopted in welding 2The symmetry welding up and down of gas shielded arc welding, little electric current; Welding finishes, treat that it cools off fully after, surveying record axle center completion amount;
    (5) berth combination:
    Mark rib bit line before and after hull center line, the big jointing line of segmentation, the big seam in building berth fixation position according to boats and ships, the altitude datum line marks respectively on the hull baseline mark post, and the stamp mark of number going abroad;
    Be the gap size between control crane span structure and the main hull; Close up the segmentation of crane span structure afterbody earlier; Adopt laser that the crane span structure center line is harmonized and coincide consistently with building berth/hull center line, it is firm to take big horse plate to fix between crane span structure and the hull, then use with quadrat method forward one by one segmentation carry out building berth and locate;
    Segmentation building berth when location, should be according to slope of building berth, promptly the hull bottom baseline is consistent therewith, confirm the hull bottom height after, guarantee parallelism between them, cenlerline of berth and hull bottom center line match, four jiaos of horizontal adjusting of segmentation are accurately carried out split fix then;
    The big seam rib of segmentation apart from all be controlled at ± 15mm between, must be noted that the length overall that guarantees boats and ships during last segment folding, finally confirm the cutting surplus of segmentation, make it the boats and ships length overall and be controlled among 1/1000 margin of tolerance;
    Segments in a circular shape seam assembling and positioning all must be used the welding of Ф 3.2mm low-hydrogen electrode; Big seam adopts CO 2Weldering; All must offer groove by following requirement: deck, outside plate, longitudinal wall and inner bottom plating are opened 30 ° of non-structural planes and are stayed root 0~2mm gap 6~8mm groove; Base plate is opened 30 ° of structural planes and is stayed root 0~2mm gap 6~8mm groove, needs welding after polishing smooth after groove is offered; Necessary fixing apart from long horse plate rigidity reinforcement before the big seam assembling and positioning weldering with surpassing a retaining rib, could transfer electric welding;
    (6) the crane span structure Fixed latches is installed:
    Before Fixed latches is installed, should crane span structure, main hull structure welding completion be applied for checking and examination; Before Fixed latches is installed, should the location be closed up in the lifting of crane span structure leading portion and finish, close up the seam welding completion greatly and apply for checking and examination; The uniformity of inspection Fixed latches processing dimension and drawing, and whether the bevel for welding that the big chamfered transition groove of periphery is connected with structure is perfect;
    On platform, be combined into one crane span structure Fixed latches and portal frame Fixed latches in advance; The 8mm gap is arranged between two latches; The assurance upper-lower position overlaps, and makes liner with the continuous firm position of two pinboards with the 8mm steel plate then, strengthens making it to fuse between the two and with fixed block temporarily; At two liftings of two Fixed latches upper end dress welderings eye plate;
    According to crane span structure Fixed latches arrangement requirement to the perforate of ruling of crane span structure and portal frame structure, during line: must be noted that portal frame is different with the shape of two latch appearance and sizes of crane span structure;
    After portal frame and the portal structure line, carry out cutting and opening holes again, bore size should add about 1.5mm with the Fixed latches periphery, leaves bevel for welding simultaneously;
    The lateral partitions of crane span structure Fixed latches installed position is cut off,, treat again its setting-in to be put in place behind the pinboard location so that lifting puts in place smoothly;
    With Fixed latches composite member hoisting and locating, confirming that under the situation that size is coincide, formally weld the side; Require before the weldering to be preheated to 150 ℃~200 ℃, postwelding is taked the insulation measure, and welding rod uses low-hydrogen electrode, and welding wire uses H08mn2siA;
    At first guarantee the completion of crane span structure pinboard and portal structure welding, when the pinboard end opening docks horizontal joint with crane span structure and is welded with difficulty, can offer fabrication hole to the end opening of portal frame pinboard, ceramic substrate is posted, this is sewn on crane span structure inside and welds; All welding must be carried out symmetrical welding up and down;
    The welding of portal frame Fixed latches: the every position that possibly weld completion that should be all over; To the position that can not weld between crane span structure and the portal frame; After treating that all engineerings of crane span structure all complete; Locating piece between original two Fixed latches is removed, be lowered to crane span structure then and can carry out welding operation construction state, again portal frame outside plate and pinboard butt joint are welded.
CN2010101229490A 2010-03-05 2010-03-05 Preparation and on-board installation process of bridge of cutter suction dredger Expired - Fee Related CN101811553B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010101229490A CN101811553B (en) 2010-03-05 2010-03-05 Preparation and on-board installation process of bridge of cutter suction dredger

