CN101798853B - Construction method of thin-wall box body hollow floor slab - Google Patents

Construction method of thin-wall box body hollow floor slab Download PDF

Info

Publication number
CN101798853B
CN101798853B CN2010101302231A CN201010130223A CN101798853B CN 101798853 B CN101798853 B CN 101798853B CN 2010101302231 A CN2010101302231 A CN 2010101302231A CN 201010130223 A CN201010130223 A CN 201010130223A CN 101798853 B CN101798853 B CN 101798853B
Authority
CN
China
Prior art keywords
casing
concrete
girt strip
box body
colligation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2010101302231A
Other languages
Chinese (zh)
Other versions
CN101798853A (en
Inventor
张进荣
陈正益
李明
张立清
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NANTONG HUARONG CONSTRUCTION GROUP CO Ltd
Original Assignee
NANTONG HUARONG CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NANTONG HUARONG CONSTRUCTION GROUP CO Ltd filed Critical NANTONG HUARONG CONSTRUCTION GROUP CO Ltd
Priority to CN2010101302231A priority Critical patent/CN101798853B/en
Publication of CN101798853A publication Critical patent/CN101798853A/en
Application granted granted Critical
Publication of CN101798853B publication Critical patent/CN101798853B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses a construction method of a thin-wall box body hollow floor slab, which comprises the steps of marking for positioning the position for placing a box body, reserving and pre-embedding various pipelines, installing the box body, binding top steel bars after box body installation, pouring concrete and the like. The invention has convenient construction, easy operation and easy quality control.

Description

Construction method of thin-wall box body hollow floor slab
Technical field:
The present invention relates to a kind of construction method of thin-wall box body hollow floor slab.
Background technology:
BDF thin-wall box body (box) or the application of light-wall pipe member in cast-in-situ hollow building roof can be saved the concrete consumption, alleviate dead load, reduce construction costs, reduce geological process; Realization large bay that also can be more convenient increases usable floor area, under the condition that guarantees the use clear height, can reduce the structure floor height, for the house that height restriction is arranged, can increase floor.Simultaneously, the cast-in-situ concrete hollow floor of embedding BDF thin-wall box body (box) member meets the requirement and the building industry policy of construction " energy and land saving type " building that country advocates, and has good economic benefit and social benefit.And existing job practices complexity, difficulty of construction is big, and construction quality is difficult to control.
Summary of the invention:
The object of the present invention is to provide a kind of easy construction, construction method of thin-wall box body hollow floor slab easy to operate, easy to control the quality.
Technical solution of the present invention is:
A kind of construction method of thin-wall box body hollow floor slab is characterized in that: comprise the following steps:
(1) according to drawing and designing requirement, alignment error is reduced in the position that casing is laid in the line location;
(2) reservation of various pipelines and steel pipe buried in advance, pipeline passes through in close girt strip;
(3) casing is installed: after bottom layer of the reinforcing steel and close girt strip colligation are finished, determine to be provided with anti-floating point distance and casing installation according to thickness of slab, specific practice is that the Electric portable drill with Φ 4 drill bits bores template, tying down girt strip bottom steel bar stress string with the 14# galvanized wire crosses on the template place supporting steel pipe that is locked in bed die tightly of electric drill boring, the anti-floating dot spacing is 1.0m-1.5m, casing is placed in the rib grid of band base plate reinforcing bar or band gauze wire cloth, around casing, should keeps the reinforcement cover distance with little close girt strip reinforcing bar; Or respectively place two small cushion blocks that 10-15mm is thick in four sides of casing, to guarantee the protective layer thickness between casing and the little close girt strip;
(4) beginning top layer reinforcing bar binding after the casing installation should be avoided the constructor directly to trample casing as far as possible or construction machinery, facility, material code are placed on the casing during colligation, in order to avoid the casing breakage; The colligation of top layer cover muscle must be firm with little close girt strip colligation, and cover muscle and casing face 10-15mm cushion block directly contact the cover muscle when preventing the casing come-up;
(5) carry out building of concrete: it is moistening preferably casing to be watered before the cast, when building concrete, assigns special messenger's nurse, avoids vibrating spear directly to contact casing, prevents that casing from destroying, and the vibrating spear elder generation emphasis casing periphery that vibrates guarantees that the bottom half concrete is closely knit;
(6) concrete adopts successively alternately to build and finishes, and directly vibrates the girt strip concrete to bed die with vibrating head behind a small amount of concrete of injection earlier, allows the concrete mortar infiltrate casing, and the required concrete that and then reinjects behind the bottom vibration compacting vibrates simultaneously; Slump is not less than 160mm;
(7) after concrete was built and finished, according to taking the normal maintenance of corresponding maintenance measure season, the intensity of concrete reached form removal after the design strength.
Easy construction of the present invention, easy to operate, easy to control the quality.
The invention will be further described below in conjunction with embodiment.
The specific embodiment:
A kind of construction method of thin-wall box body hollow floor slab comprises the following steps:
(1) according to drawing and designing requirement, alignment error is reduced in the position that casing is laid in the line location;
(2) reservation of various pipelines and steel pipe buried in advance, pipeline passes through in close girt strip;
(3) casing is installed: after bottom layer of the reinforcing steel and close girt strip colligation are finished, determine to be provided with anti-floating point distance and casing installation according to thickness of slab, specific practice is that the Electric portable drill with Φ 4 drill bits bores template, tying down girt strip bottom steel bar stress string with the 14# galvanized wire crosses on the template place supporting steel pipe that is locked in bed die tightly of electric drill boring, the anti-floating dot spacing is 1.0m-1.5m, casing is placed in the rib grid of band base plate reinforcing bar or band gauze wire cloth, around casing, should keeps the reinforcement cover distance with little close girt strip reinforcing bar; Or respectively place two small cushion blocks that 10-15mm is thick in four sides of casing, to guarantee the protective layer thickness between casing and the little close girt strip;
(4) beginning top layer reinforcing bar binding after the casing installation should be avoided the constructor directly to trample casing as far as possible or construction machinery, facility, material code are placed on the casing during colligation, in order to avoid the casing breakage; The colligation of top layer cover muscle must be firm with little close girt strip colligation, and cover muscle and casing face 10-15mm cushion block directly contact the cover muscle when preventing the casing come-up;
(5) carry out building of concrete: it is moistening preferably casing to be watered before the cast, when building concrete, assigns special messenger's nurse, avoids vibrating spear directly to contact casing, prevents that casing from destroying, and the vibrating spear elder generation emphasis casing periphery that vibrates guarantees that the bottom half concrete is closely knit;
(6) concrete adopts successively alternately to build and finishes, and directly vibrates the girt strip concrete to bed die with vibrating head behind a small amount of concrete of injection earlier, allows the concrete mortar infiltrate casing, and the required concrete that and then reinjects behind the bottom vibration compacting vibrates simultaneously; Slump is not less than 160mm;
(7) after concrete was built and finished, according to taking the normal maintenance of corresponding maintenance measure season, the intensity of concrete reached form removal after the design strength.