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010101229490A CN101811553B (en) 2010-03-05 2010-03-05 Preparation and on-board installation process of bridge of cutter suction dredger

Publications (2)

Publication Number Publication Date
CN101811553A CN101811553A (en) 2010-08-25
CN101811553B true CN101811553B (en) 2012-07-18

Family

ID=42618960

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010101229490A Expired - Fee Related CN101811553B (en) 2010-03-05 2010-03-05 Preparation and on-board installation process of bridge of cutter suction dredger

Country Status (1)

Country Link
CN (1) CN101811553B (en)

Families Citing this family (29)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102632344A (en) * 2011-03-29 2012-08-15 华泰(南通)船务有限公司 Welding deformation control process for ship superstructure
CN102910255A (en) * 2012-10-31 2013-02-06 南通港闸船舶制造有限公司 Berth combination method in ship construction
CN102922158A (en) * 2012-10-31 2013-02-13 南通港闸船舶制造有限公司 Special ship welding method
CN102922159B (en) * 2012-10-31 2014-04-23 南通港闸船舶制造有限公司 Special dredger welding method
CN103029808B (en) * 2012-11-01 2015-05-27 上海振华重工集团(南通)有限公司 Manufacturing method of lifting main structure of rubble leveling ship
CN103910036A (en) * 2014-04-15 2014-07-09 南通长航船舶配件有限公司 Construction lofting method for self-propelled trailing suction hopper dredger
CN103921897A (en) * 2014-04-15 2014-07-16 南通长航船舶配件有限公司 Shipway folding method for self-propelled trailing suction hopper dredger
CN103910028A (en) * 2014-04-15 2014-07-09 南通长航船舶配件有限公司 Segment dividing method for self-propelled drag suction dredger ship building
CN103910030A (en) * 2014-04-15 2014-07-09 南通长航船舶配件有限公司 Construction method for pump room area of self-propelled trailing suction hopper dredger
CN103910037A (en) * 2014-04-15 2014-07-09 南通长航船舶配件有限公司 Bow area construction method for self-propelled drag suction dredger ship
CN104084679A (en) * 2014-06-23 2014-10-08 南通港闸船舶制造有限公司 Manufacturing method for cutter suction dredger
CN104085502B (en) * 2014-06-23 2016-04-27 南通港闸船舶制造有限公司 In in ship building, segment section construction method
CN104085501A (en) * 2014-06-23 2014-10-08 南通港闸船舶制造有限公司 Segmental construction method for cutter suction dredger
CN104389871A (en) * 2014-09-29 2015-03-04 南通振华重型装备制造有限公司 Special flange for derrick upright posts and attaching method of special flange
CN104594421B (en) * 2014-12-29 2017-10-27 广州文冲船厂有限责任公司 A kind of installation method of cutter suction dredger reamer beam length axis hole twisted branch frame
CN109552554B (en) * 2018-10-29 2020-03-27 上海振华重工(集团)股份有限公司 Hull section construction method for self-propulsion cutter suction dredger
CN109552555B (en) * 2018-10-29 2020-01-14 上海振华重工(集团)股份有限公司 Segmentation division method for self-propulsion cutter suction dredger
CN109552557B (en) * 2018-10-29 2019-12-06 上海振华重工(集团)股份有限公司 Segmentation division method for self-propulsion cutter suction dredger
CN109231099B (en) * 2018-10-29 2023-07-25 上海振华重工(集团)股份有限公司 Tool piece for integral moving of cutter suction dredger bridge frame and moving method thereof
CN109552556B (en) * 2018-10-29 2020-03-27 上海振华重工(集团)股份有限公司 Hull section construction method for self-propulsion cutter suction dredger
CN109466693B (en) * 2018-10-31 2021-05-14 广船国际有限公司 Method for modifying cargo hold of ore carrier
CN109466694B (en) * 2018-10-31 2021-06-22 广船国际有限公司 Method for dividing steering zone of ship
CN110434559B (en) * 2019-08-14 2020-09-22 招商局重工(深圳)有限公司 Machining and mounting process for reamer bridge of cutter suction dredger
CN110524195B (en) * 2019-08-30 2021-04-23 上海振华重工启东海洋工程股份有限公司 Bridge trunnion machining process
CN110937079A (en) * 2019-10-24 2020-03-31 上海江南长兴造船有限责任公司 Double-layer bottom box position precision control method for large container ship
CN111717347B (en) * 2020-05-29 2022-05-27 招商局重工(深圳)有限公司 Track structure of large cutter suction dredger trolley and manufacturing and mounting process
CN112570859B (en) * 2020-12-08 2022-04-05 上海振华重工启东海洋工程股份有限公司 Sectional construction method for lower floating body
CN114215130B (en) * 2021-12-13 2023-03-28 上海振华重工启东海洋工程股份有限公司 Bridge integral assembly process
CN114148471B (en) * 2021-12-15 2023-04-28 上海振华重工启东海洋工程股份有限公司 Bridge frame transferring technology