Claims (1)

1. a construction method of thin-wall box body hollow floor slab is characterized in that: comprise the following steps:
(1) according to drawing and designing requirement, alignment error is reduced in the position that casing is laid in the line location;
(2) reservation of various pipelines and steel pipe buried in advance, pipeline passes through in close girt strip;
(3) casing is installed: after bottom layer of the reinforcing steel and close girt strip colligation are finished, determine to be provided with anti-floating point distance and casing installation according to thickness of slab, specific practice is that the Electric portable drill with Φ 4 drill bits bores template, tying down girt strip bottom steel bar stress string with the 14# galvanized wire crosses on the template place supporting steel pipe that is locked in bed die tightly of electric drill boring, the anti-floating dot spacing is 1.0m-1.5m, casing is placed in the rib grid of band base plate reinforcing bar or band gauze wire cloth, should keeps the reinforcement cover distance with little close girt strip reinforcing bar around the casing;
(4) beginning top layer reinforcing bar binding after the casing installation should be avoided the constructor directly to trample casing or construction machinery, facility, material code are placed on the casing during colligation, in order to avoid the casing breakage; The colligation of top layer cover muscle must be firm with little close girt strip colligation, and cover muscle and casing face 10-15mm cushion block directly contact the cover muscle when preventing the casing come-up;
(5) carry out building of concrete: it is moistening before the cast casing to be watered, and when building concrete, assigns special messenger's nurse, avoids vibrating spear directly to contact casing, prevents that casing from destroying, and the first emphasis of the vibrating spear casing periphery that vibrates guarantees that the bottom half concrete is closely knit;
(6) concrete adopts successively alternately to build and finishes, and directly vibrates the girt strip concrete to bed die with vibrating head behind a small amount of concrete of injection earlier, allows the concrete mortar infiltrate casing, and the required concrete that and then reinjects behind the bottom vibration compacting vibrates simultaneously; Slump is not less than 160mm;
(7) after concrete was built and finished, according to taking the normal maintenance of corresponding maintenance measure season, the intensity of concrete reached form removal after the design strength.
CN2010101302231A 2010-03-16 2010-03-16 Construction method of thin-wall box body hollow floor slab Expired - Fee Related CN101798853B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010101302231A CN101798853B (en) 2010-03-16 2010-03-16 Construction method of thin-wall box body hollow floor slab

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010101302231A CN101798853B (en) 2010-03-16 2010-03-16 Construction method of thin-wall box body hollow floor slab

Publications (2)

Publication Number Publication Date
CN101798853A CN101798853A (en) 2010-08-11
CN101798853B true CN101798853B (en) 2011-09-21

Family

ID=42594680

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010101302231A Expired - Fee Related CN101798853B (en) 2010-03-16 2010-03-16 Construction method of thin-wall box body hollow floor slab

Country Status (1)

Country Link
CN (1) CN101798853B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103046678A (en) * 2012-12-27 2013-04-17 山西太行建设开发有限公司 Method for constructing BDF (building distribution frame) hollow floorslab
CN106013569A (en) * 2016-06-12 2016-10-12 中国十七冶集团有限公司 Method for preventing flotation of light solid composite core formwork of composite floor system
CN109930726A (en) * 2019-04-10 2019-06-25 中建七局第二建筑有限公司 A kind of concreting process applied in hollow floor construction
CN110258883A (en) * 2019-06-24 2019-09-20 南通大学 A kind of construction method of hollow floor BDF steel mesh film filling cabinet
CN113309282A (en) * 2021-06-11 2021-08-27 中电建十一局工程有限公司 Hollow floor slab construction process

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1789642A (en) * 2004-12-14 2006-06-21 李克翔 Spliced concrete superposed member box and method for processing net girder building cover
CN100368642C (en) * 2004-12-31 2008-02-13 王本淼 Hollow floor slab with small dense ribs and its production process
KR100806820B1 (en) * 2006-12-19 2008-02-22 삼성중공업 주식회사 Two-way hollow core slab and construction method thereof
CN100547193C (en) * 2007-07-20 2009-10-07 湖南省建筑工程集团总公司 Construction method for thin wall housing body mould shell cast-in-place concrete building roof

Also Published As

Publication number Publication date
CN101798853A (en) 2010-08-11

Similar Documents

Publication Publication Date Title
CN101798853B (en) Construction method of thin-wall box body hollow floor slab
CN206070562U (en) Subassembly formula underground structure
CN102182313A (en) Anti-floating construction method of cast-in-situ concrete girderless hollow floor slab
CN103806656A (en) Construction method of cast-in-place concrete flat slab built-in thin-wall hollow box body
CN101245621A (en) Cast-in-situ hollow building roof construction method
CN102251667B (en) Construction method for reinforced concrete arched roof of grain store
CN201474152U (en) LPM cast-in-situ concrete hollow slab
CN105298040B (en) A kind of lightweight assembled stair and its construction method
CN104060760B (en) High Rise Building Transfer Floor Structure concrete super large beam construction in layer method
CN204456224U (en) A kind of structure of basement post-pouring zone
CN104405068A (en) Construction method of post-tensioned unbonded prestressed hollow floor slab
CN103161176A (en) Tower crane foundation construction method in main building connected garage
CN202300419U (en) Tunnel supporting structure of ultra-shallow-buried underpass rail long pipe shed
CN110080454A (en) LPM light filling body Construction of Cast-in-situ Concrete Hollow
CN104631674A (en) Composite floor slab and construction method thereof
CN102352690B (en) Construction method of anti-floating locating system of cast-in-place concrete hollow floorslab steel tube
CN106284653B (en) A kind of construction method that balcony construct capital interspaces in advance
CN203007974U (en) Tower crane foundation structure
CN101761187B (en) Construction separating device for concrete of vertical structure in same wall body with different labels as well as pouring and tamping method thereof
CN103046664A (en) Energy-saving wall with connecting keys and recycled concrete wall panels holding insulation block masonry, and manufacturing method of energy-saving wall
CN103243848B (en) The construction technology of cast-in-place concrete floor or superstructure and the spring support member of employing
CN102877859A (en) End mould structure for tunnel secondary lining and mounting method thereof
CN204238264U (en) A kind of sole plate post-poured strip structure
CN104047381B (en) Assembled integral rare-reinforcement concrete shear wall structure
CN110005112A (en) A kind of pitched roof concrete structure and its construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110921

Termination date: 20180316