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101173523A (en) * 2007-08-14 2008-05-07 上海远舟港湾建设有限公司 Self-propelled twisted harrow dredge boat and using method thereof
CN201082964Y (en) * 2008-02-15 2008-07-09 上海远舟港湾建设有限公司 Self-navigating type harrow-twisting dredger
CN101811245B (en) * 2010-03-05 2012-05-30 南通港闸船舶制造有限公司 Production and installation process of steel pile trolley track of cutter suction dredger
CN102220772B (en) * 2011-03-21 2013-06-19 广东精铟机械有限公司 Bridge pivot structure used for suction type dredging ship

Also Published As

Publication number Publication date
CN101811553A (en) 2010-08-25

Similar Documents

Publication Publication Date Title
CN101811553B (en) Preparation and on-board installation process of bridge of cutter suction dredger
CN102407921B (en) Mounting method for sectional inversely hung rudder arm
CN102416554B (en) Technology for making pile legs of wind power installation ship
CN102277825B (en) Steel truss bridge and method for fabricating same
CN102874379B (en) Manufacture method of offshore riprap leveling ship
CN101870335A (en) Sectional construction precision control method for cylindrical ultra-deep sea drilling platform
CN110466689B (en) Method for controlling mounting precision of stern door hinge
CN105539724A (en) Hull curved block manufacturing method
CN109648269B (en) Construction process of lifting leg pile of marine life platform
CN101811245B (en) Production and installation process of steel pile trolley track of cutter suction dredger
CN106627990A (en) Cargo hold segment corrugated wall and reinforcing plate centering installation and precision control method
CN110877674A (en) Positioning process of double rudder horn on subsection
CN110341878A (en) A kind of installation method of stern transom plate hinge
CN202099719U (en) Steel truss bridge
CN102874378A (en) Cabin basin fitting-out process
CN111645826A (en) Control method for integrated construction precision of container cabin opening circumference
CN103506846A (en) Method and device for milling steering oar base
CN113148058B (en) Process for installing and positioning double rudder sleeve and tail casting in stage of sectional construction
CN208584265U (en) A kind of marine shafting flange construction contraposition tooling
CN112550621A (en) Double-tail-fin segmented construction method for LNG ship
CN113428315A (en) Positioning and welding method for ship stern pushing equipment
CN111976916A (en) Full-rotation telescopic push mounting process for engineering ship
CN100333966C (en) Construction method of single point mooring float den
CN110254623B (en) Manufacturing method of submerged body segment
CN112339930A (en) Three-dimensional modeling and precision control method for ship stem steel casting

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120718

Termination date: 20130305